BARCHART SOLUSI-1

PENGADAAN PENYEDIA PEKERJAAN KONSTRUKSI


PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT PULAU TERLUAR - KEPULAUAN RIAU
ID Task Name Duration Start Finish Jun '13 Jul '13 Aug '13 Sep '13 Oct '13 Nov '13 Dec '13
7/0 3/0 0/0 7/0 4/0 1/0 8/0 5/0 2/0 9/0 5/0 2/0 9/0 6/0 2/0 9/0 6/0 3/0 0/0 7/1 4/1 1/1 8/1 4/1 1/1 8/1 5/1 2/1 9/1 6/1
1 PEMBANGUNAN PELABUHAN TANAH LAUT 180 days Sat 15/06/13 Wed 11/12/13
2 PEKERJAAN PERSIAPAN 180 days Sat 15/06/13 Wed 11/12/13
3 Pembuatan papan nama proyek 1 day Sat 15/06/13 Sat 15/06/13
4 Pembuatan direksi keet/gudang bahan 32 days Sat 15/06/13 Tue 16/07/13
5 Penerangan kerja 179 days Sun 16/06/13 Wed 11/12/13
6 Pengukuran dan pemasangan bowplank 5 days Sat 15/06/13 Wed 19/06/13
7 Penyediaan Air Kerja dan P3K 180 days Sat 15/06/13 Wed 11/12/13
8 Mobilisasi dan demobilisasi 11 days Sat 15/06/13 Tue 25/06/13
9 PEKERJAAN CAUSEWAY (622 x 4) m2 + SHELTER 167 days Thu 20/06/13 Tue 03/12/13
10 Beton L.Shape & plat injak 35 days Fri 25/10/13 Thu 28/11/13
11 Pasangan batu kosong 40 kg 50 days Thu 20/06/13 Thu 08/08/13
12 Pasangan batu kosong 20 kg 70 days Tue 25/06/13 Mon 02/09/13
13 Pasangan batu 1 : 3 60 days Tue 03/09/13 Fri 01/11/13
14 Filter cloth 20 days Tue 03/09/13 Sun 22/09/13
15 Pemasangan pipa PVC 2" 4 days Thu 20/06/13 Sun 23/06/13
16 Pekerjaan plesteran 1 : 3 82 days Fri 13/09/13 Tue 03/12/13
17 Timbunan Tanah 77 days Fri 13/09/13 Thu 28/11/13
18 Galian untuk gorong-gorong 60 days Thu 20/06/13 Sun 18/08/13
19 Pasir 10 cm (bedding) 50 days Mon 30/09/13 Mon 18/11/13
20 Gorong-gorong K-225 (Precast) 63 days Sun 30/06/13 Sat 31/08/13
21 PEKERJAAN AREAL DARAT (50 x 50)M2 84 days Thu 20/06/13 Wed 11/09/13
22 Pasangan batu kosong 40 kg 24 days Thu 20/06/13 Sat 13/07/13
23 Pasangan batu 1 : 3 7 days Sun 14/07/13 Sat 20/07/13
24 Pemasangan geotekstile 18 days Sun 14/07/13 Wed 31/07/13
25 Timbunan Tanah 9 days Thu 01/08/13 Fri 09/08/13
26 Pekerjaan plesteran 1 : 3 3 days Sun 21/07/13 Tue 23/07/13
27 Pekerjaan Saluran U-Ditch (keliling area reklama 19 days Sat 24/08/13 Wed 11/09/13
28 Beton tumbuk 2 days Thu 01/08/13 Fri 02/08/13
29 Beton Kepala Talud & plat injak 21 days Sat 03/08/13 Fri 23/08/13
30 PEKERJAAN LAIN - LAIN 180 days Sat 15/06/13 Wed 11/12/13
31 Administrasi/Dokumentasi 180 days Sat 15/06/13 Wed 11/12/13
32 As built drawing 180 days Sat 15/06/13 Wed 11/12/13
33 Penyelesaian dan pembersihan 8 days Wed 04/12/13 Wed 11/12/13

Project: CASHFLOW SOLUSI-1.mpp Task Progress Summary External Tasks Deadline


Date: Sun 05/05/13 Split Milestone Project Summary External Milestone