Schedule MS Project
Schedule MS Project
Start Finish Act. Start 28 Jun '21 05 Jul '21 12 Jul '21 19 Jul '21 26 Jul '21 02 Aug '21 09 Aug '21 16 Aug '21 23 Aug '21 30 Aug '21 06 Sep '21 13 Sep '21 20 Sep '21 27 Sep '21
300102030405060708091011121314151617181920212223242526272829303101020304050607080910111213141516171819202122232425262728293031010203040506070809101112131415161718192021222324252627282930
0 PRIME PARK & CONVENTION LOMBOK 90 daysThu 01/07/21 Tue 28/09/21 NA
4 Pekerjaan Pemasangan lampu taman 3FS+5 days 2 daysSat 10/07/21Sun 11/07/21 NA 10/07 11/07
9 Penarikan kabel Tegangan Menengah 8FS+5 days 4 daysSat 17/07/21Tue 20/07/21 NA 17/07 20/07
12 Pek. Pasang batu kali untuk jembatan 7FF 7 Thu Wed 04/08/21 NA 29/07 04/08
ramp belakang sisi hotel grand madani days 29/07/21
13 Pek. Penambahan badan jalan ramp 12 5 Thu Mon 09/08/21 NA 05/08 09/08
belakang yang ketemu DPT belakang days 05/08/21
18 Instalasi Penerangan Landscape sisi Pagar 16FF+3 days 7 Wed Tue 10/08/21 NA 04/08 10/08
Selatan dan belakang days 04/08/21
19 Pek. Pagar finishing plester beton dan 30 Thu Fri 30/07/21 01/07
NA 30/07
kamprot (DPT beton) days 01/07/21
20 Pek. Rumah pompa dan perapihan rumah 14FF 4 Tue Fri 13/08/21 NA 10/08 13/08
tangki minyak (solar) days 10/08/21
26 Pek. Pengganti DPT beton menjadi 23FF+10 days 21 Tue Mon 09/08/21 NA 20/07 09/08
pasangan bata ringan untuk perimeter / days 20/07/21
pot bunga
27 Pek. Baja Canopy Entrance 14 days
Sun 25/07/21Sat 07/08/21 NA 25/07 07/08
40 Pek. Tutup sumpit dan switch PH 37FF 7 daysSat 24/07/21Fri 30/07/21 NA 24/07 30/07
Page 1
ID Task Name Predecessors Duration
Start Finish Act. Start 28 Jun '21 05 Jul '21 12 Jul '21 19 Jul '21 26 Jul '21 02 Aug '21 09 Aug '21 16 Aug '21 23 Aug '21 30 Aug '21 06 Sep '21 13 Sep '21 20 Sep '21 27 Sep '21
300102030405060708091011121314151617181920212223242526272829303101020304050607080910111213141516171819202122232425262728293031010203040506070809101112131415161718192021222324252627282930
47 Pek. Keramik titanium lobby lift passenger 46 4 daysFri 13/08/21Mon 16/08/21 NA 13/08 16/08
54 Pek. Pasangan dinding bata ringan double 4 Sun Wed 04/08/21 NA 01/08 04/08
ex. area subkont days 01/08/21
55 Pek. Plester dan aci dinding bata ringan 54FF+4 days 3 Fri Sun 08/08/21 NA 06/08 08/08
double ex. Area kantor subkont days 06/08/21
58 Pek. Exposed area kantor sukont dan 32 6 Wed Mon 16/08/21 NA 11/08 16/08
gudang sanitary days 11/08/21
60 Pek. Penyelesaian / penuntasan ruang Fan 6 daysSun 08/08/21Fri 13/08/21 NA 08/08 13/08
61 Pek. Pemasangan unit fan dan ducting 59 5 daysFri 20/08/21Tue 24/08/21 NA 20/08 24/08
78 Pek. Keramik lantai area wedding gallery 70FF+2 days 14 Sat Fri 30/07/21 NA 17/07 30/07
& pre function days 17/07/21
79 Pek Inst Elektrikal lantai wedding gallery 78FF+2 days 6 daysTue 27/07/21
Sun 01/08/21 NA 27/07 01/08
81 Pek Inst Elektrikal kanopi drop off 82 4 daysSun 18/07/21Wed 21/07/21 NA 18/07 21/07
82 Pek Instalasi air hujan di area drop off 83SS 4 daysWed 14/07/21
Sat 17/07/21 NA 14/07 17/07
85 Pek. Pemasangan armatur lampu 84FF+1 day 8 daysSat 17/07/21Sat 24/07/21 NA 17/07 24/07
92 Pekerjaan Ins penerangan elektrikal coridor84 7 daysSat 24/07/21Fri 30/07/21 NA 24/07 30/07
Page 2
ID Task Name Predecessors Duration
Start Finish Act. Start 28 Jun '21 05 Jul '21 12 Jul '21 19 Jul '21 26 Jul '21 02 Aug '21 09 Aug '21 16 Aug '21 23 Aug '21 30 Aug '21 06 Sep '21 13 Sep '21 20 Sep '21 27 Sep '21
300102030405060708091011121314151617181920212223242526272829303101020304050607080910111213141516171819202122232425262728293031010203040506070809101112131415161718192021222324252627282930
95 Pek. Ins Elektrikal dan elektronik Ballroom 92FF+2 days 14 days
Mon 19/07/21
Sun 01/08/21 NA 19/07 01/08
106 Pek. Ins penerangan dan elektrikal toilet 105FF+2 days 4 daysWed 18/08/21
Sat 21/08/21 NA 18/08 21/08
107 Pek. Pemasangan outlet dan lampu 103 3 daysSun 15/08/21Tue 17/08/21 NA 15/08 17/08
113 Pek. Pemasangan outlet dan lampu tangga 1206SS 7 daysWed 18/08/21
Tue 24/08/21 NA 18/08 24/08
114 Pek. Penyelesaian tangga 1 (pas. Dinding bata) Lt. 4 - Lt. 10 14 days
Sun 01/08/21Sat 14/08/21 NA 01/08 14/08
116 Pek. Pemasangan Panel Elektrikal lt BS-10 114 7 daysSun 15/08/21Sat 21/08/21 NA 15/08 21/08
118 Pek.Terminasi power elektrikal per lantai 116 7 daysSun 22/08/21Sat 28/08/21 NA 22/08 28/08
119 Pek. Splicing kabel elektronik per lantai 117 4 daysMon 16/08/21
Thu 19/08/21 NA 16/08 19/08
133 Pek. Dinding marmer lobby lift 126 5 daysSat 31/07/21Wed 04/08/21 NA 31/07 04/08
143 Pek. Plester dan acian 7 daysSun 25/07/21Sat 31/07/21 NA 25/07 31/07
144 Pek. Pasang keramik dinding 143 7 daysSun 01/08/21Sat 07/08/21 NA 01/08 07/08
146 Pek. Ins Elektrikal dan elektronik 145FF+2 days 7 daysThu 05/08/21
Wed 11/08/21 NA 05/08 11/08
147 Pek pemasangan armatur lampu dan outlet146FF+2 days 7 daysSat 07/08/21Fri 13/08/21 NA 07/08 13/08
Page 3
ID Task Name Predecessors Duration
Start Finish Act. Start 28 Jun '21 05 Jul '21 12 Jul '21 19 Jul '21 26 Jul '21 02 Aug '21 09 Aug '21 16 Aug '21 23 Aug '21 30 Aug '21 06 Sep '21 13 Sep '21 20 Sep '21 27 Sep '21
300102030405060708091011121314151617181920212223242526272829303101020304050607080910111213141516171819202122232425262728293031010203040506070809101112131415161718192021222324252627282930
148 Pek. Cor nad dinding 7 daysThu 01/07/21
Wed 07/07/21 01/07
NA 07/07
158 Pek pemasangan armatur lampu dan outlet154FF+2 days 8 daysMon 16/08/21
Mon 23/08/21 NA 16/08 23/08
167 Pekerjaan ins Plumbing 156 4 daysSat 21/08/21Tue 24/08/21 NA 21/08 24/08
168 Pek. Ins Elektrikal dan elektronik 157 5 daysFri 27/08/21Tue 31/08/21 NA 27/08 31/08
169 Pek pemasangan armatur lampu dan outlet174FF+4 days 5 daysSat 04/09/21Wed 08/09/21 NA 04/09 08/09
170 Pek. Pasang batu alam kolam renang 174FF+5 days 21 days
Fri 20/08/21Thu 09/09/21 NA 20/08 09/09
172 Pek. Pemasangan unit balancing tank 171FF 5 daysFri 10/09/21Tue 14/09/21 NA 10/09 14/09
173 Pek. Pemasangan armatur kolam renang 165,170 5 daysFri 10/09/21Tue 14/09/21 NA 10/09 14/09
180 Pekerjaan pemasangn lampu façade (SI) 179 7 daysSat 28/08/21Fri 03/09/21 NA 28/08 03/09
182 Pekerjaan pemasangn lampu façade (SI) 181 7 daysSat 14/08/21Fri 20/08/21 NA 14/08 20/08
186 Pekerjaan pemasangn lampu façade (SI) 185FF+4 days 7 daysWed 22/09/21
Tue 28/09/21 NA 22/09 28/09
Page 4