DAFTAR ISI :
1. ACUAN EVALUASI ..................................................................................................... 3
2. DATA EVALUASI ........................................................................................................ 3
3. ANALISA EVALUASI .................................................................................................. 5
4. KESIMPULAN ............................................................................................................. 8
LAMPIRAN-LAMPIRAN :
A. GAMBAR REALISASI PELAKSANAAN PEKERJAAN
B. ANALISA PENURUNAN FINAL METODA ASAOKA
C. GRAFIK MONITORING VACUUM GAUGE DAN SETTLEMENT PLATE
D. GRAFIK MONITOIRNG VIBRATING WIRE PIEZOMETER
E. GRAFIK MONITOING INCLINOMETER
F. DATA MONITORING INSTRUMEN GEOTEKNIK
G. LOAD RATIO
H. GRAFIK SONDIR SEBELUM DAN SESUDAH PEKERJAAN VACUUM PRELOADING
DAN PENYELIDIKAN TANAH UNTUK PEMERIKSAAN DAYA DUKUNG
DISETUJUI OLEH :
PT. WASKITA KARYA Persero, (Tbk)
2
LAPORAN FINAL EVALUASI GEOTEKNIK
PEKERJAAN PERBAIKAN TANAH METODA VACUUM PRELOADING
PEMBANGUNAN JALAN TOL KAYU AGUNG – PALEMBANG – BETUNG
SEKSI 2A (IC PALINDRA) MODUL 02 (STA 40+675 ~ STA 41+010)
1. ACUAN EVALUASI
Evaluasi geoteknik yang dilakukan pada pekerjaan perbaikan tanah lunak metoda
vacuum preloading pembangunan jalan tol Kayu Agung – Palembang – Betung Seksi
2A ini mengacu pada Spesifikasi Khusus Interim Pekerjaan Percepatan Konsolidasi
Tanah dengan Metoda Penyalir Vertikal dengan Vakum dan PVD (SKh-1.4.15),
sebagai berikut :
2. DATA EVALUASI
Untuk memperkuat data yang diperoleh dari perencana, kemudian dilakukan
penyelidikan tanah ulang berupa sondir setiap interval 50 m untuk are-area yang
direkomendasikan menggunakan metode vacuum. Penyelidikan sondir ini dilakukan
untuk mengetahui kedalaman tanah kompresibel atau kedalaman tanah dengan nilai
qc < 40 kg/cm2 dan hasilnya kemudian diresumekan menjadi stratigrafi seperti pada
Gambar 1 dan Gambar 2 berikut. Dan untuk kedalaman PVD aktual ditunjukkan pada
Tabel 1.
3
AREA MODUL 02
4
Berdasarkan rekapitulasi data monitoring vacuum gauge (VG) dan settlement plate
(SP) pada Modul 02 pada tanggal 09 Agustus 2019 (Tabel 2):
a. Penurunan tanah yang terjadi selama 5 (lima) hari berturut-turut sebesar 0,0 s/d 1,0
mm
b. Tekanan vacuum pada level geomembrane mencapai -80 kPa s/d -84 kPa.
A B C D E F G=E-F H I J K
11 Modul 2 SP.10 CL STA 40+850 211 65 146 1.266 -629 -84 0.0
Laporan data monitoring vacuum gauge (VG) dan settlement plate (SP) pada Modul
02 pada tanggal 09 Agustus 2019, terlampir.
3. ANALISA EVALUASI
Berdasarkan data monitoring settlement plate (SP) pada Modul 02 sampai dengan
tanggal 09 Agustus 2019, terlampir, dilakukan analisa Asaoka dan rekapitulasi
analisanya ditunjukkan pada Tabel 3.
5
Tabel 3 Rekapitulasi analisa Asaoka Modul 02 per 09 Agustus 2019
Summary of Results
Total Asaoka Achieved
Plate no Fill Observed
duration of method Deg. Of Consolidation
Height Settlement
SP Preloading EOP U
m days mm mm %
SP-07 L 2.121 207 638 690 92
SP-07 CL 2.195 207 620 679 91
SP-07 R 2.024 207 627 688 91
SP-08 L 0.954 207 546 598 91
SP-08 CL 1.32 207 587 643 91
SP-08 R 1.298 207 564 608 93
SP-09 L 1.016 207 446 485 92
SP-09 CL 1.082 207 506 553 92
SP-09 R 0.956 207 473 519 91
SP-10 L 1.048 207 510 559 91
SP-10 CL 1.266 207 629 673 93
SP-10 R 0.988 207 510 560 91
SP-11 L 0.987 207 506 554 91
SP-11 CL 1.191 207 624 669 93
SP-11 R 1.106 207 570 609 94
SP-12 L 0.908 207 608 653 93
SP-12 CL 1.35 207 786 849 93
SP-12 R 1.402 207 712 760 94
SP-13 L 1.77 207 782 862 91
SP-13 CL 2.226 207 970 1060 91
SP-13 R 1.876 207 866 965 90
Average Degree of Consolidation Achieved = U = 92
notes: EOP = End of Primary Consolidation
U = Degree of Consolidation
Laporan analisa Asaoka pada Modul 02 sampai dengan tanggal 09 Agustus 2019,
terlampir.
3.2. Total Penurunan
Dari penurunan aktual yang diperoleh dari bacaan settlement plate kemudian
ditambahkan dengan estimasi penurunan yang diakibatkan beban lantai kerja
makan diperoleh total hasil penurunan akhir seperti pada Tabel 4 di bawah ini.
6
3.3. Analisa Daya Dukung
Uji lapangan yang dilakukan untuk menghitung daya dukung tanah adalah uji sondir
(CPT). Dari data sondir tersebut menghasilkan parameter tahanan ujung konus, qc
yang kemudian dikorelasikan untuk mendapatkan parameter kuat geser. Persamaan
umum yang dipakai untuk menghitung daya dukung tanah adalah sebagai berikut:
qult = 5,14 . Cu
Dimana:
Cu = qc / 75 (kg/cm2)
Dari data di atas dapat disimpulkan bahwa ada kenaikan daya dukung sesudah
vacuum sebesar 36,922 kPa atau naik sebesar 27,360 % dengan load ratio
terhadap beban operasional 1,853.
7
Gambar 3. Grafik Pergerakan Horizontal Tanah Berdasarkan Monitoring Inclinometer
4. KESIMPULAN
Berdasarkan data rekapitulasi monitoring vacuum gauge (VG) dan settlement plate
(SP) sampai dengan tanggal 09 Agustus 2019 pada Modul 02 (Tabel 2) serta data
rekapitulasi analisa Asaoka pada Modul 02 per 09 Agustus 2019 (Tabel 3 ) :
Berdasarkan kelima hal tersebut maka pekerjaan perbaikan tanah metoda vacuum
preloading pembangunan jalan tol Kayu Agung – Palembang – Betung Seksi 2A (IC
Palindra) pada modul 02 (STA 40+675 ~ STA 41+010) maka sesuai dengan
Spesifikasi Khusus Interim Pekerjaan Percepatan Konsolidasi Tanah dengan Metoda
Penyalir Vertikal dengan Vakum dan PVD (SKh-1.4.15) telah dapat dinyatakan
selesai.
8
LAMPIRAN
LAMPIRAN
A. AS BUILT DRAWING
LAMPIRAN
B. EVALUASI METODE ASAOKA
Prepared By: Date: PT TEKNINDO GEOSISTEM UNGGUL Job No.: Sheet :
TGU 5-Aug-19 S-013-18 Cont'd
Verified By: Date: CALCULATION SHEET Revision Notes:
200 50
0 0
-400 -100
Settlement (mm)
-600 -150
-800 -200
700
650
St+1
600
ASAOKA METHOD:
Final Results:
550 Fill Height = 212 cm
Time interval = 3 days
Settlement at U=100% = 690 mm
500 Regression Line Slope = b = 0.9345
500 550 600 650 700 750
St Max Observed Settlement = 638 mm
Data Regression Series3 Degree of Consolidation
Achieved = 92%
200 50
0 0
-400 -100
Settlement (mm)
-600 -150
-800 -200
700
650
St+1
600
ASAOKA METHOD:
Final Results:
550 Fill Height = 220 cm
Time interval = 3 days
Settlement at U=100% = 679 mm
500 Regression Line Slope = b = 0.9387
500 550 600 650 700 750
St Max Observed Settlement = 620 mm
Data Regression Series3 Degree of Consolidation
Achieved = 91%
200 50
0 0
-400 -100
Settlement (mm)
-600 -150
-800 -200
700
650
St+1
600
ASAOKA METHOD:
Final Results:
550 Fill Height = 202 cm
Time interval = 3 days
Settlement at U=100% = 688 mm
500 Regression Line Slope = b = 0.9427
500 550 600 650 700 750
St Max Observed Settlement = 627 mm
Data Regression Series3 Degree of Consolidation
Achieved = 91%
0 0
-400 -200
-600 -300
650
600
St+1
550
ASAOKA METHOD:
Final Results:
500 Fill Height = 95 cm
Time interval = 3 days
Settlement at U=100% = 598 mm
450 Regression Line Slope = b = 0.9546
450 500 550 600 650 700
St Max Observed Settlement = 546 mm
Data Regression Series3 Degree of Consolidation
Achieved = 91%
200 50
0 0
-400 -100
Settlement (mm)
-600 -150
-800 -200
640
620
St+1
600
ASAOKA METHOD:
580 Final Results:
Fill Height = 132 cm
560 Time interval = 3 days
Settlement at U=100% = 643 mm
540 Regression Line Slope = b = 0.9644
540 560 580 600 620 640 660
St Max Observed Settlement = 587 mm
Data Regression Series3 Degree of Consolidation
Achieved = 91%
0 0
-400 -200
-600 -300
620
600
580
St+1
0 0
-400 -200
-600 -300
500
480
460
St+1
0 0
-400 -200
-600 -300
560
540
520
St+1
0 0
-400 -200
-600 -300
520
500
St+1
480
ASAOKA METHOD:
460 Final Results:
Fill Height = 96 cm
440 Time interval = 3 days
Settlement at U=100% = 519 mm
420 Regression Line Slope = b = 0.9630
420 440 460 480 500 520 540
St Max Observed Settlement = 473 mm
Data Regression Series3 Degree of Consolidation
Achieved = 91%
0 0
-400 -200
-600 -300
560
540
St+1
520
ASAOKA METHOD:
500 Final Results:
Fill Height = 105 cm
480 Time interval = 3 days
Settlement at U=100% = 559 mm
460 Regression Line Slope = b = 0.9524
460 480 500 520 540 560 580
St Max Observed Settlement = 510 mm
Data Regression Series3 Degree of Consolidation
Achieved = 91%
0 0
-400 -200
Settlement (mm)
-600 -300
-800 -400
680
660
St+1
640
ASAOKA METHOD:
620 Final Results:
Fill Height = 127 cm
600 Time interval = 3 days
Settlement at U=100% = 673 mm
580 Regression Line Slope = b = 0.9262
580 600 620 640 660 680 700
St Max Observed Settlement = 629 mm
Data Regression Series3 Degree of Consolidation
Achieved = 93%
0 0
-400 -200
-600 -300
560
540
St+1
520
ASAOKA METHOD:
500 Final Results:
Fill Height = 99 cm
480 Time interval = 2 days
Settlement at U=100% = 560 mm
460 Regression Line Slope = b = 0.9497
460 480 500 520 540 560 580
St Max Observed Settlement = 510 mm
Data Regression Series3 Degree of Consolidation
Achieved = 91%
0 0
-400 -200
-600 -300
600
550
St+1
500
ASAOKA METHOD:
Final Results:
450 Fill Height = 99 cm
Time interval = 3 days
Settlement at U=100% = 554 mm
400 Regression Line Slope = b = 0.9587
400 450 500 550 600 650
St Max Observed Settlement = 506 mm
Data Regression Series3 Degree of Consolidation
Achieved = 91%
0 0
-400 -200
Settlement (mm)
-600 -300
-800 -400
680
660
640
St+1
0
0
-100
-400
Settlement (mm)
-200
-600
-800 -300
620
600
St+1
580
ASAOKA METHOD:
560 Final Results:
Fill Height = 111 cm
540 Time interval = 3 days
Settlement at U=100% = 609 mm
520 Regression Line Slope = b = 0.9323
520 540 560 580 600 620 640
St Max Observed Settlement = 570 mm
Data Regression Series3 Degree of Consolidation
Achieved = 94%
0 0
-400 -200
Settlement (mm)
-600 -300
-800 -400
660
640
St+1
620
ASAOKA METHOD:
600 Final Results:
Fill Height = 91 cm
580 Time interval = 3 days
Settlement at U=100% = 653 mm
560 Regression Line Slope = b = 0.9482
560 580 600 620 640 660 680
St Max Observed Settlement = 608 mm
Data Regression Series3 Degree of Consolidation
Achieved = 93%
200 50
0 0
-400 -100
-600 -150
Settlement (mm)
-800 -200
-1000 -250
850
800
St+1
750
ASAOKA METHOD:
Final Results:
700 Fill Height = 135 cm
Time interval = 3 days
Settlement at U=100% = 849 mm
650 Regression Line Slope = b = 0.9514
650 700 750 800 850 900
St Max Observed Settlement = 786 mm
Data Regression Series3 Degree of Consolidation
Achieved = 93%
200 50
0 0
-400 -100
Settlement (mm)
-600 -150
-800 -200
760
740
St+1
720
ASAOKA METHOD:
700 Final Results:
Fill Height = 140 cm
680 Time interval = 3 days
Settlement at U=100% = 760 mm
660 Regression Line Slope = b = 0.9396
660 680 700 720 740 760 780
St Max Observed Settlement = 712 mm
Data Regression Series3 Degree of Consolidation
Achieved = 94%
200 50
0 0
-400 -100
-600 -150
Settlement (mm)
-800 -200
-1000 -250
900
850
800
St+1
200 50
0 0
-400 -100
-600 -150
Settlement (mm)
-800 -200
-1000 -250
-1200 -300
1050
1000
950
St+1
200 50
0 0
-400 -100
-600 -150
Settlement (mm)
-800 -200
-1000 -250
1000
950
900
St+1
DATE
-100 2.500
-90
-80 2.000
-70
-60 1.500
-50
-40 1.000
-30
-20 0.500
-10
0 0.000
0
-50
-100
-150
-200
-250
SETTLEMENT CUMULATIVE (mm)
-300
-350
-400
-450
-500
-550
-600
-650
-700
DATE
PROYEK
JALANTOL KAYU AGUNG - PALEMBANG - BETUNG
PAKET II SEKSI 2A (IC PALINDRA)
STA 39+800 - 40+000 & STA 40+725 s/d 41+200
MONITORING SETTLEMENT PLATE
PT WASKITA KARYA (Persero), Tbk PT TEKNINDO GEOSISTEM UNGGUL
DATE
-100 2.500
-90
-80 2.000
-70
-60 1.500
-50
-40 1.000
-30
-20 0.500
-10
0 0.000
0
-50
-100
-150
-200
-250
SETTLEMENT CUMULATIVE (mm)
-300
-350
-400
-450
-500
-550
-600
-650
-700
DATE
PROYEK
JALANTOL KAYU AGUNG - PALEMBANG - BETUNG
PAKET II SEKSI 2A (IC PALINDRA)
STA 39+800 - 40+000 & STA 40+725 s/d 41+200
MONITORING SETTLEMENT PLATE
PT WASKITA KARYA (Persero), Tbk PT TEKNINDO GEOSISTEM UNGGUL
DATE
-100 2.500
-90
-80 2.000
-70
-60 1.500
-50
-40 1.000
-30
-20 0.500
-10
0 0.000
0
-50
-100
-150
-200
-250
SETTLEMENT CUMULATIVE (mm)
-300
-350
-400
-450
-500
-550
-600
-650
-700
DATE
PROYEK
JALANTOL KAYU AGUNG - PALEMBANG - BETUNG
PAKET II SEKSI 2A (IC PALINDRA)
STA 39+800 - 40+000 & STA 40+725 s/d 41+200
MONITORING SETTLEMENT PLATE
PT WASKITA KARYA (Persero), Tbk PT TEKNINDO GEOSISTEM UNGGUL
DATE
-100 2.000
-90 1.800
-80 1.600
-70 1.400
-60 1.200
-50 1.000
-40 0.800
-30 0.600
-20 0.400
-10 0.200
0 0.000
0
-50
-100
-150
-200
SETTLEMENT CUMULATIVE (mm)
-250
-300
-350
-400
-450
-500
-550
-600
DATE
PROYEK
JALANTOL KAYU AGUNG - PALEMBANG - BETUNG
PAKET II SEKSI 2A (IC PALINDRA)
STA 39+800 - 40+000 & STA 40+725 s/d 41+200
MONITORING SETTLEMENT PLATE
PT WASKITA KARYA (Persero), Tbk PT TEKNINDO GEOSISTEM UNGGUL
DATE
-100 2.500
-90
-80 2.000
-70
-60 1.500
-50
-40 1.000
-30
-20 0.500
-10
0 0.000
0
-50
-100
-150
-200
SETTLEMENT CUMULATIVE (mm)
-250
-300
-350
-400
-450
-500
-550
-600
-650
DATE
PROYEK
JALANTOL KAYU AGUNG - PALEMBANG - BETUNG
PAKET II SEKSI 2A (IC PALINDRA)
STA 39+800 - 40+000 & STA 40+725 s/d 41+200
MONITORING SETTLEMENT PLATE
PT WASKITA KARYA (Persero), Tbk PT TEKNINDO GEOSISTEM UNGGUL
DATE
-100 2.000
-90 1.800
-80 1.600
-70 1.400
-60 1.200
-50 1.000
-40 0.800
-30 0.600
-20 0.400
-10 0.200
0 0.000
0
-50
-100
-150
-200
SETTLEMENT CUMULATIVE (mm)
-250
-300
-350
-400
-450
-500
-550
-600
DATE
PROYEK
JALANTOL KAYU AGUNG - PALEMBANG - BETUNG
PAKET II SEKSI 2A (IC PALINDRA)
STA 39+800 - 40+000 & STA 40+725 s/d 41+200
MONITORING SETTLEMENT PLATE
PT WASKITA KARYA (Persero), Tbk PT TEKNINDO GEOSISTEM UNGGUL
DATE
-100 2.000
-90 1.800
-80 1.600
-70 1.400
-60 1.200
-50 1.000
-40 0.800
-30 0.600
-20 0.400
-10 0.200
0 0.000
0
-50
-100
-150
SETTLEMENT CUMULATIVE (mm)
-200
-250
-300
-350
-400
-450
-500
DATE
PROYEK
JALANTOL KAYU AGUNG - PALEMBANG - BETUNG
PAKET II SEKSI 2A (IC PALINDRA)
STA 39+800 - 40+000 & STA 40+725 s/d 41+200
MONITORING SETTLEMENT PLATE
PT WASKITA KARYA (Persero), Tbk PT TEKNINDO GEOSISTEM UNGGUL
DATE
-100 2.000
-90 1.800
-80 1.600
-70 1.400
-60 1.200
-50 1.000
-40 0.800
-30 0.600
-20 0.400
-10 0.200
0 0.000
0
-50
-100
-150
SETTLEMENT CUMULATIVE (mm)
-200
-250
-300
-350
-400
-450
-500
-550
DATE
PROYEK
JALANTOL KAYU AGUNG - PALEMBANG - BETUNG
PAKET II SEKSI 2A (IC PALINDRA)
STA 39+800 - 40+000 & STA 40+725 s/d 41+200
MONITORING SETTLEMENT PLATE
PT WASKITA KARYA (Persero), Tbk PT TEKNINDO GEOSISTEM UNGGUL
DATE
-100 2.000
-90 1.800
-80 1.600
-70 1.400
-60 1.200
-50 1.000
-40 0.800
-30 0.600
-20 0.400
-10 0.200
0 0.000
0
-50
-100
-150
SETTLEMENT CUMULATIVE (mm)
-200
-250
-300
-350
-400
-450
-500
DATE
PROYEK
JALANTOL KAYU AGUNG - PALEMBANG - BETUNG
PAKET II SEKSI 2A (IC PALINDRA)
STA 39+800 - 40+000 & STA 40+725 s/d 41+200
MONITORING SETTLEMENT PLATE
PT WASKITA KARYA (Persero), Tbk PT TEKNINDO GEOSISTEM UNGGUL
DATE
-100 1.500
-90
-80 1.200
-70
-60 0.900
-50
-40 0.600
-30
-20 0.300
-10
0 0.000
0
-50
-100
-150
SETTLEMENT CUMULATIVE (mm)
-200
-250
-300
-350
-400
-450
-500
-550
DATE
PROYEK
JALANTOL KAYU AGUNG - PALEMBANG - BETUNG
PAKET II SEKSI 2A (IC PALINDRA)
STA 39+800 - 40+000 & STA 40+725 s/d 41+200
MONITORING SETTLEMENT PLATE
PT WASKITA KARYA (Persero), Tbk PT TEKNINDO GEOSISTEM UNGGUL
DATE
-100 2.000
-90 1.800
-80 1.600
-70 1.400
-60 1.200
-50 1.000
-40 0.800
-30 0.600
-20 0.400
-10 0.200
0 0.000
0
-50
-100
-150
-200
-250
SETTLEMENT CUMULATIVE (mm)
-300
-350
-400
-450
-500
-550
-600
-650
-700
DATE
PROYEK
JALANTOL KAYU AGUNG - PALEMBANG - BETUNG
PAKET II SEKSI 2A (IC PALINDRA)
STA 39+800 - 40+000 & STA 40+725 s/d 41+200
MONITORING SETTLEMENT PLATE
PT WASKITA KARYA (Persero), Tbk PT TEKNINDO GEOSISTEM UNGGUL
DATE
-100 1.500
-90
-80 1.200
-70
-60 0.900
-50
-40 0.600
-30
-20 0.300
-10
0 0.000
0
-50
-100
-150
SETTLEMENT CUMULATIVE (mm)
-200
-250
-300
-350
-400
-450
-500
-550
DATE
PROYEK
JALANTOL KAYU AGUNG - PALEMBANG - BETUNG
PAKET II SEKSI 2A (IC PALINDRA)
STA 39+800 - 40+000 & STA 40+725 s/d 41+200
MONITORING SETTLEMENT PLATE
PT WASKITA KARYA (Persero), Tbk PT TEKNINDO GEOSISTEM UNGGUL
DATE
-100 1.500
-90
-80 1.200
-70
-60 0.900
-50
-40 0.600
-30
-20 0.300
-10
0 0.000
0
-50
-100
-150
SETTLEMENT CUMULATIVE (mm)
-200
-250
-300
-350
-400
-450
-500
-550
DATE
PROYEK
JALANTOL KAYU AGUNG - PALEMBANG - BETUNG
PAKET II SEKSI 2A (IC PALINDRA)
STA 39+800 - 40+000 & STA 40+725 s/d 41+200
MONITORING SETTLEMENT PLATE
PT WASKITA KARYA (Persero), Tbk PT TEKNINDO GEOSISTEM UNGGUL
DATE
-100 1.500
-90
-80 1.200
-70
-60 0.900
-50
-40 0.600
-30
-20 0.300
-10
0 0.000
0
-50
-100
-150
-200
-250
SETTLEMENT CUMULATIVE (mm)
-300
-350
-400
-450
-500
-550
-600
-650
-700
DATE
PROYEK
JALANTOL KAYU AGUNG - PALEMBANG - BETUNG
PAKET II SEKSI 2A (IC PALINDRA)
STA 39+800 - 40+000 & STA 40+725 s/d 41+200
MONITORING SETTLEMENT PLATE
PT WASKITA KARYA (Persero), Tbk PT TEKNINDO GEOSISTEM UNGGUL
DATE
-100 1.500
-90
-80 1.200
-70
-60 0.900
-50
-40 0.600
-30
-20 0.300
-10
0 0.000
0
-50
-100
-150
-200
SETTLEMENT CUMULATIVE (mm)
-250
-300
-350
-400
-450
-500
-550
-600
DATE
PROYEK
JALANTOL KAYU AGUNG - PALEMBANG - BETUNG
PAKET II SEKSI 2A (IC PALINDRA)
STA 39+800 - 40+000 & STA 40+725 s/d 41+200
MONITORING SETTLEMENT PLATE
PT WASKITA KARYA (Persero), Tbk PT TEKNINDO GEOSISTEM UNGGUL
DATE
-100 2.000
-90 1.800
-80 1.600
-70 1.400
-60 1.200
-50 1.000
-40 0.800
-30 0.600
-20 0.400
-10 0.200
0 0.000
0
-50
-100
-150
-200
SETTLEMENT CUMULATIVE (mm)
-250
-300
-350
-400
-450
-500
-550
-600
-650
DATE
PROYEK
JALANTOL KAYU AGUNG - PALEMBANG - BETUNG
PAKET II SEKSI 2A (IC PALINDRA)
STA 39+800 - 40+000 & STA 40+725 s/d 41+200
MONITORING SETTLEMENT PLATE
PT WASKITA KARYA (Persero), Tbk PT TEKNINDO GEOSISTEM UNGGUL
DATE
-100 2.000
-90 1.800
-80 1.600
-70 1.400
-60 1.200
-50 1.000
-40 0.800
-30 0.600
-20 0.400
-10 0.200
0 0.000
0
-50
-100
-150
-200
-250
-300
SETTLEMENT CUMULATIVE (mm)
-350
-400
-450
-500
-550
-600
-650
-700
-750
-800
-850
DATE
PROYEK
JALANTOL KAYU AGUNG - PALEMBANG - BETUNG
PAKET II SEKSI 2A (IC PALINDRA)
STA 39+800 - 40+000 & STA 40+725 s/d 41+200
MONITORING SETTLEMENT PLATE
PT WASKITA KARYA (Persero), Tbk PT TEKNINDO GEOSISTEM UNGGUL
DATE
-100 2.000
-90 1.800
-80 1.600
-70 1.400
-60 1.200
-50 1.000
-40 0.800
-30 0.600
-20 0.400
-10 0.200
0 0.000
0
-50
-100
-150
-200
-250
SETTLEMENT CUMULATIVE (mm)
-300
-350
-400
-450
-500
-550
-600
-650
-700
-750
DATE
PROYEK
JALANTOL KAYU AGUNG - PALEMBANG - BETUNG
PAKET II SEKSI 2A (IC PALINDRA)
STA 39+800 - 40+000 & STA 40+725 s/d 41+200
MONITORING SETTLEMENT PLATE
PT WASKITA KARYA (Persero), Tbk PT TEKNINDO GEOSISTEM UNGGUL
DATE
-100 2.000
-90 1.800
-80 1.600
-70 1.400
-60 1.200
-50 1.000
-40 0.800
-30 0.600
-20 0.400
-10 0.200
0 0.000
0
-50
-100
-150
-200
-250
-300
SETTLEMENT CUMULATIVE (mm)
-350
-400
-450
-500
-550
-600
-650
-700
-750
-800
-850
DATE
PROYEK
JALANTOL KAYU AGUNG - PALEMBANG - BETUNG
PAKET II SEKSI 2A (IC PALINDRA)
STA 39+800 - 40+000 & STA 40+725 s/d 41+200
MONITORING SETTLEMENT PLATE
PT WASKITA KARYA (Persero), Tbk PT TEKNINDO GEOSISTEM UNGGUL
DATE
-100 2.500
-90
-80 2.000
-70
-60 1.500
-50
-40 1.000
-30
-20 0.500
-10
0 0.000
0
-50
-100
-150
-200
-250
-300
-350
SETTLEMENT CUMULATIVE (mm)
-400
-450
-500
-550
-600
-650
-700
-750
-800
-850
-900
-950
-1000
-1050
DATE
PROYEK
JALANTOL KAYU AGUNG - PALEMBANG - BETUNG
PAKET II SEKSI 2A (IC PALINDRA)
STA 39+800 - 40+000 & STA 40+725 s/d 41+200
MONITORING SETTLEMENT PLATE
PT WASKITA KARYA (Persero), Tbk PT TEKNINDO GEOSISTEM UNGGUL
DATE
-100 2.500
-90
-80 2.000
-70
-60 1.500
-50
-40 1.000
-30
-20 0.500
-10
0 0.000
0
-50
-100
-150
-200
-250
-300
SETTLEMENT CUMULATIVE (mm)
-350
-400
-450
-500
-550
-600
-650
-700
-750
-800
-850
-900
-950
DATE
LAMPIRAN
D. GRAFIK MONITORING
VIBRATING WIRE
PIEZOMETER
PROYEK
JALANTOL KAYU AGUNG - PALEMBANG - BETUNG
PAKET II SEKSI 2A (IC PALINDRA)
STA 39+800 - 40+000 & STA 40+725 s/d 41+200
GRAFIK TINGGI TIMBUNAN, TEKANAN VAKUM & TEKANAN AIR PORI TANAH - GABUNGAN
3.500
3.000
2.500
PRELOAD ELEVATION (m)
2.000
1.500
1.000
0.500
0.000
-0.500
DATE
GRAPHIC OF VACUUM DEGREE MONITORING ( VG - 136 )
-110
-100
-90
-80
-70
VACUUM DEGREE (Kpa)
-60
-50
-40
-30
-20
-10
0
DATE
140
130
120
110
PORE WATER PRESSURE (kPa)
100
90
80
70
60
50
40
30
20
10
0
DATE
VWP-26
LAMPIRAN
E. GRAFIK MONITORING
INCLINOMETER
KAPB2a IN02 Off A KAPB2a IN02 Off B KAPB2a IN02 Off Top View
1/10/2019 8/4/2019 8/5/2019 8/6/2019 1/10/2019 8/4/2019 8/5/2019 8/6/2019 8/4/2019 8/5/2019 8/6/2019 8/7/2019
8/7/2019 8/8/2019 8/9/2019 8/10/2019 8/7/2019 8/8/2019 8/9/2019 8/10/2019 8/8/2019 8/9/2019 8/10/2019
( A - ) Arah ( A + ) Arah
Area Vacuum Luar Vacuum (B-) (B+)
0 0
Tanah
Asli
1 1
2 2
( A + ) Arah
3 3 Luar Vacuum
345 0 15
4 4
330 30
5 5 315 45
6 6 300
60
Depth in Meters
Depth in Meters
7 7 285 75
(B-) (B+)
8 8
270 90
40 20 0
9 9
255 105
10 10
240 120
11 11
225 135
12 12 210 150
195 180 165
13 13
( A - ) Arah
Area Vacuum
14 14
15 15
16 16
-60 -50 -40 -30 -20 -10 0 10 0 10 20 30
Profile Change in mm Profile Change in mm Resultant Profile_Change in mm
KAPB2a IN02A Off A KAPB2a IN02A Off B KAPB2a IN02A Off Top View
1/16/2019 8/4/2019 8/5/2019 1/16/2019 8/4/2019 8/5/2019 8/4/2019 8/5/2019 8/6/2019
8/6/2019 8/7/2019 8/8/2019 8/6/2019 8/7/2019 8/8/2019 8/7/2019 8/8/2019 8/9/2019
8/9/2019 8/10/2019 8/9/2019 8/10/2019 8/10/2019
( A - ) Arah ( A + ) Arah
0 Area Vacuum Luar Vacuum 0 (B-) (B+)
Tanah
Asli
1 1
2 2
3 3 ( A + ) Arah
Luar Vacuum
4 4 0
345 15
330 30
5 5
315 45
6 6 300
60
Depth in Meters
Depth in Meters
7 7
285 75
(B-)
8 8
270 90
20 0
9 9
255 105
10 10 240 120
11 11 225 135
210 150
12 12 195 180 165
13 13
( A - ) Arah
Area Vacuum
14 14
15 15
16 16
-40 -20 0 20 40 -20 -10 0 10 20
Profile Change in mm Profile Change in mm Resultant Profile_Change in mm
PREDIKSI KEMUNGKINAN RUNTUH
IN. 02
t = 1 harian
D1 = -0,380 mm
D2 = -0,250 mm
D2 Tanah Asli D3 = 0,140 mm
D3 D2 > D1
D1 D3 > D2
Syarat Kestabilan :
Dn < …..< D3 < D2 < D1
(D1, D2, D3 < 5mm)
OK!
-
PREDIKSI KEMUNGKINAN RUNTUH
IN. 02A
t = 1 harian
D1 = -0,190 mm
D2 = 0,120 mm
D2 > D1
D3 < D2
Syarat Kestabilan :
D2 Dn < …..< D3 < D2 < D1
(D1, D2, D3 < 5mm)
D3
OK!
D1
-
LAMPIRAN
F. DATA MONITORING
INSTRUMEN GEOTEKNIK
PEMBANGUNAN PROYEK JALAN TOL KAYU AGUNG-PALEMBANG-BETUNG PAKET II SEKSI 2A (IC PALINDRA)
DATA MONITORING INSTRUMENT VACUUM
MODUL 2 (STA 40+675 - 41+010)
2 SP‐08 CL 40+750 3.093 5.607 4.379 0.587 1.286 1.82 134.89 84.49 1.60
3 SP‐09 CL 40+800 3.111 5.184 4.656 0.506 1.545 1.03 125.65 75.25 1.67
4 Modul 02 SP‐10 CL 40+850 4.155 5.078 4.652 0.629 0.497 1.06 107.47 57.07 1.88
5 SP‐11 CL 40+900 3.322 5.288 4.484 0.624 1.162 1.43 125.84 75.44 1.67
6 SP‐12 CL 40+950 3.464 5.686 4.413 0.786 0.949 2.06 133.24 82.84 1.61
8 SP‐13 CL 41+000 3.487 6.086 4.203 0.97 0.716 2.85 143.17 92.77 1.54
Note:
(1) Beban Vacuum = 80.00 kPa
3
(2) Beban Pavement = 0.20 m x 23 kN/m = 4.60 kPa
3
(3) Beban Sub‐base = 0.50 m x 20 kN/m = 10.00 kPa
(4) timb = 18.7 kN/m3 untuk Modul 1 dan 17.7 kN/m3 untuk Modul 2&3 (Hasil Terlampir)
(5) Beban Traffic = 15 kPa
(6) Improvement Load = (1) + {(I + J)*(4)}
(7) Operational Load = (2) + (3) + (5) + {(I + J)*(4)}
LAMPIRAN
H. GRAFIK SONDIR SEBELUM
DAN SESUDAH PEKERJAAN
VACUUM PRELOADING
DAN PENYELIDIKAN TANAH
UNTUK PEMERIKSAAN
DAYA DUKUNG
Kedalaman vs Hambatan Konus, qc Kedalaman vs Hambatan Konus, qc Kedalaman vs Hambatan Konus, qc
MODUL 2 MODUL 2 MODUL 2
qc (kg/cm2) qc (kg/cm2) qc (kg/cm2)
0 40 80 120 0 40 80 120 0 40 80 120
5.0 5.0 5.0
Depth (m)
Depth (m)
‐15.0 ‐15.0 ‐15.0
Keterangan:
1. Kedalaman 0 ‐ 3 m, shear strength naik sebesar 21 %. Dan konsistensinya tetap medium
2. Kedalaman 3 ‐ 20 m, shear strength naik sebesar 40 %. Dan konsistensinya tetap soft
Kedalaman vs Hambatan Konus, qc Kedalaman vs Hambatan Konus, qc
MODUL 2 MODUL 2
qc (kg/cm2) qc (kg/cm2)
0 40 80 120 0 40 80 120
5.0 5.0
O.G.L O.G.L
0.0 0.0
40+975 (pra)
40+925 (pra) 40+975 (post)
40+925 (post)
‐5.0 ‐5.0
‐10.0 ‐10.0
Depth (m)
Depth (m)
‐15.0 ‐15.0
‐20.0 ‐20.0
‐25.0 ‐25.0
‐30.0 ‐30.0
4.2.3. Plate Bearing Test No. 1 STA 40+035
PLATEBEARINGTEST
Project : PembangunanJalanTolKayuAgungͲPalembangͲ PointNo : 2
BetungSeksi2danSeksi2A(KAPB2danKAPB2A)
Location : IbulModul2STA40+925 SoilType : SAND,DarkBrown
Date : 12ͲAugͲ19 PlateDia. : 0,3 meter
Tested : CepyCs PlateArea : 0,07065 m2
300
200
Stress(kN/m2)
100
0
0 0,0005 0,001 0,0015 0,002 0,0025 0,003
Settlement(m)
CindartoLie.