PEMBANGUNAN GEDUNG SERBAGUNA LANTAI 2 PEKERJAAN PERSIAPAN Pembersihan lokasi Pembuatan gudang kerja

Start: Sun 01/01/23ID: 1 Start: Sun 01/01/23ID: 2 Start: 01/01/23 ID: 3 Start: 06/01/23 ID: 4
Finish: Tue 18/04/23
Dur: 90 days Finish: Mon 23/01/23
Dur: 19 days Finish: 05/01/23 Dur: 5 days Finish: 11/01/23 Dur: 4 days
Comp: 0% Comp: 0% Res: Res:

Pengukuran dan pemasangan bowplank Galian tanah pondasi Urugan pasir bawah pondasi Urugan tanah kembali
Start: 02/01/23 ID: 5 Start: 05/01/23 ID: 6 Start: 09/01/23 ID: 8 Start: 16/01/23 ID: 7
Finish: 05/01/23 Dur: 4 days Finish: 09/01/23 Dur: 3 days Finish: 10/01/23 Dur: 1 day Finish: 17/01/23 Dur: 1 day
Res: Res: Res: Res:

PEKERJAAN PONDASI DAN BETON Pondasi plat beton bertulang (150kg besi + bekisting)
Start: Tue 10/01/23ID: 10 Start: 10/01/23 ID: 12
Finish: Thu 23/03/23
Dur: 60 days Finish: 16/01/23 Dur: 5 days
Comp: 0% Res:

Pondasi batu belah 1 PC : 5 pasir


Start: 16/01/23 ID: 11
Finish: 24/01/23 Dur: 7 days
Res:

PEKERJAAN PASANGAN DAN PLESTERAN


Start: Sat 25/02/23ID: 25
Finish: Wed 29/03/23
Dur: 26 days
Comp: 0%

Page 1
PEKERJAAN KERAMIK LANTAI DAN DINDING
Start: Thu 16/03/23ID: 30
Finish: Mon 03/04/23
Dur: 14 days
Comp: 0%

PEKERJAAN ATAP
Start: Wed 15/03/23
ID: 41
Finish: Sat 25/03/23Dur: 8 days
Comp: 0%

PEKERJAAN PLAFOND
Start: Wed 29/03/23
ID: 45
Finish: Wed 05/04/23
Dur: 6 days
Comp: 0%

Page 2
PEKERJAAN KUSEN, PINTU DAN JENDELA
Start: Wed 01/03/23
ID: 51
Finish: Tue 07/03/23
Dur: 5 days
Comp: 0%

PEKERJAAN AKSESORIS PINTU DAN JENDELA Kunci pintu 2 slaag (lantai 1 dan 2)
Start: Mon 03/04/23
ID: 57 Start: 03/04/23 ID: 58
Finish: Wed 05/04/23
Dur: 2 days Finish: 04/04/23 Dur: 1 day
Comp: 0% Res:

Kunci pintu KM/WC tipe Alpha bulat (lantai 1 dan 2)


Start: 03/04/23 ID: 59
Finish: 04/04/23 Dur: 1 day
Res:

Engsel pintu standard 4 inchi (lantai 1 dan 2)


Start: 03/04/23 ID: 60
Finish: 05/04/23 Dur: 2 days
Res:

Engsel jendela standard 3 inchi (lantai 1 dan 2)


Start: 03/04/23 ID: 61
Finish: 04/04/23 Dur: 1 day
Res:

Grendel pintu double


Start: 03/04/23 ID: 62
Finish: 04/04/23 Dur: 1 day
Res:

Grendel jendela (lantai 1 dan 2)


Start: 03/04/23 ID: 63
Finish: 05/04/23 Dur: 2 days
Res:

Kait angin jendela (lantai 1 dan 2)


Start: 03/04/23 ID: 64
Finish: 04/04/23 Dur: 1 day
Res:

Tarikan jendela (lantai 1 dan 2)


Start: 03/04/23 ID: 65
Finish: 05/04/23 Dur: 2 days
Res:

Kaca polos 3mm (lantai 1 dan 2)


Start: 03/04/23 ID: 66
Finish: 04/04/23 Dur: 1 day
Res:

Kaca polos 5mm (lantai 1 dan 2)


Page 3
Start: 03/04/23 ID: 67
Finish: 04/04/23 Dur: 1 day
Res:

PEKERJAAN SANITAIR
Start: Fri 24/02/23 ID: 68
Finish: Mon 03/04/23
Dur: 31 days
Comp: 0%

PEKERJAAN INSTALASI AIR


Start: Mon 09/01/23
ID: 77
Finish: Tue 04/04/23
Dur: 71 days
Comp: 0%

Pembuatan septictank dan rembesan


Start: 09/01/23 ID: 82
Finish: 11/01/23 Dur: 2 days
Res:

Penyambungan air bersih ke PAM


Start: 03/04/23 ID: 83
Finish: 04/04/23 Dur: 1 day
Res:

PEKERJAAN INSTALASI LISTRIK


Start: Mon 13/03/23
ID: 84
Finish: Fri 17/03/23Dur: 4 days
Comp: 0%

Page 4
PEKERJAAN PENGECATAN Dinding cat tembok kualitas baik (lantai 1 dan 2)
Start: Thu 30/03/23ID: 93 Start: 03/04/23 ID: 94
Finish: Mon 10/04/23
Dur: 9 days Finish: 10/04/23 Dur: 6 days
Comp: 0% Res:

Kusen cat minyak (lantai 1 dan 2)


Start: 05/04/23 ID: 98
Finish: 07/04/23 Dur: 2 days
Res:

Bouvenlight cat minyak (lantai 2)


Start: 05/04/23 ID: 99
Finish: 06/04/23 Dur: 1 day
Res:

Daun pintu cat minyak (lantai 1 dan 2)


Start: 05/04/23 ID: 100
Finish: 07/04/23 Dur: 2 days
Res:

Daun jendela cat minyak (lantai 1 dan 2)


Start: 05/04/23 ID: 101
Finish: 06/04/23 Dur: 1 day
Res:

Page 5
Urugan pasir bawah lantai
Start: 01/02/23 ID: 9
Finish: 02/02/23 Dur: 1 day
Res:

Sloof beton bertulang (150kg besi + bekisting) kolom beton bertulang (200kg besi + bekisting) Balok beton bertulang 20x30cm (225kg besi + bekisting) Plat beton bertulang tebal 12cm (115kg besi + bekisting)
Start: 24/01/23 ID: 13 Start: 01/02/23 ID: 14 Start: 20/02/23 ID: 16 Start: 25/02/23 ID: 20
Finish: 01/02/23 Dur: 7 days Finish: 20/02/23 Dur: 15 days Finish: 25/02/23 Dur: 5 days Finish: 04/03/23 Dur: 6 days
Res: Res: Res: Res:

Plat meja dapur beton bertulang (100kg besi + bekisting)


Start: 25/02/23 ID: 23
Finish: 27/02/23 Dur: 1 day
Res:

Balok beton bertulang 12x12cm (150kg besi + bekisting)


Start: 20/02/23 ID: 17
Finish: 21/02/23 Dur: 1 day
Res:

kolom beton bertulang 25x25cm (175kg besi + bekisting)


Start: 01/02/23 ID: 15
Finish: 03/02/23 Dur: 2 days
Res:

Ring balok beton bertulang 15x20cm (175kg besi + bekisting)Plat dak atap beton bertulang tebal 8cm (100kg besi + bekisting)
Start: 13/03/23 ID: 18 Start: 15/03/23 ID: 21
Finish: 14/03/23 Dur: 1 day Finish: 20/03/23 Dur: 4 days
Res: Res:

Ring balok beton bertulang 15x15cm (175kg besi + bekisting)


Start: 13/03/23 ID: 19
Finish: 15/03/23 Dur: 2 days
Res:

Tangga beton bertulang (200kg besi + bekisting)


Start: 13/03/23 ID: 22
Finish: 16/03/23 Dur: 3 days
Res:

Dinding bata merah 1 PC : 3 pasir (KM/WC lantai 1 dan 2)


Start: 25/02/23 ID: 26
Finish: 01/03/23 Dur: 3 days
Res:

Dinding bata merah 1 PC : 5 pasir (lantai 1, 2 dan pagar)


Start: 25/02/23 ID: 27
Finish: 13/03/23 Dur: 13 days
Res:

Plesteran campuran 1 PC
Start: 23/03/23
Finish: 29/03/23
Res:

Plesteran campuran 1 PC
Start: 23/03/23
Page 6
Start: 23/03/23
Finish: 28/03/23
Res:

Lantai keramik 40x40cm untuk tangga


Start: 16/03/23 ID: 36
Finish: 17/03/23 Dur: 1 day
Res:

Pasang rangka atap baja ringan Pasang nok/ bubungan genteng keramik Pasang atap genteng ker
Start: 15/03/23 ID: 42 Start: 20/03/23 ID: 44 Start: 23/03/23
Finish: 20/03/23 Dur: 4 days Finish: 23/03/23 Dur: 2 days Finish: 25/03/23
Res: Res: Res:

Page 7
Kusen kayu kamper samarinda 6/15 (lantai 1 dan 2)
Start: 01/03/23 ID: 52
Finish: 06/03/23 Dur: 4 days
Res:

Daun pintu panel double teakwood rangka kayu kamper (lantai 1 dan 2)
Start: 01/03/23 ID: 53
Finish: 07/03/23 Dur: 5 days
Res:

Daun pintu dan kusen PVC / pabrikasi (lantai 1 dan 2)


Start: 01/03/23 ID: 54
Finish: 02/03/23 Dur: 1 day
Res:

Daun jendela kayu kamper (lantai 1 dan 2)


Start: 01/03/23 ID: 55
Finish: 07/03/23 Dur: 5 days
Res:

Bouvenlight
Start: 01/03/23 ID: 56
Finish: 02/03/23 Dur: 1 day
Res:

Page 8
Wastafel
Start: 24/02/23 ID: 71
Finish: 25/02/23 Dur: 1 day
Res:

Kran air KM/WC (lantai 1 dan 2)


Start: 01/03/23 ID: 72
Finish: 02/03/23 Dur: 1 day
Res:

Kran air taman


Start: 13/03/23 ID: 73
Finish: 14/03/23 Dur: 1 day
Res:

Kran air meja dapur type angsa


Start: 01/03/23 ID: 74
Finish: 02/03/23 Dur: 1 day
Res:

Floordrain KM/WC (lantai 1 dan 2)


Start: 01/03/23 ID: 75
Finish: 02/03/23 Dur: 1 day
Res:

Pipa PCV 1/2 inchi lantai 2


Start: 25/02/23 ID: 78
Finish: 28/02/23 Dur: 2 days
Res:

Pipa PVC 2 inchi (lantai 1 dan 2)


Start: 25/02/23 ID: 79
Finish: 01/03/23 Dur: 3 days
Res:

Pipa PVC 4 inchi (lantai 1 dan 2)


Start: 25/02/23 ID: 80
Finish: 01/03/23 Dur: 3 days
Res:

Aksesoris lain (lem pipa, ampelas, sambungan dll 10 %)


Start: 25/02/23 ID: 81
Finish: 27/02/23 Dur: 1 day
Res:

Intalasi titik nyala lampu kabel NYM 2X2.5mm (lantai 1 dan 2)


Lampu baret 18 watt
Start: 13/03/23 ID: 85 Start: 16/03/23 ID: 87
Finish: 16/03/23 Dur: 3 days Finish: 17/03/23 Dur: 1 day
Res: Res:

Lampu SL 18 watt
Start: 16/03/23 ID: 88
Finish: 17/03/23 Dur: 1 day
Res:
Page 9
Res:

Lampu TL 1x18 watt


Start: 16/03/23 ID: 89
Finish: 17/03/23 Dur: 1 day
Res:

Instalasi titik daya stop kontak lampu kabel NYM 3X2.5mm (lantai 1 dan 2)
Start: 13/03/23 ID: 86
Finish: 15/03/23 Dur: 2 days
Res:

Panel listrik
Start: 13/03/23 ID: 91
Finish: 14/03/23 Dur: 1 day
Res:

Penyambungan daya listrik ke PLN Lampu taman 40 watt lengkap dengan tiang besi diameter 2 inchi
Start: 13/03/23 ID: 92 Start: 14/03/23 ID: 90
Finish: 14/03/23 Dur: 1 day Finish: 15/03/23 Dur: 1 day
Res: Res:

Page 10
Beton lantai kerja dibawah lantai, 1 PC : 3 split : 5 pasir
Start: 21/03/23 ID: 24
Finish: 23/03/23 Dur: 1 day
Res:

Plesteran campuran 1 PC : 3 pasir (lantai 1 dan 2)


Start: 23/03/23 ID: 28
Finish: 29/03/23 Dur: 5 days

Plesteran campuran 1 PC : 5 pasir (lantai 1 dan 2)


Start: 23/03/23 ID: 29
Page 11
Start: 23/03/23 ID: 29
Finish: 28/03/23 Dur: 4 days

Lantai keramik polis 40x40cm lantai 1


Start: 29/03/23 ID: 31
Finish: 01/04/23 Dur: 3 days
Res:

Lantai keramik polis 40x40cm lantai 2


Start: 29/03/23 ID: 32
Finish: 01/04/23 Dur: 3 days
Res:

Lantai keramik unpolis 40x40cm pada teras dan mezanine


Start: 29/03/23 ID: 33
Finish: 30/03/23 Dur: 1 day
Res:

Lantai keramik polos 20x20cm untuk KM/WC lantai 1


Start: 29/03/23 ID: 34
Finish: 30/03/23 Dur: 1 day
Res:

Lantai keramik polos 20x20cm untuk KM/WC lantai 2


Start: 29/03/23 ID: 35
Finish: 30/03/23 Dur: 1 day
Res:

Dinding keramik polos 20x20cm untuk KM/WC lantai 1


Start: 28/03/23 ID: 37
Finish: 31/03/23 Dur: 3 days
Res:

Dinding keramik polos 20x20cm untuk KM/WC lantai 2


Start: 28/03/23 ID: 38
Finish: 03/04/23 Dur: 5 days
Res:

Dinding keramik motif 20x20cm untuk meja dapur


Start: 29/03/23 ID: 39
Finish: 01/04/23 Dur: 3 days
Res:

Plint keramik 10x40cm lantai 1 dan 2


Start: 29/03/23 ID: 40
Finish: 30/03/23 Dur: 1 day
Res:

Pasang atap genteng keramik


Start: 23/03/23 ID: 43
Finish: 25/03/23 Dur: 2 days

Rangka plafond 50x100cm kayu borneo super (lantai 1 dan 2)


Start: 29/03/23 ID: 46
Finish: 05/04/23 Dur: 6 days
Res:

Plafond GRC 100x100cm tebal 4cm (lantai 1 dan 2)


Start: 29/03/23 ID: 47
Finish: 31/03/23 Dur: 2 days
Res:

Plafond kayu ramin+ rangka (lantai 1 dan 2)


Start: 29/03/23 ID: 48
Finish: 30/03/23 Dur: 1 day
Res:

Listplafond kayu profil 5cm (lantai 1 dan 2)


Start: 29/03/23 ID: 49
Finish: 01/04/23 Dur: 3 days
Res:

Page 12
Listplafond kayu 1x4cm (lantai 1 dan 2)
Start: 29/03/23 ID: 50
Finish: 30/03/23 Dur: 1 day
Res:

Page 13
Bak mandi fiberglass (lantai 1 dan 2) Kloset duduk monoblok (lantai 1 dan 2)
Start: 30/03/23 ID: 69 Start: 30/03/23 ID: 70
Finish: 01/04/23 Dur: 2 days Finish: 03/04/23 Dur: 3 days
Res: Res:

Kitchen zink meja dapur


Start: 01/04/23 ID: 76
Finish: 03/04/23 Dur: 1 day
Res:

Page 14
Plafond ramin cat melamik (lantai 1 dan 2)
Start: 30/03/23 ID: 95
Finish: 31/03/23 Dur: 1 day
Res:

Listplank cat minyak (lantai 1 dan 2)


Start: 01/04/23 ID: 96
Finish: 03/04/23 Dur: 1 day
Res:

Listplafond cat minyak (lantai 1 dan 2)


Start: 01/04/23 ID: 97
Finish: 03/04/23 Dur: 1 day
Res:

Page 15
Critical Critical Milestone Critical Summary Critical Inserted Critical Marked Critical External Project Summary Highlighted Noncritical
Project: MS PROJECT GEDUNG
Date: Sun 09/07/23 Noncritical Milestone Summary Inserted Marked External Highlighted Critical