KERJA-KERJA PENGGANTIAN KEMASAN LANTAI KARPET DI ARAS 2 DAN MEZZANINE MASJID SULTAN IBRAHIM (UTHM/08/K/04/011/2023)

MKF HAYASA ENTERPRISE

Project Start Date Fri 16/02/24 Display Week 1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7
Project Lead 11 Feb 2024 18 Feb 2024 25 Feb 2024 3 Mar 2024 10 Mar 2024 17 Mar 2024 24 Mar 2024
11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

WORK
WBS TASK LEAD START END DAYS % DONE S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
DAYS

1 Kerja Awalan
Urusan kelulusan bahan
1.1 [Name] Fri 16/02/24 Wed 21/02/24 6
Urusan tempahan bahan
1.2 (ordering material ) Fri 16/02/24 Wed 21/02/24 6

Urusan tempahan dan


1.3 pemasangan signboard Fri 16/02/24 Wed 21/02/24 6

Urusan insurans projek


1.4 Fri 16/02/24 Wed 21/02/24 6

2 ZON 4 (Masjid Sultan Ibrahim)


Kerja-kerja pembukaan
2.1 karpet lama di tapak Wed 21/02/24 Thu 22/02/24 2
projek
Kerja-kerja pembersihan
2.2 karpet lama di tapak Fri 23/02/24 Sat 24/02/24 2
projek
Kerja-kerja meratakan
2.3 (levelling) lantai di tapak Sun 25/02/24 Mon 26/02/24 2
projek
Kerja-kerja pemasangan
2.4 karpet baru di tapak Tue 27/02/24 Wed 28/02/24 2
projek
3 ZON 3 (Masjid Sultan Ibrahim)
Kerja-kerja pembukaan
3.1 karpet lama di tapak Thu 29/02/24 Fri 01/03/24 2
projek
Kerja-kerja pembersihan
3.2 karpet lama di tapak Sat 02/03/24 Sun 03/03/24 2
projek
Kerja-kerja meratakan
3.3 (levelling) lantai di tapak Mon 04/03/24 Tue 05/03/24 2
projek
Kerja-kerja pemasangan
3.4 karpet baru di tapak Wed 06/03/24 Thu 07/03/24 2
projek
4 ZON 2 (Masjid Sultan Ibrahim)
Kerja-kerja pembukaan
4.1 karpet lama di tapak Fri 08/03/24 Sat 09/03/24 2
projek
Kerja-kerja pembersihan
4.2 karpet lama di tapak Sun 10/03/24 Mon 11/03/24 2
projek
Kerja-kerja meratakan
4.3 (levelling) lantai di tapak Tue 12/03/24 Wed 13/03/24 2
projek
Kerja-kerja pemasangan
4.4 karpet baru di tapak Thu 14/03/24 Fri 15/03/24 2
projek
5 Kerja Elektrik dan Hal-hal Lain
Project Start Date Fri 16/02/24 Display Week 1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7
Project Lead 11 Feb 2024 18 Feb 2024 25 Feb 2024 3 Mar 2024 10 Mar 2024 17 Mar 2024 24 Mar 2024
11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

WORK
WBS TASK LEAD START END DAYS % DONE S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
DAYS

Kerja-kerja membekal
5.1 dan memasang bahan Sat 16/03/24 Sun 17/03/24 2
elektrik

Kerja-kerja kekemasan,
5.2 pemasangan Mon 18/03/24 Tue 19/03/24 2
kelengkapan dan aksesori

Kerja-kerja pembersihan
5.3 Wed 20/03/24 Thu 21/03/24 2
tapak projek

6 ZON 1 (Masjid Sultan Ibrahim)


Kerja-kerja pembukaan
6.1 karpet lama di tapak Fri 22/03/24 Sat 23/03/24 2
projek
Kerja-kerja pembersihan
6.2 karpet lama di tapak Sun 24/03/24 Mon 25/03/24 2
projek
Kerja-kerja meratakan
6.3 (levelling) lantai di tapak Tue 26/03/24 Wed 27/03/24 2
projek
Kerja-kerja pemasangan
6.4 karpet baru di tapak Wed 27/03/24 Thu 28/03/24 2
projek

Kerja-kerja pembersihan
6.5 Thu 28/03/24 Fri 29/03/24 2
tapak projek