JADWAL WAKTU PELAKSANAAN PEKERJAAN ( TIME SCHEDULE OLLIVANDER PARK )

NAMA TAPAK: OLLIVANDER PARK


SITE PLAN 03

BULAN - 1
NO URAIAN PEKERJAAN JUMLAH HARGA BOBOT(%) MINGGU KE -
1 2 3 4
1 PEKERJAAN PONDASI BANGUNAN Rp 15,000,000 15.43 7.7 7.7
2 PEKERJAAN CORAN BANGUNAN Rp 25,000,000 25.72 3.7 3.7
3 PEKERJAAN PAVING BLOK Rp 20,000,000 20.58 6.9 6.9
4 PEKERJAAN MAIN PLAZA Rp 15,000,000 15.43 1.5 1.5 1.5
5 PEKERJAAN PEDESTRIAN WAY Rp 10,000,000 10.29 1.0 1.0 1.0
6 BANGKU TAMAN Rp 2,200,000 2.26
7 VEGETASI TAMAN Rp 3,000,000 3.09
8 BIAYA PENGECEKAN Rp 7,000,000 7.20
TOTAL Rp 97,200,000 92.80 7.4 2.6 13.0 13.1

BOBOT RENCANA KUMULATIF(%) - 7.4 10.0 23.0 36.1

BOBOT REALISASI KUMULATIF(%) -


SELISIH(%) -
BULAN - 2 BULAN - 3
MINGGU KE - MINGGU KE -
5 6 7 8 9 10 11 12

3.7 3.7 3.7 3.7 3.7


6.9
1.5 1.5 1.5 1.5 1.5 1.5 1.5
1.0 1.0 1.0 1.0 1.0 1.0 1.0
1.1 1.1
1.5 1.5
3.6
13.1 6.2 6.2 6.2 6.2 5 5.1 3.6

49.2 55.4 61.6 67.8 74.0 79.2 84.3 87.9