PR Material Tangga Gudang Handak

No. Material Description Qty Unit Est. Unit Price Total price
1 Besi UNP 125 X 65 X 6mm, panjang 6 meter 6 ea 1,500,000 9,000,000
2 Besi hollow 40 x 40 x 2mm, panjang 6 meter 12 ea 355,000 4,260,000
3 Steel Grating Plate 90 cm x 6 meter, load bar size 23 x 1 ea 7,000,000 7,000,000
3 mm, Serrated surface
4 Stud Bolt nut 1/2 inch 16 ea 120,000 1,920,000
5 Cat Meni Besi + Thiner 5 ea 95,000 475,000
6 Cat Besi Top Coat + Thiner 5 ea 95,000 475,000
Total 23,130,000
Owner Estimate
Pembangunan Pos Jaga Mess (Guest House) 1,5 x 2 meter
No. Material Description Qty Unit Est. Unit Price Total price
1 Baja Ringan C75.100 20 btg 175,000 3,500,000
2 GRC board 4mm 7 Ea 85,000 595,000
3 Atap spandek 4 Ea 95,000 380,000
4 Baut drill Baja Ringan 1 kotak 375,000 375,000
5 Kusen + Jendela Almunium 120x100cm slidding 1 Set 1,600,000 1,600,000
6 Kusen + Jendela Almunium 100x700cm fixed 1 Set 850,000 850,000
7 Kusen + Jendela Almunium 120x100cm fixed 1 Set 1,400,000 1,400,000
8 Kusen pintu almunium 1 Set 2,100,000 2,100,000
9 Rockwoll sheet heat insulation 1 Set 1,500,000 1,500,000
10 Melamin Board 6mm 7 Ea 275,000 1,925,000
11 Taco Vinnyl flooring cover 3 m2 225,000 675,000
12 Cat dinding Setara jotun/Dulux/Mowilex 10 Liter 95,000 950,000
13 Talang pembuangan air hujan material pipa 2,5" 1 Set 350,000 350,000
14 Instalasi elektrikal 1 Set 750,000 750,000
15 Cor Lantai 1 : 2 : 3 1.00 Ls 1,250,000 1,250,000
Total 18,200,000
No Nama Lokasi/Area/Field Jenis Jumlah Tinggi Wire Sling Bolt Nut
(m) (ea)
Triangel T 1 32 meter
1 Medco Office Tarakan (MOT) Singel Pole 1 6 meter

Singel Pole 4 20 meter


2 Stasiun Pengumpul Gas G8 Menara tri 1 20 meter

Singel pole 3 20 meter


Singel Pole 1 15 meter
3 Stasiun North Mamburungan 5
Menara 1 18 meter

Singel pole 3 20 meter


Singel Pole 1 15 meter
4 Stasiun Sub Satelit Mamburungan 12
Menara 2 18 meter

Singel pole 5 20 meter


5 Gudang Handak Menara -

Singel pole 3 15 & 20 meter


6 Warehouse Pamusian dock
Menara 1 12 meter
Coating Spesifict Repairing
Jadwal Rencana Kerja
Pemasangan Uditch Tanjakan M12

Jadwal Rencana Kerja


No Uraian Kegiatan
Rabu Kamis Jumat Sabtu
1 Persiapan material batu untuk hamparan lantai kerja uditch
2 Penggalian Saluran Shelter Firehydrant
3 Fabrikasi Grill Cover Uditch
4 Mobilisasi (Stock Material Udicth)
5 Penggalian Tanah Saluran Crossing
6 Instalasi Beton Uditch Saluran
7 Pemasangan Grill Cover
8 Galian Tanah Saluran Box Culvert
Frame 1
p j t
2 4 16 m
2.3 7 32.2 m
48.2 8.033333 btg
Frame 2
1.35 4 10.8 m
2.3 5 23 m
33.8 5.633333 btg

atap
5 btg