Overview Progress IKN 3A - M49
Overview Progress IKN 3A - M49
OVERVIEW PROGRESS
Jalan Tol IKN Segmen Karangjoang – KKT Kariangau
Jalan Tol IKN Segmen Karangjoang – KKT Kariangau
- 20 AGUSTUS 2023 - 1
DATA PROYEK PT. INDEC INTERNUSA, KSO HUTAMA-ADHI-ABIPRAYA, KSO
No. Mata
Item Pekerjaan Bobot (%)
2022 2023 2024
S
Pembayaran Sept Okt Nov Des Jan Feb Mar Apr Mei Juni Juli Aug Sept Okt Nov Des Jan Feb Mar April Mei Juni Juli
a b k 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
DIVISI 1. UMUM 0,019 0,015 0,092 0,101 0,045 0,122 0,008 0,013 0,200 0,004 0,010 0,004 0,050 0,005 0,007 0,026 0,004 0,023 0,027 0,022 0,021 0,027 0,078
-
DIVISI 2. DRAINASE - - - - - - - - 0,000 0,004 0,014 - - 0,625 0,554 0,752 0,220 0,155 0,039 - - - -
-
DIVISI 3. PEKERJAAN TANAH DAN
- - - - 0,058 0,306 0,507 0,526 0,398 0,169 0,086 0,001 - 7,202 6,454 10,069 - -
ADDENDUM 02- - - ADDENDUM
- 03 -
GEOSINTETIK
-
DIVISI 5. PERKERASAN BERBUTIR
- - -
KONTRAK AWAL - - - - - - - - - - - - 0,448 0,784 0,921 1,381 1,101 - - -
DAN PERKERASAN BETON SEMEN ADDENDUM 01
-
DIVISI 6. PERKERASAN ASPAL - - - - - - - - - - - - - - - - - 1,107 2,768 2,326 2,889 3,189 -
-
DIVISI 7. STRUKTUR - - 0,454 0,314 0,349 0,213 0,448 0,623 0,381 1,211 1,407 0,001 0,331 6,333 20,524 14,662 0,384 0,134 0,389 0,378 0,378 0,472 -
0,081 2,539 5,076 5,526 6,379 7,662 6,099 6,237 6,709 6,423 6,325 6,811 7,106 6,737 5,789 4,850 1,846 1,512 1,512 1,566 1,566 1,566 0,081
RENCANAN KONTRAK AWAL
- 0,081 2,620 7,696 13,223 19,602 27,264 33,363 39,599 46,309 52,732 59,057 65,868 72,974 79,711 85,500 90,350 92,196 93,708 95,221 96,787 98,353 99,919 100,000
0,266 0,334 0,630 0,729 0,900 1,245 1,050 4,401 7,573 7,328 15,621 12,727 12,771 14,874 5,363 3,423 3,540 2,277 2,177 2,689 0,047
RENCANA KONTRAK ADDENDUM 01
0,033 0,300 0,634 1,264 1,993 2,892 4,137 5,188 9,589 17,162 24,489 40,111 52,838 65,609 80,483 85,846 89,270 92,810 95,087 97,264 99,953 100,000
0,630 0,729 0,899 1,245 1,050 4,495 7,479 7,328 15,621 12,727 12,773 14,873 5,363 3,424 3,541 2,276 2,177 2,685 0,051
RENCANA KONTRAK ADDENDUM 02
0,634 1,264 1,993 2,891 4,136 5,187 9,681 17,161 24,488 40,110 52,837 65,610 80,483 85,846 89,270 92,811 95,087 97,264 99,949 100,000
1,516 0,009 0,380 14,165 27,538 25,957 1,392 2,532 5,557 4,747 4,237 5,091 0,298
RENCANA KONTRAK ADDENDUM 03
6,580 8,096 8,105 8,485 22,650 50,188 76,145 77,537 80,070 85,627 90,374 94,611 99,702 100,000
0,019 0,015 0,547 0,415 0,435 0,652 0,937 1,160 1,009 1,392 5,738
REALISASI
0,019 0,033 0,580 0,995 1,430 2,082 3,019 4,179 5,188 6,580 12,318
DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK 774.531.363.123,50 25,776 2,897 0,152 3,048
PROGRESS ALAT BERAT S/D 20 AGUSTUS 2023 PROGRESS TENAGA KERJA S/D 20 AGUSTUS 2023
160
121 Unit Lokal Staff
120
Non-Lokal Pekerja
80
40 15 Unit 39 Unit
12 Unit
0 12 Unit Komposisi Tenaga Kerja Komposisi Tenaga Kerja
2 Unit
Bulldozer Crane
Dump
1 Unit 14 Unit
6 Unit
Non-lokal : 845 orang (75%) Pekerja : 979 orang (87%)
Truck Excavator Vibro 2 Unit Lokal : 282 orang (25%) Staff : 148 orang (13%)
Water
Wheel
Tank
Loader Borepile
Alat Total : 1127 orang Total : 1127 orang
Pancang Alat
CSP Pancang
Square
Pile
BOX CULVERT
PERSPEKTIF KAWASAN
PEKERJAAN TIANG BOR DIA. 800 MM & PILE HEAD PADA ELEVATED PILE SLAB STA 14+045 s/d 14+465
PEKERJAAN PEMANCANGAN CSP DIA. 800 MM PADA ELEVATED PILE SLAB STA 17+850
PEKERJAAN PEMANCANGAN CSP DIA. 800 MM PADA ELEVATED PILE SLAB STA 20+930
PEKERJAAN TIANG BOR BETON DIA. 1000 MM PADA JEMBATAN SUNGAI WAIN (STA. 18+800 – 19+500)
https://autode.sk/3LS0l5S