RUMAH TYPE 36
Terbilang :
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN MAT. PONDASI
1 Pasir 98.2 M3 Rp 240,000 Rp 23,568,000
2 Batu Gunung 207.8 M3 Rp 240,000 Rp 49,872,000
3 Bambu 144 Btg Rp 18,000 Rp 2,592,000
4 Semen 847 Sak Rp 50,000 Rp 42,350,000
5 Bendrat 18 Kg Rp 22,000 Rp 396,000
6 Benang 36 Roll Rp 5,000 Rp 180,000
7 Papan Cor 360 Lbr Rp 12,000 Rp 4,320,000
8 Paku 7" 18 Kg Rp 20,000 Rp 360,000
9 Paku 5" 18 Kg Rp 20,000 Rp 360,000
10 Kaso 4 x 6 72 Btg Rp 25,000 Rp 1,800,000
11 Ember 72 Bh Rp 10,000 Rp 720,000
TOTAL Rp 126,518,000
HARGA
NO PEKERJAAN / MATERIAL BANYAK SAT TOTAL HARGA
SATUAN
UPAH KERJA
1 Upah Pondasi type 36 18 Unit Rp 1,650,000 Rp 29,700,000
TOTAL Rp 29,700,000
BLOK B2 (20 UNIT)
NO URAIAN TOTAL HARGA
1 MATERIAL PONDASI Rp 140,448,000
2 ONGKOS KERJA Rp 33,000,000
Rp 173,448,000
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN MAT. PONDASI
1 Pasir 109 M3 Rp 240,000 Rp 26,160,000
2 Batu Gunung 230.7 M3 Rp 240,000 Rp 55,368,000
3 Bambu 160 Btg Rp 18,000 Rp 2,880,000
4 Semen 940 Sak Rp 50,000 Rp 47,000,000
5 Bendrat 20 Kg Rp 22,000 Rp 440,000
6 Benang 40 Roll Rp 5,000 Rp 200,000
7 Papan Cor 400 Lbr Rp 12,000 Rp 4,800,000
8 Paku 7" 20 Kg Rp 20,000 Rp 400,000
9 Paku 5" 20 Kg Rp 20,000 Rp 400,000
10 Kaso 4 x 6 80 Btg Rp 25,000 Rp 2,000,000
11 Ember 80 Bh Rp 10,000 Rp 800,000
TOTAL Rp 140,448,000
HARGA
NO PEKERJAAN / MATERIAL BANYAK SAT TOTAL HARGA
SATUAN
UPAH KERJA
1 Upah Pondasi type 36 20 Unit Rp 1,650,000 Rp 33,000,000
TOTAL Rp 33,000,000
BLOK B3 (20 UNIT)
NO URAIAN TOTAL HARGA
1 MATERIAL PONDASI Rp 140,448,000
2 ONGKOS KERJA Rp 33,000,000
Rp 173,448,000
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN MAT. PONDASI
1 Pasir 109 M3 Rp 240,000 Rp 26,160,000
2 Batu Gunung 230.7 M3 Rp 240,000 Rp 55,368,000
3 Bambu 160 Btg Rp 18,000 Rp 2,880,000
4 Semen 940 Sak Rp 50,000 Rp 47,000,000
5 Bendrat 20 Kg Rp 22,000 Rp 440,000
6 Benang 40 Roll Rp 5,000 Rp 200,000
7 Papan Cor 400 Lbr Rp 12,000 Rp 4,800,000
8 Paku 7" 20 Kg Rp 20,000 Rp 400,000
9 Paku 5" 20 Kg Rp 20,000 Rp 400,000
10 Kaso 4 x 6 80 Btg Rp 25,000 Rp 2,000,000
11 Ember 80 Bh Rp 10,000 Rp 800,000
TOTAL Rp 140,448,000
HARGA
NO PEKERJAAN / MATERIAL BANYAK SAT TOTAL HARGA
SATUAN
UPAH KERJA
1 Upah Pondasi type 36 20 Unit Rp 1,650,000 Rp 33,000,000
TOTAL Rp 33,000,000
BLOK B4 (16 UNIT)
NO URAIAN TOTAL HARGA
1 MATERIAL PONDASI Rp 112,538,000
2 ONGKOS KERJA Rp 26,400,000
Rp 138,938,000
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN MAT. PONDASI
1 Pasir 87.4 M3 Rp 240,000 Rp 20,976,000
2 Batu Gunung 184.9 M3 Rp 240,000 Rp 44,376,000
3 Bambu 128 Btg Rp 18,000 Rp 2,304,000
4 Semen 753 Sak Rp 50,000 Rp 37,650,000
5 Bendrat 16 Kg Rp 22,000 Rp 352,000
6 Benang 32 Roll Rp 5,000 Rp 160,000
7 Papan Cor 320 Lbr Rp 12,000 Rp 3,840,000
8 Paku 7" 16 Kg Rp 20,000 Rp 320,000
9 Paku 5" 16 Kg Rp 20,000 Rp 320,000
10 Kaso 4 x 6 64 Btg Rp 25,000 Rp 1,600,000
11 Ember 64 Bh Rp 10,000 Rp 640,000
TOTAL Rp 112,538,000
HARGA
NO PEKERJAAN / MATERIAL BANYAK SAT TOTAL HARGA
SATUAN
UPAH KERJA
1 Upah Pondasi type 36 16 Unit Rp 1,650,000 Rp 26,400,000
TOTAL Rp 26,400,000
BLOK B5 (14 UNIT)
NO URAIAN TOTAL HARGA
1 MATERIAL PONDASI Rp 98,608,000
2 ONGKOS KERJA Rp 23,100,000
Rp 121,708,000
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
HARGA
NO PEKERJAAN / MATERIAL BANYAK SAT TOTAL HARGA
SATUAN
UPAH KERJA
1 Upah Pondasi type 36 14 Unit Rp 1,650,000 Rp 23,100,000
TOTAL Rp 23,100,000
BLOK B6 (11 UNIT)
NO URAIAN TOTAL HARGA
1 MATERIAL PONDASI Rp 76,580,000
2 ONGKOS KERJA Rp 18,150,000
Rp 94,730,000
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
HARGA
NO PEKERJAAN / MATERIAL BANYAK SAT TOTAL HARGA
SATUAN
UPAH KERJA
1 Upah Pondasi type 36 11 Unit Rp 1,650,000 Rp 18,150,000
TOTAL Rp 18,150,000
BLOK B7 (22 UNIT)
NO URAIAN TOTAL HARGA
1 MATERIAL PONDASI Rp 155,474,000
2 ONGKOS KERJA Rp 36,300,000
Rp 191,774,000
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
HARGA
NO PEKERJAAN / MATERIAL BANYAK SAT TOTAL HARGA
SATUAN
UPAH KERJA
1 Upah Pondasi type 36 22 Unit Rp 1,650,000 Rp 36,300,000
TOTAL Rp 36,300,000
BLOK B8 (17 UNIT)
NO URAIAN TOTAL HARGA
1 MATERIAL PONDASI Rp 114,450,000
2 ONGKOS KERJA Rp 28,050,000
Rp 142,500,000
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
HARGA
NO PEKERJAAN / MATERIAL BANYAK SAT TOTAL HARGA
SATUAN
UPAH KERJA
1 Upah Pondasi type 36 17 Unit Rp 1,650,000 Rp 28,050,000
TOTAL Rp 28,050,000
BLOK B9 (6 UNIT)
NO URAIAN TOTAL HARGA
1 MATERIAL PONDASI Rp 45,664,000
2 ONGKOS KERJA Rp 9,900,000
Rp 55,564,000
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
HARGA
NO PEKERJAAN / MATERIAL BANYAK SAT TOTAL HARGA
SATUAN
UPAH KERJA
1 Upah Pondasi type 36 6 Unit Rp 1,650,000 Rp 9,900,000
TOTAL Rp 9,900,000
BLOK B10 (22 UNIT)
NO URAIAN TOTAL HARGA
1 MATERIAL PONDASI Rp 155,474,000
2 ONGKOS KERJA Rp 36,300,000
Rp 191,774,000
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
HARGA
NO PEKERJAAN / MATERIAL BANYAK SAT TOTAL HARGA
SATUAN
UPAH KERJA
1 Upah Pondasi type 36 22 Unit Rp 1,650,000 Rp 36,300,000
TOTAL Rp 36,300,000
BLOK B11 (10 UNIT)
NO URAIAN TOTAL HARGA
1 MATERIAL PONDASI Rp 70,772,000
2 ONGKOS KERJA Rp 16,500,000
Rp 87,272,000
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
HARGA
NO PEKERJAAN / MATERIAL BANYAK SAT TOTAL HARGA
SATUAN
UPAH KERJA
1 Upah Pondasi type 36 10 Unit Rp 1,650,000 Rp 16,500,000
TOTAL Rp 16,500,000
BLOK B12 (10 UNIT)
NO URAIAN TOTAL HARGA
1 MATERIAL PONDASI Rp 70,772,000
2 ONGKOS KERJA Rp 16,500,000
Rp 87,272,000
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
HARGA
NO PEKERJAAN / MATERIAL BANYAK SAT TOTAL HARGA
SATUAN
UPAH KERJA
1 Upah Pondasi type 36 10 Unit Rp 1,650,000 Rp 16,500,000
TOTAL Rp 16,500,000
BLOK C1 (10 UNIT)
NO URAIAN TOTAL HARGA
1 MATERIAL PONDASI Rp 70,772,000
2 ONGKOS KERJA Rp 16,500,000
Rp 87,272,000
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
HARGA
NO PEKERJAAN / MATERIAL BANYAK SAT TOTAL HARGA
SATUAN
UPAH KERJA
1 Upah Pondasi type 36 10 Unit Rp 1,650,000 Rp 16,500,000
TOTAL Rp 16,500,000
BLOK C2 (12 UNIT)
NO URAIAN TOTAL HARGA
1 MATERIAL PONDASI Rp 82,412,000
2 ONGKOS KERJA Rp 19,800,000
Rp 102,212,000
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN MAT. PONDASI
1 Pasir 63.9 M3 Rp 240,000 Rp 15,336,000
2 Batu Gunung 135.1 M3 Rp 240,000 Rp 32,424,000
3 Bambu 96 Btg Rp 18,000 Rp 1,728,000
4 Semen 550 Sak Rp 50,000 Rp 27,500,000
5 Bendrat 12 Kg Rp 22,000 Rp 264,000
6 Benang 24 Roll Rp 5,000 Rp 120,000
7 Papan Cor 240 Lbr Rp 12,000 Rp 2,880,000
8 Paku 7" 12 Kg Rp 20,000 Rp 240,000
9 Paku 5" 12 Kg Rp 20,000 Rp 240,000
10 Kaso 4 x 6 48 Btg Rp 25,000 Rp 1,200,000
11 Ember 48 Bh Rp 10,000 Rp 480,000
TOTAL Rp 82,412,000
HARGA
NO PEKERJAAN / MATERIAL BANYAK SAT TOTAL HARGA
SATUAN
UPAH KERJA
1 Upah Pondasi type 36 12 Unit Rp 1,650,000 Rp 19,800,000
TOTAL Rp 19,800,000
BLOK C3 (14 UNIT)
NO URAIAN TOTAL HARGA
1 MATERIAL PONDASI Rp 98,608,000
2 ONGKOS KERJA Rp 23,100,000
Rp 121,708,000
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN MAT. PONDASI
1 Pasir 76.6 M3 Rp 240,000 Rp 18,384,000
2 Batu Gunung 162 M3 Rp 240,000 Rp 38,880,000
3 Bambu 112 Btg Rp 18,000 Rp 2,016,000
4 Semen 660 Sak Rp 50,000 Rp 33,000,000
5 Bendrat 14 Kg Rp 22,000 Rp 308,000
6 Benang 28 Roll Rp 5,000 Rp 140,000
7 Papan Cor 280 Lbr Rp 12,000 Rp 3,360,000
8 Paku 7" 14 Kg Rp 20,000 Rp 280,000
9 Paku 5" 14 Kg Rp 20,000 Rp 280,000
10 Kaso 4 x 6 56 Btg Rp 25,000 Rp 1,400,000
11 Ember 56 Bh Rp 10,000 Rp 560,000
TOTAL Rp 98,608,000
HARGA
NO PEKERJAAN / MATERIAL BANYAK SAT TOTAL HARGA
SATUAN
UPAH KERJA
1 Upah Pondasi type 36 14 Unit Rp 1,650,000 Rp 23,100,000
TOTAL Rp 23,100,000
BLOK C4 (4 UNIT)
NO URAIAN TOTAL HARGA
1 MATERIAL PONDASI Rp 30,612,000
2 ONGKOS KERJA Rp 6,600,000
Rp 37,212,000
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN MAT. PONDASI
1 Pasir 24 M3 Rp 240,000 Rp 5,760,000
2 Batu Gunung 50.7 M3 Rp 240,000 Rp 12,168,000
3 Bambu 32 Btg Rp 18,000 Rp 576,000
4 Semen 206 Sak Rp 50,000 Rp 10,300,000
5 Bendrat 4 Kg Rp 22,000 Rp 88,000
6 Benang 8 Roll Rp 5,000 Rp 40,000
7 Papan Cor 80 Lbr Rp 12,000 Rp 960,000
8 Paku 7" 4 Kg Rp 20,000 Rp 80,000
9 Paku 5" 4 Kg Rp 20,000 Rp 80,000
10 Kaso 4 x 6 16 Btg Rp 25,000 Rp 400,000
11 Ember 16 Bh Rp 10,000 Rp 160,000
TOTAL Rp 30,612,000
HARGA
NO PEKERJAAN / MATERIAL BANYAK SAT TOTAL HARGA
SATUAN
UPAH KERJA
1 Upah Pondasi type 36 4 Unit Rp 1,650,000 Rp 6,600,000
TOTAL Rp 6,600,000
BLOK C5 (7 UNIT)
NO URAIAN TOTAL HARGA
1 MATERIAL PONDASI Rp 53,176,000
2 ONGKOS KERJA Rp 11,550,000
Rp 64,726,000
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN MAT. PONDASI
1 Pasir 41.6 M3 Rp 240,000 Rp 9,984,000
2 Batu Gunung 88 M3 Rp 240,000 Rp 21,120,000
3 Bambu 56 Btg Rp 18,000 Rp 1,008,000
4 Semen 358 Sak Rp 50,000 Rp 17,900,000
5 Bendrat 7 Kg Rp 22,000 Rp 154,000
6 Benang 14 Roll Rp 5,000 Rp 70,000
7 Papan Cor 140 Lbr Rp 12,000 Rp 1,680,000
8 Paku 7" 7 Kg Rp 20,000 Rp 140,000
9 Paku 5" 7 Kg Rp 20,000 Rp 140,000
10 Kaso 4 x 6 28 Btg Rp 25,000 Rp 700,000
11 Ember 28 Bh Rp 10,000 Rp 280,000
TOTAL Rp 53,176,000
HARGA
NO PEKERJAAN / MATERIAL BANYAK SAT TOTAL HARGA
SATUAN
UPAH KERJA
1 Upah Pondasi type 36 7 Unit Rp 1,650,000 Rp 11,550,000
TOTAL Rp 11,550,000
BLOK C6 (14 UNIT)
NO URAIAN TOTAL HARGA
1 MATERIAL PONDASI Rp 98,608,000
2 ONGKOS KERJA Rp 23,100,000
Rp 121,708,000
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN MAT. PONDASI
1 Pasir 76.6 M3 Rp 240,000 Rp 18,384,000
2 Batu Gunung 162 M3 Rp 240,000 Rp 38,880,000
3 Bambu 112 Btg Rp 18,000 Rp 2,016,000
4 Semen 660 Sak Rp 50,000 Rp 33,000,000
5 Bendrat 14 Kg Rp 22,000 Rp 308,000
6 Benang 28 Roll Rp 5,000 Rp 140,000
7 Papan Cor 280 Lbr Rp 12,000 Rp 3,360,000
8 Paku 7" 14 Kg Rp 20,000 Rp 280,000
9 Paku 5" 14 Kg Rp 20,000 Rp 280,000
10 Kaso 4 x 6 56 Btg Rp 25,000 Rp 1,400,000
11 Ember 56 Bh Rp 10,000 Rp 560,000
TOTAL Rp 98,608,000
HARGA
NO PEKERJAAN / MATERIAL BANYAK SAT TOTAL HARGA
SATUAN
UPAH KERJA
1 Upah Pondasi type 36 14 Unit Rp 1,650,000 Rp 23,100,000
TOTAL Rp 23,100,000
REKAPITULASI BIAYA PEKERJAAN PONDASI
CIAMPEA ASRI
RUMAH TYPE 45
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN MAT. PONDASI
1 Pasir 92.9 M3 Rp 240,000 Rp 22,296,000
2 Batu Gunung 196 M3 Rp 240,000 Rp 47,040,000
3 Bambu 128 Btg Rp 18,000 Rp 2,304,000
4 Semen 801 Sak Rp 50,000 Rp 40,050,000
5 Bendrat 16 Kg Rp 22,000 Rp 352,000
6 Benang 32 Roll Rp 5,000 Rp 160,000
7 Papan Cor 320 Lbr Rp 12,000 Rp 3,840,000
8 Paku 7" 16 Kg Rp 20,000 Rp 320,000
9 Paku 5" 16 Kg Rp 20,000 Rp 320,000
10 Kaso 4 x 6 64 Btg Rp 25,000 Rp 1,600,000
11 Ember 64 Bh Rp 10,000 Rp 640,000
TOTAL Rp 118,922,000
HARGA
NO PEKERJAAN / MATERIAL BANYAK SAT TOTAL HARGA
SATUAN
UPAH KERJA
1 Upah Pondasi type 36 16 Unit Rp 1,650,000 Rp 26,400,000
TOTAL Rp 26,400,000
BLOK A2 (18 UNIT)
NO URAIAN TOTAL HARGA
1 MATERIAL PONDASI Rp 128,966,400
2 ONGKOS KERJA Rp 29,700,000
Rp 158,666,400
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN MAT. PONDASI
1 Pasir 104.4 M3 Rp 240,000 Rp 25,056,000
2 Batu Gunung 200.76 M3 Rp 240,000 Rp 48,182,400
3 Bambu 144 Btg Rp 18,000 Rp 2,592,000
4 Semen 900 Sak Rp 50,000 Rp 45,000,000
5 Bendrat 18 Kg Rp 22,000 Rp 396,000
6 Benang 36 Roll Rp 5,000 Rp 180,000
7 Papan Cor 360 Lbr Rp 12,000 Rp 4,320,000
8 Paku 7" 18 Kg Rp 20,000 Rp 360,000
9 Paku 5" 18 Kg Rp 20,000 Rp 360,000
10 Kaso 4 x 6 72 Btg Rp 25,000 Rp 1,800,000
11 Ember 72 Bh Rp 10,000 Rp 720,000
TOTAL Rp 128,966,400
HARGA
NO PEKERJAAN / MATERIAL BANYAK SAT TOTAL HARGA
SATUAN
UPAH KERJA
1 Upah Pondasi type 36 18 Unit Rp 1,650,000 Rp 29,700,000
TOTAL Rp 29,700,000
BLOK A3 (20 UNIT)
NO URAIAN TOTAL HARGA
1 MATERIAL PONDASI Rp 148,510,000
2 ONGKOS KERJA Rp 33,000,000
Rp 181,510,000
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN MAT. PONDASI
1 Pasir 115.9 M3 Rp 240,000 Rp 27,816,000
2 Batu Gunung 245.1 M3 Rp 240,000 Rp 58,824,000
3 Bambu 160 Btg Rp 18,000 Rp 2,880,000
4 Semen 999 Sak Rp 50,000 Rp 49,950,000
5 Bendrat 20 Kg Rp 22,000 Rp 440,000
6 Benang 40 Roll Rp 5,000 Rp 200,000
7 Papan Cor 400 Lbr Rp 12,000 Rp 4,800,000
8 Paku 7" 20 Kg Rp 20,000 Rp 400,000
9 Paku 5" 20 Kg Rp 20,000 Rp 400,000
10 Kaso 4 x 6 80 Btg Rp 25,000 Rp 2,000,000
11 Ember 80 Bh Rp 10,000 Rp 800,000
TOTAL Rp 148,510,000
HARGA
NO PEKERJAAN / MATERIAL BANYAK SAT TOTAL HARGA
SATUAN
UPAH KERJA
1 Upah Pondasi type 36 20 Unit Rp 1,650,000 Rp 33,000,000
TOTAL Rp 33,000,000
BLOK A4 (22 UNIT)
NO URAIAN TOTAL HARGA
1 MATERIAL PONDASI Rp 162,188,000
2 ONGKOS KERJA Rp 36,300,000
Rp 198,488,000
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN MAT. PONDASI
1 Pasir 127.4 M3 Rp 240,000 Rp 30,576,000
2 Batu Gunung 269.4 M3 Rp 240,000 Rp 64,656,000
3 Bambu 176 Btg Rp 18,000 Rp 3,168,000
4 Semen 1098 Sak Rp 50,000 Rp 54,900,000
5 Bendrat 22 Kg Rp 22,000 Rp 484,000
6 Benang 44 Roll Rp 5,000 Rp 220,000
7 Papan Cor 352 Lbr Rp 12,000 Rp 4,224,000
8 Paku 7" 22 Kg Rp 20,000 Rp 440,000
9 Paku 5" 22 Kg Rp 20,000 Rp 440,000
10 Kaso 4 x 6 88 Btg Rp 25,000 Rp 2,200,000
11 Ember 88 Bh Rp 10,000 Rp 880,000
TOTAL Rp 162,188,000
HARGA
NO PEKERJAAN / MATERIAL BANYAK SAT TOTAL HARGA
SATUAN
UPAH KERJA
1 Upah Pondasi type 36 22 Unit Rp 1,650,000 Rp 36,300,000
TOTAL Rp 36,300,000
BLOK A5 (36 UNIT)
NO URAIAN TOTAL HARGA
1 MATERIAL PONDASI Rp 267,576,000
2 ONGKOS KERJA Rp 59,400,000
Rp 326,976,000
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN MAT. PONDASI
1 Pasir 208.8 M3 Rp 240,000 Rp 50,112,000
2 Batu Gunung 441.7 M3 Rp 240,000 Rp 106,008,000
3 Bambu 288 Btg Rp 18,000 Rp 5,184,000
4 Semen 1800 Sak Rp 50,000 Rp 90,000,000
5 Bendrat 36 Kg Rp 22,000 Rp 792,000
6 Benang 72 Roll Rp 5,000 Rp 360,000
7 Papan Cor 720 Lbr Rp 12,000 Rp 8,640,000
8 Paku 7" 36 Kg Rp 20,000 Rp 720,000
9 Paku 5" 36 Kg Rp 20,000 Rp 720,000
10 Kaso 4 x 6 144 Btg Rp 25,000 Rp 3,600,000
11 Ember 144 Bh Rp 10,000 Rp 1,440,000
TOTAL Rp 267,576,000
HARGA
NO PEKERJAAN / MATERIAL BANYAK SAT TOTAL HARGA
SATUAN
UPAH KERJA
1 Upah Pondasi type 36 36 Unit Rp 1,650,000 Rp 59,400,000
TOTAL Rp 59,400,000
REKAPITULASI BIAYA PEKERJAAN PONDASI
CIAMPEA ASRI
RUMAH TYPE 36
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN BESI PONDASI
1 Besi 10 17 Btg Rp 75,000 Rp 1,275,000
2 Bendrat 3 Kg Rp 22,000 Rp 66,000
3 Mata Cutting 1 Bh Rp 5,000 Rp 5,000
4 Cincin 8 x 15 220 Bh Rp 1,600 Rp 352,000
TOTAL Rp 1,698,000
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
UPAH KERJA
1 Upah Ikat Besi 1 Unit Rp 250,000 Rp 250,000
TOTAL Rp 250,000
CIAMPEA ASRI
RUMAH TYPE 45
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN BESI PONDASI
1 Besi 10 19 Btg Rp 75,000 Rp 1,410,000
2 Bendrat 4 Kg Rp 22,000 Rp 88,000
3 Mata Cutting 1 Bh Rp 5,000 Rp 5,000
4 Cincin 8 x 15 240 Bh Rp 1,600 Rp 384,000
TOTAL Rp 1,887,000
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
UPAH KERJA
1 Upah Ikat Besi 1 Unit Rp 300,000 Rp 300,000
TOTAL Rp 300,000
PERHITUNGAN BIAYA PEKERJAAN
PEMBANGUNAN CIAMPEA ASRI PEKERJAAN STRUKTUR DERET
TYPE 36
Luasan Dinding 124,4 m2
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN STRUKTUR
1 Hebel 60 x 20 cm 1037 bh Rp 6,500 Rp 6,740,500
2 Semen 42 sak Rp 52,000 Rp 2,184,000
3 Pasir ikat 3.73 m3 Rp 210,000 Rp 783,300
4 Paku 3 2 kg Rp 20,000 Rp 40,000
5 Paku 5 2 kg Rp 20,000 Rp 40,000
6 Paku 8 2 kg Rp 20,000 Rp 40,000
7 Bambu 23 btg Rp 13,000 Rp 299,000
8 Papan cor 2 m 15 lbr Rp 13,000 Rp 195,000
9 Ember 3 bh Rp 12,000 Rp 36,000
10 Pengki 1 bh Rp 14,000 Rp 14,000
11 Kayu Kaso 4 m btg Rp 30,000 Rp -
12 Hollow 4x2 cm btg Rp 40,000 Rp -
13 Triplek 8 mm lbr Rp 85,000 Rp -
14 Benang 5 bh Rp 5,000 Rp 25,000
TOTAL Rp 10,396,800
ONGKOS KERJA
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN STRUKTUR
1 Pekerjaan Pas Hebel dinding + atas 133.14 m2 Rp 25,000 Rp 3,328,500
2 Pekerjaan Pas Kusen 8 Bh Rp 60,000 Rp 480,000
3 Pekerjaan cor tiang dan pasang besi 17 Bh Rp 30,000 Rp 510,000
4 Pekerjaan Ringbalk dan pasang besi 42.4 m Rp 17,000 Rp 720,800
5 Pasang besi, mal dan cor dak atap ls Rp 320,000 Rp -
6 Pasang Besi, mal dan cor dak teras ls Rp 320,000 Rp -
7 Pekerjaan Plaster dan Aci dind. m2 Rp 23,000 Rp -
8 Pekerjaan Plaster dan Aci pond. m2 Rp 25,000 Rp -
9 Pekerjaan Floor lantai kasar m3 Rp 15,000 Rp -
10 Pekerjaan carport m3 Rp 40,000 Rp -
11 Pekerjaan Pembersihan ls Rp 200,000 Rp -
TOTAL Rp 5,039,300
DIGENAPKAN
PERHITUNGAN BIAYA PEKERJAAN
PEMBANGUNAN CIAMPEA ASRI PEKERJAAN STRUKTUR DERET
TYPE 45
Luasan Dinding 140,5 m2
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN STRUKTUR
1 Hebel 60 x 20 cm 1172 bh Rp 6,500 Rp 7,618,000
2 Semen 46 sak Rp 52,000 Rp 2,392,000
3 Pasir ikat 4.15 m3 Rp 210,000 Rp 871,500
4 Paku 3 2 kg Rp 20,000 Rp 40,000
5 Paku 5 2 kg Rp 20,000 Rp 40,000
6 Paku 8 2 kg Rp 20,000 Rp 40,000
7 Bambu 23 btg Rp 13,000 Rp 299,000
8 Papan cor 2 m 15 lbr Rp 13,000 Rp 195,000
9 Ember 3 bh Rp 12,000 Rp 36,000
10 Pengki 1 bh Rp 14,000 Rp 14,000
11 Kayu Kaso 4 m 16 btg Rp 30,000 Rp 480,000
12 Hollow 4x2 cm btg Rp 40,000 Rp -
13 Triplek 8 mm lbr Rp 85,000 Rp -
14 Benang 5 bh Rp 5,000 Rp 25,000
TOTAL Rp 12,050,500
ONGKOS KERJA
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN STRUKTUR
1 Pekerjaan Pas Hebel dinding + atas 149.7 m2 Rp 25,000 Rp 3,742,500
2 Pekerjaan Pas Kusen 8 Bh Rp 60,000 Rp 480,000
3 Pekerjaan cor tiang dan pasang besi 18 Bh Rp 30,000 Rp 540,000
4 Pekerjaan Ringbalk dan pasang besi 47 m Rp 17,000 Rp 799,000
5 Pasang besi, mal dan cor dak atap ls Rp 320,000 Rp -
6 Pasang Besi, mal dan cor dak teras ls Rp 320,000 Rp -
7 Pekerjaan Plaster dan Aci dind. m2 Rp 23,000 Rp -
8 Pekerjaan Plaster dan Aci pond. m2 Rp 25,000 Rp -
9 Pekerjaan Floor lantai kasar m3 Rp 15,000 Rp -
10 Pekerjaan carport m3 Rp 40,000 Rp -
11 Pekerjaan Pembersihan ls Rp 200,000 Rp -
TOTAL Rp 5,561,500
DIGENAPKAN
PERHITUNGAN BIAYA PEKERJAAN
PEMBANGUNAN CIAMPEA ASRI PEKERJAAN BESI STRUKTUR
TYPE 36
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN BESI STRUKTUR
1 Besi 10 (Kolom) 21 Btg Rp 65,000 Rp 1,365,000
2 Besi 10 (Ringbalk) 15 Btg Rp 65,000 Rp 975,000
3 Besi 10 (Dag Atap) 10 Btg Rp 65,000 Rp 650,000
4 Besi 10 (Dag Teras) 6 Btg Rp 65,000 Rp 390,000
5 Cincin Behel 212 Bh Rp 1,500 Rp 318,000
6 Kawat Ikat 5 Kg Rp 22,000 Rp 110,000
TOTAL Rp 3,808,000
ONGKOS KERJA
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN BESI STRUKTUR
1 Upah 1 Ls Rp 540,000 Rp 540,000
TOTAL Rp 540,000
PERHITUNGAN BIAYA PEKERJAAN
PEMBANGUNAN CIAMPEA ASRI PEKERJAAN BESI STRUKTUR
TYPE 45
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN BESI STRUKTUR
1 Besi 10 (Kolom) 22 Btg Rp 65,000 Rp 1,430,000
2 Besi 10 (Ringbalk) 17 Btg Rp 65,000 Rp 1,105,000
3 Besi 10 (Dag Atap) 10 Btg Rp 65,000 Rp 650,000
4 Besi 10 (Dag Teras) 6 Btg Rp 65,000 Rp 390,000
5 Cincin Behel 235 Bh Rp 1,500 Rp 352,500
6 Kawat Ikat 5 Kg Rp 22,000 Rp 110,000
TOTAL Rp 4,037,500
ONGKOS KERJA
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN BESI STRUKTUR
1 Upah 1 Ls Rp 675,000 Rp 675,000
TOTAL Rp 675,000
PERHITUNGAN BIAYA PEKERJAAN
PEMBANGUNAN CIKARANG RESIDENCE PEKERJAAN KUSEN ALUMINIUM
TYPE 36
ONGKOS KERJA
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN BESI STRUKTUR
1 Kusen Pintu Utama 7.1 m Rp 125,000 Rp 887,500
2 Kusen Pintu kamar Depan 5.2 m Rp 125,000 Rp 650,000
3 Kusen Pintu Kamar Belakang 5.2 m Rp 125,000 Rp 650,000
4 Kusen Pintu Belakang 63.94 m Rp 125,000 Rp 7,992,500
5 Kusen Jendela Ruang Tamu 14.13 m Rp 125,000 Rp 1,766,250
6 Kusen Jendela Kamar Depan 17.45 m Rp 125,000 Rp 2,181,250
7 Kusen Jendela Kamar Belakang 7.26 m Rp 125,000 Rp 907,500
TOTAL Rp 15,035,000
PERHITUNGAN BIAYA PEKERJAAN
PEMBANGUNAN CIKARANG RESIDENCE PEKERJAAN KUSEN ALUMINIUM
TYPE 45
ONGKOS KERJA
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN BESI STRUKTUR
1 Kusen Pintu Utama 7.1 m Rp 125,000 Rp 887,500
2 Kusen Pintu kamar Depan 5.2 m Rp 125,000 Rp 650,000
3 Kusen Pintu Kamar Belakang 5.2 m Rp 125,000 Rp 650,000
4 Kusen Pintu Belakang 63.94 m Rp 125,000 Rp 7,992,500
5 Kusen Jendela Ruang Tamu 14.13 m Rp 125,000 Rp 1,766,250
6 Kusen Jendela Kamar Depan 17.45 m Rp 125,000 Rp 2,181,250
7 Kusen Jendela Kamar Belakang 7.26 m Rp 125,000 Rp 907,500
TOTAL Rp 15,035,000
PERHITUNGAN BIAYA PEKERJAAN
PEMBANGUNAN CIAMPEA ASRI PEKERJAAN PAS. ATAP
TYPE 36
Luas Atap 51 m2
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN PAS. ATAP
1 Canal C 0.7 (6 m) Aplus 22 btg Rp 76,000 Rp 1,672,000
2 Reng V 0.4 (6 m) Aplus 25 btg Rp 35,000 Rp 875,000
3 Genteng 35 cm x 43 cm 480 Pcs Rp 8,500 Rp 4,080,000
4 Rabung 30 cm 72 m Rp 18,000 Rp 1,296,000
5 Baut Ruffing 3 cm rangka 1000 bh Rp 250 Rp 250,000
6 Lisplank Kalsiboard Aplus 2,4 M 11 lbr Rp 45,000 Rp 495,000
7 Cat minyak Ftalite Putih Dof 1 Klg Rp 74,500 Rp 74,500
8 Kuas 3 inch 1 bh Rp 8,000 Rp 8,000
9 Thiner 1 klg Rp 24,250 Rp 24,250
10 silikon bening 0.5 bh Rp 37,500 Rp 18,750
11 Dinabolt 6 CM 10 MM 20 bh Rp 2,500 Rp 50,000
TOTAL Rp 8,843,500
ONGKOS KERJA
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN PAS. ATAP
Pekerjaan Pemasangan rangka
1 1 Ls Rp 1,600,000 Rp 1,600,000
& atap
TOTAL Rp 1,600,000
PERHITUNGAN BIAYA PEKERJAAN
PEMBANGUNAN CIAMPEA ASRI PEKERJAAN PAS. ATAP
TYPE 45
Luas Atap 61 m2
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN PAS. ATAP
1 Canal C 0.7 (6 m) Aplus 26 btg Rp 76,000 Rp 1,976,000
2 Reng V 0.4 (6 m) Aplus 29 btg Rp 35,000 Rp 1,015,000
3 Genteng 35 cm x 43 cm 570 Pcs Rp 8,500 Rp 4,845,000
4 Rabung 30 cm 68 m Rp 18,000 Rp 1,224,000
5 Baut Ruffing 3 cm rangka 1000 bh Rp 250 Rp 250,000
6 Lisplank Kalsiboard Aplus 2,4 M 12 lbr Rp 45,000 Rp 540,000
7 Cat minyak Ftalite Putih Dof 1 Klg Rp 74,500 Rp 74,500
8 Kuas 3 inch 1 bh Rp 8,000 Rp 8,000
9 Thiner 1 klg Rp 24,250 Rp 24,250
10 silikon bening 0.5 bh Rp 37,500 Rp 18,750
11 Dinabolt 6 CM 10 MM 20 bh Rp 2,500 Rp 50,000
TOTAL Rp 10,025,500
ONGKOS KERJA
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN PAS. ATAP
Pekerjaan Pemasangan rangka
1 1 Ls Rp 1,900,000 Rp 1,900,000
& atap
TOTAL Rp 1,900,000
PERHITUNGAN BIAYA PEKERJAAN
PEMBANGUNAN CIAMPEA ASRI PEKERJAAN INST. LISTRIK
TYPE 36
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN INST. LISTRIK
1 Pipa Listrik 12 btg Rp 3,200 Rp 38,400
2 Klam Pipa Listrik 36 bh Rp 600 Rp 21,600
3 Mangkok listrik panasonic 12 bh Rp 2,800 Rp 33,600
4 Box NCB MT 6 group 1 bh Rp 14,000 Rp 14,000
5 NCB 6 Amp MT 1 bh Rp 18,000 Rp 18,000
6 Kabel NYM 2x1,5 2.5 Rol Rp 73,000 Rp 182,500
7 Kabel NYM 2x2.5 1.5 Rol Rp 73,000 Rp 109,500
8 Lampu Philips Downlight Tanam 18 watt 8 bh Rp 105,000 Rp 840,000
9 Lampu Philips Teras Outbow 18 watt 3 bh Rp 145,000 Rp 435,000
10 Isolasi Listrik 2 bh Rp 7,000 Rp 14,000
11 Plat Saklar + Stop Kontak Pan WESJ 5 bh Rp 27,000 Rp 135,000
12 Plat Stop Kontak Single Pan WESJ 2 bh Rp 20,500 Rp 41,000
13 Anak Saklar Seri Pan WESJ 4 bh Rp 12,000 Rp 48,000
14 Anak Saklar Engkol Pan WESJ 3 bh Rp 12,500 Rp 37,500
TOTAL Rp 1,968,100
ONGKOS KERJA
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN INST. LISTRIK
1 Pekerjaan instalasi pipa 19 titik Rp 60,000 Rp 1,140,000
TOTAL Rp 1,140,000
PERHITUNGAN BIAYA PEKERJAAN
PEMBANGUNAN CIAMPEA ASRI PEKERJAAN INST. LISTRIK
TYPE 45
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN INST. LISTRIK
1 Pipa Listrik 12 btg Rp 3,200 Rp 38,400
2 Klam Pipa Listrik 36 bh Rp 600 Rp 21,600
3 Mangkok listrik panasonic 12 bh Rp 2,800 Rp 33,600
4 Box NCB MT 6 group 1 bh Rp 14,000 Rp 14,000
5 NCB 6 Amp MT 1 bh Rp 18,000 Rp 18,000
6 Kabel NYM 2x1,5 2.5 Rol Rp 73,000 Rp 182,500
7 Kabel NYM 2x2.5 1.5 Rol Rp 73,000 Rp 109,500
8 Lampu Philips Downlight Tanam 18 watt 8 bh Rp 105,000 Rp 840,000
9 Lampu Philips Teras Outbow 18 watt 3 bh Rp 145,000 Rp 435,000
10 Isolasi Listrik 2 bh Rp 7,000 Rp 14,000
11 Plat Saklar + Stop Kontak Pan WESJ 5 bh Rp 27,000 Rp 135,000
12 Plat Stop Kontak Single Pan WESJ 2 bh Rp 20,500 Rp 41,000
13 Anak Saklar Seri Pan WESJ 4 bh Rp 12,000 Rp 48,000
14 Anak Saklar Engkol Pan WESJ 3 bh Rp 12,500 Rp 37,500
TOTAL Rp 1,968,100
ONGKOS KERJA
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN INST. LISTRIK
1 Pekerjaan instalasi pipa 19 titik Rp 60,000 Rp 1,140,000
TOTAL Rp 1,140,000
PERHITUNGAN BIAYA PEKERJAAN
PEMBANGUNAN CIAMPEA ASRI PEKERJAAN PAS. PLAFOND (sub)
TYPE 36
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN PLAFOND PVC
1 Ruang Tamu 8 m2 Rp 150,000 Rp 1,215,000
2 Kamar Mandi 3 m2 Rp 150,000 Rp 405,000
3 Kamar Depan 9 m2 Rp 150,000 Rp 1,350,000
4 Kamar Belakang 9 m2 Rp 150,000 Rp 1,350,000
5 Dapur 5 m2 Rp 150,000 Rp 810,000
6 Selasar 2 m2 Rp 150,000 Rp 270,000
7 Teras Depan 3 m2 Rp 150,000 Rp 450,000
8 Teras Belakang 3 m2 Rp 150,000 Rp 405,000
TOTAL 42 Rp 5,850,000
PERHITUNGAN BIAYA PEKERJAAN
PEMBANGUNAN CIAMPEA ASRI PEKERJAAN PAS. PLAFOND (sub)
TYPE 45
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN PLAFOND PVC
1 Ruang Tamu 16 m2 Rp 150,000 Rp 2,385,000
2 Kamar Mandi 3 m2 Rp 150,000 Rp 405,000
3 Kamar Depan 9 m2 Rp 150,000 Rp 1,350,000
4 Kamar Belakang 10 m2 Rp 150,000 Rp 1,440,000
5 Dapur 6 m2 Rp 150,000 Rp 900,000
6 Selasar 2 m2 Rp 150,000 Rp 270,000
7 Teras Depan 3 m2 Rp 150,000 Rp 450,000
8 Teras Belakang 3 m2 Rp 150,000 Rp 405,000
TOTAL 48 Rp 7,200,000
PERHITUNGAN BIAYA PEKERJAAN
PEMBANGUNAN CIAMPEA ASRI KERJAAN PAS. KERAMIK LANTAI
Type 36
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN KERAMIK LANTAI
1 Granit 60 x 60 cm 26 Dus Rp 140,000 Rp 3,669,167
2 Semen 11 Zak Rp 50,000 Rp 544,500
3 Pasir Ikat 2 m3 Rp 200,000 Rp 363,000
4 Nat Keramik 4 bks Rp 12,500 Rp 50,000
5 Mata Potong 1 bh Rp 30,000 Rp 30,000
TOTAL Rp 4,656,667
ONGKOS KERJA
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN KERAMIK LANTAI
1 Pek. Pas Granit 36.3 m Rp 50,000 Rp 1,815,000
TOTAL Rp 1,815,000
PERHITUNGAN BIAYA PEKERJAAN
PEMBANGUNAN CIAMPEA ASRI KERJAAN PAS. KERAMIK LANTAI
Type 45
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN KERAMIK LANTAI
1 Granit 60 x 60 cm 31 Dus Rp 140,000 Rp 4,404,167
2 Semen 14 Zak Rp 50,000 Rp 679,500
3 Pasir Ikat 2 m3 Rp 200,000 Rp 453,000
4 Nat Keramik 5 bks Rp 12,500 Rp 62,500
5 Mata Potong 1 bh Rp 30,000 Rp 30,000
TOTAL Rp 5,629,167
ONGKOS KERJA
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN KERAMIK LANTAI
1 Pek. Pas Granit 45.3 m Rp 50,000 Rp 2,265,000
TOTAL Rp 2,265,000
PERHITUNGAN BIAYA PEKERJAAN
PEMBANGUNAN CIAMPEA ASRI PEKERJAAN PAS. KAMAR MANDI
TYPE 36
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN KAMAR MANDI
1 Keramik 40 x 25 cm 15 Dus Rp 58,000 Rp 883,920
2 Keramik 25 x 25 cm 3 Dus Rp 56,000 Rp 151,200
3 Pasir ikat 0.14 m3 Rp 200,000 Rp 27,000
4 Semen 0.81 sak Rp 49,000 Rp 39,690
5 Kloset Duduk American Standart 1 bh Rp 1,100,000 Rp 1,100,000
6 Tee Kloset 1 bh Rp 60,000 Rp 60,000
7 Shower Kloset 1 bh Rp 60,000 Rp 60,000
8 Nat Keramik 1 bks Rp 12,500 Rp 12,500
9 Floor Drain Plastik 2 bh Rp 5,000 Rp 10,000
10 Pipa 1/2 inch AW 3 btg Rp 18,000 Rp 54,000
11 Knee 1/2 inch 6 bh Rp 3,500 Rp 21,000
12 Knee drat 1/2 inch 3 bh Rp 3,500 Rp 10,500
13 Pipa 2 inch D 2.5 btg Rp 45,000 Rp 112,500
14 Knee 2 inch 3 bh Rp 6,000 Rp 18,000
15 Pipa 3 inch 2 btg Rp 70,000 Rp 140,000
16 Knee 3 inch 2 bh Rp 15,000 Rp 30,000
17 Lem pipa Kaleng 1 klg Rp 60,000 Rp 60,000
18 Isolasi Air 3 bh Rp 4,000 Rp 12,000
19 Kran Air Plastik 2 bh Rp 6,000 Rp 12,000
20 Pintu Kamar Mandi Fuji 1 lbr Rp 200,000 Rp 200,000
21 T 1/2 inch 3 Bh Rp 4,500 Rp 13,500
22 Kran Angsa 1 Bh Rp 85,000 Rp 85,000
TOTAL Rp 3,112,810
ONGKOS KERJA
HARGA
NO PEKERJAAN / MATERIAL BANYAK SAT TOTAL HARGA
SATUAN
PEKERJAAN KAMAR MANDI
1 Pek. Instalasi pipa2 1 Ls Rp 160,000 Rp 160,000
2 Pekerjaan Pas Keramik dinding 14 m2 Rp 55,000 Rp 783,200
3 Pekerjaan Pas keramik Lantai 2.7 m2 Rp 50,000 Rp 135,000
4 Pas. Aksesoris (Kloset, FD, kran) 1 Ls Rp 150,000 Rp 150,000
5 Pas. Pintu KM dan sponing 1 Ls Rp 150,000 Rp 150,000
6 Pek. Nat dan pembersihan 1 Ls Rp 100,000 Rp 100,000
TOTAL Rp 1,478,200
DIBULATKAN Rp 1,500,000
PERHITUNGAN BIAYA PEKERJAAN
PEMBANGUNAN CIAMPEA ASRI PEKERJAAN PAS. KAMAR MANDI
TYPE 45
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN KAMAR MANDI
1 Keramik 40 x 25 cm 15 Dus Rp 58,000 Rp 883,920
2 Keramik 25 x 25 cm 3 Dus Rp 56,000 Rp 151,200
3 Pasir ikat 0.14 m3 Rp 200,000 Rp 27,000
4 Semen 0.81 sak Rp 49,000 Rp 39,690
5 Kloset Duduk American Standart 1 bh Rp 1,100,000 Rp 1,100,000
6 Tee Kloset 1 bh Rp 60,000 Rp 60,000
7 Shower Kloset 1 bh Rp 60,000 Rp 60,000
8 Nat Keramik 1 bks Rp 12,500 Rp 12,500
9 Floor Drain Plastik 2 bh Rp 5,000 Rp 10,000
10 Pipa 1/2 inch AW 3 btg Rp 18,000 Rp 54,000
11 Knee 1/2 inch 6 bh Rp 3,500 Rp 21,000
12 Knee drat 1/2 inch 3 bh Rp 3,500 Rp 10,500
13 Pipa 2 inch D 2.5 btg Rp 45,000 Rp 112,500
14 Knee 2 inch 3 bh Rp 6,000 Rp 18,000
15 Pipa 3 inch 2 btg Rp 70,000 Rp 140,000
16 Knee 3 inch 2 bh Rp 15,000 Rp 30,000
17 Lem pipa Kaleng 1 klg Rp 60,000 Rp 60,000
18 Isolasi Air 3 bh Rp 4,000 Rp 12,000
19 Kran Air Plastik 2 bh Rp 6,000 Rp 12,000
20 Pintu Kamar Mandi Fuji 1 lbr Rp 200,000 Rp 200,000
21 T 1/2 inch 3 Bh Rp 4,500 Rp 13,500
22 Kran Angsa 1 Bh Rp 85,000 Rp 85,000
TOTAL Rp 3,112,810
ONGKOS KERJA
HARGA
NO PEKERJAAN / MATERIAL BANYAK SAT TOTAL HARGA
SATUAN
PEKERJAAN KAMAR MANDI
1 Pek. Instalasi pipa2 1 Ls Rp 160,000 Rp 160,000
2 Pekerjaan Pas Keramik dinding 14 m2 Rp 55,000 Rp 783,200
3 Pekerjaan Pas keramik Lantai 2.7 m2 Rp 50,000 Rp 135,000
4 Pas. Aksesoris (Kloset, FD, kran) 1 Ls Rp 150,000 Rp 150,000
5 Pas. Pintu KM dan sponing 1 Ls Rp 150,000 Rp 150,000
6 Pek. Nat dan pembersihan 1 Ls Rp 100,000 Rp 100,000
TOTAL Rp 1,478,200
DIBULATKAN Rp 1,500,000
PERHITUNGAN BIAYA PEKERJAAN
PEMBANGUNAN CIKARANG RESIDENCE PEKERJAAN SEPTITANK
TYPE 36
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN SEPTITANK
1 Septitank jadi 1 Bh Rp 950,000 Rp 950,000
2 Rp -
3 Rp -
TOTAL Rp 950,000
ONGKOS KERJA
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN SEPTITANK
1 Upah Rp -
TOTAL Rp -
PERHITUNGAN BIAYA PEKERJAAN
PEMBANGUNAN CIKARANG RESIDENCE PEKERJAAN SEPTITANK
TYPE 45
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN SEPTITANK
1 Septitank jadi 1 Bh Rp 950,000 Rp 950,000
2 Rp -
3 Rp -
TOTAL Rp 950,000
ONGKOS KERJA
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN SEPTITANK
1 Upah Rp -
TOTAL Rp -
PERHITUNGAN BIAYA PEKERJAAN
PEMBANGUNAN CIKARANG RESIDENCE PINTU DAN JENDELA
TYPE 36
HARGA TOTAL
NO PEKERJAAN / MATERIAL BYK SAT
SATUAN HARGA
KONTRAKTOR
1 Daun pintu Utama Lebar 90 Panel 1 Lbr Rp 850,000 Rp 850,000
2 Daun pintu Kamar Lebar 80 Panel 2 Lbr Rp 800,000 Rp 1,600,000
3 Daun Pintu belakang Lebar 80 Panel 1 Lbr Rp 800,000 Rp 800,000
4 Daun Jendela Jelusi Pintu Utama 1 Lbr Rp 400,000 Rp 400,000
5 Daun Jendela Ruang Tamu 60x60 4 Lbr Rp 400,000 Rp 1,600,000
6 Daun Jendela Kamar Utama 80x68 4 Lbr Rp 450,000 Rp 1,800,000
7 Daun Jendela Kamar Belakang 130x45 2 Lbr Rp 550,000 Rp 1,100,000
8 Daun Jendela Belakang 130x45 1 Lbr Rp 550,000 Rp 550,000
9 kaca mati 5 mm 11 Bh Rp 100,000 Rp 1,100,000
TOTAL Rp 9,800,000
MATERIAL
10 Engsel Pintu 4 inch 6 Set Rp 50,000 Rp 300,000
11 Kunci Pintu 4 Set Rp 150,000 Rp 600,000
TOTAL Rp 900,000
PERHITUNGAN BIAYA PEKERJAAN
PEMBANGUNAN CIKARANG RESIDENCE PINTU DAN JENDELA
TYPE 45
HARGA TOTAL
NO PEKERJAAN / MATERIAL BYK SAT
SATUAN HARGA
KONTRAKTOR
1 Daun pintu Utama Lebar 90 Panel 1 Lbr Rp 850,000 Rp 850,000
2 Daun pintu Kamar Lebar 80 Panel 2 Lbr Rp 800,000 Rp 1,600,000
3 Daun Pintu belakang Lebar 80 Panel 1 Lbr Rp 800,000 Rp 800,000
4 Daun Jendela Jelusi Pintu Utama 1 Lbr Rp 400,000 Rp 400,000
5 Daun Jendela Ruang Tamu 60x60 4 Lbr Rp 400,000 Rp 1,600,000
6 Daun Jendela Kamar Utama 80x68 4 Lbr Rp 450,000 Rp 1,800,000
7 Daun Jendela Kamar Belakang 130x45 2 Lbr Rp 550,000 Rp 1,100,000
8 Daun Jendela Belakang 130x45 1 Lbr Rp 550,000 Rp 550,000
9 kaca mati 5 mm 11 Bh Rp 100,000 Rp 1,100,000
TOTAL Rp 9,800,000
MATERIAL
10 Engsel Pintu 4 inch 6 Set Rp 50,000 Rp 300,000
11 Kunci Pintu 4 Set Rp 150,000 Rp 600,000
TOTAL Rp 900,000
PERHITUNGAN BIAYA PEKERJAAN
PEMBANGUNAN CIKARANG RESIDENCE PEKERJAAN PENGECATAN
TYPE 36
MATERIAL
NO PEKERJAAN / MATERIAL BYK SAT HARGA SATUAN TOTAL HARGA
PEKERJAAN MAT. CAT
1 Sealer Outdoor Nippon Alkali 0.5 Pail Rp 900,000 Rp 450,000
2 Cat Abu-Abu Muda Jotun Weathershield 5kg 1 Klg Rp 380,000 Rp 380,000
3 Cat Abu-Abu Muda Jotun Interior 20kg 1.5 Pail Rp 1,250,000 Rp 1,875,000
4 Cat Abu-Abu Tua Jotun Weathershield 5kg 1 Klg Rp 380,000 Rp 380,000
5 Cat Gold Jotun Weathershield 5kg 0.5 Klg Rp 380,000 Rp 190,000
6 Bak Cat 1 Bh Rp 15,000 Rp 15,000
7 Cat Minyak 1 Kg Propan Impra 4 Klg Rp 95,000 Rp 380,000
8 Cat Propan Impra Clear Doff 2 Klg Rp 82,000 Rp 164,000
9 Kuas Roda 1 Bh Rp 10,000 Rp 10,000
10 Kuas 4" 2 Bh Rp 12,500 Rp 25,000
11 Kuas 2" 2 Bh Rp 6,000 Rp 12,000
12 Tiner 1 Ltr 5 Klg Rp 20,000 Rp 100,000
13 Amplas 2 M Rp 10,000 Rp 20,000
14 Dumpul Impra 5kg (Pintu) 2 Klg Rp 55,000 Rp 110,000
15 Dumpul Maltex 1Kg (Dinding) 3 Klg Rp 55,000 Rp 165,000
16 Solasi Kertas 3 Bh Rp 8,000 Rp 24,000
17 Kape Gagang 1 Bh Rp 7,500 Rp 7,500
18 Kape Dempul 1 Bh Rp 5,000 Rp 5,000
TOTAL Rp 4,312,500
MATERIAL
NO PEKERJAAN / MATERIAL BYK SAT HARGA SATUAN TOTAL HARGA
PEKERJAAN MAT. CAT
1 Sealer Outdoor Nippon Alkali 0.5 Pail Rp 900,000 Rp 450,000
2 Cat Abu-Abu Muda Jotun Weathershield 5kg 1 Klg Rp 380,000 Rp 380,000
3 Cat Abu-Abu Muda Jotun Interior 20kg 2 Pail Rp 1,250,000 Rp 2,500,000
4 Cat Abu-Abu Tua Jotun Weathershield 5kg 1 Klg Rp 380,000 Rp 380,000
5 Cat Gold Jotun Weathershield 5kg 0.5 Klg Rp 380,000 Rp 190,000
6 Bak Cat 1 Bh Rp 15,000 Rp 15,000
7 Cat Minyak 1 Kg Propan Impra 4 Klg Rp 95,000 Rp 380,000
8 Cat Propan Impra Clear Doff 2 Klg Rp 82,000 Rp 164,000
9 Kuas Roda 1 Bh Rp 10,000 Rp 10,000
10 Kuas 4" 2 Bh Rp 12,500 Rp 25,000
11 Kuas 2" 2 Bh Rp 6,000 Rp 12,000
12 Tiner 1 Ltr 5 Klg Rp 20,000 Rp 100,000
13 Amplas 2 M Rp 10,000 Rp 20,000
14 Dumpul Impra 5kg (Pintu) 2 Klg Rp 55,000 Rp 110,000
15 Dumpul Maltex 1Kg (Dinding) 3 Klg Rp 55,000 Rp 165,000
16 Solasi Kertas 3 Bh Rp 8,000 Rp 24,000
17 Kape Gagang 1 Bh Rp 7,500 Rp 7,500
18 Kape Dempul 1 Bh Rp 5,000 Rp 5,000
TOTAL Rp 4,937,500
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN BP LISTRIK
1 BP LISTRIK 6 A 1 Unit Rp 1,650,000 Rp 1,650,000
TOTAL Rp 1,650,000
PERHITUNGAN BIAYA PEKERJAAN
PEMBANGUNAN CIKARANG RESIDENCE PEKERJAAN BP LISTRIK
TYPE 45
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN BP LISTRIK
1 BP LISTRIK 6 A 1 Unit Rp 1,650,000 Rp 1,650,000
TOTAL Rp 1,650,000
PERHITUNGAN BIAYA PEKERJAAN
PEMBANGUNAN CIKARANG RESIDENCE PEKERJAAN RUMPUT TAMAN
TYPE 36
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN RUMPUT TAMAN
1 Rumput 2 m2 Rp 40,000 Rp 80,000
2 Tanah Timbun & Pemerataan 2 m2 Rp 25,000 Rp 50,000
3 Pohon Palem 1 Bh Rp 200,000 Rp 200,000
TOTAL Rp 330,000
PERHITUNGAN BIAYA PEKERJAAN
PEMBANGUNAN CIKARANG RESIDENCE PEKERJAAN RUMPUT TAMAN
TYPE 45
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN RUMPUT TAMAN
1 Rumput 5 m2 Rp 40,000 Rp 200,000
2 Tanah Timbun & Pemerataan 5 m2 Rp 25,000 Rp 125,000
3 Pohon Palem 1 Bh Rp 200,000 Rp 200,000
TOTAL Rp 525,000
PERHITUNGAN BIAYA PEKERJAAN
PEMBANGUNAN CIKARANG RESIDENCE PEKERJAAN PAVING BLOK + PEMBATAS
TYPE 36
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN PAVING BLOK
1 Paving Blok 12 m2 Rp 67,000 Rp 804,000
2 Bata Merah Pembatas Kav 170 Bh Rp 550 Rp 93,500
3 Semen (Coran + Pembatas) 4 Sak Rp 50,000 Rp 200,000
4 Pasir 0.8 m3 Rp 240,000 Rp 192,000
TOTAL Rp 1,289,500
ONGKOS KERJA
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN PAVING BLOK
1 Upah Pasang Paving Blok 12 m2 Rp 25,000 Rp 300,000
2 Upah Cor Rabat Depan Teras 1.6 m2 Rp 50,000 Rp 80,000
3 Upah Pembatas Kav 8 m Rp 13,000 Rp 104,000
TOTAL Rp 484,000
PERHITUNGAN BIAYA PEKERJAAN
PEMBANGUNAN CIKARANG RESIDENCE PEKERJAAN PAVING BLOK + PEMBATAS
TYPE 45
MATERIAL
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN PAVING BLOK
1 Paving Blok 12 m2 Rp 67,000 Rp 804,000
2 Bata Merah Pembatas Kav 200 Bh Rp 550 Rp 110,000
3 Semen (Coran + Pembatas) 4 Sak Rp 50,000 Rp 200,000
4 Pasir 0.8 m3 Rp 240,000 Rp 192,000
TOTAL Rp 1,306,000
ONGKOS KERJA
HARGA
NO PEKERJAAN / MATERIAL BYK SAT TOTAL HARGA
SATUAN
PEKERJAAN PAVING BLOK
1 Upah Pasang Paving Blok 12 m2 Rp 25,000 Rp 300,000
2 Upah Cor 1.6 m2 Rp 50,000 Rp 80,000
3 Upah Pembatas Kav 10 m Rp 13,000 Rp 130,000
TOTAL Rp 510,000
PERHITUNGAN BIAYA PEKERJAAN
PEMBANGUNAN CIAMPEA ASRI PEKERJAAN PAS. DPT SAMPING MAKAM