Biaya 31,813,894
Sumber Dana Biaya Pajak 2,312,700
Total Biaya + Pajak 34,126,594
Tajinan, 2018
Disetujui/Mengesahkan
KEPALA DESA PELAKSANA KEGIATAN
( H.ISBANDI ) ( M.ULYAH )
RENCANA ANGGARAN BIAYA
Disetujui / mengesahkan
KEPALA DESA TAJINAN
RENCANA ANGGARAN BIAYA
No. RAB :
Sumber Dana : Dana Desa
Jenis Kegiatan : TPT
Ukuran/Dimensi : 83 X 0,5 X 0,3 M
Jumlah
DPP PPN PPH Psl 22 PPH psl 23 JUMLAH TOTAL
( Rp. )
2,700,000 - - - 2,700,000
5,040,000 - - - 5,040,000
7,740,000 - - - - 7,740,000
750,000 - - - 750,000
250,000 - - - 250,000
1,000,000 - - - - 1,000,000
31,595,500 20,777,400 2,010,900 301,800 - 33,908,200
-
-
-
-
-
-
-
-
-
-
-
TAKE OF SHEET
Desa : Tajinan
Kecamatan : Tajinan
Kabupaten : Malang
Sub Kegiatan : Pembangunan TPT RT 08 ( TPS Sawah )
Sketsa Perhitungan
VT = ( V1 + V2 )
22.2 + 18.5 = 40.7 m3
RT.06 RT. 05
RT .04
Jl.Salak
JL.Klengkeng
Ke Purwosekar
Biaya 6,161,000
Sumber Dana dari
Biaya Pajak 159,100
Dana Desa
Total Biaya (Dana Desa + Pajak) 6,320,100
H. I S B A N D I NGATENO
→ OK..!
→ OK..!
→ OK..! 15,187,400 RAB Lama
8,867,300 Sisa
RENCANA ANGGARAN BIAYA
Propinsi : Jawa Timur No. RAB
Kabupaten : Malang Program
Kecamatan : Tajinan Kegiatan
Desa : Tajinan Volume
H. I S B A N D I NGATEN
NGGARAN BIAYA
:
: P3MD Kemendesa PDTT
: TPT RT 24
: 43 m
1,909,100 159,100
660,000 -
1,034,000 -
- 3,603,100 159,100
70,000 -
15,000 -
60,000 -
120,000 -
100,000 -
150,000 -
- 515,000 -
780,000 -
375,000 -
- 1,155,000 -
750,000 -
250,000 -
47,000 -
- 1,047,000 -
- 6,320,100 159,100
Dibuat Oleh :
Tim Penyusun RKP Desa
Ketua
NGATENO
TAKE OF SHEET
Desa : Tajinan
Kecamatan : Tajinan
Kabupaten : Malang
Sub Kegiatan : Pembangunan TPT RT 08 ( TPS Sawah )
Sketsa Perhitungan
VT = ( V1 + V2 )
3.5 + 2.6 = 6.1 m3
RT. 23
JL.NANGKA
Rumah Warga
Jl.Manggis
RT.24
Biaya 37,894,700
Sumber Dana dari Dana Desa Biaya Pajak 2,747,000
Total Biaya (Dana Desa + Pajak) 40,641,700
Tajinan, 2018
H. I S B A N D I NGATENO
RENCANA ANGGARAN BIAYA
Propinsi : Jawa Timur No. RAB
Kabupaten : Malang Program
Kecamatan : Tajinan Kegiatan
Desa : Tajinan Volume
VOLUME Satu Harga Satuan Jumlah
URAIAN DPP PPN PPH Psl 22
Total Swadya DD an (Rp) (Rp)
BAHAN
1 Batu Gunung 36.00 36.00 m3 250,000 9,000,000 8,181,800 818,200 122,800
2 Batu Pecah 2/3 1.00 1.00 m3 250,000 250,000 227,200 - -
3 Batako 588.00 588.00 bh 4,000 2,352,000 2,138,100 213,900 32,100
4 Pasir Pasang 21.00 21.00 m3 165,000 3,465,000 3,150,000 315,000 47,300
5 Semen (40 Kg) 134.00 134.00 zak 65,000 8,710,000 7,918,100 791,900 118,800
6 Besi Ø6 27.00 27.00 btg 29,000 783,000 711,800 - -
7 Besi Ø8 56.00 56.00 btg 49,000 2,744,000 2,494,500 249,500 37,500
8 Kawat bendrat 6.00 6.00 kg 47,000 282,000 256,300 - -
Sub Total 1) 27,586,000 25,077,800 2,388,500 358,500
ALAT
1 Selang Timbang 20.00 20.00 m 3,500 70,000 63,600 - -
2 Kereta Dorong 1.00 1.00 bh 500,000 500,000 454,500 - -
3 Benang 2.00 2.00 Roll 7,500 15,000 13,600 - -
4 Ganco 1.00 1.00 bh 75,000 75,000 68,100 - -
5 Cangkul 2.00 2.00 bh 60,000 120,000 109,000 - -
6 Sekop 2.00 2.00 bh 60,000 120,000 109,000 - -
7 Ember 10.00 10.00 bh 10,000 100,000 90,900 - -
8 Kuas 4" 1.00 1.00 bh 25,000 25,000 22,700 - -
9 Prasasti 1.00 1.00 Ls 350,000 350,000 318,100 - -
10 Papan Proyek 1.00 1.00 Ls 150,000 150,000 136,300 - -
Sub Total 2) 1,525,000 1,385,800 - -
UPAH
1 Pekerja 78.00 OH 65,000 5,070,000 - - -
2 Tukang 33.00 OH 80,000 2,640,000 - - -
Sub Total 3) 7,710,000 - - -
OPERASIONAL PK
1 Transport TPK 3.00 Org 250,000 750,000 - - -
2 Transport Pengawas 1.00 Org 250,000 250,000 - - -
3 FC + Penggandaan 1.00 Ls 73,700 73,700 - - -
Sub Total 4) 1,073,700 - - -
JUMLAH TOTAL 37,894,700 26,463,600 2,388,500 358,500
Mengetahui / Menyetujui :
KEPALA DESA
H. I S B A N D I
NGGARAN BIAYA
:
: P3MD Kemendesa PDTT
: TPT RT. 08 (TPS Sawah)
: 65 m
9,941,000 941,000
250,000 -
2,598,000 246,000
3,827,300 362,300
9,620,700 910,700
783,000 -
3,031,000 287,000
282,000 -
0 30,333,000 2,747,000
70,000 -
500,000 -
15,000 -
75,000 -
120,000 -
120,000 -
100,000 -
25,000 -
350,000 -
150,000 -
- 1,525,000 -
5,070,000 -
2,640,000 -
- 7,710,000 -
750,000 -
250,000 -
73,700 -
- 1,073,700 -
- 40,641,700 2,747,000
Tajinan, 2018
Dibuat Oleh :
Tim Penyusun RKP Desa
Ketua
NGATENO
TAKE OF SHEET
Desa : Tajinan
Kecamatan : Tajinan
Kabupaten : Malang
Sub Kegiatan : Pembangunan TPT RT 08 ( TPS Sawah )
Sketsa Perhitungan
0.1
balok 0.1
Catatan: Talud Pasangan Batu, Panjang 65 M
Batako 0.75 1.00 Tiap jarak 3 meter
Sloof 0.15 diberi kolom uk. 10 x 15 cm Perhitungan volume Pas. Batu
0.08 = 65 / 3 V1 = (1) x ( 0.30 + 0.40 ) / 2 x 1.00 x 65.0
0.30 = 22 + 1 1 x 0.35 x 1.00 x 65 = 22.8 m3
1.00 = 23 kolom
V2 = (1) x ( 0.40 x 0.40 ) x 65.0
0.1 0.1 1 x 0.40 x 0.40 x 65 = 10.4 m3
VT = ( V1 + V2 )
0.15 0.10
0.40 22.8 + 10.4 = 33.2 m3
Kolom & sloof balok Perhitungan Volume Plesteran
0.40 A = (1) x ( 0.08 + 0.20 + 0.00 ) x 65.0
Jarak antar begel = 0.20 m 1 x 0.38 x 65.0 = 24.7 m2
Jumlah begel kolom & sloof = 440 bh besi
Volume Galian Tanah
Jumlah begel balok = 325 bh pokok Ø8 V = 0.40 x 0.40 x 65 = 10.40 m3
panjang 1 begel kolom & sloof = 0.46 m Perhitungan Strikan / Siaran
panjang 1 begel balok = 0.36 m besi A = 1/4 x ( 1.00 - 0.08 ) x 65.0
Panjang total begel = 319 m begel Ø6 0.25 x 0.92 x 65.0 = 15.0 m2
Sketsa Perhitungan Batako
U PETA LOKASI A batako = 65 x 0.75 = 48.8 m2
Lokasi TPT A kolom = 0.1 x 0.75 x 23.00 = 1.73 m2
Jl. Garuda
Desa : Tajinan
Kecamatan : Tajinan
Kabupaten : Malang
Sub Kegiatan : Pembangunan Tembok Penahan Tanah ( TPT )
Sketsa Perhitungan
0.15 VT = V1 + V2 + V3 )
0.3 27.0 + 19.9 + 3.7
VT 50.6 m2
Sketsa Perhitungan
Sub Total 4) - - -
TOTAL BIAYA -
Biaya 10,183,100
Sumber Dana Biaya Pajak 444,900
Total Biaya + Pajak 10,628,000
Tajinan, 2018
Disetujui/Mengesahkan
KEPALA DESA PELAKSANA KEGIATAN
( H.ISBANDI ) ( M.ULYAH )
RENCANA ANGGARAN BIAYA
Disetujui / mengesahkan
KEPALA DESA TAJINAN
RENCANA ANGGARAN BIAYA
No. RAB :
Sumber Dana : Dana Desa
Jenis Kegiatan : TPT
Ukuran/Dimensi : 83 X 0,5 X 0,3 M
Jumlah
DPP PPN PPH Psl 22 PPH psl 23 JUMLAH TOTAL
( Rp. )
300,000 - - - 300,000
540,000 - - - 540,000
840,000 - - - - 840,000
750,000 - - - 750,000
250,000 - - - 250,000
1,000,000 - - - - 1,000,000
9,002,500 6,511,000 400,500 44,400 - 9,447,400
-
-
-
-
-
-
-
-
-
-
-
TAKE OF SHEET
Desa : Tajinan
Kecamatan : Tajinan
Kabupaten : Malang
Sub Kegiatan : Pembangunan TPT RT 04 ( Punden )
Sketsa Perhitungan
VT = ( V1 + V2 )
6.8 + 5.0 = 11.8 m3
JL.MASJID
Lokasi TPT
RT.06
PUNDEN
JL.KLENGKENG
Ke Wajak
Rumah Warga
RT.04