SKETSA PERHITUNGAN
25 M 25 M 25 M
P. JEMBATAN = 5,30 M'
L. JEMBATAN = 4,30 M'
SKETSA PERHITUNGAN
- Volume = ls
SKETSA PERHITUNGAN
BOWPLANK
-
- GALIAN PONDASI
NO NAMA P L T JML (M3) strousspile
1 POND 1 2,10 m 2,00 1,00 4,20
2 POND 2 2,00 m 2,00 1,00 4,00 galian struktur strousspile
3
4 dia = 0,3 m
5 PILAR 1 2,40 m 0,80 1,30 2,50 T= 2 m
6 PILAR 2 2,40 m 0,80 1,30 2,50
7 V = 3,14 x (0,3 x 0,3)
8 = 3,14 0,09000
9 = 0,28260 2 M
10 = 0,6
SKETSA PERHITUNGAN
SKETSA PERHITUNGAN
TABEL A
-
PASANGAN BATU
NO L T P V (POND) L ATAS L BAWAH L RATA2 TINGGI P VOL TOT VOL
POND 1 2,00 1,00 2,10 4,20 M3 1,20 2,00 1,60 1,60 2,10 5,38 m3 9,58 M3
POND 2 2,00 1,00 2,00 4,00 M3 0,50 2,00 1,25 1,60 2,10 4,20 m3 8,20 M3
pilar 1 0,80 1,00 2,80 2,24 M3 0,70 0,80 0,75 1,60 2,80 3,36 5,60 M3
pilar 2 0,80 1,00 2,80 2,24 M3 0,70 0,80 0,75 1,60 2,80 3,36 M3 5,60 M3
LONENG
LANTAI
SKETSA PERHITUNGAN
- T = 1,60 M
L = 0,35
BEGEL 0,35 X 4,00 = 1,4 M'
Ø10-10
= 19,5 KG
SKETSA PERHITUNGAN
BESI
BAGEL
Ø12-10
2,10 = 21,00 0,55 = 11,55 m x 144,00 x 0,006165 = 10,253628 kg
0,10 2 lapis = 20,5 kg
41,0 kg
cros head VERTIKAL
Ø12-10
2,10 = 21,00 0,75 = 15,75 m x 144,00 x 0,006165 = 13,98222 kg
0,1 2 lapis = 27,96444 kg
kg
0,75 = 7,50 2,10 = 15,75 m x 144,00 x 0,006165 = 13,98222 kg
0,1 2 lapis = 27,96 kg
55,92888 kg
BERAT BEI CROS HEAD = 96,94 KG
JUMLAH CROSS HEAD = 2,00 BH X 96,94 = 193,88678 KG
ANGGARAN : 0
PEKERJAAN : 0
SUB PEKERJAAN : PEJERJAAN PLESTERAN
STATION :
SKETSA PERHITUNGAN
415,6 KG
SENGKANG
P = 1,6
Ø10-10
14,4 = 144,0 1,6 = 230,4 M X 100,0 0,006165 = 142,0416 KG
0,10
BESI LANTAI
Ø10-10
14,0 = 140,00 X 2,00 M = 280,00 M 100,0 0,006165 = 172,62 KG kg
0,10
0
0
DATA PENDUKUNG SERTIFIKAT BULANAN
PROYEK PEMBANGUNAN DAERAH
KABUPATEN SUBANG
PELAKSANA : 0
NO. KONTRAK : 0
PROYEK : 0
ANGGARAN : 0
PEKERJAAN : 0
SUB PEKERJAAN : PEJERJAAN PLESTERAN
STATION :
SKETSA PERHITUNGAN
DAIFRAGMA
P = 1,0 M
L = 0,2 M
T = 0,3 M
BEGEL
P= 1 M
Ø10-15
1,0 = 10,0 M X 1,0 = 10,0 100,0 0,006165 = 6,2 KG
0,10
4Ø12
4,0 BH X 1,0 M = 4,0 M X 144,0 0,006165 = 3,6 KG
9,7 KG
REALING
P = 0,2 M
L = 0,2 M
T = 1,0 M
Ø8-15 kg
1,0 = 10,00 X 0,7 = 7 KG X 64 0,006165 = 2,76192 KG
0,1
0
0
DATA PENDUKUNG SERTIFIKAT BULANAN
PROYEK PEMBANGUNAN DAERAH
KABUPATEN SUBANG
PELAKSANA : 0
NO. KONTRAK : 0
PROYEK : 0
ANGGARAN : 0
PEKERJAAN : 0
SUB PEKERJAAN : PEJERJAAN PLESTERAN
STATION :
SKETSA PERHITUNGAN
1990,3 KG
BETON
1 STROUSPILE
TINGGGI = 2,0 M
DIA = 0,3 M
2 PONDASI TAPAK
P = 2,8 VOL = 0,448 M3 kg
L = 0,8 JML TAPK = 2 = 0,90 M3
T = 0,2
3 KOLOM PILAR
T = 1,60 VOL = 0,196 M3
L = 0,35 JML KOLOM PILAR = = 0,20 M3 X 2 BH = 0,392 M3
P = 0,35
0 0 0 0
0 0 0 Direktur
DATA PENDUKUNG SERTIFIKAT BULANAN
PROYEK PEMBANGUNAN DAERAH
KABUPATEN SUBANG
PELAKSANA : 0
NO. KONTRAK : 0
PROYEK : 0
ANGGARAN : 0
PEKERJAAN : 0
SUB PEKERJAAN : PEJERJAAN PLESTERAN
STATION :
SKETSA PERHITUNGAN
GALAGAR
P = 14,40 VOLUME = = 2,77 M3
L = 0,55 JML GALAGAR 2,00 = 2 BH X 2,77 = 5,54 M3
T = 0,35
DIAFRAGMA
P = 1,00 M VOLUME = 0,06 M3
L = 0,20 M JML DIAFRAGMA = 5,0 BH X 0,06 = 0,3 M3
T = 0,30 M
LANTAI
P = 14,40 M VOLUME = 5,8 M3
L = 2,00 M
T = 0,20 M
REALING
P = 0,15 M VOL = 0,0225 X
L = 0,15 M JML RALING = 20,00 X 0,02 = 0,45 M3
T = 1,00 M