Weekly 1 Schedule Penggantian Atap (Opsi D Atau Timpa Atap Existing) Schedule Rev2
Weekly 1 Schedule Penggantian Atap (Opsi D Atau Timpa Atap Existing) Schedule Rev2
REKAPITULASI
MINGGU KE-1
PERIODE 24 MEI - 30 MEI 2021
A PEKERJAAN PERSIAPAN 9.047 0.000 1.508 1.508 0.000 0.000 0.000 -1.508
B PEKERJAAN SIPIL 90.954 0.000 0.000 0.000 0.000 0.000 0.000 0.000
(......................................) (...................................)
NAMA PROYEK : PENGGANTIAN ATAP (OPSI D / TIMPA ATAP EXISTING)
KONTRAKTOR : PT. CITRA KARSA DINAMIKA
KLIENT : PT. TIRTA INVESTAMA
LOKASI : Jl. Olympic Raya, Sentul, Kec. Babakan Madang, Bogor, Jawa Barat 16810
MINGGU KE :1
TANGGAL : 30 MEI 2021
PERIODE : 24 MEI - 30 MEI 2021
A PEKERJAAN PERSIAPAN
1 Mobilisasi dan demobilisasi 4.338 - 0.723 0.723 0% 17% 17% - - - 0% 0% 0%
2 Safety & hygiene 2.314 - 0.386 0.386 0% 17% 17% - - - 0% 0% 0%
3 Partisi melamin 0.659 - 0.110 0.110 0% 17% 17% - - - 0% 0% 0%
4 Pembersihan area kerja 0.868 - 0.145 0.145 0% 17% 17% - - - 0% 0% 0%
5 Rapid test 0.868 - 0.145 0.145 0% 17% 17% - - - 0% 0% 0%
Sub Total - PEKERJAAN PERSIAPAN 9.047 0.000 1.508 1.508 0.000 0.000 0.000
B PEKERJAAN SIPIL
1 Penggantian Atap 0.000 - - - #DIV/0! #DIV/0! #DIV/0! - - - #DIV/0! #DIV/0! #DIV/0!
a Bongkar atap eksisting (Tidak dibongkar) 0.000 - - - #DIV/0! #DIV/0! #DIV/0! - - - #DIV/0! #DIV/0! #DIV/0!
b Pemasangan atap baru 79.948 - - - 0% 0% 0% - - - 0% 0% 0%
c Flashing 5.690 - - - 0% 0% 0% - - - 0% 0% 0%
d Nok 2.019 - - - 0% 0% 0% - - - 0% 0% 0%
e Penutupan eks. Lubang turbin ventilator 0.694 - - - 0% 0% 0% - - - 0% 0% 0%
f Install atap material eksisting 0.000 - - - #DIV/0! #DIV/0! #DIV/0! - - - #DIV/0! #DIV/0! #DIV/0!
2 Turbin Ventilator 0.000 - - - #DIV/0! #DIV/0! #DIV/0! - - - #DIV/0! #DIV/0! #DIV/0!
a Bongkar turbin ventilator 0.434 - - - 0% 0% 0% - - - 0% 0% 0%
b Install turbin ventilator baru 1.735 - - - 0% 0% 0% - - - 0% 0% 0%
c Install turbin ventilator eksisting 0.434 - - - 0% 0% 0% - - - 0% 0% 0%
Sub Total - PEKERJAAN TANAH & BONGKARAN 90.954 0.000 0.000 0.000 0.000 0.000 0.000
A PEKERJAAN PERSIAPAN
1 Mobilisasi dan demobilisasi 4.338 0.723 0.723 0.723 0.723 0.723 0.723
2 Safety & hygiene 2.314 0.386 0.386 0.386 0.386 0.386 0.386
3 Partisi melamin 0.659 0.110 0.110 0.110 0.110 0.110 0.110
4 Pembersihan area kerja 0.868 0.145 0.145 0.145 0.145 0.145 0.145
5 Rapid test 0.868 0.145 0.145 0.145 0.145 0.145 0.145
B PEKERJAAN SIPIL
1 Penggantian Atap 0.000
a Bongkar atap eksisting (Tidak dibongkar) 0.000
b Pemasangan atap baru 79.948 26.649 26.649 26.649
c Flashing 5.690 1.897 1.897 1.897
d Nok 2.019 0.673 0.673 0.673
e Penutupan eks. Lubang turbin ventilator 0.694 0.231 0.231 0.231
f Install atap material eksisting
2 Turbin Ventilator 0.000
Series1
a Bongkar turbin ventilator 0.434 Series2 0.145 0.145 0.145
b Install turbin ventilator baru 1.735 0.578 0.578 0.578
c Install turbin ventilator eksisting 0.434 0.145 0.145 0.145
TOTAL 100.000
PROGRESS RENCANA 1.508 1.508 1.508 31.826 31.826 31.826
KUMULATIF PROGRES RENCANA 1.508 3.016 4.523 36.349 68.175 100.000
PROGRES AKTUAL 0.000
KUMULATIF PROGRES AKTUAL 0.000
DEVIASI -1.508
No. Dok. :
No. Rev. :
FOTO PROGRESS KONSTRUKSI Tgl Rev. :
PROGRESS REPORT
Nama Proyek : PENGGANTIAN ATAP (OPSI D / TIMPA ATAP EXISTING) Periode : 24 MEI - 30 MEI 2021
Alamat Proyek : Jl. Olympic Raya, Sentul, Kec. Babakan Madang, Bogor, Jawa Barat 16810 Tanggal : 30 MEI 2021
Start Mgg 1 Mgg 2 Mgg 3 Mgg 4 Mgg 5 Mgg 6 Mgg 7 Mgg 8 Mgg 9 Mgg 10 Mgg 11 Mgg 12 Mgg 13 Mgg 14 Mgg 15 Mgg 16 Finish
Plan 24-May-21 1.508
Actual 0.000 04 Juli 2021
Deviasi -1.508
HSSE Pekerjaan Minggu ini : Pekerjaan Minggu depan :
Cumulative Manhour for This Week
PI & NM :
- Potential Incident 0 Material : Issues :
- Near Miss 0
Quality : Alat :
- Total NCR : 0
- NCR Clossed 0