DAFTAR KUANTITAS DAN HARGA

SATUAN : Dinas Perhubungan Provinsi Sumatera Utara


PEKERJAAN : Pengadaan dan Pemasangan Perlengkapan Jalan Lampu Penerangan Jalan Umum
(LPJU) Solar Cell
LOKASI : Ruas Jalan Balige - Tara Bunga - Meat (Bts Taput)
VOLUME : 12 Unit
TAHUN ANGGARAN : 2022

No Uraian Pekerjaan Volume Harga Satuan (Rp) Jumlah Harga (Rp)

I PEKERJAAN PERSIAPAN

1 Administrasi dan photo dokumentasi 1.00 Ls 3,000,000.00 3,000,000.00


2 Sewa gudang dan direksikeet 1.00 Ls 5,000,000.00 5,000,000.00

SUB TOTAL JUMLAH I 8,000,000.00

II PEKERJAAN LAMPU PENERANGAN JALAN UMUM (LPJU) SOLAR CELL


A PEKERJAAN PENGADAAN

1 Lampu LED 60W Multi Chip 12.00 Bh 4,500,000.00 54,000,000.00


Tiang Oktagonal 9M, Finishing -Hot dip Galvanize +
2 12.00 Bh 5,890,000.00 70,680,000.00
Powder Coating
3 Solar Panel Cell Mono crystalline silicon 200 Wp 12.00 Bh 3,450,000.00 41,400,000.00
4 MPPT Solar Charge Controller 12.00 Bh 2,100,000.00 25,200,000.00
Battery Lithium P04 25,6 Volt 50 AH Aluminium Box for
5 12.00 Bh 8,000,000.00 96,000,000.00
Battery and Solar Panel
6 Kabel NYYHY 72.00 M 30,000.00 2,160,000.00
7 Angkur dia. 19 mm 48.00 Bh 50,000.00 2,400,000.00
8 Logo Perhubungan 12.00 Bh 15,000.00 180,000.00
9 Stiker perlengkapan jalan 12.00 Bh 15,000.00 180,000.00

B PEKERJAAN PEMASANGAN DAN INSTALASI


1 Galian Tanah (M3) 5.88 M3 90,562.50 532,507.50
2 Urugan Tanah Kembali (M3) 1.56 M3 66,125.00 103,155.00
3 Urugan Pasir Bawah Pondasi (M3) 0.43 M3 313,128.90 134,645.43
4 Bakisting Untuk Pondasi (M2) 28.80 M2 278,271.25 8,014,212.00
5 Beton Cor Mutu fc = 21.7 Mpa (K-250) 4.32 M3 1,626,762.00 7,027,611.84
6 Set Pekerjaan Pemasangan Tiang dan Instalasi 12.00 Bh 1,000,000.00 12,000,000.00
7 Ongkos Angkut Ke Lokasi 12.00 Unit 45,120.00 541,440.00

C PEKERJAAN PENGADAAN DELINEATOR

1 Patok Tikungan (Delineator) Pipa besi 24.00 Bh 240,000.00 5,760,000.00


2 Cat 8.16 Kg 80,000.00 652,800.00
3 Reflektif High Intensity Grade Uk. 10 x 20 cm 48.00 Bh 50,000.00 2,400,000.00

D PEKERJAAN PEMASANGAN DELINEATOR


1 Galian Tanah 3.84 M3 90,562.50 347,760.00
2 Bakesting untuk Pondasi 20.16 M2 278,271.25 5,609,948.40
3 Urugan Pasir Bawah Pondasi 0.22 M3 1,601,128.90 352,248.36
4 Beton Cor Mutu fc = 14,5 Mpa (K-175) 1.94 M3 1,601,128.90 3,106,190.07
5 Ongkos Angkut Ke Lokasi 24.00 Unit 45,120.00 1,082,880.00

D BIAYA PENYELENGGARAAN K-3

Penyelenggaraan K3 dan Keselamatan Konstruksi 1.00 Ls 10,000,000.00 10,000,000.00

SUB TOTAL JUMLAH II 349,865,398.60


TOTAL 357,865,398.60
PPN 11% 39.365.193,84
TOTAL 397.230.592,44

Purwakarta, 30 Juni 2022


Penawaran,
CV. BHAKTI INSAN PERSADA

Taufik Mustofa
Direktur Utama