RENCANA ANGGARAN BIAYA

Propinsi : Banten No.RAB : 01


Kabupaten/Kota : Pandeglang Lokasi : Kp. Cisereh
Kecamatan : Cisata Bidang : Pembangunan Desa
Desa : Cisereh Kegiatan : Jalan Beton
Volume : 50 x3x0.2 m

Volume Jumlah Total (Rp)


Kategori Harga Satuan
URAIAN Satuan Dana Desa Swadaya
Dana Desa Swadaya Biaya
(Rp) (Rp) (Rp)
a b c d e f g=bxf h=cxf
1. BAHAN
1.1 Beton Ready Mix K-250 30.00 - M3 I-a 960,000 28,800,000 -
1.2 Batu Scroop 45.00 M3 250,000 11,250,000
1.3 Bekisting 34.00 lb 35,000 1,190,000
1.4 paku 6.00 kg 25,500 153,000
1.5 Plastik Cor 150 m2 6,000.00 900,000
Sub Total 1) 42,293,000 -
2. PERALATAN
2.1 Prasasti 1.00 - Bh II.b. 500,000 500,000 -
2.2 Papan Proyek 1.00 Bh II.b. 150,000 150,000
2.3 Benang/Tali Rafia 16.00 Gol I-b 10,000 160,000
Sub Total 2) 810,000 -
3. UPAH
3.1 Pekerja 173.00 HOK III - a 95,000 16,435,000 -
3.2 Tukang 42.00 - HOK III - a 110,000 4,620,000 -

-
Sub Total 3) 21,055,000 -
II TPK
1 Ketua 1 org 400,000.00 400,000
2 Anggota 1 org 300,000.00 300,000
3 Anggota 1 org 200,000.00 200,000
Sub Total II 900,000
Total Biaya Kontruksi 65,058,000
Total Biaya Prasarana 65,058,000
Pembulatan 65,058,000
Harga sudah termasuk PPN & PPH
Keterangan :
Kategori Biaya :
I-a Pembelian bahan hasil tenaga manusia
I-b Pembelian bahan hasil industri
II-a Pembelian alat tangan
II-b Pembelian / penyewaan alat mesin
III-a Pembayaran tenaga kerja untuk konstruksi
III-b Pembayaran tenaga untuk pengumpulan bahan
…………, Maret 2022

Disetujui oleh: Diverifikasi Oleh: Dibuat Oleh:


Kepala Desa Cisereh Sekretaris Desa Ketua TPK

Rohman Deni Kusnadi