SATUAN PEMBAYARAN : M3
PERKIRAAN
NO KOMPONEN SATUAN
KUANTITAS
A. TENAGA
1. Pekerja jam 0.0779
2. Mandor jam 0.0097
B. BAHAN
1. Agregat A M3 1.289
C. PERALATAN
1 Motor Grader jam 0.001
2 Tandem Roller jam 0.0097
3 Alat Bantu LS 1.00
21,100 1,643.69
24,500 237.65
1,881.34
208,000 268,112.00
268,112.00
489,000 489.00
504,600 4,894.62
100.1 100.10
5,483.72
275,477.06
27,547.71
303,024.77
JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas A (Perbaikan)
SATUAN PEMBAYARAN : M3
PERKIRAAN
NO KOMPONEN SATUAN
KUANTITAS
A. TENAGA
1. Pekerja jam 0.0779
2. Mandor jam 0.0097
B. BAHAN
1. Agregat A M3 1.289
C. PERALATAN
1 Motor Grader jam 0.001
2 Tandem Roller jam 0.0097
3 Alat Bantu LS 1.00
HARGA SATUAN
JUMLAH HARGA (Rp.) NILAI TKDN KET
(Rp.)
1,881.34
268,112.00
5,483.72
246,663.04 http://tkdn.kemenperin.go.id/search.php
366.75
3,670.97
100.10
252,682.20
25,268.22
277,950.41
91.73%