PROYEK PEMBANGUNAN FASILITAS PERKERETAAPIAN UNTUK MANGGARAI S/D JATINEGARA (PAKET A)(TAHAP II)
"PEKERJAAN MAIN LINE II"
KONSULTAN KONTRAKTOR
KEPALA DIVISI TEKNIS PENGEMBANGAN DOUBLE - DOUBLE DAYACIPTA - LAUDZA - SCALARINDO KSO WASKITA - UTAMA KSO
TRACK (PAKET A)
Uraian :
Volume Keterangan
No. Uraian Satuan
Kontrak RFI (Data Lokasi / Layout )
1 Structure Excavation with Support M3 22,612.53 6,035.74 Terlampir
Komentar Konsultan :
DIREKTORAT JENDERAL PERKERETAAPIAN
BALAI TEKNIK PERKERETAAPIAN WILAYAH JAKARTA DAN BANTEN
KEGIATAN PENGEMBANGAN DOUBLE-DOUBLE TRACK
PROYEK PEMBANGUNAN FASILITAS PERKERETAAPIAN UNTUK MANGGARAI S/D JATINEGARA (PAKET A)(TAHAP II)
"PEKERJAAN MAIN LINE II"
KONSULTAN KONTRAKTOR
KEPALA DIVISI TEKNIS PENGEMBANGAN DOUBLE - DOUBLE DAYACIPTA - LAUDZA - SCALARINDO KSO WASKITA - UTAMA KSO
TRACK (PAKET A)
Uraian :
Volume Keterangan
No. Uraian Satuan
Kontrak RFI (Data Lokasi / Layout )
1 Cast-In Place Concrete Pile (Dia. 1200mm) M' 15,112.00 3,498.00 Terlampir
Komentar Konsultan :
DIREKTORAT JENDERAL PERKERETAAPIAN
BALAI TEKNIK PERKERETAAPIAN WILAYAH JAKARTA DAN BANTEN
KEGIATAN PENGEMBANGAN DOUBLE-DOUBLE TRACK
PROYEK PEMBANGUNAN FASILITAS PERKERETAAPIAN UNTUK MANGGARAI S/D JATINEGARA (PAKET A)(TAHAP II)
"PEKERJAAN MAIN LINE II"
KONSULTAN KONTRAKTOR
KEPALA DIVISI TEKNIS PENGEMBANGAN DOUBLE - DOUBLE DAYACIPTA - LAUDZA - SCALARINDO KSO WASKITA - UTAMA KSO
TRACK (PAKET A)
Uraian :
Volume Keterangan
No. Uraian Satuan
Kontrak RFI (Data Lokasi / Layout )
1 Concrete Pile Load Test Ls 2.00 1.00 Terlampir
Komentar Konsultan :
DIREKTORAT JENDERAL PERKERETAAPIAN
BALAI TEKNIK PERKERETAAPIAN WILAYAH JAKARTA DAN BANTEN
KEGIATAN PENGEMBANGAN DOUBLE-DOUBLE TRACK
PROYEK PEMBANGUNAN FASILITAS PERKERETAAPIAN UNTUK MANGGARAI S/D JATINEGARA (PAKET A)(TAHAP II)
"PEKERJAAN MAIN LINE II"
KONSULTAN KONTRAKTOR
KEPALA DIVISI TEKNIS PENGEMBANGAN DOUBLE - DOUBLE DAYACIPTA - LAUDZA - SCALARINDO KSO WASKITA - UTAMA KSO
TRACK (PAKET A)
Uraian :
Volume Keterangan
No. Uraian Satuan
Kontrak RFI (Data Lokasi / Layout )
1 Concrete Class A M3 5,204.36 368.22 Terlampir
Komentar Konsultan :
DIREKTORAT JENDERAL PERKERETAAPIAN
BALAI TEKNIK PERKERETAAPIAN WILAYAH JAKARTA DAN BANTEN
KEGIATAN PENGEMBANGAN DOUBLE-DOUBLE TRACK
PROYEK PEMBANGUNAN FASILITAS PERKERETAAPIAN UNTUK MANGGARAI S/D JATINEGARA (PAKET A)(TAHAP II)
"PEKERJAAN MAIN LINE II"
KONSULTAN KONTRAKTOR
KEPALA DIVISI TEKNIS PENGEMBANGAN DOUBLE - DOUBLE DAYACIPTA - LAUDZA - SCALARINDO KSO WASKITA - UTAMA KSO
TRACK (PAKET A)
Uraian :
Volume Keterangan
No. Uraian Satuan
Kontrak RFI (Data Lokasi / Layout )
1 Concrete Class B M3 19,734.78 4,008.87 Terlampir
Komentar Konsultan :
DIREKTORAT JENDERAL PERKERETAAPIAN
BALAI TEKNIK PERKERETAAPIAN WILAYAH JAKARTA DAN BANTEN
KEGIATAN PENGEMBANGAN DOUBLE-DOUBLE TRACK
PROYEK PEMBANGUNAN FASILITAS PERKERETAAPIAN UNTUK MANGGARAI S/D JATINEGARA (PAKET A)(TAHAP II)
"PEKERJAAN MAIN LINE II"
KONSULTAN KONTRAKTOR
KEPALA DIVISI TEKNIS PENGEMBANGAN DOUBLE - DOUBLE DAYACIPTA - LAUDZA - SCALARINDO KSO WASKITA - UTAMA KSO
TRACK (PAKET A)
Uraian :
Volume Keterangan
No. Uraian Satuan
Kontrak RFI (Data Lokasi / Layout )
1 Concrete Class F M3 680.97 115.41 Terlampir
Komentar Konsultan :
DIREKTORAT JENDERAL PERKERETAAPIAN
BALAI TEKNIK PERKERETAAPIAN WILAYAH JAKARTA DAN BANTEN
KEGIATAN PENGEMBANGAN DOUBLE-DOUBLE TRACK
PROYEK PEMBANGUNAN FASILITAS PERKERETAAPIAN UNTUK MANGGARAI S/D JATINEGARA (PAKET A)(TAHAP II)
"PEKERJAAN MAIN LINE II"
KONSULTAN KONTRAKTOR
KEPALA DIVISI TEKNIS PENGEMBANGAN DOUBLE - DOUBLE DAYACIPTA - LAUDZA - SCALARINDO KSO WASKITA - UTAMA KSO
TRACK (PAKET A)
Uraian :
Volume Keterangan
No. Uraian Satuan
Kontrak RFI (Data Lokasi / Layout )
1 Reinforce Bar kg 3,626,869.61 754,383.54 Terlampir
Komentar Konsultan :
DIREKTORAT JENDERAL PERKERETAAPIAN
BALAI TEKNIK PERKERETAAPIAN WILAYAH JAKARTA DAN BANTEN
KEGIATAN PENGEMBANGAN DOUBLE-DOUBLE TRACK
PROYEK PEMBANGUNAN FASILITAS PERKERETAAPIAN UNTUK MANGGARAI S/D JATINEGARA (PAKET A)(TAHAP II)
"PEKERJAAN MAIN LINE II"
KONSULTAN KONTRAKTOR
KEPALA DIVISI TEKNIS PENGEMBANGAN DOUBLE - DOUBLE DAYACIPTA - LAUDZA - SCALARINDO KSO WASKITA - UTAMA KSO
TRACK (PAKET A)
Uraian :
Volume Keterangan
No. Uraian Satuan
Kontrak RFI (Data Lokasi / Layout )
1 Prestress Concrete Wire kg 607,994.56 13,170.93 Terlampir
Komentar Konsultan :
DIREKTORAT JENDERAL PERKERETAAPIAN
BALAI TEKNIK PERKERETAAPIAN WILAYAH JAKARTA DAN BANTEN
KEGIATAN PENGEMBANGAN DOUBLE-DOUBLE TRACK
PROYEK PEMBANGUNAN FASILITAS PERKERETAAPIAN UNTUK MANGGARAI S/D JATINEGARA (PAKET A)(TAHAP II)
"PEKERJAAN MAIN LINE II"
KONSULTAN KONTRAKTOR
KEPALA DIVISI TEKNIS PENGEMBANGAN DOUBLE - DOUBLE DAYACIPTA - LAUDZA - SCALARINDO KSO WASKITA - UTAMA KSO
TRACK (PAKET A)
Uraian :
Volume Keterangan
No. Uraian Satuan
Kontrak RFI (Data Lokasi / Layout )
1 Pipe Drain Type D for Bridge Segmen m 2,628.62 639.35 Terlampir
Komentar Konsultan :
DIREKTORAT JENDERAL PERKERETAAPIAN
BALAI TEKNIK PERKERETAAPIAN WILAYAH JAKARTA DAN BANTEN
KEGIATAN PENGEMBANGAN DOUBLE-DOUBLE TRACK
PROYEK PEMBANGUNAN FASILITAS PERKERETAAPIAN UNTUK MANGGARAI S/D JATINEGARA (PAKET A)(TAHAP II)
"PEKERJAAN MAIN LINE II"
KONSULTAN KONTRAKTOR
KEPALA DIVISI TEKNIS PENGEMBANGAN DOUBLE - DOUBLE DAYACIPTA - LAUDZA - SCALARINDO KSO WASKITA - UTAMA KSO
TRACK (PAKET A)
Uraian :
Volume Keterangan
No. Uraian Satuan
Kontrak RFI (Data Lokasi / Layout )
1 Double Slip Switch Removal set 6.00 2.00 Terlampir
Komentar Konsultan :
DIREKTORAT JENDERAL PERKERETAAPIAN
BALAI TEKNIK PERKERETAAPIAN WILAYAH JAKARTA DAN BANTEN
KEGIATAN PENGEMBANGAN DOUBLE-DOUBLE TRACK
PROYEK PEMBANGUNAN FASILITAS PERKERETAAPIAN UNTUK MANGGARAI S/D JATINEGARA (PAKET A)(TAHAP II)
"PEKERJAAN MAIN LINE II"
KONSULTAN KONTRAKTOR
KEPALA DIVISI TEKNIS PENGEMBANGAN DOUBLE - DOUBLE DAYACIPTA - LAUDZA - SCALARINDO KSO WASKITA - UTAMA KSO
TRACK (PAKET A)
Uraian :
Volume Keterangan
No. Uraian Satuan
Kontrak RFI (Data Lokasi / Layout )
1 Pipe drain Type D m 130.80 130.80 Terlampir
Komentar Konsultan :
DIREKTORAT JENDERAL PERKERETAAPIAN
BALAI TEKNIK PERKERETAAPIAN WILAYAH JAKARTA DAN BANTEN
KEGIATAN PENGEMBANGAN DOUBLE-DOUBLE TRACK
PROYEK PEMBANGUNAN FASILITAS PERKERETAAPIAN UNTUK MANGGARAI S/D JATINEGARA (PAKET A)(TAHAP II)
"PEKERJAAN MAIN LINE II"
KONSULTAN KONTRAKTOR
KEPALA DIVISI TEKNIS PENGEMBANGAN DOUBLE - DOUBLE DAYACIPTA - LAUDZA - SCALARINDO KSO WASKITA - UTAMA KSO
TRACK (PAKET A)
Uraian :
Volume Keterangan
No. Uraian Satuan
Kontrak RFI (Data Lokasi / Layout )
1 Cleaning And Grubbing m 5,367.31 5,367.31 Terlampir
Komentar Konsultan :