ID Task Task Name Duration Start Finish

Mode
Oct '20 Nov '20 Dec '20
13 20 27 04 11 18 25 01 08 15 22 29
1
TIMELINE PROJECT CA PT TIRTA INVESTAMA 83 Mon 14/09/20 Sat 05/12/20
days?
PLANT SENTUL BOGOR
2 Meeting Internal 1 day Mon 14/09/20 Mon 14/09/20
3 Kick Off Meething 1 day Mon 14/09/20 Mon 14/09/20
4 Pra Konstruksi 11 daysTue 15/09/20 Fri 25/09/20
5 Perizinan Lingkungan dan kawaasan 11 days Tue 15/09/20 Fri 25/09/20
6 Survey dan pemetaan 5 days Thu 17/09/20 Mon 21/09/20
7 Supporting Work 11 days? Tue 22/09/20 Fri 02/10/20
8 Direksikeet 1 day Tue 22/09/20 Tue 22/09/20
9 Mobilisasi Pekerja 1 day? Wed 23/09/20 Wed 23/09/20
10 Rapid Test tahap 1 1 day? Thu 24/09/20 Thu 24/09/20
11 Karantina Pekerja 7 days Thu 24/09/20 Wed 30/09/20
12 Rapid Test Tahap II 1 day? Wed 30/09/20 Wed 30/09/20
13 Induction Pekerja 1 day? Wed 30/09/20 Wed 30/09/20
14 Test Pit 2 days Thu 01/10/20 Fri 02/10/20
15 Pembuatan Pengaman Baner 1 day Thu 01/10/20 Thu 01/10/20
16 Pembuatan Rambu Pengaman 2 days Thu 01/10/20 Fri 02/10/20
17 Mobilisasi Material dan Inspeksi 33 days? Thu 01/10/20 Mon 02/11/20
18 Mobilisasi Peralatan 1 day? Thu 01/10/20 Thu 01/10/20
19 Mobilisasi Pipa dan Fitting 1 day Fri 02/10/20 Fri 02/10/20
20 Mobilisasi MRS 1 day Mon 02/11/20 Mon 02/11/20
21 Inspeksi Material dan fitting 1 day Fri 02/10/20 Fri 02/10/20
22 Pekerjaan Konstruksi 35 days? Thu 01/10/20 Wed 04/11/20
23 Pembersihan Jalur Pipa 1 day Thu 01/10/20 Thu 01/10/20
24 Penggalian Jalur Pipa dan pemasangan Turap 30 days Thu 01/10/20 Fri 30/10/20
25 Penjajaran Pipa 30 days Thu 01/10/20 Fri 30/10/20
26 Pengelasan Pipa 30 days Thu 01/10/20 Fri 30/10/20
27 Radiography Test 30 days Thu 01/10/20 Fri 30/10/20
28 FJC dan Wraping 30 days Thu 01/10/20 Fri 30/10/20
29 Holiday Test 30 days Thu 01/10/20 Fri 30/10/20
30 Penurunan Pipa 30 days Thu 01/10/20 Fri 30/10/20
31 Pemasangan Marker Tape 30 days Thu 01/10/20 Fri 30/10/20
32 Pembuatan Pondasi MRS 30 days Thu 01/10/20 Fri 30/10/20
33 Pemasangan Katodik 1 day? Mon 02/11/20 Mon 02/11/20
34 Pemasangan Marker Post Stasiun MRS 1 day Tue 03/11/20 Tue 03/11/20
35 Pemasangan Marker Post 1 day Wed 04/11/20 Wed 04/11/20
36 Precommisioning 3 days Sun 01/11/20 Tue 03/11/20
37 Cleaning 1 day Sun 01/11/20 Sun 01/11/20
38 Filling water 1 day Sun 01/11/20 Sun 01/11/20
39 Hydrotest 2 days Mon 02/11/20 Tue 03/11/20
40 Dewatering 1 day Tue 03/11/20 Tue 03/11/20
41 Swabbing 1 day Tue 03/11/20 Tue 03/11/20
42 Pengetesan Valve 2 days Mon 02/11/20 Tue 03/11/20
43 Hot Tapping 19 days? Mon 05/10/20 Fri 23/10/20
44 Tchiknes Pipa Exsisting 1 day? Mon 05/10/20 Mon 05/10/20
45 Pengurusan Izin Migas 14 days Tue 06/10/20 Mon 19/10/20
46 Inspeksi Peralatan 1 day? Tue 20/10/20 Tue 20/10/20
47 Meeting Pra Hottap 1 day? Wed 21/10/20 Wed 21/10/20
48 Pelaksanaan Hot taping 2 days Thu 22/10/20 Fri 23/10/20
49 Gas In / Commissioning 26 days? Thu 05/11/20 Mon 30/11/20
50 N2 Purging 1 day? Fri 06/11/20 Fri 06/11/20
51 Commissioning MRS 1 day Thu 05/11/20 Thu 05/11/20
52 PSSR 1 day? Fri 13/11/20 Fri 13/11/20
53 Gas In 1 day Mon 30/11/20 Mon 30/11/20
54 Demobilisasi 1 day? Tue 01/12/20 Tue 01/12/20
55 Demobilisasi alat dan personil 1 day? Tue 01/12/20 Tue 01/12/20

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: CA FERMANTECH SHED
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Wed 09/09/20
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 1