ID Task Name Duration Start Finish Predecessors Nov '22 Dec '22 Jan '23 Feb '23 Mar
Finish Predecessors Nov '22 Dec '22 Jan '23 Feb '23 Mar '23 Apr '23 May '23
06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28
0 SCHEDULE 155 days Mon 21/11/22 Fri 19/05/23
1 DIVISI 1 UMUM 152 days Mon 21/11/22 Tue 16/05/23
2 Mobilisasi 8 days Mon 21/11/22 Tue 29/11/22
3 Mobilisasi akhir 12 days Wed 03/05/23 Tue 16/05/23 25FF
4 Manajemen dan Keselamatan Lalu Lintas 1 day Wed 30/11/22 Wed 30/11/22
5 Pengaman Lingkungan Hidup 1 day Mon 21/11/22 Mon 21/11/22
6 DIVISI 2 DRAINASE 78 days Fri 09/12/22 Thu 09/03/23
7 Galian untuk Selokan Drainase dan Saluran Air 48 days Fri 09/12/22 Thu 02/02/23 4
8 Pasangan Batu dengan Mortar 48 days Fri 13/01/23 Thu 09/03/23 7FS-2 days
9 DIVISI 3 PEKERJAAN TANAH 26 days Wed 18/01/23 Thu 16/02/23
10 Galian Biasa 24 days Wed 18/01/23 Tue 14/02/23 8SS+4 days
11 Timbunan Biasa dari galian 22 days Mon 23/01/23 Thu 16/02/23 10SS+4 days
12 DIVISI 4 PELEBARAN PERKERASAN DAN BAHU JALAN 32 days Fri 03/02/23 Sat 11/03/23
13 Lapis Pondasi Agregat Kelas B 32 days Fri 03/02/23 Sat 11/03/23 11SS-10 days
14 DIVISI 5 PERKERASAN BERBUTIR 36 days Mon 13/02/23 Sat 25/03/23
15 Lapis Pondasi Agregat Kelas A 36 days Mon 13/02/23 Sat 25/03/23 13SS+8 days
16 DIVISI 6 PERKERASAN ASPAL 49 days Mon 27/02/23 Mon 24/04/23
17 Lapis Resap Pengikat - Aspal Cair 48 days Mon 27/02/23 Sat 22/04/23 15SS+12 days
18 Lapis Perekat - Aspal Cair 46 days Wed 01/03/23 Sat 22/04/23 17SS+2 days
19 Laston Lapis Aus (AC-BC) 46 days Wed 01/03/23 Sat 22/04/23 18SS
20 Laston Lapis Antara (AC-WC) 46 days Thu 02/03/23 Mon 24/04/23 19SS+1 day
21 Bahan anti pengelupasan 46 days Thu 02/03/23 Mon 24/04/23 20SS
22 DVISI 7 STRUKTUR 90 days Fri 20/01/23 Thu 04/05/23
23 Pasangan Batu 90 days Fri 20/01/23 Thu 04/05/23 10SS+2 days
24 DIVISI 8 PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR 27 days Wed 19/04/23 Fri 19/05/23
25 Marka Jalan Termoplastik 27 days Wed 19/04/23 Fri 19/05/23
Task Inactive Milestone Start-only Critical Split
Split Inactive Summary Finish-only Progress
Project: SCHEDULE Milestone Manual Task External Tasks Manual Progress
Date: Thu 24/11/22 Summary Duration-only External Milestone
Project Summary Manual Summary Rollup Deadline
Inactive Task Manual Summary Critical