Lokasi : KP.CIMEONG
HARGA
URAIAN VOLUME Satuan SATUAN JUMLAH (Rp.)
( Rp. )
I PEKERJAAN TPT
1 BAHAN
1.1 Semen PC/50 Kg 208.00 zak 66,000 13,728,000
1.2 Batu Belah 101 m3 225,000 22,725,000
1.3 Pasir pasang 32.00 m3 210,000 6,720,000
Jumlah 1) 43,173,000
2. ALAT
2.1 Papan Nama Kegiatan (60x80 cm) 1.00 bh 150,000 150,000
2.2 Prasasti Marmer 30 x 40 cm 1.00 bh 500,000 500,000
2.3 Ember 4.00 bh 26,000 104,000
2.4 Benang 15.00 bh 7,400 111,000
Jumlah 2) 865,000
3. UPAH
3.1 Pekerja 162.00 HOK 100,000 16,200,000
3.2 Tukang 63.00 HOK 120,000 7,560,000
Jumlah 3) 23,760,000
sub total I 1) + 2) + 3) 67,798,000
II Honor TPK
II.1 Honor Ketua 1.00 org 400,000 400,000
II.2 Honor Sekretaris 1.00 org 300,000 300,000
II.3 Honor Anggota 1.00 org 200,000 200,000
Sub Total II 900,000
TOTAL 68,698,000