Anda di halaman 1dari 1

MATERIAL APPROVAL

KEMENTERIAN PEKERJAAN UMUM DAN PERUMAHAN RAKYAT


D I R E K T O R A T J E N D E R A L C I P T A K A R Y A
B A L A I P R A S A R A N A P E R M U K I M A N W I L A Y A H B A N T E N
SATUAN KERJA PELAKSANAAN PRASARANA PERMUKIMAN PROVINSI BANTEN
Jl. Syech Nawawi Al Bantani, Kawasan Pusat Pemerintah Provinsi Banten (KP3B)Palima Telp/ Fax.(0254)267087

OPTIMALISASI SPAM RANGKASBITUNG DAN SPAM KAWACI KAB. LEBAK (NUWSP)

NOMOR : …...................... TANGGAL : 18-May-23

PEKERJAAN :

SIPIL/ STRUKTUR FINISHING ARSITEKTUR MEKANIKAL & ELEKTRIKAL

MATERIAL : Pipa dan aksesoris

TYPE : Pipa GIP, Bend All Flange, Loose Flange, Reducer All Flange, Stube Flange

MERK :

*)Pipa GIP 6", 16", 12". *)Bend All Flange 6" x 90°, 6" x 45°, 16" x 45°. *)Loose Flange 16". *)Reducer All Flange 16" x 12".
DIAMETER / UKURAN :
*)Stube Flange 12"

SPESIFIKASI :

SESUAI BROSUR

LAMPIRAN :

1.

2.

3.

4.

5.

HASIL PENGAJUAN* : DISETUJUI TIDAK DISETUJUI

STATUS PENGAJUAN : DITERIMA DITOLAK

CATATAN :

Disetujui Oleh: Diperiksa Oleh Diajukan Oleh:


PEJABAT PEMBUAT KOMITMEN KONSULTAN SUPERVISI KONTRAKTOR PELAKSANA
PT. CIRIAJASA EC in Joint Venture with PT. TIRTA SARANA MULIA TECHNOLOGY
PT. YODYA KARYA (PERSERO)
PT. RANCANG SEMESTA

David Parlindungan Manurung,ST, MT Arief Nugraha, ST Nanang Supriyanto, ST


NIP:19760129 1009121001 Quality Control Project Manager