SUCIPTO
SR OPR MANAGER MSN
M NATSIR
MINING DEPT MSN
SITE MANAGER
QUALITY CONTROL MSN KONTRAKTOR
KEPALA PRODUKSI
1. Asumsi :
A. Pit ke tongkang
B. Pit ke EFO ke tongkang
C. Pit ke ETO ke EFO ke tongkang (50%)
A. ASUMSI
1 Jam Kerja Siang (08.00 -17.00) 8 Jam
2 Jam Kerja Malam (19.00 - 22.00) 3 Jam
3 Cycletime Hauling Pit ke ETO 30 Menit/Rit
4 Cycletime Hauling ETO ke EFO 50 Menit/Rit
5 Cycletime Hauling Pit ke EFO 60 Menit/Rit
6 Muatan DT (12 bucket) 20 Ton/Rit
7 Jumlah DT 8 Unit
B.4 KEMAMPUAN PRODUKSI HAULING PER HARI 68.8 Rit KETIKA TIDAK ADA BARGING
KEMAMPUAN PRODUKSI HAULING PER HARI 28.8 Rit KETIKA ADA BARGING
Jun-21
URAIAN TOTAL
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Ritasi Tdk Barging 69 69 69 69 69 69 69 69 69 619.2
Ritasi Saat Barging 29 29 29 29 29 29 29 29 29 29 29 29 345.6
Total Ritasi 224 224 224 224 69 964.8
ESTIMASI PENGAPALAN BULAN JUNI 2021
A. ASUMSI
1 Jam Kerja Siang (08.00 -17.00) 8 Jam
2 Jam Kerja Malam (19.00 - 22.00) 3 Jam
3 Cycletime Hauling Pit ke ETO 30 Menit/Rit
4 Cycletime Hauling ETO ke EFO 50 Menit/Rit
5 Cycletime Hauling Pit ke EFO 60 Menit/Rit
6 Muatan DT (12 bucket) 20 Ton/Rit
7 Jumlah DT 11 Unit
B.4 KEMAMPUAN PRODUKSI HAULING PER HARI 103.6 Rit KETIKA TIDAK ADA BARGING
KEMAMPUAN PRODUKSI HAULING PER HARI 39.6 Rit KETIKA ADA BARGING
Jun-21
URAIAN TOTAL
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Ritasi Tdk Barging 104 104 104 104 104 104 104 104 104 104 103.6 1139.6
Ritasi Saat Barging 39.6 39.6 39.6 39.6 39.6 39.6 39.6 39.6 39.6 39.6 396
Total Ritasi 286.4 286.4 286.4 286.4 286.4 104 1535.6
PERFORMA DUMP TRUCK DAN HAULING ORE WEEK 32
Tanggal
Rincian
10/4/2021 10/5/2021 10/6/2021 10/7/2021 10/8/2021
Pit ke ETO 75 7
Pit ke EFO 20
ETO ke EFO 23 48 72
Siang
ETO ke Tongkang 55
EFO ke Tongkang 49
Quarry
Pit ke ETO 20 41 52 33
Malam Pit ke EFO 5 10
ETO ke EFO 8 27
Total dari Pit - 0 95 101 89 33
Total Hauling 0 144 132 137 132
Siang 14 15 14 13
Jumlah DT
Malam 6 10 10 11
Total Jam Kerja DT 120.42 155.42 146.33 135.58
Total Jam Kerja A2B 23.00 150.00 153.00 145.00 111.00
Catatan :
Plan 17 DT dengan waktu 11 jam per hari (1309 jam per minggu)
Total Keterangan
10/9/2021 10/10/2021
82
17 37
40 55 238
55
Barging
104
16 16
146
15
35
0 17 335
56 72 673
13 12
11
57.33 77.92 693.0 52.9%
65.00 84.00 731.0 87.0%
PLAN VS ACTUAL WEEK 32 BULAN OKTOBER 2021
WEEK 32
10/4/2021 10/5/2021 10/6/2021 10/7/2021
Catatan :
Tidak dilakukan ore getting karena pertimbangan :
1. Lokasi untuk penyimpanan ore sempit (rencana SM dibuat dome tersendiri berdasarkan klasifikasi kadar)
2. Ore lama masih belum terhauling mengakibatkan menjadi basah yang menyulitkan penanganan pada saat haulin
3. Meminimalisir angsur ore (dibuat jalan agar dt bisa langsung loading dome SM)
4. Bukaan deposit ore di blok alfa seluas 3.445 m2 dengan 15.000 - 20.000 estimasi MT
WEEK 32
TOTAL PERCENTAGE
10/8/2021 10/9/2021 10/10/2021
an klasifikasi kadar)
enanganan pada saat hauling