ID Task Name % Complete Duration Start Finish Jun '22 Jul '22 Aug '22 Sep '22 Oct

rt Finish Jun '22 Jul '22 Aug '22 Sep '22 Oct '22 Nov '22 Dec '22
30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19
0 Membekal, Memasang dan Menyusun Semula Peralatan 0% 132 days Wed 15/6/22 Fri 16/12/22
Dan Aksesori Untuk Menangani Fenomena Banjir
Genang Kepada Institut Penyelidikan Air Kebangsaan
Malaysia (NAHRIM)
1 KERJA- KERJA AWALAN 0% 7 days Wed 15/6/22 Thu 23/6/22
2 Insurance 0% 7 days Wed 15/6/22 Thu 23/6/22
3 KERJA-KERJA TRAILER 0% 92 days Wed 15/6/22 Thu 20/10/22
4 Designing Process 0% 7 days Wed 15/6/22 Thu 23/6/22
5 Production 0% 75 days Fri 24/6/22 Thu 6/10/22
6 Generator set 0% 92 days Wed 15/6/22 Thu 20/10/22
7 Estimate Delivery 0% 75 days Wed 15/6/22 Tue 27/9/22
8 Pemasangan 0% 7 days Wed 12/10/22 Thu 20/10/22
9 Panel elektrik di trailer jenis IP54 bagi pam air 0% 92 days Wed 15/6/22 Thu 20/10/22
10 Designing Process 0% 14 days Wed 15/6/22 Mon 4/7/22
11 Production 0% 45 days Wed 6/7/22 Tue 6/9/22
12 Testing & Commisioning 0% 7 days Wed 12/10/22 Thu 20/10/22
13 Pam air dan motor 0% 92 days Wed 15/6/22 Thu 20/10/22
14 Pam Air jenis Centrifugal End Suction 0% 92 days Wed 15/6/22 Thu 20/10/22
15 Estimate Delivery 0% 75 days Wed 15/6/22 Tue 27/9/22
16 Pemasangan 0% 7 days Wed 12/10/22 Thu 20/10/22
17 Pam Air jenis Submersible 0% 92 days Wed 15/6/22 Thu 20/10/22
18 Estimate Delivery 0% 75 days Wed 15/6/22 Tue 27/9/22
19 Pemasangan 0% 7 days Wed 12/10/22 Thu 20/10/22
20 Lain-lain kerja trailer 0% 48 days Fri 1/7/22 Tue 6/9/22
21 Meter air 0% 10 days Fri 1/7/22 Thu 14/7/22
22 Injap pembuka/ tutup 0% 10 days Fri 15/7/22 Thu 28/7/22
23 Paip 2 inci diameter dengan bahan besi tahan karat 0% 14 days Fri 29/7/22 Wed 17/8/22
yang keluar dari pam air 7.5KW/ 10 HP sepanjang
1.5 meter ke paip water to evaporator dan
sepanjang 1.5 meter ke paip long range discharge
system dan mengikut lebar trailer dan penutup paip
2 inci
24 Paip pengecilan dari 2 inci diameter ke 1.5 inci 0% 14 days Thu 18/8/22 Tue 6/9/22
diameter iaitu paip yang keluar dari pam air dan
menuju ke water to evoparator
25 Urusan JPJ dan Puspakom 0% 10 days Wed 14/9/22 Tue 27/9/22
26 KERJA-KERJA TRUCK 0% 111 days Wed 15/6/22 Wed 16/11/22
27 Four-wheel drive (4X4) double cab pickup vehicles 0% 111 days Wed 15/6/22 Wed 16/11/22
(four-door version)
28 Estimate Delivery 0% 90 days Wed 15/6/22 Tue 18/10/22
29 Modification 0% 14 days Wed 19/10/22 Mon 7/11/22
30 Urusan JPJ dan Puspakom 0% 7 days Tue 8/11/22 Wed 16/11/22
31 Four-wheel drive (4X4) single cab pickup vehicles 0% 111 days Wed 15/6/22 Wed 16/11/22
(two-door version)
32 Estimate Delivery 0% 90 days Wed 15/6/22 Tue 18/10/22
33 Modification 0% 14 days Wed 19/10/22 Mon 7/11/22
34 Urusan JPJ dan Puspakom 0% 7 days Tue 8/11/22 Wed 16/11/22
35 KERJA-KERJA PERPAIPAN & NOZZLE SPRINKLER 0% 107 days Wed 15/6/22 Thu 10/11/22
UNTUK SISTEM PEMERCIK WAP AIR
36 Nozzle sprinkler 0% 21 days Wed 15/6/22 Wed 13/7/22
37 Hos dari jenis lapisan PU 0% 14 days Thu 14/7/22 Tue 2/8/22
38 Pemasangan 0% 50 days Thu 4/8/22 Wed 12/10/22
39 Paip 1.5 inci diameter untuk water to evaporator 0% 21 days Thu 13/10/22 Thu 10/11/22
sepanjang 2 meter setiap satu
40 LAIN-LAIN 0% 90 days Wed 15/6/22 Tue 18/10/22
41 Water Jet dan Power Jet(5+5) 0% 14 days Tue 12/7/22 Fri 29/7/22
42 Magnetic Inductive Current Meter for Velocity 0% 14 days Mon 1/8/22 Thu 18/8/22
Measurement in Open Stream Channel

Task Project Summary Inactive Summary Start‐only Progress


Split External Tasks Manual Task Finish‐only
Project: Membekal, Memasang da
Date: Sat 4/6/22 Milestone External Milestone Duration‐only Deadline
Critical Milestone Inactive Task Manual Summary Rollup Critical
Summary Inactive Milestone Manual Summary Critical Split

Page 1
ID Task Name % Complete Duration Start Finish Jun '22 Jul '22 Aug '22 Sep '22 Oct '22 Nov '22 Dec '22
30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19
43 Portable Ultrasonic Flow Meter for Closed Conduit 0% 14 days Fri 19/8/22 Wed 7/9/22
Flow Measurement
44 Mesin pengangkat beban mudah alih 0% 45 days Fri 1/7/22 Thu 1/9/22
45 Multi parameter water quality sonde 0% 90 days Wed 15/6/22 Tue 18/10/22
46 3D Laser scanning system 0% 40 days Fri 1/7/22 Thu 25/8/22
47 DOCUMENTATION 0% 14 days Fri 11/11/22 Wed 30/11/22
48 FINAL TESTING & COMMISIONING 0% 14 days Fri 25/11/22 Wed 14/12/22
49 PROJECT COMPLETION AND HANDING OVER 0% 0 days Fri 16/12/22 Fri 16/12/22

Task Project Summary Inactive Summary Start‐only Progress


Split External Tasks Manual Task Finish‐only
Project: Membekal, Memasang da
Date: Sat 4/6/22 Milestone External Milestone Duration‐only Deadline
Critical Milestone Inactive Task Manual Summary Rollup Critical
Summary Inactive Milestone Manual Summary Critical Split

Page 2
Jan '23 Feb '23 Mar '23 Apr '23 May '23 Jun '23 Jul '23 Aug '23 Sep '23 Oct '23 Nov '23 Dec '23
19 26 2 9 16 23 30 6 13 20 27 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18

Task Project Summary Inactive Summary Start‐only Progress


Split External Tasks Manual Task Finish‐only
Project: Membekal, Memasang da
Date: Sat 4/6/22 Milestone External Milestone Duration‐only Deadline
Critical Milestone Inactive Task Manual Summary Rollup Critical
Summary Inactive Milestone Manual Summary Critical Split

Page 3
Jan '23 Feb '23 Mar '23 Apr '23 May '23 Jun '23 Jul '23 Aug '23 Sep '23 Oct '23 Nov '23 Dec '23
19 26 2 9 16 23 30 6 13 20 27 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18

Task Project Summary Inactive Summary Start‐only Progress


Split External Tasks Manual Task Finish‐only
Project: Membekal, Memasang da
Date: Sat 4/6/22 Milestone External Milestone Duration‐only Deadline
Critical Milestone Inactive Task Manual Summary Rollup Critical
Summary Inactive Milestone Manual Summary Critical Split