JUMLAH HARGA
NO URAIAN PEKERJAAN
( Rp. )
Terbilang : Empat Puluh Tujuh Juta Sembilan Ratus Lima Puluh Ribu Rupiah
DIBUAT OLEH :
PEJABAT PEMBUAT KOMITMEN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
KOTA TARAKAN
I PEKERJAAN PENDAHULUAN
1 #REF! 1.00 Bh 250,000.00 250,000.00
2 Dokumentasi Kegiatan dan Pelaporan 1.00 Ls 500,000.00 500,000.00
3 Pasang Rambu Kegiatan 2.00 Bh 150,000.00 300,000.00
4 Biaya Penyelenggaran K3 1.00 Ls 690,800.00 690,800.00
Sub Jumlah I 1,740,800.00
URAIAN VOLUME
NO URAIAN PELAKSANAAN VOLUME VOLUME
A Tenaga Kerja
1 Pekerja L.01 OH 0.5630 115,000.00 64,745.00
2 Mandor L.04 OH 0.0563 165,000.00 9,289.50
B Bahan
C Peralatan
A Tenaga Kerja
1 Pekerja L.01 OH 3.3780 115,000.00 388,470.00
2 Mandor L.04 OH 0.3378 165,000.00 55,737.00
B Bahan
C Peralatan
A Tenaga Kerja
1 Pekerja L.01 OH 2.7000 115,000.00 310,500.00
2 Tukang L.02 OH 0.9000 135,000.00 121,500.00
3 Kepala Tukang L.03 OH 0.0900 150,000.00 13,500.00
4 Mandor L.04 OH 0.2700 165,000.00 44,550.00
B Bahan
1 Batu Gunung M.05 M3 1.2000 575,000.00 690,000.00
2 Pasir Pasangan M.14.b M3 0.5200 140,000.00 72,800.00
3 Semen M.15 Kg 163.0000 1,480.00 241,240.00
C Peralatan
1 Molen E.28.b Unit/hari 0.16700 300,000.00 50,100.00
A Tenaga Kerja
1 Pekerja L.01 OH 1.5000 115,000.00 172,500.00
2 Tukang L.02 OH 0.7500 135,000.00 101,250.00
3 Kepala Tukang L.03 OH 0.0750 150,000.00 11,250.00
4 Mandor L.04 OH 0.0750 165,000.00 12,375.00
B Bahan
1 Batu Gunung M.05 M3 1.2000 575,000.00 690,000.00
2 Pasir Pasangan M.14.b M3 0.5200 140,000.00 72,800.00
3 Semen M.15 Kg 163.0000 1,480.00 241,240.00
C Peralatan
A Tenaga Kerja
1 Pekerja L.01 OH 0.3840 115,000.00 44,160.00
2 Tukang L.02 OH 0.1920 135,000.00 25,920.00
3 Kepala Tukang L.03 OH 0.0190 150,000.00 2,850.00
4 Mandor L.04 OH 0.0380 165,000.00 6,270.00
B Bahan
1 Pasir Pasangan M.14.b M3 0.0240 140,000.00 3,360.00
2 Semen M.15 Kg 6.2800 1,480.00 9,294.40
C Peralatan
A Tenaga Kerja
1 Pekerja L.01 OH 1.6500 115,000.00 189,750.00
2 Tukang L.02 OH 0.2750 135,000.00 37,125.00
3 Kepala Tukang L.03 OH 0.0280 150,000.00 4,200.00
4 Mandor L.04 OH 0.1650 165,000.00 27,225.00
B Bahan
1 Semen M.14.b Kg 326.0000 1,480.00 482,480.00
2 Pasir M.15 Kg 760.0000 95.89 72,876.71
3 Batu Pecah 2/3 M.12 Kg 1,029.0000 333.33 343,000.00
4 Air M.02 Liter 215.0000 59.58 12,810.42
C Peralatan
A Tenaga Kerja
1 Pekerja L.01 OH 1.3230 115,000.00 152,145.00
2 Tukang L.02 OH 0.1890 135,000.00 25,515.00
3 Kepala Tukang L.03 OH 0.0190 150,000.00 2,850.00
4 Mandor L.04 OH 0.1320 165,000.00 21,780.00
B Bahan
1 Semen M.14.b Kg 326.0000 1,480.00 482,480.00
2 Pasir M.15 Kg 760.0000 95.89 72,876.71
3 Batu Pecah 2/3 M.12 Kg 1,029.0000 333.33 343,000.00
4 Air M.02 Liter 215.0000 59.58 12,810.42
C Peralatan
1 Molen M.28.b Sewa-Hari 0.2500 300,000.00 75,000.00
A Tenaga Kerja
1 Pekerja L.01 OH 1.6500 115,000.00 189,750.00
2 Tukang L.02 OH 0.2750 135,000.00 37,125.00
3 Kepala Tukang L.03 OH 0.0280 150,000.00 4,200.00
4 Mandor L.04 OH 0.1650 165,000.00 27,225.00
B Bahan
1 Semen M.14.b Kg 371.0000 1,480.00 549,080.00
2 Pasir M.15 Kg 698.0000 95.89 66,931.51
3 Batu Pecah 2/3 M.12 Kg 1,047.0000 333.33 349,000.00
4 Air M.02 Liter 215.0000 59.58 12,810.42
C Peralatan
A Tenaga Kerja
1 Pekerja L.01 OH 1.0000 115,000.00 115,000.00
2 Tukang L.02 OH 0.2500 135,000.00 33,750.00
3 Kepala Tukang L.03 OH 0.0250 150,000.00 3,750.00
4 Mandor L.04 OH 0.0500 165,000.00 8,250.00
B Bahan
1 Semen M.14.b Kg 371.0000 1,480.00 549,080.00
2 Pasir M.15 Kg 698.0000 95.89 66,931.51
3 Batu Pecah 2/3 M.12 Kg 1,047.0000 333.33 349,000.00
4 Air M.02 Liter 215.0000 59.58 12,810.42
C Peralatan
1 Molen M.28.b Sewa-Hari 0.2380 300,000.00 71,400.00
A Tenaga Kerja
1 Pekerja L.01 OH 0.2000 115,000.00 23,000.00
2 Tukang L.02 OH 0.1000 135,000.00 13,500.00
3 Kepala Tukang L.03 OH 0.0100 150,000.00 1,500.00
4 Mandor L.04 OH 0.0200 165,000.00 3,300.00
B Bahan
1 Multiflex 9 mm* M.35.e Lembar 0.2030 170,000.00 34,510.00
2 Kaso meranti 5/7 cm* M.37.a M3 0.0080 2,700,000.00 21,600.00
3 Paku biasa M.65.b Kg 0.2200 20,000.00 4,400.00
4 Minyak bekisting M.129 Ltr 0.2000 11,000.00 2,200.00
C Peralatan
A Tenaga Kerja
1 Pekerja L.01 OH 0.3000 115,000.00 34,500.00
2 Tukang L.02 OH 0.1500 135,000.00 20,250.00
3 Kepala Tukang L.03 OH 0.0150 150,000.00 2,250.00
4 Mandor L.04 OH 0.0300 165,000.00 4,950.00
B Bahan
1 Kaso Meranti 5/7 cm* M.37.a M3 0.0350 2,700,000.00 94,500.00
2 Paku biasa M.65.b Kg 0.2500 20,000.00 5,000.00
C Peralatan
A Tenaga Kerja
1 Pekerja L.01 OH 0.3600 115,000.00 41,400.00
2 Tukang L.02 OH 0.3600 135,000.00 48,600.00
3 Kepala Tukang L.03 OH 0.0360 150,000.00 5,400.00
4 Mandor L.04 OH 0.0360 165,000.00 5,940.00
B Bahan
1 Multiflex 9 mm* M.35.e Lembar 0.2030 170,000.00 34,510.00
2 Kaso meranti 5/7 cm* M.37.a M3 0.0090 2,700,000.00 24,300.00
3 Paku biasa M.65.b Kg 0.2400 20,000.00 4,800.00
4 Minyak bekisting M.129 Ltr 0.2000 11,000.00 2,200.00
C Peralatan
B Bahan
C Peralatan
B Bahan
1 Besi Beton Polos M.55.d Kg 1.0500 14,000.00 14,700.00
2 Kawat Ikat M.60 Kg 0.0150 27,390.00 410.85
C Peralatan
A Tenaga Kerja
1 Pekerja L.01 OH 0.0070 115,000.00 805.00
2 Tukang L.02 OH 0.0070 135,000.00 945.00
3 Kepala Tukang L.03 OH 0.0007 150,000.00 105.00
4 Mandor L.04 OH 0.0007 165,000.00 115.50
B Bahan
1 Besi Beton Ulir M.55.d Kg 1.0500 15,000.00 15,750.00
2 Kawat Ikat M.60 Kg 0.0150 27,390.00 410.85
C Peralatan
Jenis
No. Kode Satuan Harga Satuan Keterangan
Upah, Bahan dan Peralatan
1 2 3 4 5 6
UPAH
1 Pekerja L.01 OH 115,000.00 16,428.57 Per Jam
2 Tukang L.02 OH 135,000.00 19,285.71 Per Jam
3 Kepala Tukang L.03 OH 150,000.00 21,428.57 Per Jam
4 Mandor L.04 OH 165,000.00 23,571.43 Per Jam
BAHAN
1 Pasir Pasang M.14.b M3 140,000.00 95.89 Per Kg (BJ. 1460 Kg/M3)
2 Tanah Timbunan Biasa M.17.b M3 66,000.00
3 Batu Gunung/Batu Belah M.06.a M3 575,000.00 383.33 Per Kg (BJ. 1500 Kg/M3)
4 Batu Pecah / Kerikil 2/3 M.12 M3 525,000.00 333.33 Per Kg (BJ. 1575 Kg/M3)
5 Semen (50 Kg) M.15 Zak 74,000.00 1,480.00 Per Kg (1 Zak = 50 Kg)
6 Air M.02 Profil 71,500.00 59.58 Liter ( 1 Profil = 1200 ltr)
7 Paku Biasa M.71.b Kg 20,000.00
8 Paku Ulin Kg 30,000.00
9 Baut Æ12mm-Panjang 20cm Bh 10,000.00
10 Papan Meranti M.35.e M3 2,700,000.00
11 Balok Meranti M.37.a M3 2,700,000.00
12 Papan Keruing M3 3,200,000.00
13 Balok Keruing M3 3,200,000.00
14 Papan Lembasung/Bengkirai M3 5,000,000.00
15 Balok Lembasung/Bengkirai M3 5,000,000.00
16 Balok Ulin M3 8,000,000.00
17 Kayu Dolken Æ8-10 cm Panjang 4m Btg 17,000.00
18 Multiflex 9 mm Lembar 170,000.00
19 Pipa PVC Æ 2" M.107 Batang 75,000.00
20 Besi Beton Polos M.55.d Kg 14,000.00
21 Besi Beton Ulir M.55.e Kg 15,000.00
22 Kawat Ikat/Bendrat M.60 Kg 27,390.00
23 Minyak Bekisting M.129 Liter 11,000.00
24 Pancang Beton 10/10 x 150 cm M.31.a Btg 140,000.00
25 Pancang Beton 10/10 x 200 cm M.31.b Btg 176,000.00
26 Pancang Beton 10/10 x 400 cm M.31.c Btg 310,000.00
PERALATAN
1 Concrete Mixer / Molen E.28.b Sewa-Hari 300,000.00
1 Excavator E.11.b Jam 600,000.00
3 Dump Truck Jam 375,000.00
4 Jack Hammer E.13 Sewa-Hari 1,200,000.00
5 Generator Set (Genset)
- 2 KVA Sewa-Hari 275,000.00
- 20 KVA Sewa-Hari 600,000.00