9/4/2023

Task Name Duration Start End


S S
Pengadaan Kantor Pengurus 56 Hari 06-Sep-23 05-Nov-23

9/4/2023
Task Name Duration Start End
S S
1. Perencanaan 7 Hari 06-Sep-23 12-Sep-23
1.1 Merancang konsep bangunan 3 Hari 06-Sep-23 08-Sep-23
1.2 Mencari pekerja 2 Hari 09-Sep-23 10-Sep-23
1.3 Survey bahan bangunan 2 Hari 11-Sep-23 12-Sep-23

9/11/2023
Task Name Duration Start End
S S
2. Pembongkaran 2 Hari 13-Sep-23 14-Sep-23
2.1 Pembongkaran tembok 1 Hari 13-Sep-23 13-Sep-23
2.2 Pembongkaran pondasi 1 Hari 14-Sep-23 14-Sep-23

9/11/2023
Task Name Duration Start End
S S
3. Pembangunan 38 Hari 15-Sep-23 22-Oct-23
3.1 Pondasi 7 Hari 15-Sep-23 21-Sep-23
3.2 Tembok 16 Hari 22-Sep-23 06-Oct-23
3.3 Pemasangan kusen pintu dan jendela 2 Hari 03-Oct-23 05-Oct-23
3.4 Pemasangan pipa saluran air 1 Hari 07-Oct-23 07-Oct-23
3.5 Pemasangan rangka atap 4 Hari 10-Oct-23 13-Oct-23
3.6 Pemasangan genteng 3 Hari 11-Oct-23 13-Oct-23
3.7 Pemasangan plafon 2 Hari 18-Oct-23 19-Oct-23
3.8 Pemasangan listrik 1 Hari 19-Oct-23 19-Oct-23
3.9 Plester dan pemasangan keramik 2 Hari 20-Oct-23 22-Oct-23
38 Hari

10/23/2023
Task Name Duration Start End
S S
4. Finishing 6 Hari 28-Oct-23 05-Nov-23
4.1 Acian tembok 2 Hari 28-Oct-23 29-Oct-23
4.2 Pemasangan jendela dan pintu 4 Hari 30-Oct-23 02-Nov-23
4.3 Pengecatan 2 Hari 03-Nov-23 04-Nov-23
4.4 Pelapisan nat keramik 1 Hari 05-Nov-23 05-Nov-23
9 Hari
9/4/2023 9/11/2023 9/18/2023 9/25/2023 10/2/2023 10/9/2023
R K J S M S S R K J S M S S R K J S M S S R K J S M S S R K J S M S S

9/4/2023 9/11/2023
R K J S M S S RKJ S M

###

9/11/2023
R K J S M

9/11/2023 9/18/2023 9/25/2023 10/2/2023 10/9/2023 10/16/2023


R K J S M S S RKJ S M S S RKJ S M S S RKJ S M S S RKJ S M S S
10/23/2023 10/30/2023
R K J S M S S RKJ S M
10/9/2023 10/16/2023 10/23/2023
R K J S M S S R K J S M S S R K J S M

10/16/2023
RKJ S M