Lampiran 1.

PT. PATRA BADAK ARUN SOLUSI

RENCANA KERJA PENYEHATAN METERING SYSTEM KRAMASAN AREA OIL MOVEMENT PLAJU
DOC. No. MET KRS RU III - 01

Time Schedule
NO. DESKRIPSI PEKERJAAN Bulan Ke 1 Bulan Ke 2 Bulan Ke 3 Bulan Ke 4 Bulan Ke 5 Bulan Ke 6 Bulan Ke 7 Bulan Ke 8
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

I PREPARATION & ENGENERRING


1 Kickoff Meeting
2 Perizinan & Administrasi Umum
3 Construction all risk & BPJS
4 Site Survey
5 Gudang/Direksi kit
6 Mobilisasi/Demobilisasi
7 Engineering Design
8 Project Mangement
9 Stuktur Organisasi
10 Project Master Schedule/Pembobotan S curve
11 Project Execution Plan
12 Engineering deliverable list
13 Electrical
14 Instrument
15 Safety
16 HSE
17 Job Stop Analysis (JSA)

II Procurement & Delivery


1 Instrument Material
2 Double Block and Bleed Valve c/w electric actuator
3 Pressure Transmitter
4 Pressure Indicator
5 Temperature Transmitter
6 Temperature Indicator
7 4-Way Valve c/w electric actuator
8 Electrical Material
9 Junction Box
10 Power Cable Feeder
11 Power Cable
12 Manual Overhead Crane
13 PC & HMI
Lampiran 1.

14 PC Workstation
15 HMI Complete with HMI Wonderware latest version
16 Dot Matrix Printer
17 Fabrikasi (local brand)
18 STRAIGHTENING VANE FOR 6" PIPE

III CONSTRUCTION
1 Delivery material to workshop
2 Hydrotes DBB Valve
3 Function test Actuator
4 Pekerjaan Electrical
5 Lepas kabel power exsisting dari MCB panel lama
6 Pulling kable untuk Terminasi Kable power yang baru ke lapangan
7 install panel listrik PDB dan JB baru
8 pembuatan rack baru sebagai distribusi bagi feeder MOV DBB yang baru
9 pemasangan feeder braker
10 instalasi kable ladder
11 pemasangan ground kabel
12 kabel route ( jalur kable, pulling dan terminasi kabel)
13 safe guard
14 Pekerjaan Instrument
15 Pulling & Terminasi Kable sinyal multi pair untuk ke MOV
16 install kable marker
Integrasi all field instrument (TT,PT,PI,TI)
17 Integrasi/install (DBB & 4WAY ACTUATOR)
18 Connect wire to field instrument
19 kalibrasi instrument yang dipasang
20 loopccheck & functional test
21 Refonfigurasi Flocom (Penambahan IO)
22 Reprograming HMI
23 Pekerjaan Manual Overhead Crane
24 Install Manual Overhead Crane
25 Penggantian straightening vane
26 SAT
27 Commisioning
28 Pre commisiong
29 Mechanical Complation
30 Commisioning Start up & Test Run
31 Operation Accpetence
Lampiran 1.

IV PEKERJAAN SERTIFIKASI DITMET


1 Waterdrwat test Prover
2 2 stream meter arus

V PEKERJAAN PENGAWASAN DAN PELAPORAN


1 Melakukan pengawasan Keselamatan Kerja oleh Safetyman
2 Membuat laporan semua hasil pekerjaan
3 Membuat dokumen as built drawing

VI PEKERJAAN MERAPIHKAN AREA KERJA


1 Membersihkan dan merapikan lokasi kerja

VIII MELAKUKAN TRAINING


1 Melakukan training untuk Engineering, Maintenance, dan Operasional.
Lampiran 1.

PROYEK PENYEHATAN METERING SYSTEM KRAMASAN AREA OIL MOVEMENT PLAJU


DOC. No. MET KRS RU III - 01

Time Schedule
NO. TASK NAME Duration START FINISH Jun-21 Jul-21 Aug-21 Sep-21 Oct-21 Nov-21 Dec-21 Jan-22 Feb-22 Mar-22
7 14 21 28 5 12 19 26 2 9 16 23 6 13 20 27 4 11 18 25 1 8 15 22 6 13 20 27 3 10 17 24 7 14 21 28 7 14

I PREPARATION & ENGENERRING


II Procurement & Delivery
1 Aproval material 5 DAYS 6/7/2021 6/11/2021
2 Instrument Material
3 Double Block and Bleed Valve c/w electric actuator 270 DAYS 6/14/2021 2/27/2022
4 4-Way Valve c/w electric actuator 270 DAYS 6/14/2021 2/27/2022
5 Electrical Material
7 STRAIGHTENING VANE FOR 6" PIPE 300 DAYS 6/14/2021 3/30/2022

III CONSTRUCTION
7 pembuatan rack baru sebagai distribusi bagi feeder MOV DBB yang baru 7 DAYS 10/20/2021 2/27/2022
13 Pekerjaan Instrument
17 Penggantian straightening vane 15 DAYS 4/1/2022 4/15/2022
18 kalibrasi instrument yang dipasang 11 DAYS 3/10/2022 3/21/2022
19 loopccheck & functional test 3 DAYS 3/22/2022 3/25/2022
20 Refonfigurasi Flocom (Penambahan IO) 30 DAYS 2/10/2022 3/10/2022
21 Reprograming HMI 30 DAYS 2/3/2022 3/18/2022
22 Delivery material to workshop
23 Hydrotes DBB Valve 5 DAYS 3/7/2022 3/11/2022
24 Integrasi all field instrument (TT,PT,PI,TI) 5 DAYS 3/7/2022 3/11/2022
25 Integrasi/install (DBB & 4WAY ACTUATOR) 5 DAYS 3/7/2022 3/11/2022
26 Function test Actuator 5 DAYS 3/7/2022 3/11/2022
27 SAT 1 DAYS 3/14/2022 3/15/2022
28 Commisioning
29 Pre commisiong 2 DAYS 3/15/2022 3/16/2022
30 Mechanical Complation 4 DAYS 3/16/2022 3/20/2022
31 Commisioning Start up & Test Run 3 DAYS 3/21/2022 3/27/2022
32 Operation Accpetence 1 DAYS 3/28/2022 3/28/2022

IV PEKERJAAN SERTIFIKASI DITMET


1 Waterdrwat test Prover 5 DAYS 4/4/2022 4/8/2022
2 2 stream meter arus 5 DAYS 4/11/2022 4/14/2022

V PEKERJAAN PENGAWASAN DAN PELAPORAN


1 Melakukan pengawasan Keselamatan Kerja oleh Safetyman 150 DAYS 10/4/2021 4/29/2022
2 Membuat laporan semua hasil pekerjaan 240 DAYS 10/15/2021 4/29/2022
3 Membuat dokumen as built drawing 240 DAYS 6/7/2021 4/29/2022

VI PEKERJAAN MERAPIHKAN AREA KERJA


1 Membersihkan dan merapikan lokasi kerja 2 DAYS 4/27/2022 4/29/2022

VIII MELAKUKAN TRAINING


1 Melakukan training untuk Engineering, Maintenance, dan Operasional. 5 DAYS 25/04/2022 4/29/2022

Disetujui oleh, Dibuat oleh,


PT. PERTAMINA RU III PT. PATRA BADAK ARUN SOLUSI
Lampiran 1.

IBNU JUNIFAN FERY D.M.


SENIOR GROUP LEADER INSTRUMENT
PROJECT MANAGER
ENGINEER
Lampiran 1.

Mar-22 Apr-22
21 28 4 11 18 25