ID Task Task Name DurationStart Finish Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018

Mode Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
1 GENERAL CONDITION 253 days 18/10 27/06
2 Sign Contract 1 day TBD TBD
3 Effective date 1 day 19/10 19/10
4 Berita Acara Serah Terima Lahan (BASTL) 0 days 19/10 19/10 19/10
5 Berita Acara Serah Terima I (BAST I) 0 days 27/06 27/06 27/06
6 Preparation Work 30 days 05/11 04/12
7 Mobilization & Demobilization Personil Proyek 2 days 05/11 06/11
8 Pemasangan Plank Nama Proyek 1 day 07/11 07/11
9 Pemasangan bowplank 3 days 08/11 10/11
10 Pemasangan Pagar keliling 7 days 11/11 17/11
11 Pembangunan Kantor Lapangan 4 days 18/11 21/11
12 Pemasangan gudang 4 days 22/11 25/11
13 Pengadaan sumber air 1 day 26/11 26/11
14 Pengadaan sumber Listrik 1 day 27/11 27/11
15 Timbunan Tanah dan pemadatan 2 days 28/11 29/11
16 landscapping (gebalan rumput) 2 days 30/11 01/12
17 Pekerjaan Pembentukan Lereng di depan Retaining wall 3 days 02/12 04/12
18 ENGINEERING 18 days 18/10 08/11
19 DESIGN ENGINEERING SLOPE PROTECTION LERENG TEBING 22 days 18/10 08/11
20 Boring test 1 day 18/10 18/10
21 Release boring report 10 days 19/10 31/10
22 Basic Design 2 days 01/11 02/11
23 Technical Specifications 1 day 03/11 03/11
24 Submit drawing for Approval 2 days 05/11 06/11
25 Release BOQ 1 day 07/11 07/11
26 Issued for Construction (IFC) drawing 1 day 08/11 08/11
27 ENGINEERING E/M 150 Kv 2 LINE BAY EQUIPMENT 5 days 26/10 30/10
28 Received approved drawing and TPG from PT PLN UIP II Medan 1 day 26/10 26/10
29 Three phase busbar Disconnector, 1250 A, 31,5 kA 1 day 26/10 26/10
30 150 kV Single Phase Capacitor Voltage transformer as per TPG in line MTU 1 day 26/10 26/10
31 Outdoor Marshalling Kiosks 1 day 26/10 26/10
32 110V DC battery, 240AH, 8 hours and 1 set charger 80A complete 1 day 26/10 26/10
33 48V DC battery, 150AH, 8 hours and 1 set charger 60A complete 1 day 26/10 26/10
34 110 V DC distribution board complete with MCB for HV equipment 1 day 26/10 26/10
35 48 VDC Distribution Board complete with MCB and include necessary 1 day 26/10 26/10
36 220/380 VAC Distribution Board complete with MCB for HV 1 day 26/10 26/10
37 LV Power and multicore Control Cables include all accessories to 1 day 26/10 26/10
38 Fiber Optic Communication Equipment's 1 day 26/10 26/10
39 Issued requisition for material procurement 2 days 27/10 30/10
40 ENGINEERING POWER TRANSFORMER (1 X 30 MVA ) EQUIPMENT 3 days 30/10 01/11

Task Project Summary Manual Task Start-only Deadline

Project: SCHEDULE GI 150 KV P Split Inactive Task Duration-only Finish-only Progress


Date: 30/10 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
ID Task Task Name DurationStart Finish Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018
Mode Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
41 Received approved drawing and TPG from PT PLN UIP II Medan 1 day 30/10 30/10
42 150/20 kV, 30 MVA 3-phase Power Transformer, oil, and all 1 day 30/10 30/10
43 150 kV NCT included accessories to complete scope of work 1 day 30/10 30/10
44 Transformer Regulation Panel complete with AVR and other acc. 1 day 30/10 30/10
45 Issued requisition for material procurement 2 days 31/10 01/11
46 ENGINEERING CONDUCTOR, STRING INSULATOR, GSW & ACC, HV 3 days 30/10 01/11
CONNECTOR, GROUNDINGAND LIGHTING SYSTEM (Priority)
47 Received approved drawing and TPG from PT PLN UIP II Medan 1 day 30/10 30/10
48 Conductor 1 x A3C 630 mm2 for double main busbar arrangement 1 day 30/10 30/10
49 Conductor 1 x A3C 300 mm2 for cross busbar & droppers/jumpers 1 day 30/10 30/10
50 GSW 55 mm2 complete with fitting, and accessories to complete 1 day 30/10 30/10
51 Single tension string insulator set & hardware (1 set consist of 1 day 30/10 30/10
52 Single suspension string insulator set & hardware (1 set consist of 1 day 30/10 30/10
53 HV connector suitable for : A3C 630 mm2, A3C 300 mm2 to HV 1 day 30/10 30/10
54 Grounding system for line whole of substation equipment, 1 day 30/10 30/10
55 Lighting for outdoor switchyard and gantry 1 day 30/10 30/10
56 Issued requisition for material procurement 2 days 31/10 01/11
57 ENGINEERING SUBSTATION AUTOMATION SYSTEM (SAS) 3 days 30/10 01/11
58 Received approved drawing and TPG from PT PLN UIP II Medan 1 day 30/10 30/10
59 Protection and Control Cubicle for 150 kV Line Bay 1 day 30/10 30/10
60 Protection and Control Cubicle for Transformer Bay 1 day 30/10 30/10
61 Central Control Equipment / HMI Client & Server (Operator Workstation) 1 day 30/10 30/10
62 Substation Automation Software : 1 day 30/10 30/10
63 AC Supply Equipment 1 day 30/10 30/10
64 Issued requisition for material procurement 2 days 31/10 01/11
65 ENGINEERING E/M 150/20 KV TRANSFORMER BAY ( 1 TRAFO BAY) EQUIPMENT 3 days 30/10 01/11
66 Received approved drawing and TPG from PT PLN UIP II Medan 1 day 30/10 30/10
67 Three phase Circuit Breaker, 1250A, 31.5kA symmetrical short 1 day 30/10 30/10
68 Three phase Busbar Disconnector, 1250A, 31.5kA, 1 sec, with 1 day 30/10 30/10
69 Single phase Current Transformer comprising : 1 day 30/10 30/10
70 Heavy duty outdoor single phase Lightning Arrester, metal oxide 1 day 30/10 30/10
71 Outdoor marshalling kiosk 1 day 30/10 30/10
72 LV Power and multicore Control Cables include all accessories to 1 day 30/10 30/10
73 Remote Control panel for 20 kV Cubicle complete accessories 1 day 30/10 30/10
74 Issued requisition for material procurement 2 days 31/10 01/11
75 ENGINEERING 20 kV SWITCHGEAR, POWER CABLE AND AUXILIARY TRANSFORMER 3 days 30/10 01/11
76 Received approved drawing and TPG from PT PLN UIP II Medan 1 day 30/10 30/10
77 20 kV XLPE power cable 2 x Cu400 mm2/phase, including cable 1 day 30/10 30/10
78 20 KV Busbar Voltage Transformer and Earthing swicth cubicle as per TPG 1 day 30/10 30/10
79 200 KVA 20/0 4 KV auxilliary Transformer include power Cable 1 day 30/10 30/10

Task Project Summary Manual Task Start-only Deadline

Project: SCHEDULE GI 150 KV P Split Inactive Task Duration-only Finish-only Progress


Date: 30/10 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 2
ID Task Task Name DurationStart Finish Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018
Mode Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
80 Issued requisition for material procurement 2 days 31/10 01/11
81 ENGINEERING ELECTRIC LIGHTING INSTALLATION 4 days 19/10 22/10
82 Received approved drawing and TPG from PT PLN UIP II Medan 1 day 19/10 19/10
83 Cable NYFGBY (2 x 4mm) 1 day 19/10 19/10
84 Lampu Penerangan Gantry 250 W (lampu sorot) 1 day 19/10 19/10
85 Lampu Penerangan Jalan 250 W +Tiang 1 day 19/10 19/10
86 Issued requisition for material procurement 2 days 20/10 22/10
87 ENGINEERING FENCING SWITCHYARD AREA 2 days 19/10 20/10
88 Received approved drawing and TPG from PT PLN UIP II Medan 1 day 19/10 19/10
89 Issued requisition for material procurement 1 day 20/10 20/10
90 ENGINEERING ROAD, LISBAN AND DRAINAGE 3 days 19/10 22/10
91 Received approved drawing and TPG from PT PLN UIP II Medan 1 day 19/10 19/10
92 Issued requisition for material procurement 2 days 20/10 22/10
93 ENGINEERING ISLAMIC PRAYER ROOM, GUARDHOUSE, OPERATOR'S HOME 3 days 30/10 01/11
AND LANGSCAPING
94 Received approved drawing and TPG from PT PLN UIP II Medan 1 day 30/10 30/10
95 Mushalla 1 day 30/10 30/10
96 Rumah Operator 1 day 30/10 30/10
97 Pos Jaga 1 day 30/10 30/10
98 Taman 1 day 30/10 30/10
99 Issued requisition for material procurement 2 days 31/10 01/11
100 PROCUREMENT 179 days 18/10 20/06
101 SUBCONTRACTING CIVIL WORK 18 days 01/11 22/11
102 Receive Requistion 1 day 01/11 01/11
103 Issued requistion for quotation (RFQ) 1 day 02/11 02/11
104 Commercial Clarification and Negotiation 1 day 03/11 03/11
105 Award Purchase Order (PO) 14 days 05/11 21/11
106 Sign Agreement and payment DP 1 day 22/11 22/11
107 SUBCONTRACTING SLOPE PROTECTION WORK LERENG TEBING 18 days 09/11 01/12
108 Receive Requistion 1 day 09/11 09/11
109 Issued requistion for quotation (RFQ) 1 day 10/11 10/11
110 Commercial Clarification and Negotiation 1 day 12/11 12/11
111 Award Purchase Order (PO) 14 days 13/11 30/11
112 Sign Agreement and payment DP 1 day 01/12 01/12
113 MATERIAL RELOKASI ex GI KILIRANJAO ( DISMANTLING) 34 days 23/10 05/12
114 Receive Requistion 1 day 23/10 23/10
115 Issued requistion for quotation (RFQ) 1 day 24/10 24/10
116 Commercial Clarification and Negotiation 1 day 25/10 25/10
117 Award Purchasin Order (PO) 14 days 26/10 12/11
118 Subcontracting Sign Agreement and payment DP 1 day 13/11 13/11

Task Project Summary Manual Task Start-only Deadline

Project: SCHEDULE GI 150 KV P Split Inactive Task Duration-only Finish-only Progress


Date: 30/10 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 3
ID Task Task Name DurationStart Finish Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018
Mode Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
119 Individual Test + dismantling + Packing 11 days 14/11 28/11
120 Three phase Circuit Breaker, 1250 A, 31,5 kA symmetrical short 2 days 14/11 15/11
121 Three phase line Disconnector w/ earthing switch 1250 A,31,5 kA, 1 day 16/11 16/11
122 Single phase Current Transformer 3 days 17/11 21/11
123 Single phase Capacitor Voltage Transformer ratio 150.000:3 3 days 22/11 24/11
124 Communication Facilities 1 day 27/11 27/11
125 Line Trap 1 day 28/11 28/11
126 Delivery Transportation/Shippment 5 days 29/11 05/12
127 Three phase Circuit Breaker, 1250 A, 31,5 kA symmetrical short 7 days 29/11 05/12
128 Three phase line Disconnector w/ earthing switch 1250 A,31,5 kA, 7 days 29/11 05/12
129 Single phase Current Transformer 7 days 29/11 05/12
130 Single phase Capacitor Voltage Transformer ratio 150.000:3 7 days 29/11 05/12
131 Communication Facilities 7 days 29/11 05/12
132 Line Trap 7 days 29/11 05/12
133 PROCUREMENT E/M 150 KV 2 LINE BAY EQUIPMENT 179 days 18/10 20/06
134 Material 149 days 31/10 23/05
135 Receive Requistion 1 day 31/10 31/10
136 Issued requistion for quotation (RFQ) 1 day 01/11 01/11
137 Commercial Clarification and Negotiation 1 day 02/11 02/11
138 Award Purchase Order (PO) 3 days 03/11 06/11
139 Sign Agreement and payment DP 1 day 07/11 07/11
140 Fabrication 140 days 08/11 21/05
141 Three phase busbar Disconnector, 1250 A, 31,5 kA 140 days 08/11 21/05
142 150 kV Single Phase Capasitor Voltage Transformer as per TPG 140 days 08/11 21/05
143 Outdoor Marshalling Kiosks 140 days 08/11 21/05
144 110V DC Battery, 240AH, 8 hours and 1 set charger 80A 140 days 08/11 21/05
145 48V DC Battery, 150AH, 8 hours and 1 set charger 60A 140 days 08/11 21/05
146 110 V DC distribution board complete with MCB for HV equipment 140 days 08/11 21/05
147 48 VDC Distribution Board complete with MCB and include necessary 140 days 08/11 21/05
148 220/380 VAC Distribution Board complete with MCB for HV 140 days 08/11 21/05
149 LV Power and multicore Control Cables include all accessories to 140 days 08/11 21/05
150 Fiber Optic Communication Equipments 140 days 08/11 21/05
151 submit request Inspection FAT with PT PLN & PT RE 20 days 24/04 21/05
152 Inspection FAT 1 day 22/05 22/05
153 Ready for delivery 1 day 23/05 23/05
154 Transportation (Forwarder) 5 days 18/10 23/10
155 Receive Requistion 1 day 18/10 18/10
156 Issued requistion for quotation (RFQ) 1 day 19/10 19/10
157 Commercial Clarification and Negotiation 1 day 20/10 20/10
158 Award Purchase Order (PO) 1 day 22/10 22/10

Task Project Summary Manual Task Start-only Deadline

Project: SCHEDULE GI 150 KV P Split Inactive Task Duration-only Finish-only Progress


Date: 30/10 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 4
ID Task Task Name DurationStart Finish Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018
Mode Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
159 Sign Agreement and payment DP 1 day 23/10 23/10
160 Domestic Delivery Transportation/Shippment include port custom clrearence15 days 24/05 13/06
161 Three phase busbar Disconnector, 1250 A, 31,5 kA 21 days 24/05 13/06
162 Outdoor Marshalling Kiosks 21 days 24/05 13/06
163 110V DC battery, 240AH, 8 hours and 1 set charger 80A 21 days 24/05 13/06
164 48V DC battery, 150AH, 8 hours and 1 set charger 60A 21 days 24/05 13/06
165 110 V DC distribution board complete with MCB for HV equipment 21 days 24/05 13/06
166 48 VDC Distribution Board complete with MCB and include necessary 21 days 24/05 13/06
167 220/380 VAC Distribution Board complete with MCB for HV 21 days 24/05 13/06
168 LV Power and multicore Control Cables include all accessories to 21 days 24/05 13/06
169 Fiber Optic Communication Equipments 21 days 24/05 13/06
170 Shippment From India include custom clearence 22 days 22/05 20/06
171 150 kV Single Phase Capasitor Voltage Transformer as per TPG 30 days 22/05 20/06
172 STEEL STRUCTURE/GANTRY, CONDUCTOR, STRING INSULATOR, GSW & ACC, 113 20/10 22/03
HV CONNECTOR, GROUNDING AND LIGHTNING SYSTEM days
173 Material 98 days 02/11 15/03
174 Receive Requistion 1 day 02/11 02/11
175 Issued requistion for quotation (RFQ) 1 day 03/11 03/11
176 Commercial Clarification and Negotiation 1 day 05/11 05/11
177 Award Purchase Order (PO) 1 day 06/11 06/11
178 Sign Agreement and payment DP 3 days 07/11 09/11
179 Fabrication 90 days 10/11 14/03
180 Steel structure/gantry (refer to drawing) 90 days 10/11 14/03
181 Conductor 1 x A3C 630 mm2 for double main busbar arrangement 90 days 10/11 14/03
182 Conductor 1 x A3C 300 mm2 for cross busbar & droppers/jumpers 90 days 10/11 14/03
183 GSW 55 mm2 complete with fitting, and accessories to complete 90 days 10/11 14/03
184 Single tension string insulator set & hardware (1 set consist of 90 days 10/11 14/03
185 Single suspension string insulator set & hardware (1 set consist of 90 days 10/11 14/03
186 HV connector suitable for : A3C 630 mm2, A3C 300 mm2 to HV 90 days 10/11 14/03
187 Grounding system for line whole of substation equipment, 90 days 10/11 14/03
188 Lighting for outdoor switchyard and gantry 90 days 10/11 14/03
189 Submit request Inspection FAT with PT PLN and PT RE 20 days 15/02 14/03
190 Inspection FAT 1 day 14/03 14/03
191 Ready for delivery 1 day 15/03 15/03
192 Transportation (Forwarder) 5 days 20/10 25/10
193 Receive Requistion 1 day 20/10 20/10
194 Issued requistion for quotation (RFQ) 1 day 22/10 22/10
195 Commercial Clarification and Negotiation 1 day 23/10 23/10
196 Award Purchase Order (PO) 1 day 24/10 24/10
197 Sign Agreement and payment DP 1 day 25/10 25/10

Task Project Summary Manual Task Start-only Deadline

Project: SCHEDULE GI 150 KV P Split Inactive Task Duration-only Finish-only Progress


Date: 30/10 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 5
ID Task Task Name DurationStart Finish Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018
Mode Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
198 Shippment include port custom clearence 5 days 16/03 22/03
199 Assembly Steel structure/gantry 7 days 16/03 22/03
200 Conductor 1 x A3C 630 mm2 for double main busbar arrangement 7 days 16/03 22/03
201 Conductor 1 x A3C 300 mm2 for cross busbar & droppers/jumpers 7 days 16/03 22/03
202 GSW 55 mm2 complete with fitting, and accessories to complete 7 days 16/03 22/03
203 Single tension string insulator set & hardware 7 days 16/03 22/03
204 Single suspension string insulator set & hardware 7 days 16/03 22/03
205 HV connector suitable for : A3C 630 mm2, A3C 300 mm2 to HV 7 days 16/03 22/03
206 Grounding system for line whole of substation equipment, 7 days 16/03 22/03
207 Lighting for outdoor switchyard and gantry 7 days 16/03 22/03
208 PROCUREMENT SUBSTATION AUTOMATION SYSTEM (SAS) EQUIPMENT 124 days 20/10 06/04
209 Material 99 days 02/11 16/03
210 Receive Requistion 1 day 02/11 02/11
211 Issued requistion for quotation (RFQ) 1 day 03/11 03/11
212 Commercial Clarification and Negotiation 1 day 05/11 05/11
213 Award Purchase Order (PO) 1 day 06/11 06/11
214 Sign agreement and payment DP 3 days 07/11 09/11
215 Fabrication 90 days 10/11 14/03
216 Protection and Control Cubicle for 150 kV Line Bay 90 days 10/11 14/03
217 Protection and Control Cubicle for Transformer Bay 90 days 10/11 14/03
218 Central Control Equipment / HMI Client & Server (Operator Workstation)90 days 10/11 14/03
219 Substation Automation Software : 90 days 10/11 14/03
220 AC Supply Equipment 90 days 10/11 14/03
221 Submit request Inspection FAT with PT PLN & PT RE 20 days 15/02 14/03
222 Inspection FAT 1 day 15/03 15/03
223 Ready for delivery 1 day 16/03 16/03
224 Selection Transportation (Forwarder) 5 days 20/10 25/10
225 Receive Requistion 1 day 20/10 20/10
226 Issued requistion for quotation (RFQ) 1 day 22/10 22/10
227 Commercial Clarification and Negotiation 1 day 23/10 23/10
228 Award Purchase Order (PO) 1 day 24/10 24/10
229 Sign Agreement and payment DP 1 day 25/10 25/10
230 Delivery shippment include port custom clearence 15 days 17/03 06/04
231 Protection and Control Cubicle for 150 kV Line Bay 21 days 17/03 06/04
232 Protection and Control Cubicle for Transformer Bay 21 days 17/03 06/04
233 Central Control Equipment / HMI Client & Server (Operator Workstation) 21 days 17/03 06/04
234 Substation Automation Software : 21 days 17/03 06/04
235 AC Supply Equipment 21 days 17/03 06/04
236 PROCUREMENT E/M 150/20 Kv TRANSFORMER BAY ( 1 TRAFO BAY) EQUIPMENT 165 days 20/10 04/06
237 Material 139 days 02/11 11/05

Task Project Summary Manual Task Start-only Deadline

Project: SCHEDULE GI 150 KV P Split Inactive Task Duration-only Finish-only Progress


Date: 30/10 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 6
ID Task Task Name DurationStart Finish Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018
Mode Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
238 Receive Requistion 1 day 02/11 02/11
239 Issued requistion for quotation (RFQ) 1 day 03/11 03/11
240 Commercial Clarification and Negotiation 1 day 05/11 05/11
241 Award Purchase Order (PO) 1 day 06/11 06/11
242 Sign agreement and payment DP 3 days 07/11 09/11
243 Fabrication 130 days 10/11 09/05
244 Three phase Circuit Breaker, 1250A, 31.5kA symmetrical short 130 days 10/11 09/05
245 Three phase Busbar Disconnector, 1250A, 31.5kA, 1 sec, with 130 days 10/11 09/05
246 Single phase Current Transformer comprising : 130 days 10/11 09/05
247 Heavy duty outdoor single phase Lightning Arrester, metal oxide 130 days 10/11 09/05
248 Outdoor marshalling kiosk 130 days 10/11 09/05
249 LV Power and multicore Control Cables include all accessories to 130 days 10/11 09/05
250 Remote Control panel for 20 kV Cubicle complete accessories 130 days 10/11 09/05
251 Submit request Inspection FAT with PT PLN & PT RE 20 days 12/04 09/05
252 Inspection FAT 1 day 10/05 10/05
253 Ready for delivery 1 day 11/05 11/05
254 Selection Transportation (Forwarder) 5 days 20/10 25/10
255 Receive Requistion 1 day 20/10 20/10
256 Issued requistion for quotation (RFQ) 1 day 22/10 22/10
257 Commercial Clarification and Negotiation 1 day 23/10 23/10
258 Award Purchase Order (PO) 1 day 24/10 24/10
259 Sign Agreement and payment DP 1 day 25/10 25/10
260 Delivery Shippment include port custom clrearence 5 days 12/05 18/05
261 Three phase Circuit Breaker, 1250A, 31.5kA symmetrical short 7 days 12/05 18/05
262 Three phase Busbar Disconnector, 1250A, 31.5kA, 1 sec, with 7 days 12/05 18/05
263 Heavy duty outdoor single phase Lightning Arrester, metal oxide 7 days 12/05 18/05
264 Outdoor marshalling kiosk 7 days 12/05 18/05
265 LV Power and multicore Control Cables include all accessories to 7 days 12/05 18/05
266 Remote Control panel for 20 kV Cubicle complete accessories 7 days 12/05 18/05
267 Delivery Shippment include port custom clrearence 10 days 22/05 04/06
268 Single phase Current Transformer 14 days 22/05 04/06
269 PROCUREMENT 20 KV SWITCHGEAR, POWER CABLE AND AUXILIARRY 114 20/10 23/03
TRANSFORMER EQUIPMENT days
270 Material 99 days 02/11 16/03
271 Receive Requistion 1 day 02/11 02/11
272 Issued requistion for quotation (RFQ) 1 day 03/11 03/11
273 Commercial Clarification and Negotiation 1 day 05/11 05/11
274 Award Purchase Order (PO) 1 day 06/11 06/11
275 Sign agreement and payment DP 3 days 07/11 09/11
276 Fabrication 90 days 10/11 14/03

Task Project Summary Manual Task Start-only Deadline

Project: SCHEDULE GI 150 KV P Split Inactive Task Duration-only Finish-only Progress


Date: 30/10 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 7
ID Task Task Name DurationStart Finish Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018
Mode Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
277 20 kV XLPE power cable 2 x Cu400 mm2/phase, including cable 90 days 10/11 14/03
278 20 KV Busbar Voltage Transformer and Earthing swicth cubicle as per TPG
90 days 10/11 14/03
279 200 KVA 20/0 4 KV auxikliary Transformer include power Cable 90 days 10/11 14/03
280 Submit request Inspection FAT with PT PLN & PT RE 20 days 15/02 14/03
281 Inspection FAT 1 day 15/03 15/03
282 Ready for delivery 1 day 16/03 16/03
283 Selection Transportation (Forwarder) 5 days 20/10 25/10
284 Receive Requistion 1 day 20/10 20/10
285 Issued requistion for quotation (RFQ) 1 day 22/10 22/10
286 Commercial Clarification and Negotiation 1 day 23/10 23/10
287 Award Purchase Order (PO) 1 day 24/10 24/10
288 Sign agreement and payment DP 1 day 25/10 25/10
289 Delivery Shippment include port custom clrearence 5 days 17/03 23/03
290 20 kV XLPE power cable 2 x Cu400 mm2/phase, including cable 7 days 17/03 23/03
291 20 KV Busbar Voltage Transformer and Earthing swicth cubicle as per TPG 7 days 17/03 23/03
292 200 KVA 20/0 4 KV auxikliary Transformer include power Cable 7 days 17/03 23/03
293 PROCUREMENT POWER TRANSFORMER (1 X 30 MVA ) 76 days 20/10 30/01
294 Material 51 days 02/11 09/01
295 Receive Requistion 1 day 02/11 02/11
296 Issued requistion for quotation (RFQ) 1 day 03/11 03/11
297 Commercial Clarification and Negotiation 1 day 05/11 05/11
298 Award Purchase Order (PO) 1 day 06/11 06/11
299 Sign agreement and payment DP 14 days 07/11 23/11
300 Material ready stock (Pretest) 30 days 24/11 04/01
301 150/20 kV, 30 MVA 3-phase Power Transformer, oil, and all 30 days 24/11 04/01
302 150 kV NCT included accessories to complete scope of work 30 days 24/11 04/01
303 Transformer Regulation Panel complete with AVR and other acc. 30 days 24/11 04/01
304 Submit request Inspection FAT with PT PLN & PT RE 20 days 08/12 04/01
305 Inspection FAT 2 days 05/01 08/01
306 Ready for delivery 1 day 09/01 09/01
307 Selection Transportation (Forwarder) 5 days 20/10 25/10
308 Receive Requistion 1 day 20/10 20/10
309 Issued requistion for quotation (RFQ) 1 day 22/10 22/10
310 Commercial Clarification and Negotiation 1 day 23/10 23/10
311 Award Purchase Order (PO) 1 day 24/10 24/10
312 Sign agreement and payment DP 1 day 25/10 25/10
313 Delivery Shippment include port custom clrearence 15 days 10/01 30/01
314 150/20 kV, 30 MVA 3-phase Power Transformer, oil, and all 21 days 10/01 30/01
315 150 kV NCT included accessories to complete scope of work 21 days 10/01 30/01
316 Transformer Regulation Panel complete with AVR and other acc. 21 days 10/01 30/01

Task Project Summary Manual Task Start-only Deadline

Project: SCHEDULE GI 150 KV P Split Inactive Task Duration-only Finish-only Progress


Date: 30/10 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 8
ID Task Task Name DurationStart Finish Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018
Mode Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
317 PEKERJAAN GEDUNG KONTROL 53 days 20/10 28/12
318 Lightning Protection 53 days 20/10 28/12
319 Material 39 days 01/11 21/12
320 Receive Requistion 1 day 01/11 01/11
321 Issued requistion for quotation (RFQ) 1 day 02/11 02/11
322 Commercial Clarification and Negotiation 1 day 03/11 03/11
323 Award Purchase Order (PO) 1 day 05/11 05/11
324 Sign agreement and payment DP 3 days 06/11 08/11
325 Fabrication 31 days 09/11 20/12
326 Air terminal 60 cm with support 30 days 09/11 19/12
327 BC 50 mm include with clamps 30 days 09/11 19/12
328 BC 70 mm include with clamps 30 days 09/11 19/12
329 Box Arrester with Ground Rod 30 days 09/11 19/12
330 Inspection with PT PLN UIP II 1 day 20/12 20/12
331 Ready For Delivery 1 day 21/12 21/12
332 Transportation (Forwarder) 5 days 20/10 25/10
333 Receive Requistion 1 day 20/10 20/10
334 Issued requistion for quotation (RFQ) 1 day 22/10 22/10
335 Commercial Clarification and Negotiation 1 day 23/10 23/10
336 Award Purchase Order (PO) 1 day 24/10 24/10
337 Sign agreement and payment DP 1 day 25/10 25/10
338 Delivery Shippment 5 days 22/12 28/12
339 Air terminal 60 cm with support 7 days 22/12 28/12
340 BC 50 mm include with clamps 7 days 22/12 28/12
341 BC 70 mm Include with clamps 7 days 22/12 28/12
342 Box Arrester with Ground Rod 7 days 22/12 28/12
343 Purchasing and Install Air Conditioner, Exhsaust Fan and Fire Extinguisher 1 day 20/10 21/10
344 Purchasing with packaging 1 day 20/10 20/10
345 AC 2 PK Mitsubishi brand for PLC 1 day 20/10 20/10
346 AC 1 1/2 PK Mitsubishi brand for control room, office and AC/DC unit room
1 day 20/10 20/10
347 Exhaust fan 10 with Panasonic brand for batteray room 1 day 20/10 20/10
348 Fire Extinguisher brand Altec Fire AT 90H 1 day 20/10 20/10
349 Delivery Transportation 0 days 21/10 21/10 21/10
350 AC 2 PK Mitsubishi brand for PLC 1 day 21/10 21/10
351 AC 1 1/2 PK Mitsubishi brand for control room, office and AC/DC unit room
1 day 21/10 21/10
352 Exhaust fan 10 with Panasonic brand for batteray room 1 day 21/10 21/10
353 Fire Extinguisher brand Altec Fire AT 90H 1 day 21/10 21/10
354 CONSTRUCTION 253 days 18/10 27/06
355 PEKERJAAN PONDASI, PARIT KABEL DAN HAMPARAN KERIKIL 176 days 18/10 11/04
356 Pekerjaan Pondasi untuk peralatan Switchyard 21 days 18/10 07/11

Task Project Summary Manual Task Start-only Deadline

Project: SCHEDULE GI 150 KV P Split Inactive Task Duration-only Finish-only Progress


Date: 30/10 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 9
ID Task Task Name DurationStart Finish Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018
Mode Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
357 Pondasi 150 KV Lighting Arrester (LA) 7 days 18/10 24/10
358 Pondasi 150 KV Disconnecting / Earthing Switches (DS/E) 10 days 18/10 27/10
359 Pondasi Marshalling Kiosk (MK) 14 days 18/10 31/10
360 Pondasi 150 KV Capasitor Voltage Transformer (CVT) 14 days 18/10 31/10
361 Pembuatan Parit Kabel type 1 21 days 18/10 07/11
362 Pembuatan Parit kabel type 2 21 days 18/10 07/11
363 Pembuatan Parit Kabel type 3 21 days 18/10 07/11
364 Pembuatan Parit kabel type 4 21 days 18/10 07/11
365 Pondasi Neutral Grounding Resistor NGR) 7 days 23/10 29/10
366 Support 1 day 23/10 23/10
367 Install Post For Gantries 150 kV 14 days 23/10 05/11
368 Rak Kabel 1 day 23/10 23/10
369 Pekerjaan Hamparan Koral 6 days 06/04 11/04
370 Urugan pasir 3 days 06/04 08/04
371 Hamparan kerikil t = 20 cm 3 days 09/04 11/04
372 MATERIAL RELOKASI ( ex GI KILIRANJAO) 16 days 12/04 27/04
373 Install 14 days 12/04 25/04
374 Three phase Circuit Breaker, 1250 A, 31,5 kA symmetrical short 14 days 12/04 25/04
375 Three phase line Disconnector w/ earthing switch 1250 A,31,5 kA, 14 days 12/04 25/04
376 Single phase Current Transformer 14 days 12/04 25/04
377 Single phase Capacitor Voltage Transformer ratio 150.000:3 14 days 12/04 25/04
378 Communication Facilities 14 days 12/04 25/04
379 Line Trap 14 days 12/04 25/04
380 Cheklist and ITP Document 1 day 26/04 26/04
381 Conduct Joint Inspection PT PLN UIP II and PT RE 1 day 27/04 27/04
382 PEMASANGAN PERALATAN E/M 150 KV 2 LINE BAY 14 days 14/06 27/06
383 Install 14 days 14/06 27/06
384 Three phase busbar Disconnector, 1250 A, 31,5 kA 7 days 14/06 20/06
385 150 kV Single Phase Capasitor Voltage transformer as per TPG 7 days 21/06 27/06
386 Outdoor Marshalling Kiosks 7 days 14/06 20/06
387 110V DC battery, 240AH, 8 hours and 1 set charger 80A 7 days 14/06 20/06
388 48V DC battery, 150AH, 8 hours and 1 set charger 60A 7 days 14/06 20/06
389 110 V DC distribution board complete with MCB for HV equipment 7 days 14/06 20/06
390 48 VDC Distribution Board complete with MCB and include necessary 7 days 14/06 20/06
391 220/380 VAC Distribution Board complete with MCB for HV 7 days 14/06 20/06
392 LV Power and multicore Control Cables include all accessories to 7 days 14/06 20/06
393 Fiber Optic Communication Equipments 7 days 14/06 20/06
394 Cheklist and ITP Document 1 day 21/06 21/06
395 Conduct Joint Inspection PT PLN UIP II and PT RE 1 day 22/06 22/06

Task Project Summary Manual Task Start-only Deadline

Project: SCHEDULE GI 150 KV P Split Inactive Task Duration-only Finish-only Progress


Date: 30/10 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 10
ID Task Task Name DurationStart Finish Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018
Mode Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
396 STEEL STRUCTURE/GANTRY, INSTALL CONDUCTOR, STRING INSULATOR, GSW 14 days 23/03 05/04
& ACC, HV CONNECTOR GROUNDING AND LIGHTING SYSTEM EQUIPMENT
397 Install 14 days 23/03 05/04
398 Erection Steel structure/gantry (refer to drawing) 14 days 23/03 05/04
399 Conductor 1 x A3C 630 mm2 for double main busbar arrangement 7 days 23/03 29/03
400 Conductor 1 x A3C 300 mm2 for cross busbar & droppers/jumpers 7 days 23/03 29/03
401 GSW 55 mm2 complete with fitting and accessories 7 days 23/03 29/03
402 Single tension string insulator set & hardware 7 days 23/03 29/03
403 Single suspension string insulator set & hardware 7 days 23/03 29/03
404 HV connector suitable 7 days 23/03 29/03
405 Grounding system for line whole of substation equipment 14 days 23/03 05/04
406 Lighting for outdoor switchyard and gantry 7 days 23/03 29/03
407 Cheklist and ITP Docuement 1 day 30/03 30/03
408 Conduct Joint Inspection PT PLN UIP II and PT RE 1 day 31/03 31/03
409 SUBSTATION AUTOMATION SYSTEM (SAS) 16 days 07/04 22/04
410 Install 14 days 07/04 20/04
411 Protection and Control Cubicle for 150 kV Line Bay 14 days 07/04 20/04
412 Protection and Control Cubicle for Transformer Bay 14 days 07/04 20/04
413 Central Control Equipment / HMI Client & Server 14 days 07/04 20/04
414 Substation Automation Software 14 days 07/04 20/04
415 AC Supply Equipment 14 days 07/04 20/04
416 Cheklist and ITP Document 1 day 21/04 21/04
417 Conduct Joint Inspection PT PLN UIP II and PT RE 1 day 22/04 22/04
418 POWER TRANSFORMER (1 X 30 MVA ) 9 days 31/01 08/02
419 Install 7 days 31/01 06/02
420 150/20 kV, 30 MVA 3-phase Power Transformer 7 days 31/01 06/02
421 150 kV NCT included accessories to complete scope of work 7 days 31/01 06/02
422 Transformer Regulation Panel complete with AVR and other acc. 7 days 31/01 06/02
423 Cheklist and ITP Document 1 day 07/02 07/02
424 Conduct Joint Inspection PT PLN UIP II and PT RE 1 day 08/02 08/02
425 E/M 150/20 KV TRANSFORMER BAY ( 1 TRAFO BAY) EQUIPMENT 31 days 19/05 18/06
426 Install 31 days 19/05 18/06
427 Three phase Circuit Breaker, 1250A, 31.5kA symmetrical short 14 days 19/05 01/06
428 Three phase Busbar Disconnector, 1250A, 31.5kA, 1 sec, with 14 days 19/05 01/06
429 Heavy duty outdoor single phase Lightning Arrester, metal oxide 14 days 19/05 01/06
430 Outdoor marshalling kiosk 14 days 19/05 01/06
431 LV Power and multicore Control Cables include all accessories 14 days 19/05 01/06
432 Remote Control panel for 20 kV Cubicle complete accessories 14 days 19/05 01/06
433 Single phase Current Transformer comprising 14 days 05/06 18/06
434 Cheklist and ITP Document 1 day 02/06 02/06

Task Project Summary Manual Task Start-only Deadline

Project: SCHEDULE GI 150 KV P Split Inactive Task Duration-only Finish-only Progress


Date: 30/10 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 11
ID Task Task Name DurationStart Finish Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018
Mode Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
435 Conduct Joint Inspection PT PLN UIP II and PT RE 1 day 03/06 03/06
436 20 KV SWITCHGEAR, POWER CABLE AND AUXILIARRY TRANSFORMER EQUIPMENT 16 days 24/03 08/04
437 Install 14 days 24/03 06/04
438 Incoming Feeder cubicle and busbar PT Cubicle 2000 A including 20 KV CB 14 days 24/03 06/04
439 Outgoing feeder cubicle, 630 A including 20 KV CB 14 days 24/03 06/04
440 Bus section cubicle 200 A including 20 KV CB 14 days 24/03 06/04
441 20 kV XLPE power cable 2 x Cu400 mm2/phase, including cable support 14 days 24/03 06/04
442 Auxiliary transformer cubicle 630 A include accecories 14 days 24/03 06/04
443 20 KV Busbar Voltage Transformer and Earthing swicth cubicle as per TPG 14 days 24/03 06/04
444 200 KVA 20/0 4 KV auxikliary Transformer include power Cable termination14 days 24/03 06/04
445 Cheklist and ITP Document 1 day 07/04 07/04
446 Conduct Joint Inspection PT PLN UIP II and PT RE 1 day 08/04 08/04
447 PEMASANGAN PENERANGAN LISTRIK 176 days 18/10 11/04
448 Install 174 days 18/10 09/04
449 Cable NYFGBY (2 x 4mm) 7 days 18/10 24/10
450 Lampu Penerangan Jalan 250 W +Tiang 7 days 25/10 31/10
451 Lampu Penerangan Gantry 250 W (lampu sorot) 4 days 06/04 09/04
452 Cheklist and ITP Document 1 day 10/04 10/04
453 Conduct Joint Inspection PT PLN UIP II and PT RE 1 day 11/04 11/04
454 PEKERJAAN PAGAR KELILING DAN PINTU PAGAR MASUK 82 days 23/12 14/03
455 Pekerjaan Persiapan 2 days 23/12 24/12
456 Survey 80 days 25/12 14/03
457 Pekerjaan galian tanah 10 days 25/12 03/01
458 Pekerjaan Pondasi 30 days 04/01 02/02
459 Pemasangan Pagar Pintu depan 30 days 03/02 04/03
460 Perform joint Inspection PT PLN and PT RE 1 day 05/03 05/03
461 PEKERJAAN GEDUNG KONTROL 79 days 30/11 16/02
462 Pekerjaan Kozen, Pintu, Jendela dan Ventilasi 14 days 30/11 13/12
463 Pekerjaan Talang, Drainase, Dan Sanitair 40 days 30/11 08/01
464 Pekerjaan Instalasi Penerangan Listrik 14 days 30/11 13/12
465 Pemasangan proteksi petir 14 days 30/11 13/12
466 Pekerjaan Pengecatan 14 days 14/12 27/12
467 Pekerjaan Pengadaan & Pemasangan AC, Exhsaust Fan dan Racun Api 14 days 28/12 10/01
468 Pekerjaan Chain Block Automatis 2 days 11/01 12/01
469 Pekerjaan Tangga darurat 4 days 13/01 16/01
470 Cheklist and ITP Document 30 days 17/01 15/02
471 Joint Inspection RE and PLN 1 day 16/02 16/02
472 PEKERJAAN PROTEKSI LERENG TEBING 120 days 09/12 07/04
473 Slope protection Work 120 days 09/12 07/04
474 PEKERJAAN RETENING WALL 40 days 12/11 21/12

Task Project Summary Manual Task Start-only Deadline

Project: SCHEDULE GI 150 KV P Split Inactive Task Duration-only Finish-only Progress


Date: 30/10 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 12
ID Task Task Name DurationStart Finish Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018
Mode Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
475 Pekerjaan Retaining wall 30 days 12/11 11/12
476 Urugan dan pemdatan tanah ke area retaining wall 7 days 15/12 21/12
477 PEKERJAAN JALAN KERJA, LISBAN AND DRAINASE 135 days 23/11 06/04
478 Pekerjaan Persiapan 2 days 23/11 24/11
479 Pekerjaan drainase 30 days 25/11 24/12
480 Lisban dan jalan Kerja 30 days 06/03 04/04
481 Sumur Dalam 14 days 25/11 08/12
482 Cheklist and ITP Document 1 day 05/04 05/04
483 Joint Inspection PT PLN and PT RE 1 day 06/04 06/04
484 MUSHOLLA, POS JAGA, RUMAH OPERATOR DAN TAMAN 115 days 30/11 24/03
485 MUSHOLLA 67 days 30/11 04/02
486 Pekerjaan Persiapan 1 day 30/11 30/11
487 Pekerjaan Tanah 5 days 01/12 05/12
488 Pekerjaan Pondasi 5 days 06/12 10/12
489 Pekerjaan Beton 10 days 11/12 20/12
490 Pekerjaan Dinding 15 days 21/12 04/01
491 Pekerjaan Atap 7 days 05/01 11/01
492 Pekerjaan Plafond 7 days 12/01 18/01
493 Pekerjaan lantai Keramik 7 days 19/01 25/01
494 Pekerjaan Pengectan 3 days 26/01 28/01
495 Pekerjaan Penggantung dan Kunci 1 day 29/01 29/01
496 Pekerjaan Instalasi Air 3 days 30/01 01/02
497 Pekerjaan Instalasi Listrik 3 days 02/02 04/02
498 RUMAH OPERATOR T70 68 days 30/11 05/02
499 Pekerjaan Persiapan 1 day 30/11 30/11
500 Pekerjaan Tanah 7 days 01/12 07/12
501 Pekerjaan Pondasi Batu Kali 5 days 08/12 12/12
502 Pekerjaan Beton 7 days 13/12 19/12
503 Pekerjaan Dinding 20 days 20/12 08/01
504 Pekerjaan Atap 4 days 09/01 12/01
505 Pekerjaan Plafond 7 days 13/01 19/01
506 Pekerjaan lantai Keramik 7 days 20/01 26/01
507 Pekerjaan Pengecatan 5 days 27/01 31/01
508 Pekerjaan jendela dan pintu 2 days 01/02 02/02
509 Pekerjaan Instalasi Air 3 days 03/02 05/02
510 Pekerjaan Instalasi Listrik 3 days 03/02 05/02
511 Pekerjaan Sanitasi 2 days 03/02 04/02
512 Pekerjaan Taman 2 days 03/02 04/02
513 RUMAH OPERATOR T54 75 days 09/01 24/03
514 Pekerjaan Persiapan 1 day 09/01 09/01

Task Project Summary Manual Task Start-only Deadline

Project: SCHEDULE GI 150 KV P Split Inactive Task Duration-only Finish-only Progress


Date: 30/10 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 13
ID Task Task Name DurationStart Finish Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018
Mode Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
515 Pekerjaan Tanah 7 days 10/01 16/01
516 Pekerjaan Pondasi Batu Kali 5 days 17/01 21/01
517 Pekerjaan Beton 7 days 22/01 28/01
518 Pekerjaan Dinding 20 days 29/01 17/02
519 Pekerjaan Atap 4 days 18/02 21/02
520 Pekerjaan Plafond 7 days 22/02 28/02
521 Pekerjaan lantai Keramik 7 days 01/03 07/03
522 Pekerjaan Pengecatan 5 days 08/03 12/03
523 Pekerjaan jendela dan pintu 2 days 13/03 14/03
524 Pekerjaan Instalasi Air 3 days 15/03 17/03
525 Pekerjaan Instalasi Listrik 3 days 18/03 20/03
526 Pekerjaan Sanitasi 2 days 21/03 22/03
527 Pekerjaan Taman 2 days 23/03 24/03
528 POS JAGA 37 days 09/01 14/02
529 Pekerjaan Persiapan 1 day 09/01 09/01
530 Pekerjaan Tanah 3 days 10/01 12/01
531 Pekerjaan beton, beton bertulang dan Pasangan 20 days 13/01 01/02
532 Pekerjaan Atap, kuda-kuda dan Plafond 3 days 02/02 04/02
533 Pekerjaan Kusen, Pintu, Jendela dan ventilasi 2 days 05/02 06/02
534 Pekerjaan Sanitair dan Instalasi air 2 days 07/02 08/02
535 Pekerjaan Pengecatan 2 days 09/02 10/02
536 Pekerjaan Drainase 2 days 11/02 12/02
537 Pekerjaan Instalasi listrik dan pendingin ruangan 2 days 13/02 14/02
538 COMMISIONING 24 days 04/06 27/06
539 HV Avaratus test 3 days 23/06 25/06
540 Protection Panel and SAS test 2 days 04/06 05/06
541 System test 2 days 26/06 27/06
542 Other system test 2 days 04/06 05/06
543 Energize 0 days 27/06 27/06 27/06

Task Project Summary Manual Task Start-only Deadline

Project: SCHEDULE GI 150 KV P Split Inactive Task Duration-only Finish-only Progress


Date: 30/10 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress