ID Task Task Name Start Finish Baseline Start Baseline Finish

Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
Mode AM J J A S OND J F MAM J J A S OND J
1 MASTER SCHEDULE D.I SADDANG Good Mon 09/05/22Fri 29/12/23 Mon 09/05/22Fri 29/12/23
2 Start Mon 09/05/22Mon 09/05/22Mon 09/05/22Mon 09/05/22
3 PEKERJAAN PERSIAPAN Wed 18/05/22Tue 12/12/23 Mon 09/05/22Fri 29/12/23
4 Mob& Demob Wed 18/05/22Tue 12/12/23 Mon 09/05/22Fri 29/12/23
5 Mobilisasi Wed 18/05/22Mon 23/10/23Mon 09/05/22Wed 20/09/23
6 Mobilisasi Personil Wed 18/05/22Thu 16/06/22 Mon 09/05/22Wed 20/09/23
7 Mobilisasi Excavator standart Wed 08/06/22Thu 09/06/22 Mon 09/05/22Wed 20/09/23
8 Mobilisasi Vibro Roller Wed 08/06/22Fri 20/10/23 Mon 09/05/22Wed 20/09/23
9 Mobilisasi Dump Truck Mon 23/05/22Sat 24/12/22 Mon 09/05/22Wed 20/09/23
10 Mobilisasi Bulldozer Sat 11/06/22 Thu 09/02/23 Mon 09/05/22Wed 20/09/23
11 Mobilisasi Water Tanker Truck Sat 11/06/22 Mon 23/10/23Mon 09/05/22Wed 20/09/23
12 Demobilisasi Tue 24/10/23 Tue 12/12/23 Thu 21/09/23 Thu 09/11/23
13 Demobilisasi Personil Tue 24/10/23 Tue 12/12/23 Thu 21/09/23 Thu 09/11/23
14 Demob Excavator standart Tue 24/10/23 Tue 12/12/23 Thu 21/09/23 Thu 09/11/23
15 Demob Vibro Roller Tue 24/10/23 Tue 12/12/23 Thu 21/09/23 Thu 09/11/23
16 Demob Dump Truck Tue 24/10/23 Tue 12/12/23 Thu 21/09/23 Thu 09/11/23
17 Demob Bulldozer Tue 24/10/23 Tue 12/12/23 Thu 21/09/23 Thu 09/11/23
18 Demob Water Tanker Truck Tue 24/10/23 Tue 12/12/23 Thu 21/09/23 Thu 09/11/23
19 Kistdam pasir (ukuran bagor 43 x 65 cm) Sat 25/06/22 Thu 09/11/23 Mon 09/05/22Fri 29/12/23
20 Pemasangan Terpal Plastik untuk Kistdam Sat 25/06/22 Fri 10/11/23 Mon 09/05/22Fri 29/12/23
21 Pengoperasian pompa air daya 5 Kw Mon 23/05/22Wed 08/11/23Mon 09/05/22Fri 29/12/23
22 PENERAPAN SMKK Fri 20/05/22 Fri 29/12/23 Mon 09/05/22Fri 29/12/23
23 Penyiapan RKK Fri 20/05/22 Mon 25/12/23Mon 09/05/22Fri 29/12/23
24 Sosialisasi, Promosi dan Pelatihan Mon 23/05/22Tue 26/12/23 Mon 09/05/22Fri 29/12/23
25 Alat pelindung Kerja dan Alat Pelindung Diri Fri 20/05/22 Fri 29/12/23 Mon 09/05/22Fri 29/12/23
26 Asuransi dan perijinan Sun 22/05/22 Wed 25/05/22Mon 09/05/22Fri 29/12/23
27 Personel Keselamatan Konstruksi Fri 20/05/22 Fri 29/12/23 Mon 09/05/22Fri 29/12/23
28 Fasilitas Sarana Kesehatan Fri 27/05/22 Fri 29/12/23 Mon 09/05/22Fri 29/12/23
29 Rambu-rambu yang diperlukan Fri 03/06/22 Fri 29/12/23 Mon 09/05/22Fri 29/12/23
30 Konsultasi dengan ahli terkait Keselamatan Wed Fri 29/12/23 Mon Fri 29/12/23
Konstruksi
25/05/22 09/05/22

Page 1
ID Task Task Name Start Finish Baseline Start Baseline Finish
Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
Mode AM J J A S OND J F MAM J J A S OND J
31 Lain-lain terkait Pengendalian resiko K3 Fri 27/05/22 Fri 29/12/23 Mon 09/05/22Fri 29/12/23
32 Protokol Pencegahan Covid-19 Wed 25/05/22Thu 28/12/23 Mon 09/05/22Fri 29/12/23
33 SALURAN SEKUNDER LISSE Sat 18/06/22 Sun 30/10/22 Mon 30/05/22Sun 25/09/22
34 Pekerjaan Tanah di Saluran Sat 18/06/22 Sun 25/09/22 Mon 30/05/22Sun 21/08/22
35 Kosrekan permukaan tanah (Mekanis) Sat 18/06/22 Thu 30/06/22 Mon 30/05/22Sun 21/08/22
36 Galian Tanah Biasa (Mekanis) Sat 18/06/22 Sun 31/07/22 Mon 30/05/22Sun 21/08/22
37 Timbunan Tanah dari borrow area jarak Mon Sun 25/09/22 Mon Sun 21/08/22
angkut diatas 10 km
04/07/22 30/05/22
38 Pemadatan Tanah dengan alat berat Mon Sun 25/09/22 Mon Sun 21/08/22
(Vibratory Roller)
04/07/22 30/05/22
39 Pekerjaan Pasangan Batu dan Beton di Saluran Mon 04/07/22Sun 25/09/22 Mon 30/05/22Sun 21/08/22
40 Pembesian wiremesh M6 Mon 04/07/22Sun 25/09/22 Mon 30/05/22Sun 21/08/22
41 Bekisting 3x pakai termasuk bongkaran Mon 04/07/22Sun 25/09/22 Mon 30/05/22Sun 21/08/22
42 Beton Mutu, fc = 19,3 Mpa (K-225) Ready MixMon 04/07/22Sun 25/09/22 Mon 30/05/22Sun 21/08/22
43 Mon
Beton Mutu, fc = 7,4 Mpa (K-100) untuk lantai kerja04/07/22Sun 25/09/22 Mon 30/05/22Sun 21/08/22
44 Joint Sealent Mon 04/07/22Sun 25/09/22 Mon 30/05/22Sun 21/08/22
45 Patok Hektometer Mon 04/07/22Sun 25/09/22 Mon 30/05/22Sun 21/08/22
46 PekerjaanTanah di Bangunan Pengatur Mon Sun 25/09/22 Mon Sun 21/08/22
dan Pelengkap
04/07/22 30/05/22
47 Galian Lumpur (manual) sedalam 1 m Mon 04/07/22Sun 25/09/22 Mon 30/05/22Sun 21/08/22
48 Timbunan Tanah Kembali Mon 04/07/22Sun 25/09/22 Mon 30/05/22Sun 21/08/22
49 Pekerjaan Pasangan Batu dan Beton di Mon Sun 25/09/22 Mon Sun 21/08/22
Bangunan Pengatur dan Pelengkap
04/07/22 30/05/22
50 Bongkar Pasangan Batu (semi mekanis) Mon 04/07/22Sun 25/09/22 Mon 30/05/22Sun 21/08/22
51 Pembesian Mon 04/07/22Sun 25/09/22 Mon 30/05/22Sun 21/08/22
52 Bekisting 3x pakai termasuk bongkaran Mon 04/07/22Sun 25/09/22 Mon 30/05/22Sun 21/08/22
53 Beton Mutu, fc = 14,5 Mpa (K-175) Mon 04/07/22Sun 25/09/22 Mon 30/05/22Sun 21/08/22
54 Pasangan Batu, 1 PC 4 PP Mon 04/07/22Sun 25/09/22 Mon 30/05/22Sun 21/08/22
55 Plesteran, 1 PC 3 PP Mon 04/07/22Sun 25/09/22 Mon 30/05/22Sun 21/08/22
56 Pekerjaan Pintu Saluran Sekunder Lisse Mon 03/10/22Sun 30/10/22 Mon 29/08/22Sun 25/09/22
57 Pengadaan Pintu sorong baja, b = 0.60 m Mon Sun 30/10/22 Mon Sun 25/09/22
h = 0.70 m
03/10/22 29/08/22

Page 2
ID Task Task Name Start Finish Baseline Start Baseline Finish
Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
Mode AM J J A S OND J F MAM J J A S OND J
58 Pemasangan Pintu sorong baja, b = 0.60 Mon Sun 30/10/22 Mon Sun 25/09/22
m h = 0.70 m
03/10/22 29/08/22
59 Pengadaan Pintu sorong baja, b = 0.60 m Mon Sun 30/10/22 Mon Sun 25/09/22
h = 0.80 m
03/10/22 29/08/22
60 Pemasangan Pintu sorong baja, b = 0.60 Mon Sun 30/10/22 Mon Sun 25/09/22
m h = 0.80 m
03/10/22 29/08/22
61 Pengadaan Pintu sorong baja, b = 0.40 m Mon Sun 30/10/22 Mon Sun 25/09/22
h = 0.80 m
03/10/22 29/08/22
62 Pemasangan Pintu sorong baja, b = 0.40 Mon Sun 30/10/22 Mon Sun 25/09/22
m h = 0.80 m
03/10/22 29/08/22
63 Pengadaan Pintu sorong baja, b = 0.45 m Mon Sun 30/10/22 Mon Sun 25/09/22
h = 1.00 m
03/10/22 29/08/22
64 Pemasangan Pintu sorong baja, b = 0.45 Mon Sun 30/10/22 Mon Sun 25/09/22
m h = 1.00 m
03/10/22 29/08/22
65 Peilschal/Mistar Duga Muka Air Mon 03/10/22Sun 30/10/22 Mon 29/08/22Sun 25/09/22
66 SALURAN SEKUNDER LANGNGA Mon 27/06/22Fri 24/11/23 Fri 01/07/22 Sun 29/10/23
67 Pekerjaan Tanah di Saluran Mon 27/06/22Thu 23/02/23 Fri 01/07/22 Thu 26/01/23
68 Kosrekan permukaan tanah (Mekanis) Mon 27/06/22Thu 23/02/23 Fri 01/07/22 Thu 26/01/23
69 Galian Tanah Biasa (Mekanis) Mon 27/06/22Tue 21/02/23 Fri 01/07/22 Thu 26/01/23
70 Timbunan Tanah dari borrow area jarak Tue 26/07/22 Tue 21/02/23 Fri 01/07/22 Thu 26/01/23
angkut diatas 10 km

71 Pemadatan Tanah dengan alat berat Tue 26/07/22 Tue 21/02/23 Fri 01/07/22 Thu 26/01/23
(Vibratory Roller)

72 Sat 01/10/22
Pekerjaan Pasangan Batu dan Beton di Saluran Fri 31/03/23 Mon 29/08/22Sun 26/02/23
73 Pembesian wiremesh M6 Sat 01/10/22 Fri 31/03/23 Mon 29/08/22Sun 26/02/23
74 Pembesian Sat 01/10/22 Fri 31/03/23 Mon 29/08/22Sun 26/02/23
75 Bekisting 3x pakai termasuk bongkaran Sat 01/10/22 Fri 31/03/23 Mon 29/08/22Sun 26/02/23
76 Beton Mutu, fc = 19,3 Mpa (K-225) Ready MixSat 01/10/22 Fri 31/03/23 Mon 29/08/22Sun 26/02/23
77 Sat
Beton Mutu, fc = 7,4 Mpa (K-100) untuk lantai 01/10/22 Fri 31/03/23
kerja Mon 29/08/22Sun 26/02/23
78 Joint Sealent Sat 01/10/22 Fri 31/03/23 Mon 29/08/22Sun 26/02/23
79 Patok Hektometer Sat 01/10/22 Fri 31/03/23 Mon 29/08/22Sun 26/02/23
80 Pekerjaan Tanah di Bangunan Pengatur Thu 27/10/22 Wed Mon Sun 26/03/23
dan Pelengkap
22/03/23 31/10/22

Page 3
ID Task Task Name Start Finish Baseline Start Baseline Finish
Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
Mode AM J J A S OND J F MAM J J A S OND J
81 Galian Lumpur (manual) sedalam 1 m Thu 27/10/22 Wed 22/03/23Mon 31/10/22Sun 26/03/23
82 Timbunan Tanah Kembali Thu 27/10/22 Wed 22/03/23Mon 31/10/22Sun 26/03/23
83 Pekerjaan Pasangan Batu dan Beton di Wed Sun 26/03/23 Mon Sun 26/03/23
Bangunan Pengatur dan Pelengkap
29/06/22 28/11/22
84 Bongkar Pasangan Batu (semi mekanis) Mon 28/11/22Sun 26/03/23 Mon 28/11/22Sun 26/03/23
85 Pembesian Mon 28/11/22Sun 26/03/23 Mon 28/11/22Sun 26/03/23
86 Bekisting 3x pakai termasuk bongkaran Mon 28/11/22Sun 26/03/23 Mon 28/11/22Sun 26/03/23
87 Beton Mutu, fc = 14,5 Mpa (K-175) Mon 28/11/22Sun 26/03/23 Mon 28/11/22Sun 26/03/23
88 Pasangan Batu, 1 PC 4 PP Wed 29/06/22Fri 10/03/23 Mon 28/11/22Sun 26/03/23
89 Plesteran, 1 PC 3 PP Fri 11/11/22 Fri 10/03/23 Mon 28/11/22Sun 26/03/23
90 Pekerjaan Pintu Saluran Sekunder Langnga Fri 21/07/23 Fri 24/11/23 Mon 26/06/23Sun 29/10/23
91 Pengadaan Pintu sorong baja, b = 1.50 m Fri 21/07/23 Fri 24/11/23 Mon Sun 29/10/23
h = 2.00 m (Elektrik)
26/06/23
92 Pemasangan Pintu sorong baja, b = 1.50 Fri 21/07/23 Fri 24/11/23 Mon Sun 29/10/23
m h = 2.00 m (Elektrik)
26/06/23
93 Pengadaan Pintu sorong baja, b = 0.70 m Fri 21/07/23 Fri 24/11/23 Mon Sun 29/10/23
h = 0.80 m
26/06/23
94 Pemasangan Pintu sorong baja, b = 0.70 Fri 21/07/23 Fri 24/11/23 Mon Sun 29/10/23
m h = 0.80 m
26/06/23
95 Pengadaan Pintu sorong baja, b = 0.80 m Fri 21/07/23 Fri 24/11/23 Mon Sun 29/10/23
h = 1.05 m
26/06/23
96 Pemasangan Pintu sorong baja, b = 0.80 Fri 21/07/23 Fri 24/11/23 Mon Sun 29/10/23
m h = 1.05 m
26/06/23
97 Pengadaan Pintu sorong baja, b = 1.00 m Fri 21/07/23 Fri 24/11/23 Mon Sun 29/10/23
h = 1.00 m
26/06/23
98 Pemasangan Pintu sorong baja, b = 1.00 Fri 21/07/23 Fri 24/11/23 Mon Sun 29/10/23
m h = 1.00 m
26/06/23
99 Pengadaan Pintu sorong baja, b = 0.90 m Fri 21/07/23 Fri 24/11/23 Mon Sun 29/10/23
h = 0.80 m
26/06/23
100 Pemasangan Pintu sorong baja, b = 0.90 Fri 21/07/23 Fri 24/11/23 Mon Sun 29/10/23
m h = 0.80 m
26/06/23
101 Pengadaan Pintu sorong baja, b = 0.70 m Fri 21/07/23 Fri 24/11/23 Mon Sun 29/10/23
h = 0.60 m
26/06/23

Page 4
ID Task Task Name Start Finish Baseline Start Baseline Finish
Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
Mode AM J J A S OND J F MAM J J A S OND J
102 Pemasangan Pintu sorong baja, b = 0.70 Fri 21/07/23 Fri 24/11/23 Mon Sun 29/10/23
m h = 0.60 m
26/06/23
103 Pengadaan Pintu sorong baja, b = 0.85 m Fri 21/07/23 Fri 24/11/23 Mon Sun 29/10/23
h = 1.00 m
26/06/23
104 Pemasangan Pintu sorong baja, b = 0.85 Fri 21/07/23 Fri 24/11/23 Mon Sun 29/10/23
m h = 1.00 m
26/06/23
105 Pengadaan Pintu sorong baja, b = 1.60 m Fri 21/07/23 Fri 24/11/23 Mon Sun 29/10/23
h = 1.60 m (Elektrik)
26/06/23
106 Pemasangan Pintu sorong baja, b = 1.60 Fri 21/07/23 Fri 24/11/23 Mon Sun 29/10/23
m h = 1.60 m (Elektrik)
26/06/23
107 Pengadaan Pintu sorong baja, b = 1.50 m Fri 21/07/23 Fri 24/11/23 Mon Sun 29/10/23
h = 2.00 m (Elektrik)
26/06/23
108 Pemasangan Pintu sorong baja, b = 1.50 Fri 21/07/23 Fri 24/11/23 Mon Sun 29/10/23
m h = 2.00 m (Elektrik)
26/06/23
109 Fri 21/07/23 Fri 24/11/23 Mon 26/06/23Sun 29/10/23
Pengaman Bangunan Pengatur (Pintu Air Elektrikal)
110 Peilschal/Mistar Duga Muka Air Fri 21/07/23 Fri 24/11/23 Mon 26/06/23Sun 29/10/23
111 SALURAN SEKUNDER CENRANA Sat 06/08/22 Fri 02/12/22 Mon 04/07/22Sun 30/10/22
112 Pekerjaan Tanah di Saluran Sat 06/08/22 Fri 28/10/22 Mon 04/07/22Sun 25/09/22
113 Kosrekan permukaan tanah (Mekanis) Sat 06/08/22 Fri 28/10/22 Mon 04/07/22Sun 25/09/22
114 Galian Tanah Biasa (Mekanis) Sat 06/08/22 Fri 28/10/22 Mon 04/07/22Sun 25/09/22
115 Timbunan Tanah dari borrow area jarak Sat 06/08/22 Fri 28/10/22 Mon Sun 25/09/22
angkut diatas 10 km
04/07/22
116 Pemadatan Tanah dengan alat berat Sat 06/08/22 Fri 28/10/22 Mon Sun 25/09/22
(Vibratory Roller)
04/07/22
117 Pekerjaan Pasangan Batu dan Beton di Saluran Sat 06/08/22 Fri 28/10/22 Mon 04/07/22Sun 25/09/22
118 Pembesian wiremesh M6 Sat 06/08/22 Fri 28/10/22 Mon 04/07/22Sun 25/09/22
119 Bekisting 3x pakai termasuk bongkaran Sat 06/08/22 Fri 28/10/22 Mon 04/07/22Sun 25/09/22
120 Beton Mutu, fc = 19,3 Mpa (K-225) Ready MixSat 06/08/22 Fri 28/10/22 Mon 04/07/22Sun 25/09/22
121 Sat
Beton Mutu, fc = 7,4 Mpa (K-100) untuk lantai 06/08/22 Fri 28/10/22 Mon 04/07/22Sun 25/09/22
kerja
122 Joint Sealent Sat 06/08/22 Fri 28/10/22 Mon 04/07/22Sun 25/09/22
123 Patok Hektometer Sat 06/08/22 Fri 28/10/22 Mon 04/07/22Sun 25/09/22
124 Pekerjaan Tanah di Bangunan Pengatur Sat 06/08/22 Fri 28/10/22 Mon Sun 25/09/22
dan Pelengkap
04/07/22

Page 5
ID Task Task Name Start Finish Baseline Start Baseline Finish
Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
Mode AM J J A S OND J F MAM J J A S OND J
125 Galian Lumpur (manual) sedalam 1 m Sat 06/08/22 Fri 28/10/22 Mon 04/07/22Sun 25/09/22
126 Pekerjaan Pasangan Batu dan Beton di Sat 06/08/22 Fri 28/10/22 Mon Sun 25/09/22
Bangunan Pengatur dan Pelengkap
04/07/22
127 Pembesian Sat 06/08/22 Fri 28/10/22 Mon 04/07/22Sun 25/09/22
128 Bekisting 3x pakai termasuk bongkaran Sat 06/08/22 Fri 28/10/22 Mon 04/07/22Sun 25/09/22
129 Beton Mutu, fc = 14,5 Mpa (K-175) Sat 06/08/22 Fri 28/10/22 Mon 04/07/22Sun 25/09/22
130 Pasangan Batu, 1 PC 4 PP Sat 06/08/22 Fri 28/10/22 Mon 04/07/22Sun 25/09/22
131 Pekerjaan Pintu Saluran Sekunder Cenrana Sat 29/10/22 Fri 02/12/22 Mon 26/09/22Sun 30/10/22
132 Pengadaan Pintu sorong baja, b = 0.60 m Sat 29/10/22 Fri 02/12/22 Mon Sun 30/10/22
h = 1.00 m
26/09/22
133 Pemasangan Pintu sorong baja, b = 0.60 Sat 29/10/22 Fri 02/12/22 Mon Sun 30/10/22
m h = 1.00 m
26/09/22
134 Pengadaan Pintu sorong baja, b = 0.30 m Sat 29/10/22 Fri 02/12/22 Mon Sun 30/10/22
h = 0.60 m
26/09/22
135 Pemasangan Pintu sorong baja, b = 0.30 Sat 29/10/22 Fri 02/12/22 Mon Sun 30/10/22
m h = 0.60 m
26/09/22
136 Pengadaan Pintu sorong baja, b = 0.50 m Sat 29/10/22 Fri 02/12/22 Mon Sun 30/10/22
h = 0.80 m
26/09/22
137 Pemasangan Pintu sorong baja, b = 0.50 Sat 29/10/22 Fri 02/12/22 Mon Sun 30/10/22
m h = 0.80 m
26/09/22
138 Pengadaan Pintu sorong baja, b = 0.50 m Sat 29/10/22 Fri 02/12/22 Mon Sun 30/10/22
h = 0.60 m
26/09/22
139 Pemasangan Pintu sorong baja, b = 0.50 Sat 29/10/22 Fri 02/12/22 Mon Sun 30/10/22
m h = 0.60 m
26/09/22
140 Pengadaan Pintu sorong baja, b = 0.50 m Sat 29/10/22 Fri 02/12/22 Mon Sun 30/10/22
h = 0.90 m
26/09/22
141 Pemasangan Pintu sorong baja, b = 0.50 Sat 29/10/22 Fri 02/12/22 Mon Sun 30/10/22
m h = 0.90 m
26/09/22
142 Pengadaan Pintu sorong baja, b = 0.60 m Sat 29/10/22 Fri 02/12/22 Mon Sun 30/10/22
h = 0.90 m
26/09/22
143 Pemasangan Pintu sorong baja, b = 0.60 Sat 29/10/22 Fri 02/12/22 Mon Sun 30/10/22
m h = 0.90 m
26/09/22
144 Pengadaan Pintu sorong baja, b = 1.00 m Sat 29/10/22 Fri 02/12/22 Mon Sun 30/10/22
h = 0.90 m
26/09/22

Page 6
ID Task Task Name Start Finish Baseline Start Baseline Finish
Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
Mode AM J J A S OND J F MAM J J A S OND J
145 Pemasangan Pintu sorong baja, b = 1.00 Sat 29/10/22 Fri 02/12/22 Mon Sun 30/10/22
m h = 0.90 m
26/09/22
146 Peilschal/Mistar Duga Muka Air Sat 29/10/22 Fri 02/12/22 Mon 26/09/22Sun 30/10/22
147 SALURAN SEKUNDER TOSULO Sat 06/08/22 Fri 02/12/22 Mon 04/07/22Sun 30/10/22
148 Pekerjaan Tanah di Saluran Sat 06/08/22 Fri 28/10/22 Mon 04/07/22Sun 25/09/22
149 Kosrekan permukaan tanah (Mekanis) Sat 06/08/22 Fri 28/10/22 Mon 04/07/22Sun 25/09/22
150 Galian Tanah Biasa (Mekanis) Sat 06/08/22 Fri 28/10/22 Mon 04/07/22Sun 25/09/22
151 Pemadatan Tanah dengan alat berat Sat 06/08/22 Fri 28/10/22 Mon Sun 25/09/22
(Vibratory Roller)
04/07/22
152 Pekerjaan Pasangan Batu dan Beton di Saluran Sat 06/08/22 Fri 28/10/22 Mon 04/07/22Sun 25/09/22
153 Pembesian wiremesh M6 Sat 06/08/22 Fri 28/10/22 Mon 04/07/22Sun 25/09/22
154 Bekisting 3x pakai termasuk bongkaran Sat 06/08/22 Fri 28/10/22 Mon 04/07/22Sun 25/09/22
155 Beton Mutu, fc = 19,3 Mpa (K-225) Ready MixSat 06/08/22 Fri 28/10/22 Mon 04/07/22Sun 25/09/22
156 Sat
Beton Mutu, fc = 7,4 Mpa (K-100) untuk lantai 06/08/22 Fri 28/10/22 Mon 04/07/22Sun 25/09/22
kerja
157 Joint Sealent Sat 06/08/22 Fri 28/10/22 Mon 04/07/22Sun 25/09/22
158 Patok Hektometer Sat 06/08/22 Fri 28/10/22 Mon 04/07/22Sun 25/09/22
159 Pekerjaan Tanah di Bangunan Pengatur Sat 06/08/22 Fri 28/10/22 Mon Sun 25/09/22
dan Pelengkap
04/07/22
160 Galian Lumpur (manual) sedalam 1 m Sat 06/08/22 Fri 28/10/22 Mon 04/07/22Sun 25/09/22
161 Timbunan Tanah Kembali Sat 06/08/22 Fri 28/10/22 Mon 04/07/22Sun 25/09/22
162 Pekerjaan Pasangan Batu dan Beton di Sat 06/08/22 Fri 28/10/22 Mon Sun 25/09/22
Bangunan Pengatur dan Pelengkap
04/07/22
163 Bongkar Pasangan Batu (semi mekanis) Sat 06/08/22 Fri 28/10/22 Mon 04/07/22Sun 25/09/22
164 Pembesian Sat 06/08/22 Fri 28/10/22 Mon 04/07/22Sun 25/09/22
165 Bekisting 3x pakai termasuk bongkaran Sat 06/08/22 Fri 28/10/22 Mon 04/07/22Sun 25/09/22
166 Pasangan Batu, 1 PC 4 PP Sat 06/08/22 Fri 28/10/22 Mon 04/07/22Sun 25/09/22
167 Beton Mutu, fc = 14,5 Mpa (K-175) Sat 06/08/22 Fri 28/10/22 Mon 04/07/22Sun 25/09/22
168 Plesteran, 1 PC 3 PP Sat 06/08/22 Fri 28/10/22 Mon 04/07/22Sun 25/09/22
169 Pekerjaan Pintu Saluran Sekunder Tosulo Sat 29/10/22 Fri 02/12/22 Mon 26/09/22Sun 30/10/22
170 Pengadaan Pintu sorong baja, b = 0.30 m Sat 29/10/22 Fri 02/12/22 Mon Sun 30/10/22
h = 0.50 m
26/09/22

Page 7
ID Task Task Name Start Finish Baseline Start Baseline Finish
Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
Mode AM J J A S OND J F MAM J J A S OND J
171 Pemasangan Pintu sorong baja, b = 0.30 Sat 29/10/22 Fri 02/12/22 Mon Sun 30/10/22
m h = 0.50 m
26/09/22
172 Pengadaan Pintu sorong baja, b = 0.40 m Sat 29/10/22 Fri 02/12/22 Mon Sun 30/10/22
h = 0.50 m
26/09/22
173 Pemasangan Pintu sorong baja, b = 0.40 Sat 29/10/22 Fri 02/12/22 Mon Sun 30/10/22
m h = 0.50 m
26/09/22
174 Pengadaan Pintu sorong baja, b = 0.80 m Sat 29/10/22 Fri 02/12/22 Mon Sun 30/10/22
h = 1.00 m
26/09/22
175 Pemasangan Pintu sorong baja, b = 0.80 Sat 29/10/22 Fri 02/12/22 Mon Sun 30/10/22
m h = 1.00 m
26/09/22
176 Peilschal/Mistar Duga Muka Air Sat 29/10/22 Fri 02/12/22 Mon 26/09/22Sun 30/10/22
177 SALURAN SEKUNDER CENGKONG Tue 17/05/22 Sun 30/10/22 Mon 04/07/22Sun 30/10/22
178 Pekerjaan Tanah di Saluran Tue 17/05/22 Tue 25/10/22 Mon 04/07/22Sun 25/09/22
179 Kosrekan permukaan tanah (Mekanis) Sun 19/06/22 Tue 25/10/22 Mon 04/07/22Sun 25/09/22
180 Galian Tanah Biasa (Mekanis) Mon 13/06/22Tue 09/08/22 Mon 04/07/22Sun 25/09/22
181 Timbunan Tanah dari borrow area jarak Tue 17/05/22 Tue 09/08/22 Mon Sun 25/09/22
angkut diatas 10 km
04/07/22
182 Pemadatan Tanah dengan alat berat Mon Sun 25/09/22 Mon Sun 25/09/22
(Vibratory Roller)
04/07/22 04/07/22
183 Pekerjaan Pasangan Batu dan Beton di Saluran Mon 04/07/22Sun 25/09/22 Mon 04/07/22Sun 25/09/22
184 Pembesian wiremesh M6 Mon 04/07/22Sun 25/09/22 Mon 04/07/22Sun 25/09/22
185 Bekisting 3x pakai termasuk bongkaran Mon 04/07/22Sun 25/09/22 Mon 04/07/22Sun 25/09/22
186 Beton Mutu, fc = 19,3 Mpa (K-225) Ready MixMon 04/07/22Sun 25/09/22 Mon 04/07/22Sun 25/09/22
187 Mon
Beton Mutu, fc = 7,4 Mpa (K-100) untuk lantai kerja04/07/22Sun 25/09/22 Mon 04/07/22Sun 25/09/22
188 Joint Sealent Mon 04/07/22Sun 25/09/22 Mon 04/07/22Sun 25/09/22
189 Patok Hektometer Mon 04/07/22Sun 25/09/22 Mon 04/07/22Sun 25/09/22
190 Pekerjaan Tanah di Bangunan Pengatur Sat 25/06/22 Sun 25/09/22 Mon Sun 25/09/22
dan Pelengkap
04/07/22
191 Galian Lumpur (manual) sedalam 1 m Sat 25/06/22 Mon 19/09/22Mon 04/07/22Sun 25/09/22
192 Timbunan Tanah Kembali Mon 04/07/22Sun 25/09/22 Mon 04/07/22Sun 25/09/22
193 Pekerjaan Pasangan Batu dan Beton di Sat 25/06/22 Sun 25/09/22 Mon Sun 25/09/22
Bangunan Pengatur dan Pelengkap
04/07/22
194 Bongkar Pasangan Batu (semi mekanis) Mon 04/07/22Sun 25/09/22 Mon 04/07/22Sun 25/09/22

Page 8
ID Task Task Name Start Finish Baseline Start Baseline Finish
Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
Mode AM J J A S OND J F MAM J J A S OND J
195 Pembesian Mon 04/07/22Sun 25/09/22 Mon 04/07/22Sun 25/09/22
196 Bekisting 3x pakai termasuk bongkaran Mon 04/07/22Sun 25/09/22 Mon 04/07/22Sun 25/09/22
197 Beton Mutu, fc = 14,5 Mpa (K-175) Mon 04/07/22Sun 25/09/22 Mon 04/07/22Sun 25/09/22
198 Pasangan Batu, 1 PC 4 PP Sat 25/06/22 Mon 04/07/22Mon 04/07/22Sun 25/09/22
199 Plesteran, 1 PC 3 PP Mon 04/07/22Sun 25/09/22 Mon 04/07/22Sun 25/09/22
200 Pekerjaan Pintu Saluran Sekunder Cengkong Mon 26/09/22Sun 30/10/22 Mon 26/09/22Sun 30/10/22
201 Pengadaan Pintu sorong baja, b = 0.75 m Mon Sun 30/10/22 Mon Sun 30/10/22
h = 0.80 m
26/09/22 26/09/22
202 Pemasangan Pintu sorong baja, b = 0.75 Mon Sun 30/10/22 Mon Sun 30/10/22
m h = 0.80 m
26/09/22 26/09/22
203 Pengadaan Pintu sorong baja, b = 0.60 m Mon Sun 30/10/22 Mon Sun 30/10/22
h = 0.60 m
26/09/22 26/09/22
204 Pemasangan Pintu sorong baja, b = 0.60 Mon Sun 30/10/22 Mon Sun 30/10/22
m h = 0.60 m
26/09/22 26/09/22
205 Pengadaan Pintu sorong baja, b = 0.90 m Mon Sun 30/10/22 Mon Sun 30/10/22
h = 0.70 m
26/09/22 26/09/22
206 Pemasangan Pintu sorong baja, b = 0.90 Mon Sun 30/10/22 Mon Sun 30/10/22
m h = 0.70 m
26/09/22 26/09/22
207 Pengadaan Pintu sorong baja, b = 0.40 m Mon Sun 30/10/22 Mon Sun 30/10/22
h = 0.50 m
26/09/22 26/09/22
208 Pemasangan Pintu sorong baja, b = 0.40 Mon Sun 30/10/22 Mon Sun 30/10/22
m h = 0.50 m
26/09/22 26/09/22
209 Pengadaan Pintu sorong baja, b = 0.70 m Mon Sun 30/10/22 Mon Sun 30/10/22
h = 0.50 m
26/09/22 26/09/22
210 Pemasangan Pintu sorong baja, b = 0.70 Mon Sun 30/10/22 Mon Sun 30/10/22
m h = 0.50 m
26/09/22 26/09/22
211 Pengadaan Pintu sorong baja, b = 0.50 m Mon Sun 30/10/22 Mon Sun 30/10/22
h = 0.60 m
26/09/22 26/09/22
212 Pemasangan Pintu sorong baja, b = 0.50 Mon Sun 30/10/22 Mon Sun 30/10/22
m h = 0.60 m
26/09/22 26/09/22
213 Pengadaan Pintu sorong baja, b = 0.70 m Mon Sun 30/10/22 Mon Sun 30/10/22
h = 0.80 m
26/09/22 26/09/22
214 Pemasangan Pintu sorong baja, b = 0.70 Mon Sun 30/10/22 Mon Sun 30/10/22
m h = 0.80 m
26/09/22 26/09/22

Page 9
ID Task Task Name Start Finish Baseline Start Baseline Finish
Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
Mode AM J J A S OND J F MAM J J A S OND J
215 Pengadaan Pintu sorong baja, b = 0.50 mMon Sun 30/10/22 Mon Sun 30/10/22
h = 0.50 m
26/09/22 26/09/22
216 Pemasangan Pintu sorong baja, b = 0.50 Mon Sun 30/10/22 Mon Sun 30/10/22
m h = 0.50 m
26/09/22 26/09/22
217 Peilschal/Mistar Duga Muka Air Mon 26/09/22Sun 30/10/22 Mon 26/09/22Sun 30/10/22
218 SALURAN SEKUNDER BARANG Sat 01/10/22 Fri 28/04/23 Mon 29/08/22Sun 26/03/23
219 Pekerjaan Tanah di Saluran Sat 01/10/22 Fri 30/12/22 Mon 29/08/22Sun 27/11/22
220 Kosrekan permukaan tanah (Mekanis) Sat 01/10/22 Fri 30/12/22 Mon 29/08/22Sun 27/11/22
221 Galian Tanah Biasa (Mekanis) Sat 01/10/22 Fri 30/12/22 Mon 29/08/22Sun 27/11/22
222 Timbunan Tanah dari borrow area jarak Sat 01/10/22 Fri 30/12/22 Mon Sun 27/11/22
angkut diatas 10 km
29/08/22
223 Pemadatan Tanah dengan alat berat Sat 01/10/22 Fri 30/12/22 Mon Sun 27/11/22
(Vibratory Roller)
29/08/22
224 Sat 29/10/22
Pekerjaan Pasangan Batu dan Beton di Saluran Fri 28/04/23 Mon 26/09/22Sun 26/03/23
225 Pembesian wiremesh M6 Sat 29/10/22 Fri 28/04/23 Mon 26/09/22Sun 26/03/23
226 Bekisting 3x pakai termasuk bongkaran Sat 29/10/22 Fri 28/04/23 Mon 26/09/22Sun 26/03/23
227 Beton Mutu, fc = 19,3 Mpa (K-225) Ready MixSat 29/10/22 Fri 28/04/23 Mon 26/09/22Sun 26/03/23
228 Sat
Beton Mutu, fc = 7,4 Mpa (K-100) untuk lantai 29/10/22
kerja Fri 28/04/23 Mon 26/09/22Sun 26/03/23
229 Joint Sealent Sat 29/10/22 Fri 28/04/23 Mon 26/09/22Sun 26/03/23
230 Patok Hektometer Sat 29/10/22 Fri 28/04/23 Mon 26/09/22Sun 26/03/23
231 Pekerjaan Tanah di Bangunan Pengatur Sat 03/12/22 Fri 03/03/23 Mon Sun 29/01/23
dan Pelengkap
31/10/22
232 Galian Lumpur (manual) sedalam 1 m Sat 03/12/22 Fri 03/03/23 Mon 31/10/22Sun 29/01/23
233 Timbunan Tanah Kembali Sat 03/12/22 Fri 03/03/23 Mon 31/10/22Sun 29/01/23
234 Pekerjaan Pasangan Batu dan Beton di Sat 31/12/22 Fri 28/04/23 Mon Sun 26/03/23
Bangunan Pengatur dan Pelengkap
28/11/22
235 Bongkar Pasangan Batu (semi mekanis) Sat 31/12/22 Fri 28/04/23 Mon 28/11/22Sun 26/03/23
236 Bongkar Beton Sat 31/12/22 Fri 28/04/23 Mon 28/11/22Sun 26/03/23
237 Pembesian Sat 31/12/22 Fri 28/04/23 Mon 28/11/22Sun 26/03/23
238 Bekisting 3x pakai termasuk bongkaran Sat 31/12/22 Fri 28/04/23 Mon 28/11/22Sun 26/03/23
239 Beton Mutu, fc = 14,5 Mpa (K-175) Sat 31/12/22 Fri 28/04/23 Mon 28/11/22Sun 26/03/23
240 Pasangan Batu, 1 PC 4 PP Sat 31/12/22 Fri 28/04/23 Mon 28/11/22Sun 26/03/23

Page 10
ID Task Task Name Start Finish Baseline Start Baseline Finish
Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
Mode AM J J A S OND J F MAM J J A S OND J
241 Plesteran, 1 PC 3 PP Sat 31/12/22 Fri 28/04/23 Mon 28/11/22Sun 26/03/23
242 Pekerjaan Pintu Saluran Sekunder Barang Sat 04/03/23 Fri 28/04/23 Mon 30/01/23Sun 26/03/23
243 Pengadaan Pintu sorong baja, b = 0.75 m Sat 04/03/23 Fri 28/04/23 Mon Sun 26/03/23
h = 0.50 m
30/01/23
244 Pemasangan Pintu sorong baja, b = 0.75 Sat 04/03/23 Fri 28/04/23 Mon Sun 26/03/23
m h = 0.50 m
30/01/23
245 Pengadaan Pintu sorong baja, b = 0.55 m Sat 04/03/23 Fri 28/04/23 Mon Sun 26/03/23
h = 0.90 m
30/01/23
246 Pemasangan Pintu sorong baja, b = 0.55 Sat 04/03/23 Fri 28/04/23 Mon Sun 26/03/23
m h = 0.90 m
30/01/23
247 Pengadaan Pintu sorong baja, b = 1.60 m Sat 04/03/23 Fri 28/04/23 Mon Sun 26/03/23
h = 0.90 m (Elektrik)
30/01/23
248 Pemasangan Pintu sorong baja, b = 1.60 Sat 04/03/23 Fri 28/04/23 Mon Sun 26/03/23
m h = 0.90 m (Elektrik)
30/01/23
249 Pengadaan Pintu sorong baja, b = 0.80 m Sat 04/03/23 Fri 28/04/23 Mon Sun 26/03/23
h = 0.80 m
30/01/23
250 Pemasangan Pintu sorong baja, b = 0.80 Sat 04/03/23 Fri 28/04/23 Mon Sun 26/03/23
m h = 0.80 m
30/01/23
251 Pengadaan Pintu sorong baja, b = 0.60 m Sat 04/03/23 Fri 28/04/23 Mon Sun 26/03/23
h = 0.80 m
30/01/23
252 Pemasangan Pintu sorong baja, b = 0.60 Sat 04/03/23 Fri 28/04/23 Mon Sun 26/03/23
m h = 0.80 m
30/01/23
253 Pengadaan Pintu sorong baja, b = 1.10 m Sat 04/03/23 Fri 28/04/23 Mon Sun 26/03/23
h = 1.20 m
30/01/23
254 Pemasangan Pintu sorong baja, b = 1.10 Sat 04/03/23 Fri 28/04/23 Mon Sun 26/03/23
m h = 1.20 m
30/01/23
255 Pengadaan Pintu sorong baja, b = 0.45 m Sat 04/03/23 Fri 28/04/23 Mon Sun 26/03/23
h = 1.00 m
30/01/23
256 Pemasangan Pintu sorong baja, b = 0.45 Sat 04/03/23 Fri 28/04/23 Mon Sun 26/03/23
m h = 1.00 m
30/01/23
257 Pengadaan Pintu sorong baja, b = 0.95 m Sat 04/03/23 Fri 28/04/23 Mon Sun 26/03/23
h = 0.95 m
30/01/23
258 Pemasangan Pintu sorong baja, b = 0.95 Sat 04/03/23 Fri 28/04/23 Mon Sun 26/03/23
m h = 0.95 m
30/01/23

Page 11
ID Task Task Name Start Finish Baseline Start Baseline Finish
Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
Mode AM J J A S OND J F MAM J J A S OND J
259 Pengadaan Pintu sorong baja, b = 1.00 m Sat 04/03/23 Fri 28/04/23 Mon Sun 26/03/23
h = 1.00 m
30/01/23
260 Pemasangan Pintu sorong baja, b = 1.00 Sat 04/03/23 Fri 28/04/23 Mon Sun 26/03/23
m h = 1.00 m
30/01/23
261 Pengadaan Pintu sorong baja, b = 0.65 m Sat 04/03/23 Fri 28/04/23 Mon Sun 26/03/23
h = 0.85 m
30/01/23
262 Pemasangan Pintu sorong baja, b = 0.65 Sat 04/03/23 Fri 28/04/23 Mon Sun 26/03/23
m h = 0.85 m
30/01/23
263 Pengadaan Pintu sorong baja, b = 0.80 m Sat 04/03/23 Fri 28/04/23 Mon Sun 26/03/23
h = 0.80 m
30/01/23
264 Pemasangan Pintu sorong baja, b = 0.80 Sat 04/03/23 Fri 28/04/23 Mon Sun 26/03/23
m h = 0.80 m
30/01/23
265 Pengadaan Pintu sorong baja, b = 1.10 m Sat 04/03/23 Fri 28/04/23 Mon Sun 26/03/23
h = 1.00 m
30/01/23
266 Pemasangan Pintu sorong baja, b = 1.10 Sat 04/03/23 Fri 28/04/23 Mon Sun 26/03/23
m h = 1.00 m
30/01/23
267 Pengadaan Pintu sorong baja, b = 0.50 m Sat 04/03/23 Fri 28/04/23 Mon Sun 26/03/23
h = 0.65 m
30/01/23
268 Pemasangan Pintu sorong baja, b = 0.50 Sat 04/03/23 Fri 28/04/23 Mon Sun 26/03/23
m h = 0.65 m
30/01/23
269 Sat 04/03/23 Fri 28/04/23 Mon 30/01/23Sun 26/03/23
Pengaman Bangunan Pengatur (Pintu Air Elektrikal)
270 Peilschal/Mistar Duga Muka Air Sat 04/03/23 Fri 28/04/23 Mon 30/01/23Sun 26/03/23
271 SALURAN SEKUNDER PUNNIA Sat 29/10/22 Wed 04/10/23Mon 26/09/22Fri 01/09/23
272 Pekerjaan Tanah di Saluran Sat 29/10/22 Fri 26/05/23 Mon 26/09/22Sun 23/04/23
273 Kosrekan permukaan tanah (Mekanis) Sat 29/10/22 Fri 26/05/23 Mon 26/09/22Sun 23/04/23
274 Galian Tanah Biasa (Mekanis) Sat 29/10/22 Fri 26/05/23 Mon 26/09/22Sun 23/04/23
275 Timbunan Tanah dari borrow area jarak Sat 29/10/22 Fri 26/05/23 Mon Sun 23/04/23
angkut diatas 10 km
26/09/22
276 Pemadatan Tanah dengan alat berat Sat 29/10/22 Fri 26/05/23 Mon Sun 23/04/23
(Vibratory Roller)
26/09/22
277 Sat 03/12/22 Fri 28/07/23 Mon 31/10/22Sun 25/06/23
Pekerjaan Pasangan Batu dan Beton di Saluran
278 Pembesian wiremesh M6 Sat 03/12/22 Fri 28/07/23 Mon 31/10/22Sun 25/06/23
279 Pembesian Sat 03/12/22 Fri 28/07/23 Mon 31/10/22Sun 25/06/23

Page 12
ID Task Task Name Start Finish Baseline Start Baseline Finish
Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
Mode AM J J A S OND J F MAM J J A S OND J
280 Bekisting 3x pakai termasuk bongkaran Sat 03/12/22 Fri 28/07/23
Mon 31/10/22Sun 25/06/23
281 Beton Mutu, fc = 19,3 Mpa (K-225) Ready MixSat 03/12/22 Fri 28/07/23
Mon 31/10/22Sun 25/06/23
282 Sat
Beton Mutu, fc = 7,4 Mpa (K-100) untuk lantai 03/12/22
kerja Fri 28/07/23
Mon 31/10/22Sun 25/06/23
283 Joint Sealent Sat 03/12/22 Fri 28/07/23
Mon 31/10/22Sun 25/06/23
284 Patok Hektometer Sat 03/12/22 Fri 28/07/23
Mon 31/10/22Sun 25/06/23
285 Pekerjaan Tanah di Bangunan Pengatur Sat 28/01/23 Fri 28/04/23
Mon Sun 26/03/23
dan Pelengkap
26/12/22
286 Galian Lumpur (manual) sedalam 1 m Sat 28/01/23 Fri 28/04/23 Mon 26/12/22Sun 26/03/23
287 Pekerjaan Pasangan Batu dan Beton di Sat 04/03/23 Fri 26/05/23 Mon Sun 23/04/23
Bangunan Pengatur dan Pelengkap
30/01/23
288 Bongkar Beton Sat 04/03/23 Fri 26/05/23 Mon 30/01/23Sun 23/04/23
289 Bongkar Pasangan Batu (semi mekanis) Sat 04/03/23 Fri 26/05/23 Mon 30/01/23Sun 23/04/23
290 Pasangan Batu, 1 PC 4 PP Sat 04/03/23 Fri 26/05/23 Mon 30/01/23Sun 23/04/23
291 Pembesian Sat 04/03/23 Fri 26/05/23 Mon 30/01/23Sun 23/04/23
292 Bekisting 3x pakai termasuk bongkaran Sat 04/03/23 Fri 26/05/23 Mon 30/01/23Sun 23/04/23
293 Beton Mutu, fc = 14,5 Mpa (K-175) Sat 04/03/23 Fri 26/05/23 Mon 30/01/23Sun 23/04/23
294 Plesteran, 1 PC 3 PP Sat 04/03/23 Fri 26/05/23 Mon 30/01/23Sun 23/04/23
295 Pekerjaan Pintu Saluran Sekunder Punnia Thu 04/05/23 Wed 04/10/23Sat 01/04/23 Fri 01/09/23
296 Pengadaan Pintu sorong baja, b = 1.00 m Thu 04/05/23 Wed Sat 01/04/23 Fri 01/09/23
h = 1.20 m
04/10/23
297 Pemasangan Pintu sorong baja, b = 1.00 Thu 04/05/23 Wed Sat 01/04/23 Fri 01/09/23
m h = 1.20 m
04/10/23
298 Pengadaan Pintu sorong baja, b = 1.50 m Thu 04/05/23 Wed Sat 01/04/23 Fri 01/09/23
h = 1.20 m (Elektrik)
04/10/23
299 Pemasangan Pintu sorong baja, b = 1.50 Thu 04/05/23 Wed Sat 01/04/23 Fri 01/09/23
m h = 1.20 m (Elektrik)
04/10/23
300 Pengadaan Pintu sorong baja, b = 0.90 m Thu 04/05/23 Wed Sat 01/04/23 Fri 01/09/23
h = 1.20 m
04/10/23
301 Pemasangan Pintu sorong baja, b = 0.90 Thu 04/05/23 Wed Sat 01/04/23 Fri 01/09/23
m h = 1.20 m
04/10/23
302 Pengadaan Pintu sorong baja, b = 0.90 m Thu 04/05/23 Wed Sat 01/04/23 Fri 01/09/23
h = 1.00 m
04/10/23

Page 13
ID Task Task Name Start Finish Baseline Start Baseline Finish
Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
Mode AM J J A S OND J F MAM J J A S OND J
303 Pemasangan Pintu sorong baja, b = 0.90 Thu 04/05/23 Wed Sat 01/04/23 Fri 01/09/23
m h = 1.00 m
04/10/23
304 Pengadaan Pintu sorong baja, b = 1.50 m Thu 04/05/23 Wed Sat 01/04/23 Fri 01/09/23
h = 1.00 m (Elektrik)
04/10/23
305 Pemasangan Pintu sorong baja, b = 1.50 Thu 04/05/23 Wed Sat 01/04/23 Fri 01/09/23
m h = 1.00 m (Elektrik)
04/10/23
306 Pengadaan Pintu sorong baja, b = 1.20 m Thu 04/05/23 Wed Sat 01/04/23 Fri 01/09/23
h = 1.00 m
04/10/23
307 Pemasangan Pintu sorong baja, b = 1.20 Thu 04/05/23 Wed Sat 01/04/23 Fri 01/09/23
m h = 1.00 m
04/10/23
308 Pengadaan Pintu sorong baja, b = 1.00 m Thu 04/05/23 Wed Sat 01/04/23 Fri 01/09/23
h = 1.00 m
04/10/23
309 Pemasangan Pintu sorong baja, b = 1.00 Thu 04/05/23 Wed Sat 01/04/23 Fri 01/09/23
m h = 1.00 m
04/10/23
310 Pengadaan Pintu sorong baja, b = 1.00 m Thu 04/05/23 Wed Sat 01/04/23 Fri 01/09/23
h = 2.20 m (Elektrik)
04/10/23
311 Pemasangan Pintu sorong baja, b = 1.00 Thu 04/05/23 Wed Sat 01/04/23 Fri 01/09/23
m h = 2.20 m (Elektrik)
04/10/23
312 Pengadaan Pintu sorong baja, b = 1.20 m Thu 04/05/23 Wed Sat 01/04/23 Fri 01/09/23
h = 1.25 m (Elektrik)
04/10/23
313 Pemasangan Pintu sorong baja, b = 1.20 Thu 04/05/23 Wed Sat 01/04/23 Fri 01/09/23
m h = 1.25 m (Elektrik)
04/10/23
314 Thu 04/05/23 Wed 04/10/23Sat 01/04/23 Fri 01/09/23
Pengaman Bangunan Pengatur (Pintu Air Elektrikal)
315 Peilschal/Mistar Duga Muka Air Thu 04/05/23 Wed 04/10/23Sat 01/04/23 Fri 01/09/23
316 SALURAN SEKUNDER TALLANG Sat 28/01/23 Fri 29/09/23 Mon 26/12/22Sun 27/08/23
317 Pekerjaan Tanah di Saluran Sat 28/01/23 Fri 26/05/23 Mon 26/12/22Sun 23/04/23
318 Kosrekan permukaan tanah (Mekanis) Sat 28/01/23 Fri 26/05/23 Mon 26/12/22Sun 23/04/23
319 Galian Tanah Biasa (Mekanis) Sat 28/01/23 Fri 26/05/23 Mon 26/12/22Sun 23/04/23
320 Timbunan Tanah dari borrow area jarak Sat 28/01/23 Fri 26/05/23 Mon Sun 23/04/23
angkut diatas 10 km
26/12/22
321 Pemadatan Tanah dengan alat berat Sat 28/01/23 Fri 26/05/23 Mon Sun 23/04/23
(Vibratory Roller)
26/12/22
322 Sat 01/04/23 Fri 01/09/23 Mon 27/02/23Sun 30/07/23
Pekerjaan Pasangan Batu dan Beton di Saluran
323 Bongkar Pasangan Batu (semi mekanis) Sat 01/04/23 Fri 01/09/23 Mon 27/02/23Sun 30/07/23

Page 14
ID Task Task Name Start Finish Baseline Start Baseline Finish
Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
Mode AM J J A S OND J F MAM J J A S OND J
324 Pembesian wiremesh M6 Sat 01/04/23 Fri 01/09/23 Mon 27/02/23Sun 30/07/23
325 Bekisting 3x pakai termasuk bongkaran Sat 01/04/23 Fri 01/09/23 Mon 27/02/23Sun 30/07/23
326 Beton Mutu, fc = 19,3 Mpa (K-225) Ready MixSat 01/04/23 Fri 01/09/23 Mon 27/02/23Sun 30/07/23
327 Sat
Beton Mutu, fc = 7,4 Mpa (K-100) untuk lantai 01/04/23
kerja Fri 01/09/23 Mon 27/02/23Sun 30/07/23
328 Joint Sealent Sat 01/04/23 Fri 01/09/23 Mon 27/02/23Sun 30/07/23
329 Patok Hektometer Sat 01/04/23 Fri 01/09/23 Mon 27/02/23Sun 30/07/23
330 Pekerjaan Tanah di Bangunan Pengatur Sat 01/04/23 Fri 28/04/23 Mon Sun 26/03/23
dan Pelengkap
27/02/23
331 Galian Lumpur (manual) sedalam 1 m Sat 01/04/23 Fri 28/04/23 Mon 27/02/23Sun 26/03/23
332 Pekerjaan Pasangan Batu dan Beton di Sat 29/04/23 Fri 01/09/23 Mon Sun 30/07/23
Bangunan Pengatur dan Pelengkap
27/03/23
333 Bongkar Beton Sat 29/04/23 Fri 01/09/23 Mon 27/03/23Sun 30/07/23
334 Pasangan Batu, 1 PC 4 PP Sat 29/04/23 Fri 01/09/23 Mon 27/03/23Sun 30/07/23
335 Pembesian Sat 29/04/23 Fri 01/09/23 Mon 27/03/23Sun 30/07/23
336 Bekisting 3x pakai termasuk bongkaran Sat 29/04/23 Fri 01/09/23 Mon 27/03/23Sun 30/07/23
337 Beton Mutu, fc = 14,5 Mpa (K-175) Sat 29/04/23 Fri 01/09/23 Mon 27/03/23Sun 30/07/23
338 Pekerjaan Pintu Saluran Sekunder Tallang Sat 02/09/23 Fri 29/09/23 Mon 31/07/23Sun 27/08/23
339 Pengadaan Pintu sorong baja, b = 0.20 m Sat 02/09/23 Fri 29/09/23 Mon Sun 27/08/23
h = 0.30 m
31/07/23
340 Pemasangan Pintu sorong baja, b = 0.20 Sat 02/09/23 Fri 29/09/23 Mon Sun 27/08/23
m h = 0.30 m
31/07/23
341 Pengadaan Pintu sorong baja, b = 0.50 m Sat 02/09/23 Fri 29/09/23 Mon Sun 27/08/23
h = 0.60 m
31/07/23
342 Pemasangan Pintu sorong baja, b = 0.50 Sat 02/09/23 Fri 29/09/23 Mon Sun 27/08/23
m h = 0.60 m
31/07/23
343 Pengadaan Pintu sorong baja, b = 0.35 m Sat 02/09/23 Fri 29/09/23 Mon Sun 27/08/23
h = 0.60 m
31/07/23
344 Pemasangan Pintu sorong baja, b = 0.35 Sat 02/09/23 Fri 29/09/23 Mon Sun 27/08/23
m h = 0.60 m
31/07/23
345 Pengadaan Pintu sorong baja, b = 0.75 m Sat 02/09/23 Fri 29/09/23 Mon Sun 27/08/23
h = 0.60 m
31/07/23
346 Pemasangan Pintu sorong baja, b = 0.75 Sat 02/09/23 Fri 29/09/23 Mon Sun 27/08/23
m h = 0.60 m
31/07/23

Page 15
ID Task Task Name Start Finish Baseline Start Baseline Finish
Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
Mode AM J J A S OND J F MAM J J A S OND J
347 Pengadaan Pintu sorong baja, b = 0.90 m Sat 02/09/23 Fri 29/09/23 Mon Sun 27/08/23
h = 0.60 m
31/07/23
348 Pemasangan Pintu sorong baja, b = 0.90 Sat 02/09/23 Fri 29/09/23 Mon Sun 27/08/23
m h = 0.60 m
31/07/23
349 Pengadaan Pintu sorong baja, b = 0.60 m Sat 02/09/23 Fri 29/09/23 Mon Sun 27/08/23
h = 0.80 m
31/07/23
350 Pemasangan Pintu sorong baja, b = 0.60 Sat 02/09/23 Fri 29/09/23 Mon Sun 27/08/23
m h = 0.80 m
31/07/23
351 Peilschal/Mistar Duga Muka Air Sat 02/09/23 Fri 29/09/23 Mon 31/07/23Sun 27/08/23
352 PEKERJAAN JALAN Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
353 Perkerasan Jalan Inspeksi (Sub base Type C) Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
354 SALURAN SEKUNDER ALUPPANG Mon 15/05/23Sun 12/11/23 Mon 01/05/23Sun 29/10/23
355 Pekerjaan Tanah di Saluran Mon 15/05/23Sun 10/09/23 Mon 01/05/23Sun 27/08/23
356 Kosrekan permukaan tanah (Mekanis) Mon 15/05/23Sun 10/09/23 Mon 01/05/23Sun 27/08/23
357 Galian Tanah Biasa (Mekanis) Mon 15/05/23Sun 10/09/23 Mon 01/05/23Sun 27/08/23
358 Timbunan Tanah dari borrow area jarak Mon Sun 10/09/23 Mon Sun 27/08/23
angkut diatas 10 km
15/05/23 01/05/23
359 Pemadatan Tanah dengan alat berat Mon Sun 10/09/23 Mon Sun 27/08/23
(Vibratory Roller)
15/05/23 01/05/23
360 Pekerjaan Pasangan Batu dan Beton di Saluran Tue 23/05/23 Mon 21/08/23Tue 09/05/23 Mon 07/08/23
361 Bongkar Pasangan Batu (semi mekanis) Tue 23/05/23 Mon 21/08/23Tue 09/05/23 Mon 07/08/23
362 Pembesian wiremesh M6 Tue 23/05/23 Mon 21/08/23Tue 09/05/23 Mon 07/08/23
363 Bekisting 3x pakai termasuk bongkaran Tue 23/05/23 Mon 21/08/23Tue 09/05/23 Mon 07/08/23
364 Beton Mutu, fc = 19,3 Mpa (K-225) Ready MixTue 23/05/23 Mon 21/08/23Tue 09/05/23 Mon 07/08/23
365 Tue
Beton Mutu, fc = 7,4 Mpa (K-100) untuk lantai 23/05/23 Mon 21/08/23Tue 09/05/23 Mon 07/08/23
kerja
366 Joint Sealent Tue 23/05/23 Mon 21/08/23Tue 09/05/23 Mon 07/08/23
367 Patok Hektometer Tue 23/05/23 Mon 21/08/23Tue 09/05/23 Mon 07/08/23
368 Pekerjaan Tanah di Bangunan Pengatur Wed Tue 11/07/23 Wed Tue 27/06/23
dan Pelengkap
14/06/23 31/05/23
369 Galian Lumpur (manual) sedalam 1 m Wed 14/06/23Tue 11/07/23 Wed 31/05/23Tue 27/06/23
370 Timbunan Tanah Kembali Wed 14/06/23Tue 11/07/23 Wed 31/05/23Tue 27/06/23
371 Pekerjaan Pasangan Batu dan Beton di Mon Sun 15/10/23 Mon Sun 01/10/23
Bangunan Pengatur dan Pelengkap
14/08/23 31/07/23
Page 16
ID Task Task Name Start Finish Baseline Start Baseline Finish
Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
Mode AM J J A S OND J F MAM J J A S OND J
372 Bongkar Pasangan Batu (semi mekanis) Mon 14/08/23Sun 15/10/23 Mon 31/07/23Sun 01/10/23
373 Pasangan Batu, 1 PC 4 PP Mon 14/08/23Sun 15/10/23 Mon 31/07/23Sun 01/10/23
374 Pembesian Mon 14/08/23Sun 15/10/23 Mon 31/07/23Sun 01/10/23
375 Bekisting 3x pakai termasuk bongkaran Mon 14/08/23Sun 15/10/23 Mon 31/07/23Sun 01/10/23
376 Beton Mutu, fc = 14,5 Mpa (K-175) Mon 14/08/23Sun 15/10/23 Mon 31/07/23Sun 01/10/23
377 Plesteran, 1 PC 3 PP Mon 14/08/23Sun 15/10/23 Mon 31/07/23Sun 01/10/23
378 Pekerjaan Pintu Saluran Sekunder AluppangMon 16/10/23Sun 12/11/23 Mon 02/10/23Sun 29/10/23
379 Pengadaan Pintu sorong baja, b = 1.10 m Mon Sun 12/11/23 Mon Sun 29/10/23
h = 1.00 m
16/10/23 02/10/23
380 Pemasangan Pintu sorong baja, b = 1.10 Mon Sun 12/11/23 Mon Sun 29/10/23
m h = 1.00 m
16/10/23 02/10/23
381 Peilschal/Mistar Duga Muka Air Mon 16/10/23Sun 12/11/23 Mon 02/10/23Sun 29/10/23
382 SALURAN SEKUNDER LABUMPUNG Sat 03/06/23 Fri 29/12/23 Mon 01/05/23Sun 26/11/23
383 Pekerjaan Tanah di Saluran Sat 03/06/23 Fri 29/09/23 Mon 01/05/23Sun 27/08/23
384 Kosrekan permukaan tanah (Mekanis) Sat 03/06/23 Fri 29/09/23 Mon 01/05/23Sun 27/08/23
385 Galian Tanah Biasa (Mekanis) Sat 03/06/23 Fri 29/09/23 Mon 01/05/23Sun 27/08/23
386 Timbunan Tanah dari borrow area jarak Sat 03/06/23 Fri 29/09/23 Mon Sun 27/08/23
angkut diatas 10 km
01/05/23
387 Pemadatan Tanah dengan alat berat Sat 03/06/23 Fri 29/09/23 Mon Sun 27/08/23
(Vibratory Roller)
01/05/23
388 Pekerjaan Pasangan Batu dan Beton di Saluran Sat 01/07/23 Fri 01/12/23 Mon 29/05/23Sun 29/10/23
389 Bongkar Pasangan Batu (semi mekanis) Sat 01/07/23 Fri 01/12/23 Mon 29/05/23Sun 29/10/23
390 Bekisting 3x pakai termasuk bongkaran Sat 01/07/23 Fri 01/12/23 Mon 29/05/23Sun 29/10/23
391 Pembesian wiremesh M6 Sat 01/07/23 Fri 01/12/23 Mon 29/05/23Sun 29/10/23
392 Beton Mutu, fc = 19,3 Mpa (K-225) Ready MixSat 01/07/23 Fri 01/12/23 Mon 29/05/23Sun 29/10/23
393 Sat
Beton Mutu, fc = 7,4 Mpa (K-100) untuk lantai 01/07/23 Fri 01/12/23 Mon 29/05/23Sun 29/10/23
kerja
394 Joint Sealent Sat 01/07/23 Fri 01/12/23 Mon 29/05/23Sun 29/10/23
395 Patok Hektometer Sat 01/07/23 Fri 01/12/23 Mon 29/05/23Sun 29/10/23
396 Pekerjaan Tanah di Bangunan Pengatur Sat 02/09/23 Fri 29/09/23 Mon Sun 27/08/23
dan Pelengkap
31/07/23
397 Galian Lumpur (manual) sedalam 1 m Sat 02/09/23 Fri 29/09/23 Mon 31/07/23Sun 27/08/23

Page 17
ID Task Task Name Start Finish Baseline Start Baseline Finish
Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
Mode AM J J A S OND J F MAM J J A S OND J
398 Pekerjaan Pasangan Batu dan Beton di Sat 30/09/23 Fri 01/12/23 Mon Sun 29/10/23
Bangunan Pengatur dan Pelengkap
28/08/23
399 Bongkar Pasangan Batu (semi mekanis) Sat 30/09/23 Fri 01/12/23 Mon 28/08/23Sun 29/10/23
400 Pembesian Sat 30/09/23 Fri 01/12/23 Mon 28/08/23Sun 29/10/23
401 Bekisting 3x pakai termasuk bongkaran Sat 30/09/23 Fri 01/12/23 Mon 28/08/23Sun 29/10/23
402 Pasangan Batu, 1 PC 4 PP Sat 30/09/23 Fri 01/12/23 Mon 28/08/23Sun 29/10/23
403 Beton Mutu, fc = 14,5 Mpa (K-175) Sat 30/09/23 Fri 01/12/23 Mon 28/08/23Sun 29/10/23
404 Plesteran, 1 PC 3 PP Sat 30/09/23 Fri 01/12/23 Mon 28/08/23Sun 29/10/23
405 Pekerjaan Pintu Saluran Sekunder Labumpung Sat 02/12/23 Fri 29/12/23 Mon 30/10/23Sun 26/11/23
406 Pengadaan Pintu sorong baja, b = 0.50 m Sat 02/12/23 Fri 29/12/23 Mon Sun 26/11/23
h = 0.75 m
30/10/23
407 Pemasangan Pintu sorong baja, b = 0.50 Sat 02/12/23 Fri 29/12/23 Mon Sun 26/11/23
m h = 0.75 m
30/10/23
408 Pengadaan Pintu sorong baja, b = 0.30 m Sat 02/12/23 Fri 29/12/23 Mon Sun 26/11/23
h = 0.50 m
30/10/23
409 Pemasangan Pintu sorong baja, b = 0.30 Sat 02/12/23 Fri 29/12/23 Mon Sun 26/11/23
m h = 0.50 m
30/10/23
410 Peilschal/Mistar Duga Muka Air Sat 02/12/23 Fri 29/12/23 Mon 30/10/23Sun 26/11/23
411 PEKERJAAN FASILITAS OPERASI DAN Mon Wed Sat 04/06/22 Fri 03/11/23
PEMELIHARAAN
20/06/22 06/12/23
412 Kantor Cabang MIMU , Tipe 70 = 1 unit Wed 22/06/22Mon 19/06/23Sat 04/06/22 Fri 03/11/23
413 Gudang Cabang MIMU, Tipe 60 = 1 unit Thu 07/07/22 Wed 06/12/23Sat 04/06/22 Fri 03/11/23
414 Bengkel Cabang MIMU, Tipe 45 = 1 unit Thu 07/07/22 Wed 06/12/23Sat 04/06/22 Fri 03/11/23
415 Kantor Juru Pengairan, Tipe 21 = 8 unit Thu 07/07/22 Wed 06/12/23Sat 04/06/22 Fri 03/11/23
416 Perumahan Staf Kantor CabangMIMU, Tipe 50 Mon
= 1 unit20/06/22Mon 19/06/23Sat 04/06/22 Fri 03/11/23
417 Perumahan Juru Pengairan, Tipe 45 = 8 unit Thu 07/07/22 Wed 06/12/23Sat 04/06/22 Fri 03/11/23
418 Saung P3A, Type 100 = 1 unit Thu 07/07/22 Wed 06/12/23Sat 04/06/22 Fri 03/11/23
419 Saung P3A, Type 15 = 58 unit Thu 07/07/22 Wed 06/12/23Sat 04/06/22 Fri 03/11/23
420 Mesin Pemotong Rumput Thu 07/07/22 Wed 06/12/23Sat 04/06/22 Fri 03/11/23
421 PEKERJAAN SCADA Fri 25/11/22 Wed 06/12/23Fri 25/11/22 Wed 06/12/23
422 Pekerjaan Scada di B.La.1 Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
423 Smart datalogger, including GPRS modem Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23

Page 18
ID Task Task Name Start Finish Baseline Start Baseline Finish
Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
Mode AM J J A S OND J F MAM J J A S OND J
424 Mon 26/12/22Tue 05/12/23
Water Level Sensor, up-stream& down-stream Mon 26/12/22Tue 05/12/23
425 Visual Sensor Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
426 Actuator, Smart, HKM-20 Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
427 Actuator, reduction gear, small Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
428 Actuator, reduction gear, medium Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
429 Pemasangan instalasi listrik, 6.600 watt Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
430 Shelter and protection Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
431 Installation material& protection accessoriesMon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
432 Installation, testing& programming Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
433 Pekerjaan Scada di B.La.4 Fri 25/11/22 Tue 05/12/23 Fri 25/11/22 Tue 05/12/23
434 Telemetry datalogger, including GPRS modem Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
435 Water Level Sensor, up-stream& down-stream Fri 25/11/22 Tue 05/12/23 Fri 25/11/22 Tue 05/12/23
436 Gate Position Sensor Fri 25/11/22 Tue 05/12/23 Fri 25/11/22 Tue 05/12/23
437 Visual Sensor Fri 25/11/22 Tue 05/12/23 Fri 25/11/22 Tue 05/12/23
438 Actuator, Smart, HKM-20 Fri 25/11/22 Tue 05/12/23 Fri 25/11/22 Tue 05/12/23
439 Actuator, reduction gear, small Fri 25/11/22 Tue 05/12/23 Fri 25/11/22 Tue 05/12/23
440 Actuator, reduction gear, medium Fri 25/11/22 Tue 05/12/23 Fri 25/11/22 Tue 05/12/23
441 Pemasangan instalasi listrik, 6.600 watt Fri 25/11/22 Tue 05/12/23 Fri 25/11/22 Tue 05/12/23
442 Shelter and protection Fri 25/11/22 Tue 05/12/23 Fri 25/11/22 Tue 05/12/23
443 Installation material& protection accessoriesFri 25/11/22 Tue 05/12/23 Fri 25/11/22 Tue 05/12/23
444 Installation, testing& programming Fri 25/11/22 Tue 05/12/23 Fri 25/11/22 Tue 05/12/23
445 Pekerjaan Scada di B.La.6 Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
446 Telemetry datalogger, including GPRS modem Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
447 Water Level Sensor, up-stream& down-stream Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
448 Visual Sensor Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
449 Actuator, Smart, HKM-20 Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
450 Actuator, reduction gear, small Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
451 Pemasangan instalasi listrik, 6.600 watt Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
452 Shelter and protection Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
453 Installation material& protection accessoriesMon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
454 Installation, testing& programming Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23

Page 19
ID Task Task Name Start Finish Baseline Start Baseline Finish
Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
Mode AM J J A S OND J F MAM J J A S OND J
455 Pekerjaan Scada di B.La.8 Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
456 Telemetry datalogger, including GPRS modem Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
457 Water Level Sensor, up-stream& down-stream Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
458 Visual Sensor Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
459 Actuator, Smart, HKM-20 Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
460 Actuator, reduction gear, small Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
461 Actuator, reduction gear, medium Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
462 Solar Power, panel, 24VDC, 300Wp Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
463 Solar Power, deep-cycle battery, 24VDC, 100AhMon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
464 Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
Solar Power, charge-controller& inverter, 5KVA
465 Shelter and protection Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
466 Installation material& protection accessoriesMon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
467 Installation, testing& programming Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
468 Pekerjaan Scada di B.La.11 Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
469 Telemetry datalogger, including GPRS modem Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
470 Water Level Sensor, up-stream& down-stream Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
471 Gate Position Sensor Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
472 Installation material& protection accessoriesMon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
473 Installation, testing& programming Mon 26/12/22Tue 05/12/23 Mon 26/12/22Tue 05/12/23
474 Pekerjaan Scada di B.P.6 Mon 01/05/23Tue 05/12/23 Mon 01/05/23Tue 05/12/23
475 Telemetry datalogger, including GPRS modem Mon 01/05/23Tue 05/12/23 Mon 01/05/23Tue 05/12/23
476 Water Level Sensor, up-stream& down-stream Mon 01/05/23Tue 05/12/23 Mon 01/05/23Tue 05/12/23
477 Gate Position Sensor Mon 01/05/23Tue 05/12/23 Mon 01/05/23Tue 05/12/23
478 Installation material& protection accessoriesMon 01/05/23Tue 05/12/23 Mon 01/05/23Tue 05/12/23
479 Installation, testing& programming Mon 01/05/23Tue 05/12/23 Mon 01/05/23Tue 05/12/23
480 Pekerjaan Scada di B.P.11 Mon 01/05/23Tue 05/12/23 Mon 01/05/23Tue 05/12/23
481 Telemetry datalogger, including GPRS modem Mon 01/05/23Tue 05/12/23 Mon 01/05/23Tue 05/12/23
482 Water Level Sensor, up-stream& down-stream Mon 01/05/23Tue 05/12/23 Mon 01/05/23Tue 05/12/23
483 Gate Position Sensor Mon 01/05/23Tue 05/12/23 Mon 01/05/23Tue 05/12/23
484 Visual Sensor Mon 01/05/23Tue 05/12/23 Mon 01/05/23Tue 05/12/23
485 Actuator, Smart, HKM-20 Mon 01/05/23Tue 05/12/23 Mon 01/05/23Tue 05/12/23

Page 20
ID Task Task Name Start Finish Baseline Start Baseline Finish
Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
Mode AM J J A S OND J F MAM J J A S OND J
486 Actuator, reduction gear, medium Mon 01/05/23Tue 05/12/23 Mon 01/05/23Tue 05/12/23
487 Pemasangan instalasi listrik, 6.600 watt Mon 01/05/23Tue 05/12/23 Mon 01/05/23Tue 05/12/23
488 Shelter and protection Mon 01/05/23Tue 05/12/23 Mon 01/05/23Tue 05/12/23
489 Installation material& protection accessoriesMon 01/05/23Tue 05/12/23 Mon 01/05/23Tue 05/12/23
490 Installation, testing& programming Mon 01/05/23Tue 05/12/23 Mon 01/05/23Tue 05/12/23
491 FINISH Wed 06/12/23Wed 06/12/23Wed 06/12/23Wed 06/12/23