ID Task No.

WBS Task Name Duration Start Finish


Mode
0 0 PWBK Rumah Sederhana 1 Lantai 111 days Sun 17/05/15 Fri 04/09/15
1
2
3 3 1 Pekerjaan Tanah 52 days Sun 17/05/15 Tue 07/07/15
4 4 1.1 Pembuatan Bouwplank 3 days Sun 17/05/15 Tue 19/05/15
5 5 1.2 Galian tanah untuk pondasi 19 days Wed 20/05/15 Sun 07/06/15
6 6 1.3 Urugan tanah kembali untuk pondasi 3 days Tue 16/06/15 Thu 18/06/15
7 7 1.4 Urugan tanah untuk peninggian lantai 1 day Sat 27/06/15 Sat 27/06/15
8 8 1.5 Urugan pasir di bawah pondasi ; t = 15 cm 2 days Sun 07/06/15 Mon 08/06/15
9 9 1.6 Urugan pasir dibawah lantai ; t = 20 cm 3 days Sun 05/07/15 Tue 07/07/15
10 10 2 Pekerjaan Pondasi 7 days Tue 09/06/15 Mon 15/06/15
11 11 2.1 Pasangan pondasi batu kali belah 1 Pc : 5 Ps 5 days Thu 11/06/15 Mon 15/06/15
12 12 2.2 Pemasangan Aanstamping; t = 20 cm 2 days Tue 09/06/15 Wed 10/06/15
13 13 3 Pekerjaan Sloof 8 days Fri 19/06/15 Fri 26/06/15
14 14 3.1 Pekerjan Penulangan Sloof 3 days Fri 19/06/15 Sun 21/06/15
15 15 3.2 Pekerjaan Penulangan Sengkang Sloof 1 day Sun 21/06/15 Sun 21/06/15
16 16 3.3 Pekerjaan Bekisting Sloof 5 days Fri 19/06/15 Tue 23/06/15
17 17 3.4 Pekerjaan Pengecoran Beton - Beton K175 3 days Wed 24/06/15 Fri 26/06/15
18 18 4 Pekerjaan Kolom 13 days Mon 22/06/15 Sat 04/07/15
19 19 4.1 Pekerjan Penulangan Kolom 2 days Mon 22/06/15 Tue 23/06/15
20 20 4.2 Pekerjaan Penulangan Sengkang Kolom 1 day Tue 23/06/15 Tue 23/06/15
21 21 4.3 Pekerjaan Bekisting Kolom 5 days Sat 27/06/15 Wed 01/07/15

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: PWBK Rumah Sederhan
Summary Manual Summary Rollup Progress
Date: Thu 21/05/15
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task No. WBS Task Name Duration Start Finish
Mode
22 22 4.4 Pekerjaan Pengecoran Beton Kolom - Beton K175 3 days Thu 02/07/15 Sat 04/07/15
23 23 5 Pekerjaan Ringbalk 7 days Wed 08/07/15 Tue 14/07/15
24 24 5.1 Pekerjaan Ringbalk 10x15cm 7 days Wed 08/07/15 Tue 14/07/15
25 25 6 Pekerjaan Dinding 63 days Tue 30/06/15 Mon 31/08/15
26 26 6.1 Pemasangan dinding bata merah 1 Pc : 5 Pp ; t = 1/2 bata 8 days Tue 30/06/15 Tue 07/07/15
27 27 6.2 Pemasangan dinding bata merah 1 Pc : 3 Pp ; t = 1/2 bata 1 day Tue 30/06/15 Tue 30/06/15
28 28 6.3 Plesteran halus 1 Pc : 5 Ps ; t = 1,5 cm 19 days Wed 08/07/15 Sun 26/07/15
29 29 6.4 Plesteran halus 1 Pc : 3 Ps ; t = 1,5 cm 3 days Fri 24/07/15 Sun 26/07/15
30 30 6.5 Pekerjaan acian 15 days Mon 27/07/15 Mon 10/08/15
31 31 6.6 Pengecatan dinding dalam baru 9 days Fri 14/08/15 Sat 22/08/15
32 32 6.7 Pengecatan dinding luar baru 9 days Sun 23/08/15 Mon 31/08/15
33 33 7 Pekerjaan Lantai 6 days Wed 29/07/15 Mon 03/08/15
34 34 7.1 Pemasangan tegel keramik 40 cm x 40 cm 5 days Wed 29/07/15 Sun 02/08/15
35 35 7.2 Pemasangan tegel keramik 30 cm x 30 cm 4 days Thu 30/07/15 Sun 02/08/15
36 36 7.3 Pemasangan tegel keramik 20 cm x 20 cm 1 day Sun 02/08/15 Sun 02/08/15
37 37 7.4 Pemasangan tegel plin dinding keramik dinding (kamar mandi & dapur) 1 day Mon 03/08/15 Mon 03/08/15

38 38 8 Pekerjaan Atap 19 days Sat 18/07/15 Wed 05/08/15


39 39 8.1 Pemasangan Kuda-Kuda Kayu Kamper (bentang max 7 m) 3 days Sat 18/07/15 Mon 20/07/15

40 40 8.2 Pemasangan gording kayu kamper 8/12 1 day Tue 21/07/15 Tue 21/07/15
41 41 8.3 Pemasangan wuwung genteng jawa 1 day Wed 29/07/15 Wed 29/07/15

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: PWBK Rumah Sederhan
Summary Manual Summary Rollup Progress
Date: Thu 21/05/15
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
ID Task No. WBS Task Name Duration Start Finish
Mode
42 42 8.4 Pemasangan usuk kayu kamper 5/7 dan reng kayu kamper 3/5 4 days Wed 22/07/15 Sat 25/07/15

43 43 8.5 Pemasangan Genteng Jawa (soka) 3 days Sun 26/07/15 Tue 28/07/15
44 44 8.6 Pemasangan Listplank kayu kamper 2/20 2 days Tue 04/08/15 Wed 05/08/15
45 45 8.7 Pemasangan Talang Tritisan dari Seng BJLS 30 (lebar 60 cm) 6 days Wed 29/07/15 Mon 03/08/15

46 46 9 Pekerjaan Plafon 16 days Wed 29/07/15 Thu 13/08/15


47 47 9.1 Pemasangan rangka plafon 7 days Wed 29/07/15 Tue 04/08/15
48 48 9.2 Pemasangan plafon 9 days Wed 05/08/15 Thu 13/08/15
49 49 9.3 Pemasangan list plafon uk. 1/5 2 days Wed 12/08/15 Thu 13/08/15
50 50 10 Pekerjaan Kusen 3 days Fri 03/07/15 Sun 05/07/15
51 51 10.1 Kusen Pintu kayu kamper 3 days Fri 03/07/15 Sun 05/07/15
52 52 10.2 Kusen Jendela Kayu Kamper 1 day Fri 03/07/15 Fri 03/07/15
53 53 11 Pekerjaan Pintu 82 days Sun 17/05/15 Thu 06/08/15
54 54 11.1 Daun Pintu Papan Kayu Kamper 9 days Wed 29/07/15 Thu 06/08/15
55 55 11.2 Pemasangan Engsel Kuningan Pintu 2 days Sun 17/05/15 Mon 18/05/15
56 56 11.3 Pemangan Kunci Tanam 1 day Sun 17/05/15 Sun 17/05/15
57 57 11.4 Pemasangan Grendel (besar) 1 day Sun 17/05/15 Sun 17/05/15
58 58 12 Pekerjaan Jendela 89 days Sun 17/05/15 Thu 13/08/15
59 59 12.1 Daun Jendela kayu kamper (belum kaca) 6 days Fri 07/08/15 Wed 12/08/15
60 60 12.2 Pemasangan Kaca Nako 5 mm 1 day Thu 13/08/15 Thu 13/08/15
61 61 12.3 Pemasangan Engsel Kuningan Jendela 1 day Sun 17/05/15 Sun 17/05/15
62 62 12.4 Pemasangan Grendel Tanam 1 day Sun 17/05/15 Sun 17/05/15
Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: PWBK Rumah Sederhan
Summary Manual Summary Rollup Progress
Date: Thu 21/05/15
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3
ID Task No. WBS Task Name Duration Start Finish
Mode
63 63 13 Pembuatan Septictank 5 days Fri 19/06/15 Tue 23/06/15
64 64 13.1 Penggalian tanah 2 days Fri 19/06/15 Sat 20/06/15
65 65 13.2 Bekisting dinding septictank 2 days Sun 21/06/15 Mon 22/06/15
66 66 13.3 Bekisting dinding pemisah septictank 1 day Sun 21/06/15 Sun 21/06/15
67 67 13.4 Lantai kerja k-100 1 day Tue 23/06/15 Tue 23/06/15
68 68 13.5 Beton + trasram dinding septictank 1 day Tue 23/06/15 Tue 23/06/15
69 69 13.6 Beton + trasram dinding pemisah septictank 1 day Tue 23/06/15 Tue 23/06/15
70 70 14 Pembuatan Sumur Resapan 9 days Fri 19/06/15 Sat 27/06/15
71 71 14.1 Penggalian tanah 3 days Fri 19/06/15 Sun 21/06/15
72 72 14.2 Bekisting dinding 1 day Mon 22/06/15 Mon 22/06/15
73 73 14.3 Lantai Kerja K 100 1 day Tue 23/06/15 Tue 23/06/15
74 74 14.4 Trasram 1 day Fri 26/06/15 Fri 26/06/15
75 75 14.5 Lapisan ijuk 1 day Sat 27/06/15 Sat 27/06/15
76 76 14.6 Tembok non spesi 1 day Sat 27/06/15 Sat 27/06/15
77 77 14.7 Kerikil kasar 1 day Sat 27/06/15 Sat 27/06/15
78 78 14.8 Kerikil halus 1 day Sat 27/06/15 Sat 27/06/15
79 79 14.9 Pasir 1 day Sat 27/06/15 Sat 27/06/15
80 80 15 Pembuatan Bak Kontrol 5 days Sun 28/06/15 Thu 02/07/15
81 81 15.1 Penggalian tanah 1 day Sun 28/06/15 Sun 28/06/15
82 82 15.2 Lantai kerja K 100 1 day Mon 29/06/15 Mon 29/06/15
83 83 15.3 Pekerjaan beton 1 day Mon 29/06/15 Mon 29/06/15
84 84 15.4 Trasram 1 day Thu 02/07/15 Thu 02/07/15

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: PWBK Rumah Sederhan
Summary Manual Summary Rollup Progress
Date: Thu 21/05/15
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 4
ID Task No. WBS Task Name Duration Start Finish
Mode
85 85 16 Pekerjaan Sanitasi Air 31 days Fri 03/07/15 Sun 02/08/15
86 86 16.1 Pemasangan pipa air bersih 1 day Fri 03/07/15 Fri 03/07/15
87 87 16.2 Pemasangan pipa air kotor 2 days Sat 04/07/15 Sun 05/07/15
88 88 16.3 Pemasangan pipa saluran tinja 1 day Mon 06/07/15 Mon 06/07/15
89 89 16.4 Pemasangan kran air 1 day Tue 07/07/15 Tue 07/07/15
90 90 16.5 Pemasangan kloset duduk 2 days Sat 01/08/15 Sun 02/08/15
91 91 16.6 Pemasangan wastafel 2 days Sat 01/08/15 Sun 02/08/15
92 92 17 Pekerjaan Instalasi Listrik 37 days Wed 08/07/15 Thu 13/08/15
93 93 17.1 Pemasangan titik stop kontak rumah 1 day Wed 08/07/15 Wed 08/07/15
94 94 17.2 Pemasangan titik lampu gedung 4 days Mon 10/08/15 Thu 13/08/15
95 95 17.3 Pemasangan saklar tunggal 1 day Thu 09/07/15 Thu 09/07/15
96 96 17.4 Pemasangan saklar ganda 1 day Thu 09/07/15 Thu 09/07/15
97 97 18 Pembuatan Pagar 7 days Fri 14/08/15 Thu 20/08/15
98 98 18.1 Pekerjaan pembuatan pagar besi 6 days Fri 14/08/15 Wed 19/08/15
99 99 18.2 Pemasangan pintu pagar besi 1 day Thu 20/08/15 Thu 20/08/15
100 100 19 Pekerjaan Finishing 4 days Tue 01/09/15 Fri 04/09/15
101 101 19.1 Pemasangan wallpaper 4 days Tue 01/09/15 Fri 04/09/15

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: PWBK Rumah Sederhan
Summary Manual Summary Rollup Progress
Date: Thu 21/05/15
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 5
Predecessors
15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20

4
11
17
5FS-1 day
22

12
8

6
14FF
6
16

15
19FF
20FS+3 days

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: PWBK Rumah Sederhan
Summary Manual Summary Rollup Progress
Date: Thu 21/05/15
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 6
Predecessors
15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20
21

26

17FS+3 days
17FS+3 days
26
28FF
28
30FS+3 days
31

43
34FF
34FF
34

24FS+3 days

39
43

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: PWBK Rumah Sederhan
Summary Manual Summary Rollup Progress
Date: Thu 21/05/15
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 7
Predecessors
15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20
40

42
45
43

43
47
48FF

26SS+3 days
26SS+3 days

43

54
59

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: PWBK Rumah Sederhan
Summary Manual Summary Rollup Progress
Date: Thu 21/05/15
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 8
Predecessors
15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20

6
64
64
65
65
65

6
71
72
73FS+2 days
74
74
74
74
74

79
81
81
83FS+2 days

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: PWBK Rumah Sederhan
Summary Manual Summary Rollup Progress
Date: Thu 21/05/15
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 9
Predecessors
15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20

84
86
87
88
36FF
36FF

26
48FF
93
93

30FS+3 days
98

32

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: PWBK Rumah Sederhan
Summary Manual Summary Rollup Progress
Date: Thu 21/05/15
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 10
20 21 22 23 24 25 26 27 28 29 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: PWBK Rumah Sederhan
Summary Manual Summary Rollup Progress
Date: Thu 21/05/15
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 11
20 21 22 23 24 25 26 27 28 29 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: PWBK Rumah Sederhan
Summary Manual Summary Rollup Progress
Date: Thu 21/05/15
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 12
20 21 22 23 24 25 26 27 28 29 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: PWBK Rumah Sederhan
Summary Manual Summary Rollup Progress
Date: Thu 21/05/15
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 13
20 21 22 23 24 25 26 27 28 29 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: PWBK Rumah Sederhan
Summary Manual Summary Rollup Progress
Date: Thu 21/05/15
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 14
20 21 22 23 24 25 26 27 28 29 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: PWBK Rumah Sederhan
Summary Manual Summary Rollup Progress
Date: Thu 21/05/15
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 15
30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: PWBK Rumah Sederhan
Summary Manual Summary Rollup Progress
Date: Thu 21/05/15
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 16
30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: PWBK Rumah Sederhan
Summary Manual Summary Rollup Progress
Date: Thu 21/05/15
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 17
30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: PWBK Rumah Sederhan
Summary Manual Summary Rollup Progress
Date: Thu 21/05/15
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 18
30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: PWBK Rumah Sederhan
Summary Manual Summary Rollup Progress
Date: Thu 21/05/15
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 19
30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: PWBK Rumah Sederhan
Summary Manual Summary Rollup Progress
Date: Thu 21/05/15
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 20

Anda mungkin juga menyukai