BILL OF QUANTITY (BOQ)

PEKERJAAN : REVITALISASI KAWASAN ISLAMIC CENTER KOTA PALOPO


LOKASI : KOTA PALOPO - SULAWESI SELATAN
TAHUN ANGGARAN : 2021

GEDUNG SEKOLAH MENEGAH ATAS (SMA)


perubahan progres ket
NO JENIS PEKERJAAN SAT VOLUME 31 agustus

IV PEKERJAAN LAIN-LAIN

PEKERJAAN GWT DAN BIOFILTER


1 Pek. Galian tanah m3 45.75
2 Pek. Urugan kembali m3 9.00
3 Pek. Urugan Pasir m3 3.05
4 Pek. Lantai kerja t = 5 cm m3 1.60
5 GWT kapasitas 4 m3 unit 1.00
6 Septi tank biotek kap. 3 m3 unit 2.00
7 Instalasi septictank biotek lengkap lot 2.00 minimal 110 meter

SUBTOTAL PEKERJAAN LAIN-LAIN :

D PEKERJAAN SANITASI

I PEKERJAAN ELEV. 0.00 - ELEV. 4.00


I.1. PEKERJAAN PASANG SANITASI
1 Pas. Closed duduk bh 14.00
2 Pek. Wastafel + accecories bh 10.00 9.00
4 Pek. Jet washer bh 14.00
5 Pek. Kran air bh 14.00 17.00
6 Pek. Floordrain bh 14.00
8 Pek. Cermin bh 10.00 9.00

1.00 Pek kran leher angsa dan Kitchen


SUBTOTAL PEKERJAAN SANITASI LT.1:

II PEKERJAAN ELEV. 4.00 - ELEV. 8.00


II.1 PEKERJAAN PASANG SANITASI
1 Pas. Closed duduk bh 14.00
2 Pek. Wastafel + accecories bh 10.00 9.00
3 Pek. Jet washer bh 14.00
4 Pek. Kran air bh 14.00
5 Pek. Floordrain bh 14.00
6 Pek. Cermin bh 10.00 9.00

SUBTOTAL PEKERJAAN SANITASI LT.2:


TOTAL PEKERJAAN SANITASI:

E PEKERJAAN MEKANIKAL ELEKTRIKAL DAN PLUMBING

1 GEDUNG A
I PEKERJAAN PANEL - PANEL & PERLENGKAPANNYA
LANTAI 1
1 Main Distribution Panel ( MDP ) unit 1.00 1.00
2 Panel Pompa Transfer unit 1.00 1.00
3 Sub Distribution Panel Lantai 1 (SDP LT.1) unit 1.00 1.00
4 Pan. Pen & SK lantai 1 unit 1.00 1.00
5 Panel Power AC lantai 1 unit 1.00 1.00
perubahan progres ket
NO JENIS PEKERJAAN SAT VOLUME 31 agustus

LANTAI 2
1 Sub Distribution Panel Lantai 1 (SDP LT.2) unit 1.00 1.00
2 Pan. Pen & SK lantai 2 unit 1.00 1.00
3 Panel Power AC lantai 2 unit 1.00 1.00
TOTAL PEKERJAAN PANEL-PANEL:

II PEKERJAAN GROUND SYSTEM


1 Grounding elektrikal include bak kontrol, tahanan max. 2 set 1.00
TOTAL PEKERJAAN GROUND SYSTEM:

III PEKERJAAN PENARIKAN & KONEKSI KABEL FEEDER


LANTAI 1
1 LVMDP eksisting ke MDP (NYY 4x240mm²) m' 20.00 2.50 - Kabel feeder dr meteran pln ke M
2 Dari MDP ke SDP LT.1 (NYY 4x6mm² + NYA 4mm²) m' 2.50 2.50 2.50 nyy 4 x 16mm + nya 4mm
3 Dari MDP ke SDP LT.2 (NYY 4x6mm² + NYA 4mm²) m' 5.00 12.00 - nyy 4 x 16mm + nya 4mm
4 SDP LT. 1 ke Pan. Pen & SK (NYY 4x4mm² + NYA 2,5mm²) m' 2.50 5.00 5.00 nyy 4 x 6mm + nya 4mm
5 SDP LT. 1 ke Panel AC (NYY 4x6mm² + NYA 4mm²) m' 2.50 2.50 2.50 nyy 4 x 16mm + nya 4mm
6 MDP ke panel pompa tranfer (NYY 4x6mm² + NYA 4mm²) m' 10.00 7.50 - nyy 4 x 2.5mm + nya 2.5mm
7 Panel Pom. Transfer ke unit Pom. transfer (NYY 4x4mm² m' 10.00 10.00 - nyy 4 x 2.5mm
LANTAI 2 -
1 SDP LT. 2 ke Pan. Pen & SK (NYY 4x4mm² + NYA 2,5mm²) m' 2.50 5.00 5.00 nyy 4 x 6mm + nya 4mm
2 SDP LT. 2 ke Panel AC (NYY 4x6mm² + NYA 4mm²) m' 2.50 2.50 2.50 nyy 4 x 16mm + nya 4mm
TOTAL PEKERJAAN PENARIKAN & KONEKSI KABEL FEEDER:

IV PEKERJAAN PENERANGAN & STOP KONTAK


LANTAI 1
1 RMI 2 x 16W LED bh 24.00 -
2 Downlight 18W LED bh 27.00 66.00 66.00
3 Downlight 7W LED bh 8.00 8.00
4 Saklar tunggal bh 2.00
5 Saklar ganda bh 12.00
6 Stop kontak bh 12.00 24.00 24.00
7 Celling Exhaust Fan bh 8.00
8 Instalasi penerangan (NYM 3 x 2,5mm² dlm pipa conduit Titik 59.00 74.00 74.00
9 Instalasi stop kontak (NYM 3 x 2,5mm² dlm pipa conduit Titik 12.00 24.00 24.00
LANTAI 2
1 RMI 2 x 16W LED bh 24.00
2 Downlight 18W LED bh 27.00 68.00
3 Downlight 7W LED bh 8.00
4 Saklar tunggal bh 2.00
5 Saklar ganda bh 12.00
6 Stop kontak/ Stop Kontak AC bh 24.00 21.00
7 Celling Exhaust Fan bh 8.00
8 Instalasi penerangan (NYM 3 x 2,5mm² dlm pipa conduit titik 59.00 76.00 73.00
9 Instalasi stop kontak (NYM 3 x 2,5mm² dlm pipa conduit titik 24.00 24.00
TOTAL PEKERJAAN PENERANGAN & STOP KONTAK:

V PEKERJAAN PLUMBING
Pekerjaan Pompa - Pompa dan Perlengkapannya
1 Pompa tranfer (GWT ke rooftank) unit 1.00
2 Pipa GIP Medium Ø 2" m' 5.00
3 Strainer Ø 50mm (2") bh 1.00
4 Flexsible joint Ø 50mm (2") bh 2.00
5 Check valve Ø 50mm (2") bh 1.00
6 Gate valve Ø 50mm (2") bh 2.00
7 Foot valve Ø 50mm (2") bh 1.00
8 Preasure gauge + ball valve bh 1.00
9 Suppot, fitting, hanger, cat dll. ls 1.00
Pekerjaan Instalasi Rooftank
1 Roof tank kap. 1000 liter bh 2.00
2 Pipa PVC AW Ø 2" (pipa kuras dan over flow rooftank) m' 10.00 1 inch
3 Pipa PVC AW Ø 2" (pipa distribusi) m' 10.00 90.00 68.00 1 inch
4 Gate valve Ø 50mm (2") bh 2.00 4.00 1 inch
LANTAI 1
Instalasi perpipaan distribusi air bersih
perubahan progres ket
NO JENIS PEKERJAAN SAT VOLUME 31 agustus

1 Pipa PVC AW Ø 2" (riser) m' 10.00 1 inch


2 Pipa PVC AW Ø 2" m' 20.00 16.00 1 inch
3 Pipa PVC AW Ø 3/4" m' 45.00 40.00
4 Pipa PVC AW Ø 1/2" m' 10.00 8.00
5 Gate valve Ø 50mm (2") bh 2.00
6 Fitting, support, hanger,dll ls 1.00
Instalasi perpipaan distribusi air bekas
1 Pipa PVC AW Ø 4" (riser) m' 10.00 3 inch
2 Pipa PVC AW Ø 2,5" m' 22.00 32.00 28.00 3 inch
3 Pipa PVC AW Ø 2" m' 20.50 16.00 1 1/4 inch
4 Fitting, support, hanger,dll ls 1.00
Instalasi perpipaan distribusi air kotor
1 Pipa PVC AW Ø 4" (riser) m' 10.00
2 Pipa PVC D Ø 2" (riser vent) m' 10.00
3 Pipa PVC AW Ø 4" m' 7.50 24.00 18.00
4 Pipa PVC D Ø 2" vent m' 2.00
5 Fitting, support, hanger,dll ls 1.00
Instalasi perpipaan distribusi air hujan
1 Pipa PVC AW Ø 4" (riser) m' 20.00 72.00 44.00 18 titik x 4 meter
LANTAI 2
Instalasi perpipaan distribusi air bersih
1 Pipa PVC AW Ø 2" (riser) m' 10.00 1 inch

2 Pipa PVC AW Ø 2" m' 20.00 70.00 1 inch


3 Pipa PVC AW Ø 3/4" m' 45.00
4 Pipa PVC AW Ø 1/2" m' 10.00
5 Gate valve Ø 50mm (2") bh 2.00
6 Fitting, support, hanger,dll ls 1.00
Instalasi perpipaan distribusi air bekas
1 Pipa PVC AW Ø 4" (riser) m' 10.00 3 inch
2 Pipa PVC AW Ø 2,5" m' 22.00 32.00 28.00 3 inch
3 Pipa PVC AW Ø 2" m' 20.50 16.00 1 1/4 inch
4 Fitting, support, hanger,dll ls 1.00
Instalasi perpipaan distribusi air kotor
1 Pipa PVC AW Ø 4" (riser) m' 10.00
2 Pipa PVC D Ø 2" (riser vent) m' 10.00
3 Pipa PVC AW Ø 4" m' 7.50 24.00 18.00
4 Pipa PVC D Ø 2" vent m' 2.00
5 Fitting, support, hanger,dll ls 1.00
Instalasi perpipaan distribusi air hujan
1 Pipa PVC AW Ø 4" (riser) m' 20.00 72.00 44.00 18 titik x 4 meter
TOTAL PEKERJAAN PLUMBING:

VI PEKERJAAN TATA SUARA


Peralatan Utama
1 Terminal Box Telepon Dan Data (IDF-C.1) terdiri dari : unit 1.00
2 2x300 W Power Amplifier unit 1.00 ampli 240 watt

3 7x300 W Power Amplifier unit 1.00 ampli 240 watt


4 Radio Tunner AM/FM unit 1.00
5 Autorserve Cassete unit 1.00
6 CD / DVD/MP3 - Playaer unit 1.00
7 Microphone unit 1.00
8 Equalizer unit 1.00
9 Mixer Frame w/ Module unit 1.00
10 Cabinet Rack unit 1.00
LANTAI 1
1 MDF bh 1.00 hapus
2 TBS-SB bh 1.00 1.00
3 Kabel dari MDF ke TSB-SB, NYHMY 3(3x2.5 mm2) m' 10.00 60.00 60.00
4 Ceiling Speaker 3 watt bh 11.00 11.00
5 Titik Instalasi Speaker, NYMHY 3x1,5 mm2 dalam conduit titik 11.00 nymhy 2 x 2.5mm
LANTAI 2
1 MDF bh 1.00 hapus
2 TBS-SB bh 1.00 1.00
perubahan progres ket
NO JENIS PEKERJAAN SAT VOLUME 31 agustus

3 Kabel dari MDF ke TSB-SB, NYHMY 3(3x2.5 mm2) m' 10.00 70.00
4 Ceiling Speaker 3 watt bh 11.00 11.00
5 Titik Instalasi Speaker, NYMHY 3x1,5 mm2 dalam conduit titik 11.00 nymhy 2 x 2.5mm
TOTAL PEKERJAAN TATA SUARA:
TOTAL PEKERJAAN MEP GEDUNG A:

2 GEDUNG B
I PEKERJAAN PANEL - PANEL & PERLENGKAPANNYA
LANTAI 1
1 Sub Distribution Panel Lantai 1 (SDP LT.1) unit 1.00 1.00
2 Pan. Pen & SK lantai 1 unit 1.00 1.00
3 Panel Power AC lantai 1 unit 1.00 1.00
LANTAI 2
1 Sub Distribution Panel Lantai 1 (SDP LT.2) unit 1.00 1.00
2 Pan. Pen & SK lantai 2 unit 1.00 1.00
3 Panel Power AC lantai 2 unit 1.00 1.00 dipasang di auditorium smp
TOTAL PEKERJAAN PANEL-PANEL:

II PEKERJAAN PENARIKAN & KONEKSI KABEL FEEDER


LANTAI 1
1 Dari MDP ke SDP LT.1 (NYY 4x6mm² + NYA 4mm²) m' 2.50 60.00 60.00 nyy 4 x 16mm + nya 4mm
2 Dari MDP ke SDP LT.2 (NYY 4x6mm² + NYA 4mm²) m' 5.00 70.00 70.00 nyy 4 x 16mm + nya 4mm
3 SDP LT. 1 ke Pan. Pen & SK (NYY 4x4mm² + NYA 2,5mm²) m' 2.50 5.00 5.00 nyy 4 x 6mm + nya 4mm
4 SDP LT. 1 ke Panel AC (NYY 4x6mm² + NYA 4mm²) m' 2.50 2.50 2.50 nyy 4 x 16mm + nya 4mm
LANTAI 2
1 SDP LT. 2 ke Pan. Pen & SK (NYY 4x4mm² + NYA 2,5mm²) m' 2.50 5.00 2.50 nyy 4 x 6mm + nya 4mm
2 SDP LT. 2 ke Panel AC (NYY 4x6mm² + NYA 4mm²) m' 2.50 2.50 nyy 4 x 16mm + nya 4mm
TOTAL PEKERJAAN PENARIKAN & KONEKSI KABEL FEEDER:

III PEKERJAAN PENERANGAN & STOP KONTAK


LANTAI 1
1 RMI 2 x 16W LED bh 15.00 - -
2 Downlight 18W LED bh 25.00 51.00 51.00
3 Downlight 7W LED bh 6.00 6.00
4 Saklar tunggal bh 4.00
5 Saklar ganda bh 7.00
6 Stop kontak bh 18.00 28.00 28.00
7 Celling Exhaust Fan bh 6.00
8 Instalasi penerangan (NYM 3 x 2,5mm² dlm pipa conduit Titik 46.00 57.00 57.00
9 Instalasi stop kontak (NYM 3 x 2,5mm² dlm pipa conduit Titik 18.00 28.00 28.00
LANTAI 2
1 RMI 2 x 16W LED bh 15.00 -
2 Downlight 18W LED bh 25.00 48.00 46.00
3 Downlight 7W LED bh 7.00 2.00
4 Saklar tunggal bh 6.00
5 Saklar ganda bh 8.00
6 Stop kontak/ Stop Kontak AC bh 17.00 22.00 22.00
7 Celling Exhaust Fan bh 6.00
8 Instalasi penerangan (NYM 3 x 2,5mm² dlm pipa conduit titik 47.00 55.00 48.00
9 Instalasi stop kontak (NYM 3 x 2,5mm² dlm pipa conduit titik 17.00
TOTAL PEKERJAAN PENERANGAN & STOP KONTAK:

IV PEKERJAAN PLUMBING
Pekerjaan Instalasi Rooftank
1 Roof tank kap. 1000 liter bh 2.00
2 Pipa PVC AW Ø 2" (pipa kuras dan over flow rooftank) m' 10.00 1 inch
3 Pipa PVC AW Ø 2" (pipa distribusi) m' 10.00 35.00 35.00 1 inch
4 Gate valve Ø 50mm (2") bh 2.00 4.00 1 inch
LANTAI 1
Instalasi perpipaan distribusi air bersih
1 Pipa PVC AW Ø 2" (riser) m' 10.00 1 inch
2 Pipa PVC AW Ø 2" m' 20.00 8.00 1 inch
3 Pipa PVC AW Ø 3/4" m' 45.00 32.00
4 Pipa PVC AW Ø 1/2" m' 10.00 8.00
5 Gate valve Ø 50mm (2") bh 2.00
perubahan progres ket
NO JENIS PEKERJAAN SAT VOLUME 31 agustus

6 Fitting, support, hanger,dll ls 1.00


Instalasi perpipaan distribusi air bekas
1 Pipa PVC AW Ø 4" (riser) m' 10.00 3 inch
2 Pipa PVC AW Ø 2,5" m' 22.00 22.00 3 inch
3 Pipa PVC AW Ø 2" m' 20.50 8.00
16.00 4.00 pipa 1 1/4 inch
4 Fitting, support, hanger,dll ls 1.00
Instalasi perpipaan distribusi air kotor
1 Pipa PVC AW Ø 4" (riser) m' 10.00
2 Pipa PVC D Ø 2" (riser vent) m' 10.00
3 Pipa PVC AW Ø 4" m' 7.50 12.00 12.00
4 Pipa PVC D Ø 2" vent m' 2.00
5 Fitting, support, hanger,dll ls 1.00
Instalasi perpipaan distribusi air hujan
1 Pipa PVC AW Ø 4" (riser) m' 20.00 64.00 48.00 16 titik x 4 meter
LANTAI 2
Instalasi perpipaan distribusi air bersih

1 Pipa PVC AW Ø 2" (riser) m' 10.00 1 inch

2 Pipa PVC AW Ø 2" m' 20.00 1 inch

3 Pipa PVC AW Ø 3/4" m' 45.00


4 Pipa PVC AW Ø 1/2" m' 10.00

5 Gate valve Ø 50mm (2") bh 2.00 1 inch

6 Fitting, support, hanger,dll ls 1.00


Instalasi perpipaan distribusi air bekas

1 Pipa PVC AW Ø 4" (riser) m' 10.00 3 inch

2 Pipa PVC AW Ø 2,5" m' 22.00 12.00 3 inch

3 Pipa PVC AW Ø 2" m' 20.50

4 Fitting, support, hanger,dll ls 1.00


Instalasi perpipaan distribusi air kotor
1 Pipa PVC AW Ø 4" (riser) m' 10.00
2 Pipa PVC D Ø 2" (riser vent) m' 10.00

3 Pipa PVC AW Ø 4" m' 7.50 12.00

4 Pipa PVC D Ø 2" vent m' 2.00


5 Fitting, support, hanger,dll ls 1.00
Instalasi perpipaan distribusi air hujan
1 Pipa PVC AW Ø 4" (riser) m' 20.00 64.00 48.00 16 titik x 4 meter
TOTAL PEKERJAAN PLUMBING:

V PEKERJAAN TATA SUARA


LANTAI 1
1 MDF bh 1.00 1.00
2 TBS-SB bh 1.00 1.00 ada
3 Kabel dari MDF ke TSB-SB, NYHMY 3(3x2.5 mm2) m' 10.00
4 Ceiling Speaker 3 watt bh 10.00 10.00
5 Titik Instalasi Speaker, NYMHY 3x1,5 mm2 dalam conduit titik 10.00 nymhy 2 x 2.5mm

LANTAI 2

1 MDF bh 1.00 hapus


2 TBS-SB bh 1.00 1.00
3 Kabel dari MDF ke TSB-SB, NYHMY 3(3x2.5 mm2) m' 10.00
4 Ceiling Speaker 3 watt bh 10.00 10.00
5 Titik Instalasi Speaker, NYMHY 3x1,5 mm2 dalam conduit titik 10.00 nymhy 2 x 2.5mm
TOTAL PEKERJAAN TATA SUARA:
TOTAL PEKERJAAN MEP GEDUNG B:
TOTAL PEKERJAAN MEP SMA:
BILL OF QUANTITY (BOQ)
PEKERJAAN : REVITALISASI KAWASAN ISLAMIC CENTER KOTA PALOPO
LOKASI : KOTA PALOPO - SULAWESI SELATAN
TAHUN ANGGARAN : 2021

GEDUNG SEKOLAH MENEGAH PERTAMA (SMP)


progress
perubahan
NO JENIS PEKERJAAN SAT VOLUME

B PEKERJAAN STRUKTUR

IV PEKERJAAN LAIN-LAIN
PEKERJAAN GWT DAN BIOFILTER
1 Pek. Galian tanah m3 22.88
2 Pek. Urugan kembali m3 4.50
3 Pek. Urugan Pasir m3 1.53
4 Pek. Lantai kerja t = 5 cm m3 0.76
5 GWT kapasitas 4 m3 unit 1.00
6 Septi tank biotek kap. 3 m3 unit 2.00
7 Instalasi septictank biotek lengkap lot 2.00
SUBTOTAL PEKERJAAN LAIN-LAIN :
TOTAL PEKERJAAN STRUKTUR :

D PEKERJAAN SANITASI

I PEKERJAAN ELEV. 0.00 - ELEV. 4.00

I.1. PEKERJAAN PASANG SANITASI


1 Pas. Closed duduk bh 11.00
2 Pek. Wastafel + accecories bh 3.00 6.00
4 Pek. Jet washer bh 11.00
5 Pek. Kran air bh 14.00 16
6 Pek. Floordrain bh 14.00
8 Pek. Cermin bh 3.00 6.00
1.00
SUBTOTAL PEKERJAAN SANITASI LANTAI 1:

II PEKERJAAN ELEV. 4.00 - ELEV. 8.00

II.1 PEKERJAAN PASANG SANITASI


1 Pas. Closed duduk bh 8.00
2 Pek. Wastafel + accecories bh 2.00 6.00
3 Pek. Jet washer bh 8.00
4 Pek. Kran air bh 8.00
5 Pek. Floordrain bh 10.00
6 Pek. Cermin bh 2.00 6.00

SUBTOTAL PEKERJAAN SANITASI LANTAI 2:


TOTAL PEKERJAAN SANITASI:

E PEKERJAAN MEKANIKAL ELEKTRIKAL DAN PLUMBING

1 GEDUNG 1
I PEKERJAAN PANEL - PANEL & PERLENGKAPANNYA
LANTAI 1
1 Main Distribution Panel ( MDP ) unit 1.00 1.00
progress
perubahan
NO JENIS PEKERJAAN SAT VOLUME

2 Panel Pompa Transfer unit 1.00 1.00


3 Sub Distribution Panel Lantai 1 (SDP LT.1) unit 1.00 1.00
4 Pan. Pen & SK lantai 1 unit 1.00 1.00
5 Panel Power AC lantai 1 unit 1.00 1.00
LANTAI 2
1 Sub Distribution Panel Lantai 1 (SDP LT.2) unit 1.00
2 Pan. Pen & SK lantai 2 unit 1.00
3 Panel Power AC lantai 2 unit 1.00
TOTAL PEKERJAAN PANEL-PANEL:

II PEKERJAAN GROUND SYSTEM


1 Grounding elektrikal include bak kontrol, tahanan max. 2ohm set 1.00
TOTAL PEKERJAAN GROUND SYSTEM:

III PEKERJAAN PENARIKAN & KONEKSI KABEL FEEDER


LANTAI 1
1 LVMDP eksisting ke MDP (NYY 4x240mm²) m' 40.00 2.50
2 Dari MDP ke SDP LT.1 (NYY 4x6mm² + NYA 4mm²) m' 2.50 2.50 2.50
3 Dari MDP ke SDP LT.2 (NYY 4x6mm² + NYA 4mm²) m' 5.00 27.00
4 SDP LT. 1 ke Pan. Pen & SK (NYY 4x4mm² + NYA 2,5mm²) m' 2.50 5.00 5.00
5 SDP LT. 1 ke Panel AC (NYY 4x6mm² + NYA 4mm²) m' 2.50 2.50 2.50
6 MDP ke panel pompa tranfer (NYY 4x6mm² + NYA 4mm²) m' 10.00 7.50
7 Panel Pom. Transfer ke unit Pom. transfer (NYY 4x4mm² + m' 10.00 10.00
LANTAI 2
1 SDP LT. 2 ke Pan. Pen & SK (NYY 4x4mm² + NYA 2,5mm²) m' 2.50 5.00
2 SDP LT. 2 ke Panel AC (NYY 4x6mm² + NYA 4mm²) m' 2.50 2.50
TOTAL PEKERJAAN PENARIKAN & KONEKSI KABEL FEEDER:

IV PEKERJAAN PENERANGAN & STOP KONTAK


LANTAI 1
1 RMI 2 x 16W LED bh 16.00 - -

2 Downlight 18W LED bh 11.00 37.00 37.00


3 Downlight 7W LED bh 6.00 6.00
4 Saklar tunggal bh 4.00
5 Saklar ganda bh 4.00
6 Stop kontak bh 16.00 16.00
7 Celling Exhaust Fan bh 6.00
8 Instalasi penerangan (NYM 3 x 2,5mm² dlm pipa conduit 20 Titik 33.00 43.00 43.00
9 Instalasi stop kontak (NYM 3 x 2,5mm² dlm pipa conduit 20 Titik 16.00 16.00
LANTAI 2
1 RMI 2 x 16W LED bh 16.00 -

2 Downlight 18W LED bh 12.00 42.00 42.00


3 Downlight 7W LED bh 6.00
4 Saklar tunggal bh 4.00
5 Saklar ganda bh 4.00
6 Stop kontak/ Stop Kontak AC bh 16.00 14.00
7 Celling Exhaust Fan bh 6.00
8 Instalasi penerangan (NYM 3 x 2,5mm² dlm pipa conduit 20 titik 34.00 48.00 48.00
9 Instalasi stop kontak (NYM 3 x 2,5mm² dlm pipa conduit 20 titik 16.00 14.00
TOTAL PEKERJAAN PENERANGAN & STOP KONTAK:

V PEKERJAAN PLUMBING
Pekerjaan Pompa - Pompa dan Perlengkapannya
1 Pompa tranfer (GWT ke rooftank) unit 1.00
2 Pipa GIP Medium Ø 2" m' 5.00
3 Strainer Ø 50mm (2") bh 1.00
4 Flexsible joint Ø 50mm (2") bh 2.00
5 Check valve Ø 50mm (2") bh 1.00
6 Gate valve Ø 50mm (2") bh 2.00
7 Foot valve Ø 50mm (2") bh 1.00
8 Preasure gauge + ball valve bh 1.00
progress
perubahan
NO JENIS PEKERJAAN SAT VOLUME

9 Suppot, fitting, hanger, cat dll. ls 1.00


Pekerjaan Instalasi Rooftank
1 Roof tank kap. 1000 liter bh 2.00
2 Pipa PVC AW Ø 2" (pipa kuras dan over flow rooftank) m' 10.00

3 Pipa PVC AW Ø 2" (pipa distribusi) m' 10.00


4 Gate valve Ø 50mm (2") bh 2.00 4.00
LANTAI 1

Instalasi perpipaan distribusi air bersih


1 Pipa PVC AW Ø 2" (riser) m' 10.00
2 Pipa PVC AW Ø 2" m' 20.00 14.00
3 Pipa PVC AW Ø 3/4" m' 45.00 20.00
4 Pipa PVC AW Ø 1/2" m' 10.00 8.00
5 Gate valve Ø 50mm (2") bh 2.00
6 Fitting, support, hanger,dll ls 1.00
Instalasi perpipaan distribusi air bekas
1 Pipa PVC AW Ø 4" (riser) m' 10.00 6.00
2 Pipa PVC AW Ø 2,5" m' 22.00 22.00
3 Pipa PVC AW Ø 2" m' 20.50 18.00
4 Fitting, support, hanger,dll ls 1.00
Instalasi perpipaan distribusi air kotor
1 Pipa PVC AW Ø 4" (riser) m' 10.00 6.00
2 Pipa PVC D Ø 2" (riser vent) m' 10.00 4.00
3 Pipa PVC AW Ø 4" m' 7.50 8.00
4 Pipa PVC D Ø 2" vent m' 2.00 2.00
5 Fitting, support, hanger,dll ls 1.00
Instalasi perpipaan distribusi air hujan
1 Pipa PVC AW Ø 4" (riser) m' 20.00 52.00 52.00
LANTAI 2
Instalasi perpipaan distribusi air bersih
1 Pipa PVC AW Ø 2" (riser) m' 10.00
2 Pipa PVC AW Ø 2" m' 20.00 48.00 48.00
3 Pipa PVC AW Ø 3/4" m' 45.00 32.00
4 Pipa PVC AW Ø 1/2" m' 10.00 8.00
5 Gate valve Ø 50mm (2") bh 2.00
6 Fitting, support, hanger,dll ls 1.00
Instalasi perpipaan distribusi air bekas
1 Pipa PVC AW Ø 4" (riser) m' 10.00
2 Pipa PVC AW Ø 2,5" m' 22.00 18.00
3 Pipa PVC AW Ø 2" m' 20.50
16.00 12.00
4 Fitting, support, hanger,dll ls 1.00
Instalasi perpipaan distribusi air kotor
1 Pipa PVC AW Ø 4" (riser) m' 10.00 6.00
2 Pipa PVC D Ø 2" (riser vent) m' 10.00 10.00
3 Pipa PVC AW Ø 4" m' 7.50 8.00
4 Pipa PVC D Ø 2" vent m' 2.00 2.00
5 Fitting, support, hanger,dll ls 1.00
Instalasi perpipaan distribusi air hujan
1 Pipa PVC AW Ø 4" (riser) m' 20.00 52.00 52.00
TOTAL PEKERJAAN PLUMBING:

VI PEKERJAAN TATA SUARA


Peralatan Utama
1 Terminal Box Telepon Dan Data (IDF-C.1) terdiri dari : unit 1.00
2 2x300 W Power Amplifier unit 1.00
3 7x300 W Power Amplifier unit 1.00
4 Radio Tunner AM/FM unit 1.00
5 Autorserve Cassete unit 1.00
progress
perubahan
NO JENIS PEKERJAAN SAT VOLUME

6 CD / DVD/MP3 - Playaer unit 1.00


7 Microphone unit 1.00
8 Equalizer unit 1.00
9 Mixer Frame w/ Module unit 1.00
10 Cabinet Rack unit 1.00
LANTAI 1
1 MDF bh 1.00
2 TBS-SB bh 1.00 1.00
3 Kabel dari MDF ke TSB-SB, NYHMY 3(3x2.5 mm2) m' 10.00 10.00
4 Ceiling Speaker 3 watt bh 8.00 8.00
5 Titik Instalasi Speaker, NYMHY 3x1,5 mm2 dalam conduit titik 8.00
LANTAI 2
1 MDF bh 1.00
2 TBS-SB bh 1.00
3 Kabel dari MDF ke TSB-SB, NYHMY 3(3x2.5 mm2) m' 10.00 10.00
4 Ceiling Speaker 3 watt bh 8.00 8.00
5 Titik Instalasi Speaker, NYMHY 3x1,5 mm2 dalam conduit titik 8.00
TOTAL PEKERJAAN TATA SUARA:
TOTAL PEKERJAAN MEP GEDUNG 1:

2 GEDUNG 2
I PEKERJAAN PENARIKAN & KONEKSI KABEL FEEDER
LANTAI 1
1 Dari MDP ke SDP LT.1 (NYY 4x6mm² + NYA 4mm²) m' 2.50
2 Dari MDP ke SDP LT.2 (NYY 4x6mm² + NYA 4mm²) m' 5.00
3 SDP LT. 1 ke Pan. Pen & SK (NYY 4x4mm² + NYA 2,5mm²) m' 2.50
4 SDP LT. 1 ke Panel AC (NYY 4x6mm² + NYA 4mm²) m' 2.50
LANTAI 2
1 SDP LT. 2 ke Pan. Pen & SK (NYY 4x4mm² + NYA 2,5mm²) m' 2.50
2 SDP LT. 2 ke Panel AC (NYY 4x6mm² + NYA 4mm²) m' 2.50
TOTAL PEKERJAAN PENARIKAN & KONEKSI KABEL FEEDER:

II PEKERJAAN PENERANGAN & STOP KONTAK


LANTAI 1
1 RMI 2 x 16W LED bh 18.00 -

2 Downlight 18W LED bh 17.00 38.00 39.00


3 Downlight 7W LED bh 2.00 2.00
4 Saklar tunggal bh 7.00
5 Saklar ganda bh 3.00
6 Stop kontak bh 33.00 39.00 33.00
7 Celling Exhaust Fan bh 2.00
8 Instalasi penerangan (NYM 3 x 2,5mm² dlm pipa conduit 20 Titik 37.00 41.00
9 Instalasi stop kontak (NYM 3 x 2,5mm² dlm pipa conduit 20 Titik 33.00 33.00
LANTAI 2
1 RMI 2 x 16W LED bh 14.00 - -

2 Downlight 18W LED bh 15.00 37.00 37.00

3 Downlight 7W LED bh 3.00 2.00


4 Saklar tunggal bh 3.00
5 Saklar ganda bh 6.00
6 Stop kontak/ Stop Kontak AC bh 19.00 20.00 20.00
7 Celling Exhaust Fan bh 2.00
8 Instalasi penerangan (NYM 3 x 2,5mm² dlm pipa conduit 20 titik 32.00 39.00 39.00
9 Instalasi stop kontak (NYM 3 x 2,5mm² dlm pipa conduit 20 titik 19.00 20.00 20.00
TOTAL PEKERJAAN PENERANGAN & STOP KONTAK:

III PEKERJAAN PLUMBING


Pekerjaan Instalasi Rooftank
1 Roof tank kap. 1000 liter bh 1.00
2 Pipa PVC AW Ø 2" (pipa kuras dan over flow rooftank) m' 10.00
3 Pipa PVC AW Ø 2" (pipa distribusi) m' 10.00
progress
perubahan
NO JENIS PEKERJAAN SAT VOLUME

4 Gate valve Ø 50mm (2") bh 1.00 2.00


LANTAI 1
Instalasi perpipaan distribusi air bersih
1 Pipa PVC AW Ø 2" (riser) m' 10.00
2 Pipa PVC AW Ø 2" m' 20.00 12.00
3 Pipa PVC AW Ø 3/4" m' 45.00 20.00
4 Pipa PVC AW Ø 1/2" m' 10.00 8.00
5 Gate valve Ø 50mm (2") bh 2.00 1.00
6 Fitting, support, hanger,dll ls 1.00
Instalasi perpipaan distribusi air bekas
1 Pipa PVC AW Ø 4" (riser) m' 10.00
2 Pipa PVC AW Ø 2,5" m' 22.00 12.00
3 Pipa PVC AW Ø 2" m' 20.50 8.00
4 Fitting, support, hanger,dll ls 1.00
Instalasi perpipaan distribusi air kotor
1 Pipa PVC AW Ø 4" (riser) m' 10.00
2 Pipa PVC D Ø 2" (riser vent) m' 10.00 8.00
3 Pipa PVC AW Ø 4" m' 7.50
4 Pipa PVC D Ø 2" vent m' 2.00
5 Fitting, support, hanger,dll ls 1.00
Instalasi perpipaan distribusi air hujan
1 Pipa PVC AW Ø 4" (riser) m' 20.00 52.00 52.00
LANTAI 2
Instalasi perpipaan distribusi air bersih
1 Pipa PVC AW Ø 2" (riser) m' 10.00
2 Pipa PVC AW Ø 2" m' 20.00 8.00
3 Pipa PVC AW Ø 3/4" m' 45.00 16.00
4 Pipa PVC AW Ø 1/2" m' 10.00 4.00
5 Gate valve Ø 50mm (2") bh 2.00
6 Fitting, support, hanger,dll ls 1.00
Instalasi perpipaan distribusi air bekas
1 Pipa PVC AW Ø 4" (riser) m' 10.00
2 Pipa PVC AW Ø 2,5" m' 22.00 12.00
3 Pipa PVC AW Ø 2" m' 20.50
4 Fitting, support, hanger,dll ls 1.00
Instalasi perpipaan distribusi air kotor
1 Pipa PVC AW Ø 4" (riser) m' 10.00
2 Pipa PVC D Ø 2" (riser vent) m' 10.00 8.00
3 Pipa PVC AW Ø 4" m' 7.50
4 Pipa PVC D Ø 2" vent m' 2.00
5 Fitting, support, hanger,dll ls 1.00
Instalasi perpipaan distribusi air hujan
1 Pipa PVC AW Ø 4" (riser) m' 20.00 52.00 52.00
TOTAL PEKERJAAN PLUMBING:

V PEKERJAAN TATA SUARA


LANTAI 1
1 MDF bh 1.00 1.00
2 TBS-SB bh 1.00
3 Kabel dari MDF ke TSB-SB, NYHMY 3(3x2.5 mm2) m' 10.00 10.00
4 Ceiling Speaker 3 watt bh 11.00 11.00
5 Titik Instalasi Speaker, NYMHY 3x1,5 mm2 dalam conduit titik 11.00
LANTAI 2
1 MDF bh 1.00
2 TBS-SB bh 1.00
3 Kabel dari MDF ke TSB-SB, NYHMY 3(3x2.5 mm2) m' 10.00 10.00
4 Ceiling Speaker 3 watt bh 11.00 11.00
5 Titik Instalasi Speaker, NYMHY 3x1,5 mm2 dalam conduit titik 11.00
TOTAL PEKERJAAN TATA SUARA:
TOTAL PEKERJAAN MEP GEDUNG 2:

3 GEDUNG 3
I PEKERJAAN PENARIKAN & KONEKSI KABEL FEEDER
Audiotorium
progress
perubahan
NO JENIS PEKERJAAN SAT VOLUME

1 Dari MDP ke SDP Audiotorium (NYY 4x6mm² + NYA 4mm²) m' 41.50 85.00 85.00
2 SDP LT. 1 ke Pan. Pen & SK (NYY 4x4mm² + NYA 2,5mm²) m' 2.50
3 SDP LT. 1 ke Panel AC (NYY 4x6mm² + NYA 4mm²) m' 2.50
TOTAL PEKERJAAN PENARIKAN & KONEKSI KABEL FEEDER:

II PEKERJAAN PENERANGAN & STOP KONTAK


LANTAI 1
1 RMI 2 x 16W LED bh 14.00 - -
2 Downlight 18W LED bh 18.00 31.00 31.00
3 Downlight 7W LED bh 4.00 2.00 2.00
4 Saklar tunggal bh 2.00 2.00
5 Saklar ganda bh 6.00 6.00
6 Stop kontak bh 12.00 12.00 12.00
7 Celling Exhaust Fan bh 3.00 3.00
8 Instalasi penerangan (NYM 3 x 2,5mm² dlm pipa conduit 20 Titik 36.00 33.00 33.00
9 Instalasi stop kontak (NYM 3 x 2,5mm² dlm pipa conduit 20 Titik 12.00 12.00 12.00
TOTAL PEKERJAAN PENERANGAN & STOP KONTAK:

III PEKERJAAN PLUMBING


LANTAI 1
Instalasi perpipaan distribusi air bersih
1 Pipa PVC AW Ø 2" (riser) m' 10.00
2 Pipa PVC AW Ø 2" m' 20.00 90.00
3 Pipa PVC AW Ø 3/4" m' 45.00
4 Pipa PVC AW Ø 1/2" m' 10.00
5 Gate valve Ø 50mm (2") bh 1.00
6 Fitting, support, hanger,dll ls 1.00
Instalasi perpipaan distribusi air bekas
1 Pipa PVC AW Ø 4" (riser) m' 10.00
2 Pipa PVC AW Ø 2,5" m' 15.00
3 Pipa PVC AW Ø 2" m' 15.00
4 Fitting, support, hanger,dll ls 1.00
Instalasi perpipaan distribusi air kotor
1 Pipa PVC AW Ø 4" (riser) m' 10.00
2 Pipa PVC D Ø 2" (riser vent) m' 10.00
3 Pipa PVC AW Ø 4" m' 7.50
4 Pipa PVC D Ø 2" vent m' 2.00
5 Fitting, support, hanger,dll ls 1.00
Instalasi perpipaan distribusi air hujan
1 Pipa PVC AW Ø 4" (riser) m' 20.00 40.00 56.00
TOTAL PEKERJAAN PLUMBING:

V PEKERJAAN TATA SUARA


LANTAI 1
1 MDF bh 1.00
2 TBS-SB bh 1.00 1.00
3 Kabel dari MDF ke TSB-SB, NYHMY 3(3x2.5 mm2) m' 10.00 10.00
4 Ceiling Speaker 3 watt bh 11.00 11.00 11.00
5 Titik Instalasi Speaker, NYMHY 3x1,5 mm2 dalam conduit titik 11.00
TOTAL PEKERJAAN TATA SUARA:
TOTAL PEKERJAAN MEP GEDUNG 3:

4 GEDUNG 4
I PEKERJAAN PENARIKAN & KONEKSI KABEL FEEDER
1 Dari MDP ke SDP Gedung 4 (NYY 4x6mm² + NYA 4mm²) m' 55.00
2 SDP LT. 1 ke Pan. Pen & SK (NYY 4x4mm² + NYA 2,5mm²) m' 2.50
3 SDP LT. 1 ke Panel AC (NYY 4x6mm² + NYA 4mm²) m' 2.50
TOTAL PEKERJAAN PENARIKAN & KONEKSI KABEL FEEDER:

II PEKERJAAN PENERANGAN & STOP KONTAK


LANTAI 1
1 RMI 2 x 16W LED bh 27.00 -

2 Downlight 18W LED bh 16.00 55.00 55.00


progress
perubahan
NO JENIS PEKERJAAN SAT VOLUME

3 Downlight 7W LED bh -
4 Saklar tunggal bh 1.00
5 Saklar ganda bh 8.00
6 Stop kontak bh 29.00 30.00 30.00
7 Celling Exhaust Fan bh -
8 Instalasi penerangan (NYM 3 x 2,5mm² dlm pipa conduit 20 Titik 43.00 55.00
9 Instalasi stop kontak (NYM 3 x 2,5mm² dlm pipa conduit 20 Titik 29.00 30.00
TOTAL PEKERJAAN PENERANGAN & STOP KONTAK:

III PEKERJAAN PLUMBING


LANTAI 1
Instalasi perpipaan distribusi air hujan
1 Pipa PVC AW Ø 4" (riser) m' 10.00 64.00 64.00
TOTAL PEKERJAAN PLUMBING:

V PEKERJAAN TATA SUARA


LANTAI 1
1 MDF bh 1.00
2 TBS-SB bh 1.00 1.00
3 Kabel dari MDF ke TSB-SB, NYHMY 3(3x2.5 mm2) m' 10.00 10.00
4 Ceiling Speaker 3 watt bh 13.00 13.00
5 Titik Instalasi Speaker, NYMHY 3x1,5 mm2 dalam conduit titik 13.00
TOTAL PEKERJAAN TATA SUARA:
TOTAL PEKERJAAN MEP GEDUNG 4:
TOTAL PEKERJAAN MEP SMP:
LL OF QUANTITY (BOQ)

OLAH MENEGAH PERTAMA (SMP)


keterangan

minimal pipa 4 inch 80 meter.

belum termasuk kantin

Pek kran leher angsa dan Kitchen zink


keterangan

Kabel feeder dr meteran pln ke MDP nyy 4 x 25mm + nya 4mm


nyy 4 x 16mm + nya 4mm
nyy 4 x 16mm + nya 4mm
nyy 4 x 6mm + nya 4mm
nyy 4 x 16mm + nya 4mm
nyy 4 x 2.5mm + nya 2.5mm
nyy 4 x 2.5mm

nyy 4 x 6mm + nya 4mm


nyy 4 x 16mm + nya 4mm
keterangan

ganti 1 inch

1 inch
1 inch

1 inch
1 inch

ganti 3 inch
3 inch
pipa 1 1/4 inch utk wastafel

13 titik x 4 meter

ganti 1 inch
1 inch

ganti 3 inch
3 inch

pipa 1 1/4 inch utk wastafel

13 titik x 4 meter

ampli 240 watt


ampli 240 watt
keterangan

hapus

hapus
hapus

hapus
hapus
hapus
hapus

hapus
hapus

1 inch
1 inch
keterangan

1 inch
1 inch

13 titik x 4 meter

13 titik x 4 meter

hapus

nymhy 2 x 2.5mm

hapus

nymhy 2 x 2.5mm
keterangan

ada
hapus
hapus

1 inch
1 inch

10 titik 3 inch + mendatar

hapus

nymhy 2 x 2.5mm

hapus
hapus
hapus
keterangan

16 titik 3 inch

hapus

nymhy 2 x 2.5mm
BILL OF QUANTITY (BOQ)
PEKERJAAN : REVITALISASI KAWASAN ISLAMIC CENTER KOTA PALOPO
LOKASI : KOTA PALOPO - SULAWESI SELATAN
TAHUN ANGGARAN : ###

GEDUNG SEKOLAH DASAR (SD)


keterangan JUMLAH HARGA
NO JENIS PEKERJAAN SAT VOLUME Perubahan progress
(Rp.)

B PEKERJAAN STRUKTUR
IV PEKERJAAN LAIN-LAIN
PEKERJAAN GWT DAN BIOFILTER
1 Pek. Galian tanah m3 22.88
2 Pek. Urugan kembali m3 4.50
3 Pek. Urugan Pasir m3 1.53
4 Pek. Lantai kerja t = 5 cm m3 0.76
5 GWT kapasitas 4 m3 unit 1.00
6 Septi tank biotek kap. 3 m3 unit 2.00
7 Instalasi septictank biotek lengkap lot 2.00 80.00 rugi. panjang pipa mungkin 80 meter 4 inch dihitung 1 lo
SUBTOTAL PEKERJAAN LAIN-LAIN :
TOTAL PEKERJAAN STRUKTUR :

D PEKERJAAN SANITASI

I PEKERJAAN ELEV. 0.00 - ELEV. 4.00


I.1. PEKERJAAN PASANG SANITASI
1 Pas. Closed duduk bh 8.00
2 Pek. Wastafel + accecories bh 4.00 6.00
4 Pek. Jet washer bh 8.00
5 Pek. Kran air bh 15.00 17.00 tambahan 4 di kantin, pengurangan di lap. upacara dr 3 m
6 Pek. Floordrain bh 11.00
8 Pek. Cermin bh 4.00 6.00
1.00 Pek kran leher angsa dan Kitchen zink
SUBTOTAL PEKERJAAN SANITASI LANTAI 1 :

II PEKERJAAN ELEV. 4.00 - ELEV. 8.00

II.1 PEKERJAAN PASANG SANITASI


1 Pas. Closed duduk bh 8.00
2 Pek. Wastafel + accecories bh 2.00 6.00
3 Pek. Jet washer bh 8.00
4 Pek. Kran air bh 7.00 8.00
5 Pek. Floordrain bh 10.00
6 Pek. Cermin bh 2.00 8.00

SUBTOTAL PEKERJAAN SANITASI LANTAI 2:


TOTAL PEKERJAAN SANITASI:

E PEKERJAAN MEKANIKAL ELEKTRIKAL DAN PLUMBING


I PEKERJAAN PANEL - PANEL & PERLENGKAPANNYA
LANTAI 1
1 Main Distribution Panel ( MDP ) unit 1.00 1.00
2 Panel Pompa Transfer unit 1.00 1.00
3 Sub Distribution Panel Lantai 1 (SDP L unit 1.00 1.00
keterangan JUMLAH HARGA
NO JENIS PEKERJAAN SAT VOLUME Perubahan progress
(Rp.)
4 Pan. Pen & SK lantai 1 unit 1.00 1.00
5 Panel Power AC lantai 1 unit 1.00 1.00
LANTAI 2
1 Sub Distribution Panel Lantai 1 (SDP L unit 1.00 1.00
2 Pan. Pen & SK lantai 2 unit 1.00 1.00
3 Panel Power AC lantai 2 unit 1.00 1.00
TOTAL PEKERJAAN PANEL-PANEL:

II PEKERJAAN GROUND SYSTEM


1 Grounding elektrikal include bak kont set 1.00
TOTAL PEKERJAAN GROUND SYSTEM:

III PEKERJAAN PENARIKAN & KONEKSI KABEL FEEDER


LANTAI 1
1 LVMDP eksisting ke MDP (NYY 4x240 m' 20.00 2.50 Kabel feeder dr meteran pln ke MDP nyy 4 x 25mm + nya
2 Dari MDP ke SDP LT.1 (NYY 4x6mm² m' 2.50 2.50 2.50 nyy 4 x 16mm + nya 4mm
3 Dari MDP ke SDP LT.2 (NYY 4x6mm² + m' 5.00 27.00 13.00 nyy 4 x 16mm + nya 4mm
4 SDP LT. 1 ke Pan. Pen & SK (NYY 4x4 m' 2.50 5.00 5.00 nyy 4 x 6mm + nya 4mm
5 SDP LT. 1 ke Panel AC (NYY 4x6mm² m' 2.50 2.50 2.50 nyy 4 x 16mm + nya 4mm
6 MDP ke panel pompa tranfer (NYY 4x m' 10.00 7.50 nyy 4 x 2.5mm + nya 2.5mm
7 Panel Pom. Transfer ke unit Pom. tra m' 10.00 10.00 nyy 4 x 2.5mm
LANTAI 2
1 SDP LT. 2 ke Pan. Pen & SK (NYY 4x4 m' 2.50 5.00 5.00 nyy 4 x 6mm + nya 4mm
2 SDP LT. 2 ke Panel AC (NYY 4x6mm² m' 2.50 2.50 2.50 nyy 4 x 16mm + nya 4mm
TOTAL PEKERJAAN PENARIKAN & KONEKSI KABEL FEEDER:

IV PEKERJAAN PENERANGAN & STOP KONTAK


LANTAI 1
1 RMI 2 x 16W LED bh 38.00 - -

2 Downlight 18W LED bh 57.00 127.00 127.00


3 Downlight 7W LED bh 8.00 8.00
4 Saklar tunggal bh 8.00
5 Saklar ganda bh 16.00
6 Stop kontak bh 51.00 49.00 49.00
7 Celling Exhaust Fan bh 8.00
8 Instalasi penerangan (NYM 3 x 2,5mm Titik 103.00 135.00 135.00
9 Instalasi stop kontak (NYM 3 x 2,5mm Titik 51.00 49.00 49.00
LANTAI 2
1 RMI 2 x 16W LED bh 44.00 - -

2 Downlight 18W LED bh 37.00 119.00 119.00


3 Downlight 7W LED bh 8.00 8.00
4 Saklar tunggal bh 4.00
5 Saklar ganda bh 19.00
6 Stop kontak/ Stop Kontak AC bh 48.00 51.00 51.00
7 Celling Exhaust Fan bh 8.00
8 Instalasi penerangan (NYM 3 x 2,5mm titik 89.00 127.00 127.00
9 Instalasi stop kontak (NYM 3 x 2,5mm titik 48.00 51.00 51.00
TOTAL PEKERJAAN PENERANGAN & STOP KONTAK:

V PEKERJAAN PLUMBING
Pekerjaan Pompa - Pompa dan Perlengkapannya
1 Pompa tranfer (GWT ke rooftank) unit 1.00
2 Pipa GIP Medium Ø 2" m' 5.00
3 Strainer Ø 50mm (2") bh 1.00
4 Flexsible joint Ø 50mm (2") bh 2.00
5 Check valve Ø 50mm (2") bh 1.00
6 Gate valve Ø 50mm (2") bh 2.00
7 Foot valve Ø 50mm (2") bh 1.00
8 Preasure gauge + ball valve bh 1.00
9 Suppot, fitting, hanger, cat dll. ls 1.00
Pekerjaan Instalasi Rooftank
1 Roof tank kap. 1000 liter bh 2.00
keterangan JUMLAH HARGA
NO JENIS PEKERJAAN SAT VOLUME Perubahan progress
(Rp.)
2 Pipa PVC AW Ø 2" (pipa kuras dan over m' 10.00
3 Pipa PVC AW Ø 2" (pipa distribusi) m' 10.00
4 Gate valve Ø 50mm (2") bh 2.00
LANTAI 1
Instalasi perpipaan distribusi air bersih
1 Pipa PVC AW Ø 2" (riser) m' 30.00 25.00 24.00 ganti 1 inch
2 Pipa PVC AW Ø 2" m' 60.00 163.50 120.00 1 inch
3 Pipa PVC AW Ø 3/4" m' 135.00 72.00 72.00
4 Pipa PVC AW Ø 1/2" m' 30.00 60.00 40.00
5 Gate valve Ø 50mm (2") bh 5.00 ganti 1 inch
6 Fitting, support, hanger,dll ls 1.00
Instalasi perpipaan distribusi air bekas
1 Pipa PVC AW Ø 4" (riser) m' 30.00 24.00 ganti 3 inch
2 Pipa PVC AW Ø 2,5" m' 59.00 48.00 ganti 3 inch
3 Pipa PVC AW Ø 2" m' 56.00 16.00 8.00
36.00 16.00 tambah pipa 1 1/4 inch
4 Fitting, support, hanger,dll ls 1.00
Instalasi perpipaan distribusi air kotor
1 Pipa PVC AW Ø 4" (riser) m' 30.00 24.00
2 Pipa PVC D Ø 2" (riser vent) m' 30.00 16.00
3 Pipa PVC AW Ø 4" m' 22.50 24.00
4 Pipa PVC D Ø 2" vent m' 6.00 6.00
5 Fitting, support, hanger,dll ls 1.00
Instalasi perpipaan distribusi air hujan
1 Pipa PVC AW Ø 4" (riser) m' 80.00 192.00 164.00 48 titik x 4 meter
LANTAI 2
Instalasi perpipaan distribusi air bersih
1 Pipa PVC AW Ø 2" (riser) m' 20.00 ganti 1 inch
2 Pipa PVC AW Ø 2" m' 41.00 24.00 1 inch
3 Pipa PVC AW Ø 3/4" m' 91.00 40.00
4 Pipa PVC AW Ø 1/2" m' 30.00 24.00
5 Gate valve Ø 50mm (2") bh 9.00 5.00 1 inch
6 Fitting, support, hanger,dll ls 1.00
Instalasi perpipaan distribusi air bekas
1 Pipa PVC AW Ø 4" (riser) m' 20.00 ganti 3 inch
2 Pipa PVC AW Ø 2,5" m' 44.00 32.00 ganti 3 inch
3 Pipa PVC AW Ø 2" m' 41.00 16.00
16.00 12.00 tambah pipa 1 1/4 inch
4 Fitting, support, hanger,dll ls 1.00
Instalasi perpipaan distribusi air kotor
1 Pipa PVC AW Ø 4" (riser) m' 20.00 20.00
2 Pipa PVC D Ø 2" (riser vent) m' 20.00 20.00
3 Pipa PVC AW Ø 4" m' 15.00 15.00
4 Pipa PVC D Ø 2" vent m' 4.00 4.00
5 Fitting, support, hanger,dll ls 1.00
Instalasi perpipaan distribusi air hujan
1 Pipa PVC AW Ø 4" (riser) m' 40.00 160.00 144.00 40 titik x 4 meter
TOTAL PEKERJAAN PLUMBING:

VI PEKERJAAN TATA SUARA


Peralatan Utama
1 Terminal Box Telepon Dan Data (IDF-C.1unit 1.00
2 2x300 W Power Amplifier unit 1.00 ampli 240 watt
3 7x300 W Power Amplifier unit 1.00 ampli 240 watt
4 Radio Tunner AM/FM unit 1.00
5 Autorserve Cassete unit 1.00
6 CD / DVD/MP3 - Playaer unit 1.00
7 Microphone unit 1.00 paging mic with chime
8 Equalizer unit 1.00
9 Mixer Frame w/ Module unit 1.00
10 Cabinet Rack unit 1.00
LANTAI 1
1 MDF bh 1.00 1.00
2 TBS-SB bh 1.00 hapus
3 Kabel dari MDF ke TSB-SB, NYHMY 3( m' 35.00 35.00 4rb/meter
keterangan JUMLAH HARGA
NO JENIS PEKERJAAN SAT VOLUME Perubahan progress
(Rp.)
4 Ceiling Speaker 3 watt bh 30.00 30.00
5 Titik Instalasi Speaker, NYMHY 3x1,5 titik 30.00 ganti kabel nymhy 2 x 2,5mm
LANTAI 2
1 MDF bh 1.00 hapus
2 TBS-SB bh 1.00 1.00
3 Kabel dari MDF ke TSB-SB, NYHMY 3( m' 35.00 35.00
4 Ceiling Speaker 3 watt bh 30.00 30.00
5 Titik Instalasi Speaker, NYMHY 3x1,5 titik 30.00 ganti kabel 2 x 2.5mm
TOTAL PEKERJAAN TATA SUARA: