ID Task Task Name Duration Start Finish Predecessors

Resource Names January 2024 February 2024 March 2024 April 2024 May 2024 June 2024
Mode 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17
0 SCHEDULE DESAIN RTA BANGUNAN PENGGANTI 109 days? Mon 1/1/24Thu 5/30/24
1 1 SD N GUNUNGSARI 47 days Mon 1/1/24 Tue 3/5/24
2 1.1 FASE PERSETUJUAN IJIN PRINSIP 45 days Mon 1/1/24 Fri 3/1/24
3 1.1.1 Rapat Koordinasi Dengan Bina Marga 7 days Mon 1/1/24 Tue 1/9/24 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
4 1.1.2 Penyusunan Berita Acara Ijin Prinsip 7 days Wed 1/10/24Thu 1/18/24 3 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
5 1.1.3 Sirkuler Tanda Tangan di Bina Marga 30 days Fri 1/19/24 Thu 2/29/24 4 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
6 1.1.4 Serah Terima Berita Acara Ijin Prinsip 1 day Fri 3/1/24 Fri 3/1/24 5 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
7 1.2 FASE PRODUKSI 2 days Mon 3/4/24 Tue 3/5/24 6
8 1.2.1 Serah terima dokumen RTA ke bidang produksi WSP
2 days Mon 3/4/24 Tue 3/5/24 6 WSP TEKNIK WSP TEKNIK
9 2 MUSHOLLA DARUL IMAN 47 days Mon 1/1/24 Tue 3/5/24
10 2.1 FASE PERSETUJUAN IJIN PRINSIP 45 days Mon 1/1/24 Fri 3/1/24
11 2.1.1 Rapat Koordinasi Dengan Bina Marga 7 days Mon 1/1/24 Tue 1/9/24 WSP TEKNIK,JBH,PPK WSP TEKNIK,JBH,PPK
12 2.1.2 Penyusunan Berita Acara Ijin Prinsip 7 days Wed 1/10/24Thu 1/18/24 11 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
13 2.1.3 Sirkuler Tanda Tangan di Bina Marga 30 days Fri 1/19/24 Thu 2/29/24 12 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
14 2.1.4 Serah Terima Berita Acara Ijin Prinsip 1 day Fri 3/1/24 Fri 3/1/24 13 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
15 2.2 FASE PRODUKSI 2 days Mon 3/4/24 Tue 3/5/24 14
16 2.2.1 Serah terima dokumen RTA ke bidang produksi WSP
2 days Mon 3/4/24 Tue 3/5/24 14 WSP TEKNIK WSP TEKNIK
17 3 MUSHOLLA BAITUL SALAM 1 day? Mon 1/1/24 Mon 1/1/24
18 3.1 FASE PRODUKSI 1 day? Mon 1/1/24 Mon 1/1/24
19 3.2 Serah terima dokumen RTA ke bidang produksi WSP 1 day Mon 1/1/24 Mon 1/1/24 WSP TEKNIK WSP TEKNIK
20 4 SD PASIR SEDANG 109 days Mon 1/1/24 Thu 5/30/24
21 4.1 DESAIN RTA BANGUNAN PENGGANTI 64 days Mon 1/1/24 Thu 3/28/24
22 4.1.1 Pengadaan Konsultan 14 days Mon 1/1/24 Thu 1/18/24 WSP TEKNIK WSP TEKNIK
23 4.1.2 Survey Lahan 7 days Fri 1/19/24 Mon 1/29/2422 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA
24 4.1.3 Pengambilan Data Tanah 7 days Tue 1/30/24 Wed 2/7/24 23 KONSULTAN PERENCANA KONSULTAN PERENCANA
25 4.1.4 Berita Acara Usulan Desain 7 days Thu 2/8/24 Fri 2/16/24 24 WSP TEKNIK,KONSULTAN PERENCANA,PPK WSP TEKNIK,KONSULTAN PERENCANA,PPK
26 4.1.5 Proses Desain 14 days Mon 2/19/24Thu 3/7/24 25 KONSULTAN PERENCANA KONSULTAN PERENCANA
27 4.1.6 Sirkuler Tanda Tangan di Bina Marga 14 days Fri 3/8/24 Wed 3/27/2426 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA
28 4.1.7 Serah Terima Desain BUJT 1 day Thu 3/28/24 Thu 3/28/24 27 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA
29 4.2 FASE PERSETUJUAN IJIN PRINSIP 45 days Fri 3/29/24 Thu 5/30/24 28
30 4.2.1 Rapat Koordinasi Dengan Bina Marga 7 days Fri 3/29/24 Mon 4/8/24 28 WSP TEKNIK,JBH,PPK WSP TEKNIK,JBH,PPK
31 4.2.2 Penyusunan Berita Acara Ijin Prinsip 7 days Tue 4/9/24 Wed 4/17/2430 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
32 4.2.3 Sirkuler Tanda Tangan di Bina Marga 30 days Thu 4/18/24 Wed 5/29/2431 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
33 4.2.4 Serah Terima Berita Acara Ijin Prinsip 1 day Thu 5/30/24 Thu 5/30/24 32 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
34 5 SD PASIR SEDANG 109 days Mon 1/1/24 Thu 5/30/24
35 5.1 DESAIN RTA BANGUNAN PENGGANTI 64 days Mon 1/1/24 Thu 3/28/24
36 5.1.1 Pengadaan Konsultan 14 days Mon 1/1/24 Thu 1/18/24 WSP TEKNIK WSP TEKNIK
37 5.1.2 Survey Lahan 7 days Fri 1/19/24 Mon 1/29/2436 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA
38 5.1.3 Pengambilan Data Tanah 7 days Tue 1/30/24 Wed 2/7/24 37 KONSULTAN PERENCANA KONSULTAN PERENCANA
39 5.1.4 Berita Acara Usulan Desain 7 days Thu 2/8/24 Fri 2/16/24 38 WSP TEKNIK,KONSULTAN PERENCANA,PPK WSP TEKNIK,KONSULTAN PERENCANA,PPK
40 5.1.5 Proses Desain 14 days Mon 2/19/24Thu 3/7/24 39 KONSULTAN PERENCANA KONSULTAN PERENCANA
41 5.1.6 Sirkuler Tanda Tangan di Bina Marga 14 days Fri 3/8/24 Wed 3/27/2440 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA
42 5.1.7 Serah Terima Desain BUJT 1 day Thu 3/28/24 Thu 3/28/24 41 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA
43 5.2 FASE PERSETUJUAN IJIN PRINSIP 45 days Fri 3/29/24 Thu 5/30/24 42
44 5.2.1 Rapat Koordinasi Dengan Bina Marga 7 days Fri 3/29/24 Mon 4/8/24 42 WSP TEKNIK,JBH,PPK WSP TEKNIK,JBH,PPK
45 5.2.2 Penyusunan Berita Acara Ijin Prinsip 7 days Tue 4/9/24 Wed 4/17/2444 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
46 5.2.3 Sirkuler Tanda Tangan di Bina Marga 30 days Thu 4/18/24 Wed 5/29/2445 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
47 5.2.4 Serah Terima Berita Acara Ijin Prinsip 1 day Thu 5/30/24 Thu 5/30/24 46 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
48 6 MADRASAH MDTA MATHLAUL ANWAR 109 days Mon 1/1/24 Thu 5/30/24
49 6.1 DESAIN RTA BANGUNAN PENGGANTI 64 days Mon 1/1/24 Thu 3/28/24
50 6.1.1 Pengadaan Konsultan 14 days Mon 1/1/24 Thu 1/18/24 WSP TEKNIK WSP TEKNIK
51 6.1.2 Survey Lahan 7 days Fri 1/19/24 Mon 1/29/2450 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA
52 6.1.3 Pengambilan Data Tanah 7 days Tue 1/30/24 Wed 2/7/24 51 KONSULTAN PERENCANA KONSULTAN PERENCANA
53 6.1.4 Berita Acara Usulan Desain 7 days Thu 2/8/24 Fri 2/16/24 52 WSP TEKNIK,KONSULTAN PERENCANA,PPK WSP TEKNIK,KONSULTAN PERENCANA,PPK
54 6.1.5 Proses Desain 14 days Mon 2/19/24Thu 3/7/24 53 KONSULTAN PERENCANA KONSULTAN PERENCANA
55 6.1.6 Sirkuler Tanda Tangan di Bina Marga 14 days Fri 3/8/24 Wed 3/27/2454 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA
56 6.1.7 Serah Terima Desain BUJT 1 day Thu 3/28/24 Thu 3/28/24 55 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA
57 6.2 FASE PERSETUJUAN IJIN PRINSIP 45 days Fri 3/29/24 Thu 5/30/24 56
58 6.2.1 Rapat Koordinasi Dengan Bina Marga 7 days Fri 3/29/24 Mon 4/8/24 56 WSP TEKNIK,JBH,PPK WSP TEKNIK,JBH,PPK
59 6.2.2 Penyusunan Berita Acara Ijin Prinsip 7 days Tue 4/9/24 Wed 4/17/2458 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
60 6.2.3 Sirkuler Tanda Tangan di Bina Marga 30 days Thu 4/18/24 Wed 5/29/2459 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
61 6.2.4 Serah Terima Berita Acara Ijin Prinsip 1 day Thu 5/30/24 Thu 5/30/24 60 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
62 7 SDN PASIR KADU 1 109 days Mon 1/1/24 Thu 5/30/24
63 7.1 DESAIN RTA BANGUNAN PENGGANTI 64 days Mon 1/1/24 Thu 3/28/24
64 7.1.1 Pengadaan Konsultan 14 days Mon 1/1/24 Thu 1/18/24 WSP TEKNIK WSP TEKNIK
65 7.1.2 Survey Lahan 7 days Fri 1/19/24 Mon 1/29/2464 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA
66 7.1.3 Pengambilan Data Tanah 7 days Tue 1/30/24 Wed 2/7/24 65 KONSULTAN PERENCANA KONSULTAN PERENCANA
67 7.1.4 Berita Acara Usulan Desain 7 days Thu 2/8/24 Fri 2/16/24 66 WSP TEKNIK,KONSULTAN PERENCANA,PPK WSP TEKNIK,KONSULTAN PERENCANA,PPK
68 7.1.5 Proses Desain 14 days Mon 2/19/24Thu 3/7/24 67 KONSULTAN PERENCANA KONSULTAN PERENCANA
69 7.1.6 Sirkuler Tanda Tangan di Bina Marga 14 days Fri 3/8/24 Wed 3/27/2468 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA
70 7.1.7 Serah Terima Desain BUJT 1 day Thu 3/28/24 Thu 3/28/24 69 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA
71 7.2 FASE PERSETUJUAN IJIN PRINSIP 45 days Fri 3/29/24 Thu 5/30/24 70
72 7.2.1 Rapat Koordinasi Dengan Bina Marga 7 days Fri 3/29/24 Mon 4/8/24 70 WSP TEKNIK,JBH,PPK WSP TEKNIK,JBH,PPK
73 7.2.2 Penyusunan Berita Acara Ijin Prinsip 7 days Tue 4/9/24 Wed 4/17/2472 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
74 7.2.3 Sirkuler Tanda Tangan di Bina Marga 30 days Thu 4/18/24 Wed 5/29/2473 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: SCHEDULE DESAIN RTA
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Tue 1/16/24
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 1
ID Task Task Name Duration Start Finish Predecessors
Resource Names January 2024 February 2024 March 2024 April 2024 May 2024 June 2024
Mode 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17
75 7.2.4 Serah Terima Berita Acara Ijin Prinsip 1 day Thu 5/30/24 Thu 5/30/24 74 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
76 8 MUSHOLLA SIROTUL JANNAH PASIR KADU 109 days Mon 1/1/24 Thu 5/30/24
77 8.1 DESAIN RTA BANGUNAN PENGGANTI 64 days Mon 1/1/24 Thu 3/28/24
78 8.1.1 Pengadaan Konsultan 14 days Mon 1/1/24 Thu 1/18/24 WSP TEKNIK WSP TEKNIK
79 8.1.2 Survey Lahan 7 days Fri 1/19/24 Mon 1/29/2478 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA
80 8.1.3 Pengambilan Data Tanah 7 days Tue 1/30/24 Wed 2/7/24 79 KONSULTAN PERENCANA KONSULTAN PERENCANA
81 8.1.4 Berita Acara Usulan Desain 7 days Thu 2/8/24 Fri 2/16/24 80 WSP TEKNIK,KONSULTAN PERENCANA,PPK WSP TEKNIK,KONSULTAN PERENCANA,PPK
82 8.1.5 Proses Desain 14 days Mon 2/19/24Thu 3/7/24 81 KONSULTAN PERENCANA KONSULTAN PERENCANA
83 8.1.6 Sirkuler Tanda Tangan di Bina Marga 14 days Fri 3/8/24 Wed 3/27/2482 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA
84 8.1.7 Serah Terima Desain BUJT 1 day Thu 3/28/24 Thu 3/28/24 83 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA
85 8.2 FASE PERSETUJUAN IJIN PRINSIP 45 days Fri 3/29/24 Thu 5/30/24 84
86 8.2.1 Rapat Koordinasi Dengan Bina Marga 7 days Fri 3/29/24 Mon 4/8/24 84 WSP TEKNIK,JBH,PPK WSP TEKNIK,JBH,PPK
87 8.2.2 Penyusunan Berita Acara Ijin Prinsip 7 days Tue 4/9/24 Wed 4/17/2486 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
88 8.2.3 Sirkuler Tanda Tangan di Bina Marga 30 days Thu 4/18/24 Wed 5/29/2487 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
89 8.2.4 Serah Terima Berita Acara Ijin Prinsip 1 day Thu 5/30/24 Thu 5/30/24 88 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
90 9 BALAI KAMPUNG DESA GOMBONG 109 days Mon 1/1/24 Thu 5/30/24
91 9.1 DESAIN RTA BANGUNAN PENGGANTI 64 days Mon 1/1/24 Thu 3/28/24
92 9.1.1 Pengadaan Konsultan 14 days Mon 1/1/24 Thu 1/18/24 WSP TEKNIK WSP TEKNIK
93 9.1.2 Survey Lahan 7 days Fri 1/19/24 Mon 1/29/2492 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA
94 9.1.3 Pengambilan Data Tanah 7 days Tue 1/30/24 Wed 2/7/24 93 KONSULTAN PERENCANA KONSULTAN PERENCANA
95 9.1.4 Berita Acara Usulan Desain 7 days Thu 2/8/24 Fri 2/16/24 94 WSP TEKNIK,KONSULTAN PERENCANA,PPK WSP TEKNIK,KONSULTAN PERENCANA,PPK
96 9.1.5 Proses Desain 14 days Mon 2/19/24Thu 3/7/24 95 KONSULTAN PERENCANA KONSULTAN PERENCANA
97 9.1.6 Sirkuler Tanda Tangan di Bina Marga 14 days Fri 3/8/24 Wed 3/27/2496 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA
98 9.1.7 Serah Terima Desain BUJT 1 day Thu 3/28/24 Thu 3/28/24 97 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA
99 9.2 FASE PERSETUJUAN IJIN PRINSIP 45 days Fri 3/29/24 Thu 5/30/24 98
100 9.2.1 Rapat Koordinasi Dengan Bina Marga 7 days Fri 3/29/24 Mon 4/8/24 98 WSP TEKNIK,JBH,PPK WSP TEKNIK,JBH,PPK
101 9.2.2 Penyusunan Berita Acara Ijin Prinsip 7 days Tue 4/9/24 Wed 4/17/24100 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
102 9.2.3 Sirkuler Tanda Tangan di Bina Marga 30 days Thu 4/18/24 Wed 5/29/24101 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
103 9.2.4 Serah Terima Berita Acara Ijin Prinsip 1 day Thu 5/30/24 Thu 5/30/24 102 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
104 10 MASJID AL IKHLAS DESA GOMBONG 109 days Mon 1/1/24 Thu 5/30/24
105 10.1 DESAIN RTA BANGUNAN PENGGANTI 64 days Mon 1/1/24 Thu 3/28/24
106 10.1.1 Pengadaan Konsultan 14 days Mon 1/1/24 Thu 1/18/24 WSP TEKNIK WSP TEKNIK
107 10.1.2 Survey Lahan 7 days Fri 1/19/24 Mon 1/29/24106 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA
108 10.1.3 Pengambilan Data Tanah 7 days Tue 1/30/24 Wed 2/7/24 107 KONSULTAN PERENCANA KONSULTAN PERENCANA
109 10.1.4 Berita Acara Usulan Desain 7 days Thu 2/8/24 Fri 2/16/24 108 WSP TEKNIK,KONSULTAN PERENCANA,PPK WSP TEKNIK,KONSULTAN PERENCANA,PPK
110 10.1.5 Proses Desain 14 days Mon 2/19/24Thu 3/7/24 109 KONSULTAN PERENCANA KONSULTAN PERENCANA
111 10.1.6 Sirkuler Tanda Tangan di Bina Marga 14 days Fri 3/8/24 Wed 3/27/24110 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA
112 10.1.7 Serah Terima Desain BUJT 1 day Thu 3/28/24 Thu 3/28/24 111 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA
113 10.2 FASE PERSETUJUAN IJIN PRINSIP 45 days Fri 3/29/24 Thu 5/30/24 112
114 10.2.1 Rapat Koordinasi Dengan Bina Marga 7 days Fri 3/29/24 Mon 4/8/24 112 WSP TEKNIK,JBH,PPK WSP TEKNIK,JBH,PPK
115 10.2.2 Penyusunan Berita Acara Ijin Prinsip 7 days Tue 4/9/24 Wed 4/17/24114 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
116 10.2.3 Sirkuler Tanda Tangan di Bina Marga 30 days Thu 4/18/24 Wed 5/29/24115 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
117 10.2.4 Serah Terima Berita Acara Ijin Prinsip 1 day Thu 5/30/24 Thu 5/30/24 116 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
118 11 MASJID CIJAKAN (NURUL IMAN) 109 days Mon 1/1/24 Thu 5/30/24
119 11.1 DESAIN RTA BANGUNAN PENGGANTI 64 days Mon 1/1/24 Thu 3/28/24
120 11.1.1 Pengadaan Konsultan 14 days Mon 1/1/24 Thu 1/18/24 WSP TEKNIK WSP TEKNIK
121 11.1.2 Survey Lahan 7 days Fri 1/19/24 Mon 1/29/24120 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA
122 11.1.3 Pengambilan Data Tanah 7 days Tue 1/30/24 Wed 2/7/24 121 KONSULTAN PERENCANA KONSULTAN PERENCANA
123 11.1.4 Berita Acara Usulan Desain 7 days Thu 2/8/24 Fri 2/16/24 122 WSP TEKNIK,KONSULTAN PERENCANA,PPK WSP TEKNIK,KONSULTAN PERENCANA,PPK
124 11.1.5 Proses Desain 14 days Mon 2/19/24Thu 3/7/24 123 KONSULTAN PERENCANA KONSULTAN PERENCANA
125 11.1.6 Sirkuler Tanda Tangan di Bina Marga 14 days Fri 3/8/24 Wed 3/27/24124 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA
126 11.1.7 Serah Terima Desain BUJT 1 day Thu 3/28/24 Thu 3/28/24 125 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA
127 11.2 FASE PERSETUJUAN IJIN PRINSIP 45 days Fri 3/29/24 Thu 5/30/24 126
128 11.2.1 Rapat Koordinasi Dengan Bina Marga 7 days Fri 3/29/24 Mon 4/8/24 126 WSP TEKNIK,JBH,PPK WSP TEKNIK,JBH,PPK
129 11.2.2 Penyusunan Berita Acara Ijin Prinsip 7 days Tue 4/9/24 Wed 4/17/24128 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
130 11.2.3 Sirkuler Tanda Tangan di Bina Marga 30 days Thu 4/18/24 Wed 5/29/24129 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
131 11.2.4 Serah Terima Berita Acara Ijin Prinsip 1 day Thu 5/30/24 Thu 5/30/24 130 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
132 12 SDN 2 CIJAKAN 109 days Mon 1/1/24 Thu 5/30/24
133 12.1 DESAIN RTA BANGUNAN PENGGANTI 64 days Mon 1/1/24 Thu 3/28/24
134 12.1.1 Pengadaan Konsultan 14 days Mon 1/1/24 Thu 1/18/24 WSP TEKNIK WSP TEKNIK
135 12.1.2 Survey Lahan 7 days Fri 1/19/24 Mon 1/29/24134 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA
136 12.1.3 Pengambilan Data Tanah 7 days Tue 1/30/24 Wed 2/7/24 135 KONSULTAN PERENCANA KONSULTAN PERENCANA
137 12.1.4 Berita Acara Usulan Desain 7 days Thu 2/8/24 Fri 2/16/24 136 WSP TEKNIK,KONSULTAN PERENCANA,PPK WSP TEKNIK,KONSULTAN PERENCANA,PPK
138 12.1.5 Proses Desain 14 days Mon 2/19/24Thu 3/7/24 137 KONSULTAN PERENCANA KONSULTAN PERENCANA
139 12.1.6 Sirkuler Tanda Tangan di Bina Marga 14 days Fri 3/8/24 Wed 3/27/24138 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA
140 12.1.7 Serah Terima Desain BUJT 1 day Thu 3/28/24 Thu 3/28/24 139 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA
141 12.2 FASE PERSETUJUAN IJIN PRINSIP 45 days Fri 3/29/24 Thu 5/30/24 140
142 12.2.1 Rapat Koordinasi Dengan Bina Marga 7 days Fri 3/29/24 Mon 4/8/24 140 WSP TEKNIK,JBH,PPK WSP TEKNIK,JBH,PPK
143 12.2.2 Penyusunan Berita Acara Ijin Prinsip 7 days Tue 4/9/24 Wed 4/17/24142 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
144 12.2.3 Sirkuler Tanda Tangan di Bina Marga 30 days Thu 4/18/24 Wed 5/29/24143 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
145 12.2.4 Serah Terima Berita Acara Ijin Prinsip 1 day Thu 5/30/24 Thu 5/30/24 144 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
146 13 MUSHOLLA CIJAKAN (AL-HIDAYAH) 109 days Mon 1/1/24 Thu 5/30/24
147 13.1 DESAIN RTA BANGUNAN PENGGANTI 64 days Mon 1/1/24 Thu 3/28/24
148 13.1.1 Pengadaan Konsultan 14 days Mon 1/1/24 Thu 1/18/24 WSP TEKNIK WSP TEKNIK
149 13.1.2 Survey Lahan 7 days Fri 1/19/24 Mon 1/29/24148 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: SCHEDULE DESAIN RTA
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Tue 1/16/24
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 2
ID Task Task Name Duration Start Finish Predecessors
Resource Names January 2024 February 2024 March 2024 April 2024 May 2024 June 2024
Mode 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17
150 13.1.3 Pengambilan Data Tanah 7 days Tue 1/30/24 Wed 2/7/24 149 KONSULTAN PERENCANA KONSULTAN PERENCANA
151 13.1.4 Berita Acara Usulan Desain 7 days Thu 2/8/24 Fri 2/16/24 150 WSP TEKNIK,KONSULTAN PERENCANA,PPK WSP TEKNIK,KONSULTAN PERENCANA,PPK
152 13.1.5 Proses Desain 14 days Mon 2/19/24Thu 3/7/24 151 KONSULTAN PERENCANA KONSULTAN PERENCANA
153 13.1.6 Sirkuler Tanda Tangan di Bina Marga 14 days Fri 3/8/24 Wed 3/27/24152 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA
154 13.1.7 Serah Terima Desain BUJT 1 day Thu 3/28/24 Thu 3/28/24 153 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA
155 13.2 FASE PERSETUJUAN IJIN PRINSIP 45 days Fri 3/29/24 Thu 5/30/24 154
156 13.2.1 Rapat Koordinasi Dengan Bina Marga 7 days Fri 3/29/24 Mon 4/8/24 154 WSP TEKNIK,JBH,PPK WSP TEKNIK,JBH,PPK
157 13.2.2 Penyusunan Berita Acara Ijin Prinsip 7 days Tue 4/9/24 Wed 4/17/24156 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
158 13.2.3 Sirkuler Tanda Tangan di Bina Marga 30 days Thu 4/18/24 Wed 5/29/24157 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
159 13.2.4 Serah Terima Berita Acara Ijin Prinsip 1 day Thu 5/30/24 Thu 5/30/24 158 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
160 14 SDN 3 CIJAKAN 109 days Mon 1/1/24 Thu 5/30/24
161 14.1 DESAIN RTA BANGUNAN PENGGANTI 64 days Mon 1/1/24 Thu 3/28/24
162 14.1.1 Pengadaan Konsultan 14 days Mon 1/1/24 Thu 1/18/24 WSP TEKNIK WSP TEKNIK
163 14.1.2 Survey Lahan 7 days Fri 1/19/24 Mon 1/29/24162 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA
164 14.1.3 Pengambilan Data Tanah 7 days Tue 1/30/24 Wed 2/7/24 163 KONSULTAN PERENCANA KONSULTAN PERENCANA
165 14.1.4 Berita Acara Usulan Desain 7 days Thu 2/8/24 Fri 2/16/24 164 WSP TEKNIK,KONSULTAN PERENCANA,PPK WSP TEKNIK,KONSULTAN PERENCANA,PPK
166 14.1.5 Proses Desain 14 days Mon 2/19/24Thu 3/7/24 165 KONSULTAN PERENCANA KONSULTAN PERENCANA
167 14.1.6 Sirkuler Tanda Tangan di Bina Marga 14 days Fri 3/8/24 Wed 3/27/24166 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA
168 14.1.7 Serah Terima Desain BUJT 1 day Thu 3/28/24 Thu 3/28/24 167 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA
169 14.2 FASE PERSETUJUAN IJIN PRINSIP 45 days Fri 3/29/24 Thu 5/30/24 168
170 14.2.1 Rapat Koordinasi Dengan Bina Marga 7 days Fri 3/29/24 Mon 4/8/24 168 WSP TEKNIK,JBH,PPK WSP TEKNIK,JBH,PPK
171 14.2.2 Penyusunan Berita Acara Ijin Prinsip 7 days Tue 4/9/24 Wed 4/17/24170 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
172 14.2.3 Sirkuler Tanda Tangan di Bina Marga 30 days Thu 4/18/24 Wed 5/29/24171 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
173 14.2.4 Serah Terima Berita Acara Ijin Prinsip 1 day Thu 5/30/24 Thu 5/30/24 172 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
174 15 MUSHOLLA PASIR KADU 109 days Mon 1/1/24 Thu 5/30/24
175 15.1 DESAIN RTA BANGUNAN PENGGANTI 64 days Mon 1/1/24 Thu 3/28/24
176 15.1.1 Pengadaan Konsultan 14 days Mon 1/1/24 Thu 1/18/24 WSP TEKNIK WSP TEKNIK
177 15.1.2 Survey Lahan 7 days Fri 1/19/24 Mon 1/29/24176 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA
178 15.1.3 Pengambilan Data Tanah 7 days Tue 1/30/24 Wed 2/7/24 177 KONSULTAN PERENCANA KONSULTAN PERENCANA
179 15.1.4 Berita Acara Usulan Desain 7 days Thu 2/8/24 Fri 2/16/24 178 WSP TEKNIK,KONSULTAN PERENCANA,PPK WSP TEKNIK,KONSULTAN PERENCANA,PPK
180 15.1.5 Proses Desain 14 days Mon 2/19/24Thu 3/7/24 179 KONSULTAN PERENCANA KONSULTAN PERENCANA
181 15.1.6 Sirkuler Tanda Tangan di Bina Marga 14 days Fri 3/8/24 Wed 3/27/24180 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA
182 15.1.7 Serah Terima Desain BUJT 1 day Thu 3/28/24 Thu 3/28/24 181 WSP TEKNIK,KONSULTAN PERENCANA WSP TEKNIK,KONSULTAN PERENCANA
183 15.2 FASE PERSETUJUAN IJIN PRINSIP 45 days Fri 3/29/24 Thu 5/30/24 182
184 15.2.1 Rapat Koordinasi Dengan Bina Marga 7 days Fri 3/29/24 Mon 4/8/24 182 WSP TEKNIK,JBH,PPK WSP TEKNIK,JBH,PPK
185 15.2.2 Penyusunan Berita Acara Ijin Prinsip 7 days Tue 4/9/24 Wed 4/17/24184 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
186 15.2.3 Sirkuler Tanda Tangan di Bina Marga 30 days Thu 4/18/24 Wed 5/29/24185 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK
187 15.2.4 Serah Terima Berita Acara Ijin Prinsip 1 day Thu 5/30/24 Thu 5/30/24 186 JBH,PPK,WSP TEKNIK JBH,PPK,WSP TEKNIK

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: SCHEDULE DESAIN RTA
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Tue 1/16/24
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress