Pembangunan Jembatan Gunungwungkal

ID Task Mode Task Name Work Duration Start Finish


Qtr 4, 2019
October November December
Details 9/30 10/7 10/14 10/21 10/28 11/4 11/11 11/18 11/25 12/2 12/9 12/16 12/23
1 DIVISI 1 MOBILISASI 1,344 hrs84 days Tue 10/1/19Mon 12/23/19 Work 96h 112h 112h 112h 112h 112h 112h 112h 112h 112h 112h 112h 16h
2 Mobilisasi Dan Demobili 1,344 hrs12 wks Tue 10/1/19Mon 12/23/19 Work 96h 112h 112h 112h 112h 112h 112h 112h 112h 112h 112h 112h 16h
pekerja 672 hrs Tue 10/1/19Mon 12/23/19 Work 48h 56h 56h 56h 56h 56h 56h 56h 56h 56h 56h 56h 8h
mandor 672 hrs Tue 10/1/19Mon 12/23/19 Work 48h 56h 56h 56h 56h 56h 56h 56h 56h 56h 56h 56h 8h
3 DIVISI 2 DRAINASE 1,400 hrs56 days Tue 10/1/19Mon 11/25/19 Work 96h 256h 184h 168h 168h 168h 168h 168h 24h
4 Pekerjaan Galian Untuk 224 hrs2 wks Tue 10/1/19Mon 10/14/19 Work 96h 112h 16h
pekerja 112 hrs Tue 10/1/19Mon 10/14/19 Work 48h 56h 8h
mandor 112 hrs Tue 10/1/19Mon 10/14/19 Work 48h 56h 8h
5 Pekerjaan Pasangan Bat 1,176 hrs7 wks Tue 10/8/19Mon 11/25/19 Work 144h 168h 168h 168h 168h 168h 168h 24h
Semen 205.83 kg Tue 10/8/19Mon 11/25/19 Work (kg 25.2 29.4 29.4 29.4 29.4 29.4 29.4 4.2
pasir 118.22 m3 Tue 10/8/19Mon 11/25/19 Work (m 14.48 16.89 16.89 16.89 16.89 16.89 16.89 2.41
pekerja 392 hrs Tue 10/8/19Mon 11/25/19 Work 48h 56h 56h 56h 56h 56h 56h 8h
tukang 392 hrs Tue 10/8/19Mon 11/25/19 Work 48h 56h 56h 56h 56h 56h 56h 8h
mandor 392 hrs Tue 10/8/19Mon 11/25/19 Work 48h 56h 56h 56h 56h 56h 56h 8h
batu pecah 205.83 m3 Tue 10/8/19Mon 11/25/19 Work (m 25.2 29.4 29.4 29.4 29.4 29.4 29.4 4.2
6 DIVISI 3 PEKERJAAN TANA 560 hrs35 days Tue 10/15/19Mon 11/18/19 Work 96h 112h 112h 112h 112h 16h
7 Galian Biasa 224 hrs2 wks Tue 10/15/19Mon 10/28/19 Work 96h 112h 16h
pekerja 112 hrs Tue 10/15/19Mon 10/28/19 Work 48h 56h 8h
mandor 112 hrs Tue 10/15/19Mon 10/28/19 Work 48h 56h 8h
8 Timbunan Pilihan 336 hrs3 wks Tue 10/29/19Mon 11/18/19 Work 96h 112h 112h 16h
Material Tanah Pilih,535.35 m3 Tue 10/29/19Mon 11/18/19 Work (m 1,010.1 1,178.... 1,178.... 168.35
pekerja 168 hrs Tue 10/29/19Mon 11/18/19 Work 48h 56h 56h 8h
mandor 168 hrs Tue 10/29/19Mon 11/18/19 Work 48h 56h 56h 8h
9 DIVISI 4 PERKERASAN BER 1,008 hrs56 days Tue 10/15/19 Mon 12/9/19 Work 96h 112h 112h 208h 128h 112h 112h 112h 16h
10 Lapis Pondasi Agregat Ke 560 hrs5 wks Tue 11/5/19 Mon 12/9/19 Work 96h 112h 112h 112h 112h 16h
Agregat klas‐a ,490.75 m3 Tue 11/5/19 Mon 12/9/19 Work (m 255.56 298.15 298.15 298.15 298.15 42.59
pekerja 280 hrs Tue 11/5/19 Mon 12/9/19 Work 48h 56h 56h 56h 56h 8h
mandor 280 hrs Tue 11/5/19 Mon 12/9/19 Work 48h 56h 56h 56h 56h 8h
11 Lapis Pondasi Agregat Ke 448 hrs4 wks Tue 10/15/19Mon 11/11/19 Work 96h 112h 112h 112h 16h
Agregat klas‐b ,114.45 m3 Tue 10/15/19Mon 11/11/19 Work (m 453.1 528.61 528.61 528.61 75.52
pekerja 224 hrs Tue 10/15/19Mon 11/11/19 Work 48h 56h 56h 56h 8h
mandor 224 hrs Tue 10/15/19Mon 11/11/19 Work 48h 56h 56h 56h 8h
12 DIVISI 5 PERKERASAN ASP 2,352 hrs56 days Tue 10/29/19Mon 12/23/19 Work 96h 208h 224h 416h 352h 336h 336h 336h 48h
13 Lapis Resap Pengikat 336 hrs3 wks Tue 11/5/19Mon 11/25/19 Work 96h 112h 112h 16h
Aspal 1,331.27 kg Tue 11/5/19Mon 11/25/19 Work (kg 380.36 443.76 443.76 63.39
kerosene 727 liter Tue 11/5/19Mon 11/25/19 Work (lit 207.71 242.33 242.33 34.62
pekerja 168 hrs Tue 11/5/19Mon 11/25/19 Work 48h 56h 56h 8h
mandor 168 hrs Tue 11/5/19Mon 11/25/19 Work 48h 56h 56h 8h
14 Lapis Perekat 560 hrs5 wks Tue 11/19/19Mon 12/23/19 Work 96h 112h 112h 112h 112h 16h
Aspal 3,035.06 kg Tue 11/19/19Mon 12/23/19 Work (kg 520.3 607.01 607.01 607.01 607.01 86.72
kerosene 736.68 liter Tue 11/19/19Mon 12/23/19 Work (lit 126.29 147.34 147.34 147.34 147.34 21.05
pekerja 280 hrs Tue 11/19/19Mon 12/23/19 Work 48h 56h 56h 56h 56h 8h
mandor 280 hrs Tue 11/19/19Mon 12/23/19 Work 48h 56h 56h 56h 56h 8h
15 Laston Lapis Aus (AC/WC 560 hrs5 wks Tue 11/19/19Mon 12/23/19 Work 96h 112h 112h 112h 112h 16h
Semen 8,878.65 kg Tue 11/19/19Mon 12/23/19 Work (kg 1,522.... 1,775.... 1,775.... 1,775.... 1,775.... 253.68
pasir 316.94 m3 Tue 11/19/19Mon 12/23/19 Work (m 54.33 63.39 63.39 63.39 63.39 9.06
Project1 logistik mk
Pembangunan Jembatan Gunungwungkal
ID Task Mode Task Name Work Duration Start Finish
Qtr 4, 2019
October November December
Details 9/30 10/7 10/14 10/21 10/28 11/4 11/11 11/18 11/25 12/2 12/9 12/16 12/23
Aspal 3,950.24 kg Tue 11/19/19Mon 12/23/19 Work (kg 9,248.... 10,79... 10,79... 10,79... 10,79... 1,541....
pekerja 280 hrs Tue 11/19/19Mon 12/23/19 Work 48h 56h 56h 56h 56h 8h
mandor 280 hrs Tue 11/19/19Mon 12/23/19 Work 48h 56h 56h 56h 56h 8h
batu pecah 267.91 m3 Tue 11/19/19Mon 12/23/19 Work (m 45.93 53.58 53.58 53.58 53.58 7.65
16 Laston Lapis Aus Perata 560 hrs5 wks Tue 11/19/19Mon 12/23/19 Work 96h 112h 112h 112h 112h 16h
Semen 3,248.12 kg Tue 11/19/19Mon 12/23/19 Work (kg 556.82 649.62 649.62 649.62 649.62 92.8
pasir 115.94 m3 Tue 11/19/19Mon 12/23/19 Work (m 19.88 23.19 23.19 23.19 23.19 3.31
Aspal 0,676.72 kg Tue 11/19/19Mon 12/23/19 Work (kg 3,544.... 4,135.... 4,135.... 4,135.... 4,135.... 590.76
pekerja 280 hrs Tue 11/19/19Mon 12/23/19 Work 48h 56h 56h 56h 56h 8h
mandor 280 hrs Tue 11/19/19Mon 12/23/19 Work 48h 56h 56h 56h 56h 8h
batu pecah 98 m3 Tue 11/19/19Mon 12/23/19 Work (m 16.8 19.6 19.6 19.6 19.6 2.8
17 Laton Lapis Pondasi (AC‐ 336 hrs3 wks Tue 10/29/19Mon 11/18/19 Work 96h 112h 112h 16h
Semen 5,478.86 kg Tue 10/29/19Mon 11/18/19 Work (kg 1,565.... 1,826.... 1,826....260.9
pasir 133.71 m3 Tue 10/29/19Mon 11/18/19 Work (m 38.2 44.57 44.57 6.37
Aspal 7,338.95 kg Tue 10/29/19Mon 11/18/19 Work (kg 7,811.... 9,112.... 9,112....
1,301....
pekerja 168 hrs Tue 10/29/19Mon 11/18/19 Work 48h 56h 56h 8h
mandor 168 hrs Tue 10/29/19Mon 11/18/19 Work 48h 56h 56h 8h
batu pecah 237.8 m3 Tue 10/29/19Mon 11/18/19 Work (m 67.94 79.27 79.27 11.32
18 DIVISI 6 STRUKTUR 2,856 hrs63 days Tue 10/8/19 Mon 12/9/19 Work 144h 168h 312h 336h 480h 504h 504h 216h 168h 24h
19 Beton Mutu rendah fc'1 336 hrs2 wks Tue 10/22/19 Mon 11/4/19 Work 144h 168h 24h
Semen 7,225.25 kg Tue 10/22/19 Mon 11/4/19 Work (kg 7,382.... 8,612.... 1,230....
pasir beton 34.54 m3 Tue 10/22/19 Mon 11/4/19 Work (m 14.8 17.27 2.47
pekerja 112 hrs Tue 10/22/19 Mon 11/4/19 Work 48h 56h 8h
tukang 112 hrs Tue 10/22/19 Mon 11/4/19 Work 48h 56h 8h
mandor 112 hrs Tue 10/22/19 Mon 11/4/19 Work 48h 56h 8h
batu pecah 61.15 m3 Tue 10/22/19 Mon 11/4/19 Work (m 26.21 30.58 4.37
20 Baja Tulangan U 24 Polo 504 hrs3 wks Tue 11/5/19Mon 11/25/19 Work 144h 168h 168h 24h
baja tulangan (polos9,374.09 kg Tue 11/5/19Mon 11/25/19 Work (kg 5,535.... 6,458.... 6,458.... 922.58
kawat beton 44.03 kg Tue 11/5/19Mon 11/25/19 Work (kg 12.58 14.68 14.68 2.1
pekerja 168 hrs Tue 11/5/19Mon 11/25/19 Work 48h 56h 56h 8h
tukang 168 hrs Tue 11/5/19Mon 11/25/19 Work 48h 56h 56h 8h
mandor 168 hrs Tue 11/5/19Mon 11/25/19 Work 48h 56h 56h 8h
21 Baja Tulangan U 32 Ulir 504 hrs3 wks Tue 11/5/19Mon 11/25/19 Work 144h 168h 168h 24h
baja tulangan (ulir) D 247.5 kg Tue 11/5/19Mon 11/25/19 Work (kg 70.71 82.5 82.5 11.79
kawat beton 4.5 kg Tue 11/5/19Mon 11/25/19 Work (kg 1.29 1.5 1.5 0.21
pekerja 168 hrs Tue 11/5/19Mon 11/25/19 Work 48h 56h 56h 8h
tukang 168 hrs Tue 11/5/19Mon 11/25/19 Work 48h 56h 56h 8h
mandor 168 hrs Tue 11/5/19Mon 11/25/19 Work 48h 56h 56h 8h
22 Pasangan Batu 1,512 hrs9 wks Tue 10/8/19 Mon 12/9/19 Work 144h 168h 168h 168h 168h 168h 168h 168h 168h 24h
Semen 5,659.54 kg Tue 10/8/19 Mon 12/9/19 Work (kg 22,44... 26,18... 26,18... 26,18... 26,18... 26,18... 26,18... 26,18... 26,18... 3,740....
pasir 753.45 m3 Tue 10/8/19 Mon 12/9/19 Work (m 71.76 83.72 83.72 83.72 83.72 83.72 83.72 83.72 83.72 11.96
pekerja 504 hrs Tue 10/8/19 Mon 12/9/19 Work 48h 56h 56h 56h 56h 56h 56h 56h 56h 8h
tukang 504 hrs Tue 10/8/19 Mon 12/9/19 Work 48h 56h 56h 56h 56h 56h 56h 56h 56h 8h
mandor 504 hrs Tue 10/8/19 Mon 12/9/19 Work 48h 56h 56h 56h 56h 56h 56h 56h 56h 8h
batu pecah 1,549 m3 Tue 10/8/19 Mon 12/9/19 Work (m 147.52 172.11 172.11 172.11 172.11 172.11 172.11 172.11 172.11 24.59