Kementerian Sumber Manusia

Ministry of Human Resources

TENDER PERKHIDMATAN SEWAAN PERALATAN ICT SECARA SEWA GUNA BAGI TEMPOH 36 BULAN UNTUK 22 BAHAGIAN DAN 9 JABATAN DI KEMENTERIAN SUMBER MANUSIA
JADUAL PELAKSANAAN
2023/2024
Task Name Duration Start Finish
M1 M2 M3 M4
TENDER PERKHIDMATAN SEWAAN PERALATAN ICT SECARA SEWA
GUNA BAGI TEMPOH 36 BULAN UNTUK 22 BAHAGIAN DAN 9 87 days Mon 2/10/23 Tue 30/1/24
JABATAN DI KEMENTERIAN SUMBER MANUSIA

Start Project 6 days Mon 2/10/23 Mon 9/10/23

Letter of Award 1 day Mon 2/10/23 Mon 2/10/23

Contract Negotiation (If Any) 2 days Tue 3/10/23 Wed 4/10/23

Kick-off meeting On-Site 2 days Thu 5/10/23 Fri 6/10/23

Penerimaan Surat Setuju Terima (SST) 1 day Mon 9/10/23 Mon 9/10/23

Procurement Process 21 days Tue 10/10/23 Tue 7/11/23

Preparation of Procurement process of all Hardware and Delivery 21 days Tue 10/10/23 Tue 7/11/23

Image Creation, Installation , Commissioning and Testing 48 days Wed 8/11/23 Fri 12/1/24

Rollout Implementation to all KSM Branches 48 days Wed 8/11/23 Fri 12/1/24

Jabatan Tenaga Manusia 48 days Wed 8/11/23 Fri 12/1/24

Jabatan Keselamatan Dan Kesihatan Pekerjaan 48 days Wed 8/11/23 Fri 12/1/24

Jabatan Tenaga Kerja Semenanjung 48 days Wed 8/11/23 Fri 12/1/24

Jabatan Tenaga Kerja Sarawak 48 days Wed 8/11/23 Fri 12/1/24

Jabatan Tenaga Kerja Sabah 48 days Wed 8/11/23 Fri 12/1/24

Jabatan Pembangunan Kemahiran 48 days Wed 8/11/23 Fri 12/1/24

Jabatan Hal Ehwal Kesatuan Sekerja 48 days Wed 8/11/23 Fri 12/1/24

Jabatan Perhubungan Perusahaan 48 days Wed 8/11/23 Fri 12/1/24

Mahkamah Perusahaan Malaysia 48 days Wed 8/11/23 Fri 12/1/24


Bahagian Khidmat Pengurusan 48 days Wed 8/11/23 Fri 12/1/24

Bahagian Pembangunan, Kewangan & Sumber Manusia 48 days Wed 8/11/23 Fri 12/1/24

Bahagian Pengurusan Maklumat 48 days Wed 8/11/23 Fri 12/1/24

Bahagian Dasar 48 days Wed 8/11/23 Fri 12/1/24

Bahagian Hal Ehwal Antarabangsa 48 days Wed 8/11/23 Fri 12/1/24

Bahagian Akaun 48 days Wed 8/11/23 Fri 12/1/24

Compiling All User Acceptance Test (UAT) Documents 5 days Mon 15/1/24 Fri 19/1/24

Sign-off Project Final Acceptance Test (FAT) by Project Owner 3 days Mon 22/1/24 Wed 24/1/24

Project Commissioning 1 day Thu 25/1/24 Thu 25/1/24

Submission of Final Project Installation Documentation 3 days Fri 26/1/24 Tue 30/1/24