Gantt-Chart - KERJA PENGGANTIAN KEMASAN LANTAI KARPET DI ARAS 2 DAN MEZZANINE MASJID SULTAN IBRAHIM
Gantt-Chart - KERJA PENGGANTIAN KEMASAN LANTAI KARPET DI ARAS 2 DAN MEZZANINE MASJID SULTAN IBRAHIM
Project Start Date Fri 16/02/24 Display Week 1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7
Project Lead 11 Feb 2024 18 Feb 2024 25 Feb 2024 3 Mar 2024 10 Mar 2024 17 Mar 2024 24 Mar 2024
11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
WORK
WBS TASK LEAD START END DAYS % DONE S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
DAYS
1 Kerja Awalan
Urusan kelulusan bahan
1.1 [Name] Fri 16/02/24 Wed 21/02/24 6
Urusan tempahan bahan
1.2 (ordering material ) Fri 16/02/24 Wed 21/02/24 6
WORK
WBS TASK LEAD START END DAYS % DONE S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
DAYS
Kerja-kerja membekal
5.1 dan memasang bahan Sat 16/03/24 Sun 17/03/24 2
elektrik
Kerja-kerja kekemasan,
5.2 pemasangan Mon 18/03/24 Tue 19/03/24 2
kelengkapan dan aksesori
Kerja-kerja pembersihan
5.3 Wed 20/03/24 Thu 21/03/24 2
tapak projek
Kerja-kerja pembersihan
6.5 Thu 28/03/24 Fri 29/03/24 2
tapak projek