Anda di halaman 1dari 1

RENCANA ANGGARAN BIAYA

PEKERJAAN : KANOPI CLINIC DAN KANOPI DEPAN ANEX BUILDING


LOKASI : PLTU
TAHUN : 2022

NO URAIAN PEKERJAAN VOL SATUAN HARGA SATUAN JUMLAH


I BAHAN MATERIAL
1 BBM Genset 180 liter Rp 19,000 Rp 3.420,000
2 BBM Pick Up 110 liter Rp 19,000 Rp 2.090,000
3 Batu Potong Gerinda 40 pak Rp 350,000 Rp 14.000,000
4 BBM Truck 90 liter Rp 19,000 Rp 1.710,000
TOTAL I Rp 21.220,000
II TENAGA KERJA
1 Tenaga Bongkar 6 Orang 12 hari Rp 1.260,000 Rp 15.120,000
2 Tenaga Angkut Armada (Truck) 5 Orang 10 hari Rp 840,000 Rp 8.400,000
3 Tenaga Install dan Bongkar Scaffolding 7 Orang 12 hari Rp 470,000 Rp 5.640,000
4 Tenaga Plekmen 4 orang 12 hari Rp 1.080,000 Rp 12.960,000
TOTAL II Rp 42.120,000
III SEWA PERALATAN
1 Scaffolding T = 3, 5M L=1M P=6M 4 set Rp 10.500,000 Rp 42.000,000
2 1 Unit Pick Up 8 hari Rp 275,000 Rp 2.200,000
3 1 Unit Truck 4 hari Rp 3.750,000 Rp 15.000,000
4 1 Unit Genset 12 hari Rp 150,000 Rp 1.800,000
5 4 Unit Bor Tangan 12 hari Rp 200,000 Rp 2.400,000
6 3 Unit Gerenda Tangan 12 hari Rp 150,000 Rp 1.800,000
7 Tali Seling Tambang 4 roll Rp 600,000 Rp 2.400,000
TOTAL III Rp 67.600,000

Jumlah I + II + III Rp 130.940,000


Dikurangi besi 750kg x Rp 3250 Rp 2.437,500
TOTAL Rp 128.502,500
Dibulatkan Rp 128.500,000
Ppn 11% Rp 14.135,000
JUMLAH Rp 142.635,000

Batang, 19 Oktober 2022


CV HIDA LOGAM

RONDHI
Direktur