SCHEDULE PERCEPATAN PEKERJAAN LBCV S/D PONDASI

Mei
No Description
6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
1 LBCV #4

- Install rebar + Pengecoran borepile


4 4 4 4 4 4 4

- PDA test
2

- Perataan tanah + Lantai kerja


6 6 6 6

- Pembesian pondasi
6 6 6

- Bekisting pondasi
6 6 6

- Pengecoran
6

2 LBCV #3

- Penimbunan
4 2

- Install rebar + Pengecoran borepile


8 8 8 8 8 8 8 8 8 8 8 8 8

- PDA test
2

- Lantai kerja
6 6 6 6

- Pembesian pondasi
4 4 4 6 6 6

- Bekisting pondasi + angkur


6 6 6 6 6 6

- Pengecoran
6

3 LBCV #2
SCHEDULE PERCEPATAN PEKERJAAN LBCV S/D PONDASI

Mei
No Description
6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
- Clearing + Penimbunan

- Mobilisasi Spun pile SPK Produksi spun pile


5 5 5 5 5 5 5 5 5 5 5 5 5 5 5

- Mobilisasi Hammer pile Assembly


5 5 5

- Piling
5 5 5 5 5 5

- PDA test
2

- Lantai kerja

- Pembesian pondasi

- Bekisting pondasi + angkur

- Pengecoran

4 LBCV #1

- Clearing + Penimbunan

- Mobilisasi Spun pile SPK Produksi spun pile


5 5 5 5 5 5 5 5 5 5 5 5 5 5 5

- Mobilisasi Hammer pile Assembly


5

- Piling

- PDA test

- Lantai kerja

- Pembesian pondasi
SCHEDULE PERCEPATAN PEKERJAAN LBCV S/D PONDASI

Mei
No Description
6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

- Bekisting pondasi + angkur

- Pengecoran

5 KEBUTUHAN MANPOWER 8 6 12 12 12 22 28 26 30 36 30 30 18 22 34 28 33 38 32 27 5 5 5 7
Juni
30 31 1 2 3 4 5 6 7 8 9 10 11 12
Juni
30 31 1 2 3 4 5 6 7 8 9 10 11 12

6 6

6 6

6 6

Assembly
5 5

5 5 5 5 5

6 6
Juni
30 31 1 2 3 4 5 6 7 8 9 10 11 12
6 6

6 6

11 17 17 17 5 5 5 2 6 12 12 12 0
300
144 6 24
2.083333

LBCV 1 14 m Bottom 8 12 96
Upper 7 12 84

LBCV 2 20 m Bottom 8 12 96
Upper 13 12 156

48 432 16 3
ITEM OF CONCERN

1 Alat borepile di LBCV 3 akan disediakan 2 unit


2 Spiral untuk LBCV 3 harus dimulai dikerjakan di LBCV 4
3 Vendor PDA test segera d