REKLAMASI DAN PENGERUKAN New
REKLAMASI DAN PENGERUKAN New
Disusun oleh :
HARIS PRIONO (D1111191005)
DITYA AMANDA PRATIWI (D1111191023)
1
DAFTAR ISI
BAB 1........................................................................................................................................4
PENDAHULUAN........................................................................................................................4
1.1 Latar belakang...............................................................................................................4
1.2 Tujuan............................................................................................................................5
1.3 Rumusan Masalah.........................................................................................................5
BAB 2........................................................................................................................................6
2.1 Menentukan Desain Bentuk Dan Ukuran Reklamasi....................................................6
2.2 Menentukan Lokasi Quarry...........................................................................................6
2.3 Perencanaan Jangka Waktu Pelaksanaan.....................................................................8
2.4 Data Perhitungan Primer Settlement............................................................................9
2.5 Analisa Perhitungan Primer Settlement Bawah..........................................................10
b. Menghitung σ'0 ( kN/m2 )......................................................................................11
d. Menghitung ∆σ' = y ' × H × 2I Pada Lapisan 2..................................................14
e. Menghitung ∆σ' = y ' × H × 2I Pada Lapisan 3..................................................15
f. Menghitung ∆σ' = y ' × H × 2I Pada Lapisan 4..................................................16
g. Menghitung Hx Cc 1+e 0 log σ ' 0+∆ σ ' σ ' 0 Pada Lapisan 1...........................19
h. Menghitung Hx Cc 1+e 0 log σ ' 0+∆ σ ' σ ' 0 Pada Lapisan 2...........................21
i. Menghitung Hx Cc 1+e 0 log σ ' 0+∆ σ ' σ ' 0 Pada Lapisan 3...........................24
2.6 Data Perhitungan Immediate Settlement (Si) Bawah...................................................36
2.7 Analisa Perhitungan Immediate Settlement Bawah.....................................................37
a. Menghitung y' (kN/m3 )........................................................................................37
b. Menghitung Immediate Settlement...........................................................................39
c. Menghitung HR-H..................................................................................................40
h. Menghitung Pada Lapisan 1...........................46
k. Menghitung Pada Lapisan 2..........................48
.......................................................................................................................................48
l. Menghitung Immediate Settlement (Si)..............................................................50
2.8 Rangkuman Tabel Perhitungan Settlement Total (St)..................................................53
a. Menghitung Settlement Total (St).........................................................................54
1
b. Menghitung HR-H..................................................................................................54
BAB 3......................................................................................................................................55
3.1 Kesimpulan...................................................................................................................55
a. Perhitungan Primer Settlement (Scp).........................................................................55
3.2 Saran............................................................................................................................56
2
BAB 1
PENDAHULUAN
1.1 Latar belakang
Reklamasi adalah salah satu upaya yang dilakukan dalam pembangunan.
Reklamasi dapat diartikan sebagai upaya pengadaan lahan dengan cara
mengeringkan rawa, daerah pasang surut dan sebagainya (Peterson, 2005).
Reklamasi menjadi alasan utama dalam pemekaran kota sehingga alternatif
reklamasi pantai dilakukan karena berbagai alasan berkaitan dari pertambahan
penduduk alami maupun migrasi dan kesejahteraan penduduk yang miskin
mendorong mereka yang semula tinggal di tengah kota memilih ke daerah
pinggiran atau tempat baru untuk dapat memulai usaha demi meningkatkan
kesejahteraannya serta penyebaran keramaian kota, semula semua kegiatan
terpusat di kota sehingga dibutuhkan ruang baru untuk menampung semua
kegiatan yang mana tidak bisa difasilitasi dalam kota (Departemen Kelautan dan
Perikanan, 2001:19).
Reklamasi merupakan subsistem dari sistem pantai. Reklamasi pantai
merupakan upaya teknologi yang dilakukan manusia untuk merubah suatu
lingkungan alam menjadi lingkungan buatan, suatu tipologi ekosistem estuaria,
mangrove dan terumbu karang menjadi suatu bentang alam daratan (Maskur,
2008). Ruang lingkup Undang – Undang No. 27 Tahun 2007 Jo No.1 Tahun 2014
tentang pengelolaan wilayah pesisir dan pulau – pulau kecil, reklamasi wilayah
pesisir dan pulau – pulau kecil dilakukan dalam rangka meningkatkan manfaat
dan/ atau nilai tambah wilayah pesisir dan pulau – pulau kecil ditinjau dari aspek
teknis, lingkungan dan sosial ekonomi.
3
Dampak reklamasi pantai adalah hal yang patut dikaji dan diperhatikan
dalam lingkungan perkotaan yang berkelanjutan sehingga kedepannya manusia
tidak mengulangi kesalahan yang sama. Lingkungan perkotaan yang
berkelanjutan mempengaruhi pola perilaku manusia yang ada di dalamnya.
Hubungan timbal balik manusia dengan lingkungan perkotaan merupakan proses
dua arah yang konstruktif, didukung baik oleh ciri citra (image) lingkungan
maupun ciri sifat kegiatan dan kejiwaan manusia. Kota – kota besar di Indonesia
merupakan kota – kota yang berada di tepi pantai dengan jumlah penduduk yang
besar dan kegiatan perekonomian yang pesat, tetapi sering kali lahan yang
tersedia tidak mendukung laju pertumbuhan dan perkembangan wilayah yang
berlangsung di suatu kota.
1.2 Tujuan
Adapun yang menjadi tujuan dalam laporan reklamasi itu sendiri antara lain:
4
BAB 2
ANALISA PERHITUNGAN
1. Quarry Pasir
2. Quarry Batu
5
longititude 111°55’45.39°T. Jarak quarry batu ke lokasi reklamasi 11 km
dengan jarak tempuh selama ± 30 Menit.
4. Quarry Kerikil
6
2.3 Perencanaan Jangka Waktu Pelaksanaan
Pelaksanaan reklamasi Kubu Raya memerlukan waktu selama 12 tahun
dimana kegiatan pelaksanan reklamasi tersebut memiliki bobot pengerjaan dan
waktu pengerjaannyaa masing-masing yang meliputi :
1. Pekerjaan persiapan
2. Pengukuran dan pengolahan data
3. Pemasangan tanggul dan reklamasi
4. Penyempurnaan
7
2.4 Data Perhitungan Primer Settlement
Tabel 2.1 Data Perhitungan Primer Settlement
Kedalama Ysat yw n
No Jenis Tanah W (%) y' (kN/m3) e0 Cc e Gs
n (m) (kN/m3) (kN/m3) (%)
Pasir seragam
1 2 19 5,61 9,81 -4,20 0,67 0,01 0,51 34 2,68
padat
Pasir berbutir
2 3,5 16 4,75 9,81 -5,06 1,9 0,01 0,43 30 2,65
campuran padat
Lempung lunak
3 sedikit organik 4 70 22,01 9,81 12,20 1,9 0,15 1,9 66 2,65
+ kerikil
Lempung lunak
4 6 110 42,24 9,81 32,43 3 1 3 75 2,65
sangat organik
8
2.5 Analisa Perhitungan Primer Settlement Bawah
a. Menghitung y' (kN/m3 )
Menghitung y' pada lapisan 1
Dik : ysat = 5,61 kN/m3
yw = 9,81 kN/m3
Jawab :
y' = ysat - yw
= 5,61 – 9,81
= -4,2 kN/m3
Menghitung y' pada lapisan 2
Dik : ysat = 4,75 kN/m3
yw = 9,81 kN/m3
Jawab :
y' = ysat – yw
= 4,75– 9,81
= -5,06 kN/m3
Menghitung y' pada lapisan 3
yw = 9,81 kN/m3
Jawab :
y' = ysat – yw
= 22,01– 9,8
= 12,21 kN/m3
Menghitung y' pada lapisan 4
Dik : ysat = 42,24 kN/m3
yw = 9,81 kN/m3
Jawab :
9
y' = ysat – yw
= 42,24 – 9,81
= 32,43 kN/m3
Menghitung y' pada lapisan 5
Dik : ysat = 0,0 kN/m3
yw = 0,0 kN/m3
Jawab :
y' = ysat – yw
= 0,0 – 0,0
= 0 kN/m3
b. Menghitung σ'0 ( kN/m2 )
Menghitung σ'0 pada lapisan 1
Dik : y' = 0,24 kN/m3
h =2m
Jawab :
σ'0 = y ' x (h /2)
= 0,24 x (2/2)
= -9,762 kN/m2
Menghitung σ'0 pada lapisan 2
Dik : y' = 0,20 kN/m3
h = 3,5 m
Jawab :
σ'0 = (y ' x h + y ' x (h /2))
= (0,24 x 2 +0,20 x (3,5 / 2))
= -36,673 kN/m2
10
Jawab :
σ'0 = (y ' x h + y ' x h + y ' x (h /2))
= (0,24 x 2 +0,20 x 3,5 + 0,88 x (4/ 2))
= -52,545 kN/m2
Menghitung σ'0 pada lapisan 4
Dik : y' = 1,38 kN/m3
h =6m
Jawab :
σ'0 = (y ' x h+ y ' x h + y ' x h + y ' x (h /2))
= (0,24 x 2 +0,20 x 3,5 + 0,88 x 4 + 32,43 x (6/ 2))
= -62,361 kN/m2
Menghitung σ'0 pada lapisan 5
Dik : y' = 0 kN/m3
h = 9,50 m
Jawab :
σ'0 = (y ' x h + y ' x h + y ' x h + y ' x h+ y ' x (h /2))
= -99,235 kN/m2
11
I = 0,7
Jawab :
∆σ' = y ' × H × 2I
= -4,20 x 3,5 x 2(0,7)
= -20,57 kN/m2
12
= -55,84 kN/m2
13
Jawab :
∆σ' = y ' × H × 2I
= -5,06 x 6 x 2(0,7)
= -42,53 kN/m2
Menghitung ∆σ' = y ' × H × 2I (+5.00 LWS)
Dik : y' = -5,06 kN/m3
H = 9,5 m
I = 0,7
Jawab :
∆σ' = y ' × H × 2I
= -5,06 x 9,5 x 2(0,7)
= -67,35 kN/m2
e. Menghitung ∆σ' = y ' × H × 2I Pada Lapisan 3
Menghitung ∆σ' = y ' × H × 2I (LWS)
Dik : y' = 12,20 kN/m3
H =2m
I = 0,7
Jawab :
∆σ' = y ' × H × 2I
= 12,20 x 1 x 2(0,7)
= 34,16 kN/m2
Menghitung ∆σ' = y ' × H × 2I (HWL)
Dik : y' = 12,20 kN/m3
H = 3,5 m
I = 0,7
Jawab :
∆σ' = y ' × H × 2I
= 12,20 x 3,5 x 2(0,7)
= 59,78 kN/m2
Menghitung ∆σ' = y ' × H × 2I (+3.00 LWS)
14
Dik : y' = 12,20 kN/m3
H =4m
I = 0,7
Jawab :
∆σ' = y ' × H × 2I
= 12,20 x 4 x 2(0,7)
= 68,32 kN/m2
15
∆σ' = y ' × H × 2I
= 32,43 x 2 x 2(0,7)
= 90,80 kN/m2
Menghitung ∆σ' = y ' × H × 2I (HWL)
Dik : y' = 32,43 kN/m3
H = 3,5 m
I = 0,7
Jawab :
∆σ' = y ' × H × 2I
= 32,43 x 3,5 x 2(0,7)
= 158,91 kN/m2
Menghitung ∆σ' = y ' × H × 2I (+3.00 LWS)
Dik : y' = 32,43 kN/m3
H =4m
I = 0,7
Jawab :
∆σ' = y ' × H × 2I
= 32,43 x 4 x 2(0,7)
= 181,61 kN/m2
Menghitung ∆σ' = y ' × H × 2I (+4.00 LWS)
Dik : y' = 32,43 kN/m3
H =6m
I = 0,7
Jawab :
∆σ' = y ' × H × 2I
= 32,43 x 6 x 2(0,7)
= 272,41 kN/m2
Menghitung ∆σ' = y ' × H × 2I (+5.00 LWS)
Dik : y' = 32,43 kN/m3
H = 9,5 m
16
I = 0,7
Jawab :
∆σ' = y ' × H × 2I
= 32,43 x 9,5 x 2(0,7)
= 431,32 kN/m2
Menghitung ∆σ' = y ' × H × 2I (HWL)
Dik : y' = 0 kN/m3
H = 3,5 m
I = 0,7
Jawab :
∆σ' = y ' × H × 2I
= 0 x 3,5 x 2(0,7)
= 0 kN/m2
Menghitung ∆σ' = y ' × H × 2I (+3.00 LWS)
Dik : y' = 0 kN/m3
H =4m
I = 0,7
Jawab :
∆σ' = y ' × H × 2I
= 0 x 4 x 2(0,7)
= 0 kN/m2
Menghitung ∆σ' = y ' × H × 2I (+4.00 LWS)
Dik : y' = 0 kN/m3
H =6m
I = 0,7
Jawab :
∆σ' = y ' × H × 2I
= 0 x 6 x 2(0,7)
= 0 kN/m2
Menghitung ∆σ' = y ' × H × 2I (+5.00 LWS)
17
Dik : y' = 0 kN/m3
H = 9,5 m
I = 0,7
Jawab :
∆σ' = y ' × H × 2I
= 0 x 9,5 x 2(0,7)
= 0 kN/m2
Hx Cc σ '0 + ∆ σ '
g. Menghitung log Pada Lapisan 1
1+e 0 σ '0
Hx Cc σ '0 + ∆ σ '
Menghitung log (LWS)
1+e 0 σ '0
Dik : H =2m
Cc = 0,01
e0 = 0,51
’0 = -9,762kN/m2
’ = -11,76 kN/m2
Jawab :
HxCc σ '0 + ∆ σ '
∆h1 = log
1+e 0 σ '0
2 x 0,0100 −9,762+−11,76
= log
1+0,51 −9,762
= 0,01 m
Hx Cc σ '0 + ∆ σ '
Menghitung log (HWL)
1+e 0 σ '0
Dik : H = 3,5 m
Cc = 0,01
18
e0 = 0,51
’0 = -9,762kN/m2
’ = -20,57 kN/m2
Jawab :
HxCc σ '0 + ∆ σ '
∆h1 = log
1+e 0 σ '0
= 0,02 m
Hx Cc σ '0 + ∆ σ '
Menghitung log (+3.00 LWS)
1+e 0 σ '0
Dik : H =4m
Cc = 0,01
e0 = 0,51
’0 = -9,762kN/m2
’ = -23,51 kN/m2
Jawab :
HxCc σ '0 + ∆ σ '
∆h1 = log
1+e 0 σ '0
4 x 0,0100 −9,762±23,51
= log
1+ 0,51 −9,762
= 0,0212 m
Hx Cc σ '0 + ∆ σ '
Menghitung log (+4.00 LWS)
1+e 0 σ '0
19
Dik : H =6m
Cc = 0,01
e0 = 0,51
’0 = -9,762kN/m2
’ = -35,27 kN/m2
Jawab :
HxCc σ '0 + ∆ σ '
∆h1 = log
1+e 0 σ '0
5 x 0,0100 −9,762±35,27
= log
1+0,51 −9,762
= 0,0264 m
Hx Cc σ '0 + ∆ σ '
Menghitung log (+5.00 LWS)
1+e 0 σ '0
Dik : H = 9,5 m
Cc = 0,01
e0 = 0,51
’0 = -9,762kN/m2
’ = -55,84 kN/m2
Jawab :
HxCc σ ' +∆ σ '
∆h1 = log 0
1+e 0 σ '0
6 x 0,0100 −9,762+−55,84
= log
1+ 0,51 −9,762
= 0,0264 m
20
Hx Cc σ '0 + ∆ σ '
h. Menghitung log Pada Lapisan 2
1+e 0 σ '0
Hx Cc σ ' +∆ σ '
Menghitung log 0 (LWS)
1+e 0 σ '0
Dik : H =2m
Cc = 0,01
e0 = 0,43
’0 = -36,673kN/m2
’ = -14,18 kN/m2
Jawab :
HxCc σ '0 + ∆ σ '
∆h1 = log
1+e 0 σ '0
3 x 0,01 −36,673±14,18
= log
1+0,43 −36,673
= 0,0037 m
Hx Cc σ '0 + ∆ σ '
Menghitung log (HWL)
1+e 0 σ '0
Dik : H = 3,5 m
Cc = 0,01
e0 = 0,43
’0 = -36,673 kN/m2
’ = -24,81 kN/m2
Jawab :
HxCc σ ' +∆ σ '
∆h1 = log 0
1+e 0 σ '0
21
3 x 0,01 −36,673+−24,81
= log
1+0,43 −36,673
= 0,01 m
Hx Cc σ ' +∆ σ '
Menghitung log 0 (+3.00 LWS)
1+e 0 σ '0
Dik : H =4m
Cc = 0,01
e0 = 0,43
’0 = -36,673 kN/m2
’ = -28,36 kN/m2
Jawab :
HxCc σ '0 + ∆ σ '
∆h1 = log
1+e 0 σ '0
4 x 0,01 −36,673+−28,36 7
= log
1+ 0,43 −36,67
= 0,0104 m
Hx Cc σ ' +∆ σ '
Menghitung log 0 (+4.00 LWS)
1+e 0 σ '0
Dik : H =6m
Cc = 0,01
e0 = 0,43
’0 = -36,673 kN/m2
22
’ = -42,53 kN/m2
Jawab :
HxCc σ ' +∆ σ '
∆h1 = log 0
1+e 0 σ '0
6 x 0,01 −36,673+−42,53
= log
1+0,43 −36,673
= 0,0140 m
Hx Cc σ ' +∆ σ '
Menghitung log 0 (+5.00 LWS)
1+e 0 σ '0
Dik : H = 9,5 m
Cc = 0,01
e0 = 0,43
’0 = -36,673 kN/m2
’ = -67,35 kN/m2
Jawab :
HxCc σ '0 + ∆ σ '
∆h1 = log
1+e 0 σ '0
6 x 0,01 −36,673+−67,35
= log
1+0,43 −36,673
= 0,0190 m
Hx Cc σ ' +∆ σ '
i. Menghitung log 0 Pada Lapisan 3
1+e 0 σ '0
23
Hx Cc σ '0 + ∆ σ '
Menghitung log (LWS)
1+e 0 σ '0
Dik : H =3m
Cc = 0,15
e0 = 1,90
’0 = -52,545 kN/m2
’ = 34,16 kN/m2
Jawab :
HxCc σ ' +∆ σ '
∆h1 = log 0
1+e 0 σ '0
3 x 0,15 −52,545+34,16
= log
1+1,90 −52,545
= -0,1415 m
Hx Cc σ ' +∆ σ '
Menghitung log 0 (HWL)
1+e 0 σ '0
Dik : H = 3,5 m
Cc = 0,15
e0 = 1,90
’0 = -52,545 kN/m2
’ = 59,78 kN/m2
Jawab :
HxCc σ '0 + ∆ σ '
∆h1 = log
1+e 0 σ '0
24
= 0,1769 m
Hx Cc σ '0 + ∆ σ '
Menghitung log (+3.00 LWS)
1+e 0 σ '0
Dik : H =4m
Cc = 0,15
e0 = 1,90
’0 = -52,545 kN/m2
’ = 68,32 kN/m2
Jawab :
HxCc σ '0 + ∆ σ '
∆h1 = log
1+e 0 σ '0
4 x 0,15 −52,545+68,32
= log
1+ 1,90 −52,545
= 0,1903 m
Hx Cc σ '0 + ∆ σ '
Menghitung log (+4.00 LWS)
1+e 0 σ '0
Dik : H =6m
Cc = 0,15
e0 = 1,90
’0 = -52,545 kN/m2
’ = 102,48 kN/m2
Jawab :
HxCc σ '0 + ∆ σ '
∆h1 = log
1+e 0 σ '0
6 x 0,15 −52,545+102,48
= log
1+1,90 −52,545
25
= 0,2335 m
Hx Cc σ '0 + ∆ σ '
Menghitung log (+5.00 LWS)
1+e 0 σ '0
Dik : H = 9,5 m
Cc = 0,15
e0 = 1,90
’0 = -52,545 kN/m2
’ = 102,48 kN/m2
Jawab :
HxCc σ '0 + ∆ σ '
∆h1 = log
1+e 0 σ '0
= 0,2864 m
Hx Cc σ '0 + ∆ σ '
Menghitung log Pada Lapisan 4
1+e 0 σ '0
Hx Cc σ '0 + ∆ σ '
Menghitung log (LWS)
1+e 0 σ '0
Dik : H =2m
Cc = 1,00
e0 = 3,00
’0 = -62,361 kN/m2
26
’ = 90,80 kN/m2
Jawab :
HxCc σ ' +∆ σ '
∆h1 = log 0
1+e 0 σ '0
2 x 0,15 −62,361+90,80
= log
1+1,90 −62,361
= 0,7474 m
Hx Cc σ '0 + ∆ σ '
Menghitung log (HWL)
1+e 0 σ '0
Dik : H = 3,5 m
Cc = 1,00
e0 = 1,90
’0 = 3,00 kN/m2
’ = 158,91 kN/m2
Jawab :
HxCc σ '0 + ∆ σ '
∆h1 = log
1+e 0 σ '0
Hx Cc σ '0 + ∆ σ '
Menghitung log (+3.00 LWS)
1+e 0 σ '0
Dik : H =4m
Cc = 1,00
e0 = 1,90
27
’0 = 3,00 kN/m2
’ = 181,61 kN/m2
Jawab :
HxCc σ ' +∆ σ '
∆h1 = log 0
1+e 0 σ '0
4 x 0,15 −52,545+181,61
= log
1+ 1,90 −52,545
= 1,0863 m
Hx Cc σ '0 + ∆ σ '
Menghitung log (+4.00 LWS)
1+e 0 σ '0
Dik : H =6m
Cc = 1,00
e0 = 1,90
’0 = 3,00 kN/m2
’ = 272,41 kN/m2
Jawab :
HxCc σ '0 + ∆ σ '
∆h1 = log
1+e 0 σ '0
6 x 0,15 −52,545+272,41
= log
1+1,90 −52,545
= 1,3082 m
Hx Cc σ ' +∆ σ '
Menghitung log 0 (+5.00 LWS)
1+e 0 σ '0
Dik : H = 9,5 m
Cc = 1,00
28
e0 = 1,90
’0 = 3,00kN/m2
’ = 431,32 kN/m2
Jawab :
HxCc σ '0 + ∆ σ '
∆h1 = log
1+e 0 σ '0
=1,5745 m
Dik : H =2m
Cc =0
e0 =0
’0 = -99,235 kN/m2
’ = 0 kN/m2
Jawab :
HxCc σ '0 + ∆ σ '
∆h1 = log
1+e 0 σ '0
2x 0 −99,235+0
= log
1+0 −99,235
29
=0m
Hx Cc σ ' +∆ σ '
Menghitung log 0 (HWL)
1+e 0 σ '0
Dik : H = 3,5 m
Cc =0
e0 =0
’0 = -99,235 kN/m2
’ = 0 kN/m2
Jawab :
HxCc σ ' +∆ σ '
∆h1 = log 0
1+e 0 σ '0
3,5 x 0 −99,235+0
= log
1+0 −99,235
=0m
Hx Cc σ '0 + ∆ σ '
Menghitung log (+3.00 LWS)
1+e 0 σ '0
Dik : H =4m
Cc =0
e0 =0
’0 = -99,235 kN/m2
’ = 0 kN/m2
Jawab :
30
HxCc σ '0 + ∆ σ '
∆h1 = log
1+e 0 σ '0
1x 0 −99,235+0
= log
1+0 −99,235
=0m
Dik : H =6m
Cc =0
e0 =0
’0 = -99,235 kN/m2
’ = 0 kN/m2
Jawab :
HxCc σ ' +∆ σ '
∆h1 = log 0
1+e 0 σ '0
6 x0 −99,235+ 0
= log
1+0 −99,235
=0m
HxCc σ '0 + ∆ σ '
Menghitung log (+5.00 LWS)
1+e 0 σ '0
Dik : H = 9,5 m
Cc =0
e0 =0
31
’0 = -99,235 kN/m2
’ = 0 kN/m2
Jawab :
HxCc σ ' +∆ σ '
∆h1 = log 0
1+e 0 σ '0
9,5 x 0 −99,235+ 0
= log
1+0 −99,235
=0m
Jawab :
Scp = ∆h1 + ∆h2 + ∆h3 + ∆h4 + ∆h5
= 0,01 + 0,0037 + -0,1415 + 0,7474 +0,0000
= 0,623 m
32
∆h4 = 1,0167 m
∆h5 = 0,0000 m
Jawab :
Scp = ∆h1 + ∆h2 + ∆h3 + ∆h4 + ∆h5
= 0,02 + 0,01 + 0,1769 + 1,0167 +0,0000
= 1,223 m
Menghitung Primer Settlement (+3.00 LWS)
Dik : ∆h1 = 0,0212 m
∆h2 = 0,0104 m
∆h3 = 0,1903 m
∆h4 = 1,0863 m
∆h5 = 0,0000 m
Jawab :
Scp = ∆h1 + ∆h2 + ∆h3 + ∆h4 + ∆h5
= 0,0212 + 0,0104 + 0,1903 + 1,0863 +0,0000
= 1,308 m
Jawab :
Scp = ∆h1 + ∆h2 + ∆h3 + ∆h4 + ∆h5
= 0,0264 + 0,0140 + 0,2335 + 0,2864 +0,0000
33
= 1,582 m
Menghitung Primer Settlement (+5.00 LWS)
Jawab :
Scp = ∆h1 + ∆h2 + ∆h3 + ∆h4 + ∆h5
= 0,0329 + 0,0190 + 0,2864 + 1,5755 + 0,0000
= 1,913 m
34
Elevasi Timbunan +3.0 +4.0
SETTLEMENT LWS HWL
LWS LWS
HR (m) 2 3,5 4 6
Koreksi
OSTERBERG (I) 0,7 0,7 0,7 0,7
35
2.6 Data Perhitungan Immediate Settlement (Si) Bawah
W Ysat yw y' n
Lapisa Kedalama
Jenis Tanah (% (kN/ (kN/m3 (kN/m3 Cc e (% Gs
n n (m)
) m3) ) ) )
Pasir
0,010
1 padat+Kerik 2,00 19 5,61 9,81 -4,20 0,51 34 2,68
0
il
Tanah
2 3,50 16 4,75 9,81 -5,06 0,01 0,43 30 2,65
kuning
Lempung
3 4,00 70 22,01 9,81 12,20 0,15 1,90 66 2,65
lunak
Lempung
4 lunak sangat 6,00 110 42,24 9,81 32,43 1,00 3,00 75 2,65
organik
36
2.7 Analisa Perhitungan Immediate Settlement Bawah
a. Menghitung y' (kN/m3 )
Menghitung y' pada lapisan 1
Dik : ysat = 5,61kN/m3
yw = 9,81 kN/m3
Jawab :
y' = ysat - yw
= 5,61– 9,81
= -4,20 kN/m3
Menghitung y' pada lapisan 2
Dik : ysat = 4,75kN/m3
yw = 9,81 kN/m3
Jawab :
y' = ysat – yw
= 45,8488 – 9,81
= -5,06 kN/m3
37
Jawab :
y' = ysat – yw
= 42,24 – 9,81
= 32,43 kN/m3
38
b. Menghitung Immediate Settlement
Menghitung Settlement Total (St) Yang Ke-1
Dik : Scp = 0,623 m
Si = 0,313 m
Jawab :
St = Scp + Si
= 0,623 + 0,313
= 0,936 m
39
Menghitung Settlement Total (St) Yang Ke-4
Dik : Scp = 1,582 m
Si = 0,938 m
Jawab :
St = Scp + Si
= 1,582 + 0,938
= 2,520 m
c. Menghitung HR-H
Menghitung HR-H Yang Ke-1
Dik : HR =2
H = 25
Jawab :
HR-H = 2-25
= -23
40
Menghitung HR-H Yang Ke-2
Dik : HR = 3,5
H = 25
Jawab :
HR-H = 3,5-25
= -21,5
41
HR-H = 9,5 - 25
= -15,5
Ked
ala W Ysat y'
n
c Jenis Tanah ma (% (kN/ (kN/m3 Cc e Gs
(%)
n ) m3) )
(m)
Pasir seragam
1 2 19 5,61 -4,20 0,01 0,51 34 2,68
padat
Pasir berbutir
2 campuran 3,5 16 4,75 -5,06 0,01 0,43 30 2,65
padat
42
Jawab :
σ' =y'xh
= -5,06 x 3,5
= -17,149 kN/m2
2.3 x−8,398 ¿)
=
= -9,762 kN/m2
43
2.3 x−17,723 ¿)
=
= -17,149 kN/m2
2.3 x−8,398 ¿)
=
= -9,762 kN/m2
2.3 x−17,723 ¿)
=
= -17,149 kN/m2
44
g. Menghitung y 'timb × Htimb Pada Lapisan 1
Menghitung y 'timb × Htimb (LWS)
Dik : y' = -4,20 kN/m3
H =2m
Jawab :
y 'timb × Htimb = y ' × H
= -4,20 x 2
= -8,40 kN/m2
45
= -4,20 x 6
= -25,19 kN/m2
hi
h. Menghitung y ' timb × H timb ∑ Pada Lapisan 1
E oed
Menghitung (LWS)
Jawab : hi
y ' timb × H timb ∑
∆h1 = E oed
2
= −0,0006858 ∑
−0,0006004
= 0,00576 m
hi
Menghitung y ' timb × H timb ∑ (HWL)
E oed
46
Eoed = -9,762 kN/m2
Jawab :
hi
∆h1 = y ' timb × H timb ∑
E oed
2
= −0,0006858 ∑ −0,0006004
= 0,010008 m
hi
Menghitung y ' timb × H timb ∑ (+3.0 LWS)
E oed
4
= −0,0006858 ∑ −0,0006004
= 0,01152 m
hi
i. Menghitung y ' timb × H timb ∑ (+4.0 LWS)
E oed
6
−0,0006858 ∑
−0,0006004
47
=
= 0,01728 m
hi
j. Menghitung y ' timb × H timb ∑ (+5.0 LWS)
E oed
9,5
= −0,0006858 ∑ −0,0006004
= 0,02735 m
hi
k. Menghitung y ' timb × H timb ∑ Pada Lapisan 2
E oed
hi
Menghitung y ' timb × H timb ∑ (LWS)
E oed
2
= −0,0006004 ∑
−17,149
48
= -0,0050423 m
hi
Menghitung y ' timb × H timb ∑ (HWL)
E oed
3,5
−0,0006004 ∑
= −17,149
= 0,0088240908 m
hi
Menghitung y ' timb × H timb ∑ (+3.0 LWS)
E oed
4
−0,0006004 ∑
= −17,149
= 0,0100846752m
hi
Menghitung y ' timb × H timb ∑ (+4.0 LWS)
E oed
49
Dik : y ‘timb × Htimb = -0,0006004 kN/m2
H =6m
Eoed = -17,149 kN/m2
Jawab : hi
y ' timb × H timb ∑
∆h2 = E oed
6
−0,0006004 ∑
= −17,149
= 0,0151270128 m
hi
Menghitung y ' timb × H timb ∑ (+5.0 LWS)
E oed
9,5
−0,0006004 ∑
= −17,149
= 0,0239511036 m
50
= 0,01080 m
= 0,01890 m
= 0,02160 m
51
= 0,03240 m
= 0,05130 m
Elevasi
SETTLEMENT Timbunan LWS HWL
HR (m) 8 10
52
g'timb x HRtimb2 288,310 360,388
N g'timb x Htimb
∆h
∆h
1 g'timb x Htimb 0,0006858 ∆h1 0,00288 0,00864
1
∆h 0,000001 0,000000000
2 g'timb x Htimb 0,0006004 ∆h2
2 7 0
2 3,5 4 6 9,5
0,00576
0,01008 0,01152 0,01728 0,02735
53
2.8 Rangkuman Tabel Perhitungan Settlement Total (St)
54
Dik : HR =2
H =8
Jawab :
HR-H = 2-8
= -6
Menghitung HR-H Yang Ke-2
Dik : HR = 3,5
H =8
Jawab :
HR-H = 3,5-8
= -4,5
BAB 3
KESIMPULAN DAN SARAN
3.1 Kesimpulan
a. Perhitungan Primer Settlement (Scp)
Pada analisa perhitungan di atas, ada 5 lapisan tanah yang diperhitunkan
dimana ketiga lapisan tanah tersebut terdiri dari jenis pasir seragam padat
dengan kedalaman 2,00 m, jenis pasir berbutir campuran padat dengan
kedalaman 3,50 m, lempung lunak sedikit organic dan kerikil dengan
kedalaman 4,00 m, jenis tanah lempung lunak sangat organik degan
kedalaman 6,00 m dan jenis tanah Batu dengan kedalaman 9,50 m. Dari
analisa perhitungan keempat jenis tanah tersebut nilai Primer Settlement yang
didapat, antara lain :
1. Pada elevasi timbunan dengan HR 2 m nilai Primer Settlement nyaa
adalah 0,623 m.
2. Pada elevasi timbunan dengan HR 3,5 m nilai Primer Settlement nya
adalah 1,223 m.
55
3. Pada elevasi timbunan dengan HR 4 m nilai Primer Settlement nya
adalah 1,308 m.
4. Pada elevasi timbunan dengan HR 6 m nilai Primer Settlement nya
adalah 1,582 m.
5. Pada elevasi timbunan dengan HR 9,5 m nilai Primer Settlement nya
adalah 1,913 m.
b. Perhitungan Immediate Settlement (Si)
56
4. Pada elevasi timbunan dengan HR 6 m nilai Total Settlement nya
adalah 2,520 m.
5. Pada elevasi timbunan dengan HR 9,5 m nilai Total Settlement nya
adalah 3,398 m.
3.2 Saran
1. Nilai – nilai Wc (%), , e0 dan nilai Cc harus sesuai dengan jenis tanah yanag
akan kita perhitungkan dan mengikuti petunjuk – petunjuk rumus yang ada,
agar hasil perhitungan konsolidasi penurunan total settlement yang diperoleh
dapat sesuai dengan jenis tanah yang kita perhitungkan.
2. Saat melalukan perhitungan disarankan agar lebih teliti dalam penggunaan
rumusnya, karena kesusaian rumus yang digunakan tersebut sangat
berpengaruh pada hasil perhitungan.
57