PEKERJAAN PERSIAPAN PENYELENGGARAAN KESELAMATAN KERJA SISTEM MANAJEMEN KESELAMATAN KONSTRUKSI (SMKK)

Start: Wed 18/05/22


ID: 1 Start: Wed 18/05/22
ID: 2 Start: 18/05/22 ID: 3
Finish: Wed 22/06/22
Dur: 26 days Finish: Fri 27/05/22 Dur: 8 days Finish: 27/05/22 Dur: 8 days
Comp: 0% Comp: 0% Res:

PEKERJAAN PEMATANGAN LAHAN PEKERJAAN PENDAHULUAN PEKERJAAN TANAH


Start: Wed 18/05/22
ID: 5 Start: 18/05/22 ID: 6 Start: 23/05/22 ID: 7
Finish: Fri 27/05/22 Dur: 8 days Finish: 20/05/22 Dur: 3 days Finish: 27/05/22 Dur: 5 days
Comp: 0% Res: Res:

PEKERJAAN DINDING PENAHAN TANAH DAN SALURAN PEKERJAAN PENDAHULUAN PEKERJAAN DINDING PENAHAN TANAH PEKERJAAN SALURAN PEKERJAAN PLAT DUIKER
Start: Mon 23/05/22
ID: 9 Start: 23/05/22 ID: 10 Start: 23/05/22 ID: 11 Start: 30/05/22 ID: 12 Start: 01/06/22 ID: 13
Finish: Fri 03/06/22 Dur: 10 days Finish: 23/05/22 Dur: 1 day Finish: 27/05/22 Dur: 5 days Finish: 31/05/22 Dur: 2 days Finish: 03/06/22 Dur: 3 days
Comp: 0% Res: Res: Res: Res:

PEKERJAAN PEMBANGUNAN KORIDOR PENGHUBUNG PEKERJAAN PENDAHULUAN PEKERJAAN PONDASI PEKERJAAN STRUKTUR LANTAI DASAR PEKERJAAN STRUKTUR LANTAI I PEKERJAAN KAP ATAP
Start: Mon 30/05/22
ID: 15 Start: 30/05/22 ID: 16 Start: 30/05/22 ID: 17 Start: 01/06/22 ID: 18 Start: 06/06/22 ID: 19 Start: 09/06/22 ID: 20
Finish: Tue 14/06/22Dur: 12 days Finish: 30/05/22 Dur: 1 day Finish: 01/06/22 Dur: 3 days Finish: 06/06/22 Dur: 4 days Finish: 09/06/22 Dur: 4 days Finish: 10/06/22 Dur: 2 days
Comp: 0% Res: Res: Res: Res: Res:

PEKERJAAN LANTAI PEKERJAAN FINISHING


Start: 07/06/22 ID: 21 Start: 13/06/22 ID: 22
Finish: 10/06/22 Dur: 4 days Finish: 14/06/22 Dur: 2 days
Res: Res:

PEKERJAAN PEMBANGUNAN KORIDOR PEKERJAAN PENDAHULUAN PEKERJAAN PONDASI PEKERJAAN BETON BERTULANG PEKERJAAN KAP ATAP PEKERJAAN LANTAI PEKERJAAN FINISHING PEKERJAAN SALURAN
Start: Thu 02/06/22ID: 24 Start: 02/06/22 ID: 25 Start: 02/06/22 ID: 26 Start: 06/06/22 ID: 27 Start: 09/06/22 ID: 28 Start: 10/06/22 ID: 29 Start: 15/06/22 ID: 30 Start: 20/06/22 ID: 31
Finish: Wed 22/06/22
Dur: 15 days Finish: 02/06/22 Dur: 1 day Finish: 03/06/22 Dur: 2 days Finish: 09/06/22 Dur: 4 days Finish: 13/06/22 Dur: 3 days Finish: 15/06/22 Dur: 4 days Finish: 20/06/22 Dur: 4 days Finish: 22/06/22 Dur: 3 days
Comp: 0% Res: Res: Res: Res: Res: Res: Res:

PEKERJAAN PEMBANGUNAN IGD DAN POLI PEKERJAAN STRUKTUR PEKERJAAN PENDAHULUAN PEKERJAAN PONDASI PEKERJAAN STRUKTUR LANTAI DASAR PEKERJAAN STRUKTUR LANTAI I PEKERJAAN STRUKTUR LANTAI II PEKERJAAN KAP ATAP PEKERJAAN KAP ATAP ENTRANCE PEKERJAAN ACP
Start: Mon 23/05/22
ID: 34 Start: Mon 23/05/22
ID: 35 Start: 23/05/22 ID: 36 Start: 23/05/22 ID: 37 Start: 25/05/22 ID: 38 Start: 30/05/22 ID: 39 Start: 02/06/22 ID: 40 Start: 13/06/22 ID: 43 Start: 15/06/22 ID: 42 Start: 17/06/22 ID: 41
Finish: Mon 11/07/22
Dur: 36 days Finish: Mon 27/06/22
Dur: 26 days Finish: 23/05/22 Dur: 1 day Finish: 27/05/22 Dur: 5 days Finish: 02/06/22 Dur: 7 days Finish: 07/06/22 Dur: 7 days Finish: 10/06/22 Dur: 7 days Finish: 22/06/22 Dur: 8 days Finish: 17/06/22 Dur: 3 days Finish: 27/06/22 Dur: 7 days
Comp: 0% Comp: 0% Res: Res: Res: Res: Res: Res: Res: Res:

PEKERJAAN ARSITEKTUR LANTAI DASAR PEKERJAAN TANGGA


Start: Mon 13/06/22
ID: 45 Start: 13/06/22 ID: 46
Finish: Tue 14/06/22Dur: 2 days Finish: 14/06/22 Dur: 2 days
Comp: 0% Res:

PEKERJAAN ARSITEKTUR LANTAI I PEKERJAAN DINDING PEKERJAAN PLAFOND PEKERJAAN LANTAI PEKERJAAN TANGGA
Start: Wed 01/06/22
ID: 48 Start: 01/06/22 ID: 49 Start: 09/06/22 ID: 50 Start: 16/06/22 ID: 51 Start: 21/06/22 ID: 52
Finish: Tue 28/06/22Dur: 20 days Finish: 03/06/22 Dur: 3 days Finish: 15/06/22 Dur: 5 days Finish: 27/06/22 Dur: 8 days Finish: 23/06/22 Dur: 3 days
Comp: 0% Res: Res: Res: Res:

PEKERJAAN TERAS
Start: 27/06/22 ID: 57
Finish: 28/06/22 Dur: 2 days
Res:

PEKERJAAN PINTU DAN JENDELA PEKERJAAN SANITASI


Start: 06/06/22 ID: 53 Start: 14/06/22 ID: 54
Finish: 13/06/22 Dur: 6 days Finish: 16/06/22 Dur: 3 days
Res: Res:

PEKERJAAN FINISHING
Start: 14/06/22 ID: 55
Finish: 16/06/22 Dur: 3 days
Res:

PEKERJAAN PERLENGKAPAN RUANG RADIOLOGI


Start: 06/06/22 ID: 56
Finish: 13/06/22 Dur: 6 days
Res:

PEKERJAAN ARSITEKTUR LANTAI II PEKERJAAN DINDING PEKERJAAN PLAFOND PEKERJAAN LANTAI PEKERJAAN SANITASI
Start: Wed 01/06/22
ID: 59 Start: 01/06/22 ID: 60 Start: 09/06/22 ID: 61 Start: 16/06/22 ID: 62 Start: 20/06/22 ID: 64
Finish: Mon 27/06/22
Dur: 19 days Finish: 03/06/22 Dur: 3 days Finish: 15/06/22 Dur: 5 days Finish: 27/06/22 Dur: 8 days Finish: 22/06/22 Dur: 3 days
Comp: 0% Res: Res: Res: Res:

PEKERJAAN PINTU DAN JENDELA PEKERJAAN FINISHING


Start: 13/06/22 ID: 63 Start: 21/06/22 ID: 65
Finish: 20/06/22 Dur: 6 days Finish: 23/06/22 Dur: 3 days
Res: Res:

PEKERJAAN MEP PLUMBIMG MEKANIKAL ELEKTRIKAL


Start: Mon 30/05/22
ID: 67 Start: 30/05/22 ID: 68 Start: 10/06/22 ID: 69 Start: 30/06/22 ID: 70
Finish: Mon 11/07/22
Dur: 31 days Finish: 01/06/22 Dur: 3 days Finish: 27/06/22 Dur: 12 days Finish: 11/07/22 Dur: 8 days
Comp: 0% Res: Res: Res:

PEKERJAAN PEMBANGUNAN APOTIK FARMASI PEKERJAAN STRUKTUR PEKERJAAN PENDAHULUAN PEKERJAAN PONDASI PEKERJAAN STRUKTUR LANTAI DASAR PEKERJAAN STRUKTUR LANTAI I PEKERJAAN KAP ATAP
Start: Mon 23/05/22
ID: 72 Start: Mon 23/05/22
ID: 73 Start: 23/05/22 ID: 74 Start: 23/05/22 ID: 75 Start: 25/05/22 ID: 76 Start: 26/05/22 ID: 77 Start: 06/06/22 ID: 78
Finish: Mon 11/07/22
Dur: 36 days Finish: Wed 15/06/22
Dur: 18 days Finish: 23/05/22 Dur: 1 day Finish: 27/05/22 Dur: 5 days Finish: 02/06/22 Dur: 7 days Finish: 03/06/22 Dur: 7 days Finish: 15/06/22 Dur: 8 days
Comp: 0% Comp: 0% Res: Res: Res: Res: Res:

PEKERJAAN ARSITEKTUR LANTAI DASAR PEKERJAAN DINDING PEKERJAAN PLAFOND PEKERJAAN LANTAI PEKERJAAN SANITASI
Start: Mon 06/06/22
ID: 80 Start: 06/06/22 ID: 81 Start: 09/06/22 ID: 82 Start: 10/06/22 ID: 83 Start: 22/06/22 ID: 85
Finish: Fri 24/06/22 Dur: 15 days Finish: 08/06/22 Dur: 3 days Finish: 09/06/22 Dur: 1 day Finish: 21/06/22 Dur: 8 days Finish: 24/06/22 Dur: 3 days
Comp: 0% Res: Res: Res: Res:

PEKERJAAN PINTU DAN JENDELA PEKERJAAN FINISHING


Start: 09/06/22 ID: 84 Start: 17/06/22 ID: 86
Finish: 16/06/22 Dur: 6 days Finish: 21/06/22 Dur: 3 days
Res: Res:

PEKERJAAN ARSITEKTUR LANTAI I PEKERJAAN DINDING PEKERJAAN PLAFOND


Start: Mon 06/06/22
ID: 88 Start: 06/06/22 ID: 89 Start: 14/06/22 ID: 90
Finish: Wed 22/06/22
Dur: 13 days Finish: 08/06/22 Dur: 3 days Finish: 14/06/22 Dur: 1 day
Comp: 0% Res: Res:

PEKERJAAN PINTU DAN JENDELA PEKERJAAN SANITASI


Start: 10/06/22 ID: 92 Start: 20/06/22 ID: 93
Finish: 17/06/22 Dur: 6 days Finish: 22/06/22 Dur: 3 days
Res: Res:

PEKERJAAN FINISHING
Start: 21/06/22 ID: 94
Finish: 21/06/22 Dur: 1 day
Res:

PEKERJAAN LANTAI
Start: ID: 91
Finish: Dur:
Res:

PEKERJAAN MEP PLUMBIMG MEKANIKAL ELEKTRIKAL


Start: Mon 30/05/22
ID: 96 Start: 30/05/22 ID: 97 Start: 10/06/22 ID: 98 Start: 30/06/22 ID: 99
Finish: Mon 11/07/22
Dur: 31 days Finish: 01/06/22 Dur: 3 days Finish: 27/06/22 Dur: 12 days Finish: 11/07/22 Dur: 8 days
Comp: 0% Res: Res: Res:

PEKERJAAN PEMBANGUNAN LAUNDRY PEKERJAAN PENDAHULUAN PEKERJAAN PONDASI PEKERJAAN BETON BERTULANG PEKERJAAN DINDING PEKERJAAN KAP ATAP PEKERJAAN PINTU DAN JENDELA PEKERJAAN SANITASI
Start: Mon 23/05/22
ID: 102 Start: 23/05/22 ID: 103 Start: 23/05/22 ID: 104 Start: 25/05/22 ID: 105 Start: 08/06/22 ID: 106 Start: 17/06/22 ID: 107 Start: 20/06/22 ID: 110 Start: 23/06/22 ID: 111
Finish: Mon 11/07/22
Dur: 36 days Finish: 23/05/22 Dur: 1 day Finish: 24/05/22 Dur: 2 days Finish: 01/06/22 Dur: 6 days Finish: 10/06/22 Dur: 3 days Finish: 20/06/22 Dur: 2 days Finish: 27/06/22 Dur: 6 days Finish: 27/06/22 Dur: 3 days
Comp: 0% Res: Res: Res: Res: Res: Res: Res:

PEKERJAAN FINISHING PEKERJAAN RABAT KELILING


Start: 28/06/22 ID: 112 Start: 28/06/22 ID: 113
Finish: 30/06/22 Dur: 3 days Finish: 30/06/22 Dur: 3 days
Res: Res:

PEKERJAAN PLAFOND
Start: ID: 108
Finish: Dur:
Res:

PEKERJAAN LANTAI
Start: ID: 109
Finish: Dur:
Res:

PEKERJAAN MEP PLUMBIMG MEKANIKAL ELEKTRIKAL


Start: Mon 30/05/22
ID: 115 Start: 30/05/22 ID: 116 Start: 10/06/22 ID: 117 Start: 30/06/22 ID: 118
Finish: Mon 11/07/22
Dur: 31 days Finish: 01/06/22 Dur: 3 days Finish: 27/06/22 Dur: 12 days Finish: 11/07/22 Dur: 8 days
Comp: 0% Res: Res: Res:

PEKERJAAN PEMBANGUNAN INSTALASI KEBIDANAN PEKERJAAN PENDAHULUAN PEKERJAAN PONDASI PEKERJAAN BETON BERTULANG PEKERJAAN DINDING PEKERJAAN KAP ATAP PEKERJAAN PINTU DAN JENDELA
Start: Mon 23/05/22
ID: 121 Start: 23/05/22 ID: 122 Start: 23/05/22 ID: 123 Start: 25/05/22 ID: 124 Start: 31/05/22 ID: 125 Start: 08/06/22 ID: 126 Start: 10/06/22 ID: 129
Finish: Mon 11/07/22
Dur: 36 days Finish: 23/05/22 Dur: 1 day Finish: 27/05/22 Dur: 5 days Finish: 02/06/22 Dur: 7 days Finish: 02/06/22 Dur: 3 days Finish: 14/06/22 Dur: 5 days Finish: 17/06/22 Dur: 6 days
Comp: 0% Res: Res: Res: Res: Res: Res:

PEKERJAAN PLAFOND PEKERJAAN LANTAI PEKERJAAN SANITASI


Start: 08/06/22 ID: 127 Start: 15/06/22 ID: 128 Start: 17/06/22 ID: 130
Finish: 14/06/22 Dur: 5 days Finish: 24/06/22 Dur: 8 days Finish: 21/06/22 Dur: 3 days
Res: Res: Res:

PEKERJAAN FINISHING PEKERJAAN RABAT KELILING


Start: 27/06/22 ID: 131 Start: 27/06/22 ID: 132
Finish: 29/06/22 Dur: 3 days Finish: 29/06/22 Dur: 3 days
Res: Res:

PEKERJAAN MEP PLUMBIMG MEKANIKAL ELEKTRIKAL


Start: Mon 30/05/22
ID: 134 Start: 30/05/22 ID: 135 Start: 10/06/22 ID: 136 Start: 30/06/22 ID: 137
Finish: Mon 11/07/22
Dur: 31 days Finish: 01/06/22 Dur: 3 days Finish: 27/06/22 Dur: 12 days Finish: 11/07/22 Dur: 8 days
Comp: 0% Res: Res: Res:

PEKERJAAN PEMBANGUNAN INSTALASI RAWAT INAP PEKERJAAN PENDAHULUAN PEKERJAAN PONDASI PEKERJAAN BETON BERTULANG
Start: Mon 23/05/22
ID: 140 Start: 23/05/22 ID: 141 Start: 23/05/22 ID: 142 Start: 25/05/22 ID: 143
Finish: Mon 11/07/22
Dur: 36 days Finish: 23/05/22 Dur: 1 day Finish: 27/05/22 Dur: 5 days Finish: 02/06/22 Dur: 7 days
Comp: 0% Res: Res: Res:

PEKERJAAN DINDING PEKERJAAN KAP ATAP PEKERJAAN PLAFOND PEKERJAAN LANTAI PEKERJAAN SANITASI
Start: 31/05/22 ID: 144 Start: 08/06/22 ID: 145 Start: 08/06/22 ID: 146 Start: 15/06/22 ID: 147 Start: 17/06/22 ID: 149
Finish: 02/06/22 Dur: 3 days Finish: 14/06/22 Dur: 5 days Finish: 14/06/22 Dur: 5 days Finish: 24/06/22 Dur: 8 days Finish: 21/06/22 Dur: 3 days
Res: Res: Res: Res: Res:

PEKERJAAN FINISHING PEKERJAAN RABAT KELILING


Start: 27/06/22 ID: 150 Start: 27/06/22 ID: 151
Finish: 29/06/22 Dur: 3 days Finish: 29/06/22 Dur: 3 days
Res: Res:

PEKERJAAN PINTU DAN JENDELA


Start: 10/06/22 ID: 148
Finish: 17/06/22 Dur: 6 days
Res:

PEKERJAAN MEP PLUMBIMG MEKANIKAL ELEKTRIKAL


Start: Mon 30/05/22
ID: 153 Start: 30/05/22 ID: 154 Start: 10/06/22 ID: 155 Start: 30/06/22 ID: 156
Finish: Mon 11/07/22
Dur: 31 days Finish: 01/06/22 Dur: 3 days Finish: 27/06/22 Dur: 12 days Finish: 11/07/22 Dur: 8 days
Comp: 0% Res: Res: Res:

PEKERJAAN PEMBANGUNAN INSTALASI GIZI PEKERJAAN PENDAHULUAN PEKERJAAN PONDASI PEKERJAAN DINDING PEKERJAAN KAP ATAP PEKERJAAN PLAFOND PEKERJAAN LANTAI PEKERJAAN SANITASI
Start: Mon 23/05/22
ID: 159 Start: 23/05/22 ID: 160 Start: 23/05/22 ID: 161 Start: 31/05/22 ID: 163 Start: 08/06/22 ID: 164 Start: 08/06/22 ID: 165 Start: 15/06/22 ID: 166 Start: 17/06/22 ID: 168
Finish: Mon 11/07/22
Dur: 36 days Finish: 23/05/22 Dur: 1 day Finish: 27/05/22 Dur: 5 days Finish: 02/06/22 Dur: 3 days Finish: 14/06/22 Dur: 5 days Finish: 14/06/22 Dur: 5 days Finish: 24/06/22 Dur: 8 days Finish: 21/06/22 Dur: 3 days
Comp: 0% Res: Res: Res: Res: Res: Res: Res:

PEKERJAAN FINISHING PEKERJAAN RABAT KELILING


Start: 27/06/22 ID: 169 Start: 27/06/22 ID: 170
Finish: 29/06/22 Dur: 3 days Finish: 29/06/22 Dur: 3 days
Res: Res:

PEKERJAAN PINTU DAN JENDELA


Start: 10/06/22 ID: 167
Finish: 17/06/22 Dur: 6 days
Res:

PEKERJAAN BETON BERTULANG


Start: 25/05/22 ID: 162
Finish: 02/06/22 Dur: 7 days
Res:

PEKERJAAN MEP PLUMBIMG MEKANIKAL ELEKTRIKAL


Start: Mon 30/05/22
ID: 172 Start: 30/05/22 ID: 173 Start: 10/06/22 ID: 174 Start: 30/06/22 ID: 175
Finish: Mon 11/07/22
Dur: 31 days Finish: 01/06/22 Dur: 3 days Finish: 27/06/22 Dur: 12 days Finish: 11/07/22 Dur: 8 days
Comp: 0% Res: Res: Res:

PEKERJAAN PEMBANGUNAN IPRS PEKERJAAN PENDAHULUAN PEKERJAAN PONDASI PEKERJAAN DINDING PEKERJAAN KAP ATAP PEKERJAAN PLAFOND PEKERJAAN PINTU DAN JENDELA
Start: Mon 23/05/22
ID: 178 Start: 23/05/22 ID: 179 Start: 23/05/22 ID: 180 Start: 31/05/22 ID: 182 Start: 08/06/22 ID: 183 Start: 08/06/22 ID: 184 Start: 13/06/22 ID: 186
Finish: Mon 11/07/22
Dur: 36 days Finish: 23/05/22 Dur: 1 day Finish: 27/05/22 Dur: 5 days Finish: 02/06/22 Dur: 3 days Finish: 14/06/22 Dur: 5 days Finish: 14/06/22 Dur: 5 days Finish: 20/06/22 Dur: 6 days
Comp: 0% Res: Res: Res: Res: Res: Res:

PEKERJAAN LANTAI PEKERJAAN SANITASI


Start: 15/06/22 ID: 185 Start: 17/06/22 ID: 187
Finish: 24/06/22 Dur: 8 days Finish: 21/06/22 Dur: 3 days
Res: Res:

PEKERJAAN FINISHING PEKERJAAN RABAT KELILING


Start: 27/06/22 ID: 188 Start: 27/06/22 ID: 189
Finish: 29/06/22 Dur: 3 days Finish: 29/06/22 Dur: 3 days
Res: Res:

PEKERJAAN BETON BERTULANG


Start: 25/05/22 ID: 181
Finish: 02/06/22 Dur: 7 days
Res:

PEKERJAAN MEP PLUMBIMG MEKANIKAL ELEKTRIKAL


Start: Mon 30/05/22
ID: 191 Start: 30/05/22 ID: 192 Start: 10/06/22 ID: 193 Start: 30/06/22 ID: 194
Finish: Mon 11/07/22
Dur: 31 days Finish: 01/06/22 Dur: 3 days Finish: 27/06/22 Dur: 12 days Finish: 11/07/22 Dur: 8 days
Comp: 0% Res: Res: Res:

PEKERJAAN PEMBANGUNAN KAMAR JENAZAH PEKERJAAN PENDAHULUAN PEKERJAAN PONDASI PEKERJAAN BETON BERTULANG
Start: Mon 23/05/22
ID: 197 Start: 23/05/22 ID: 198 Start: 23/05/22 ID: 199 Start: 25/05/22 ID: 200
Finish: Mon 11/07/22
Dur: 36 days Finish: 23/05/22 Dur: 1 day Finish: 27/05/22 Dur: 5 days Finish: 02/06/22 Dur: 7 days
Comp: 0% Res: Res: Res:

Page 1
PEKERJAAN DINDING PEKERJAAN KAP ATAP PEKERJAAN PLAFOND PEKERJAAN LANTAI PEKERJAAN SANITASI
Start: 31/05/22 ID: 201 Start: 08/06/22 ID: 202 Start: 08/06/22 ID: 203 Start: 15/06/22 ID: 204 Start: 17/06/22 ID: 206
Finish: 02/06/22 Dur: 3 days Finish: 14/06/22 Dur: 5 days Finish: 14/06/22 Dur: 5 days Finish: 24/06/22 Dur: 8 days Finish: 21/06/22 Dur: 3 days
Res: Res: Res: Res: Res:

PEKERJAAN FINISHING PEKERJAAN RABAT KELILING


Start: 27/06/22 ID: 207 Start: 27/06/22 ID: 208
Finish: 29/06/22 Dur: 3 days Finish: 29/06/22 Dur: 3 days
Res: Res:

PEKERJAAN PINTU DAN JENDELA


Start: 10/06/22 ID: 205
Finish: 17/06/22 Dur: 6 days
Res:

PEKERJAAN MEP PLUMBIMG MEKANIKAL ELEKTRIKAL


Start: Mon 30/05/22
ID: 210 Start: 30/05/22 ID: 211 Start: 10/06/22 ID: 212 Start: 30/06/22 ID: 213
Finish: Mon 11/07/22
Dur: 31 days Finish: 01/06/22 Dur: 3 days Finish: 27/06/22 Dur: 12 days Finish: 11/07/22 Dur: 8 days
Comp: 0% Res: Res: Res:

PEKERJAAN PEMBANGUNAN GUDANG LIMBAH B3 PEKERJAAN PENDAHULUAN PEKERJAAN PONDASI PEKERJAAN STRUKTUR PEKERJAAN LANTAI PEKERJAAN FINISHING
Start: Mon 23/05/22
ID: 216 Start: 23/05/22 ID: 217 Start: 23/05/22 ID: 218 Start: 25/05/22 ID: 219 Start: 15/06/22 ID: 221 Start: 27/06/22 ID: 223
Finish: Wed 29/06/22
Dur: 28 days Finish: 23/05/22 Dur: 1 day Finish: 27/05/22 Dur: 5 days Finish: 02/06/22 Dur: 7 days Finish: 24/06/22 Dur: 8 days Finish: 29/06/22 Dur: 3 days
Comp: 0% Res: Res: Res: Res: Res:

PEKERJAAN RABAT KELILING


Start: 27/06/22 ID: 224
Finish: 29/06/22 Dur: 3 days
Res:

PEKERJAAN PINTU DAN JENDELA


Start: 10/06/22 ID: 222
Finish: 17/06/22 Dur: 6 days
Res:

PEKERJAAN DINDING
Start: 31/05/22 ID: 220
Finish: 02/06/22 Dur: 3 days
Res:

Start: ID: 225


Finish: Dur: 3 days
Res:

PEKERJAAN IPAL MAIN SYSTEM PEKERJAAN SIPIL BIO SAVE TANK


Start: Thu 16/06/22ID: 226 Start: 16/06/22 ID: 227 Start: 17/06/22 ID: 228
Finish: Tue 28/06/22Dur: 9 days Finish: 21/06/22 Dur: 4 days Finish: 23/06/22 Dur: 5 days
Comp: 0% Res: Res:

PEKERJAAN SIPIL CHEMICAL REDUCER PEKERJAAN SIPIL PRE TREATMENT LAUNDRY PEKERJAAN SIPIL GREASE TRAP PEKERJAAN SIPIL EV 8 COLLECTING TANK PEKERJAAN SIPIL EV 8 POST TREATMENT TANK PEKERJAAN KOLAM INDIKATOR
Start: 22/06/22 ID: 229 Start: 22/06/22 ID: 230 Start: 22/06/22 ID: 231 Start: 24/06/22 ID: 232 Start: 24/06/22 ID: 233 Start: 24/06/22 ID: 234
Finish: 23/06/22 Dur: 2 days Finish: 23/06/22 Dur: 2 days Finish: 23/06/22 Dur: 2 days Finish: 24/06/22 Dur: 1 day Finish: 24/06/22 Dur: 1 day Finish: 28/06/22 Dur: 3 days
Res: Res: Res: Res: Res: Res:

PEKERJAAN GEOLISTRIK PEKERJAAN PERSIAPAN PEKERJAAN PENGUKURAN TERMASUK OBSERVASI LAPANGAN


PELAPORAN KEGIATAN
Start: Wed 25/05/22
ID: 236 Start: 25/05/22 ID: 237 Start: 26/05/22 ID: 238 Start: 27/05/22 ID: 239
Finish: Tue 31/05/22Dur: 5 days Finish: 27/05/22 Dur: 3 days Finish: 30/05/22 Dur: 3 days Finish: 31/05/22 Dur: 3 days
Comp: 0% Res: Res: Res:

PEKERJAAN SUMUR BOR DALAM PEKERJAAN PERSIAPAN BIAYA PEMBORAN BIAYA PENGADAAN BAHAN
Start: Thu 02/06/22ID: 241 Start: 02/06/22 ID: 242 Start: 03/06/22 ID: 243 Start: 07/06/22 ID: 244
Finish: Wed 08/06/22
Dur: 5 days Finish: 03/06/22 Dur: 2 days Finish: 08/06/22 Dur: 4 days Finish: 08/06/22 Dur: 2 days
Comp: 0% Res: Res: Res:

PEKERJAAN PEMBANGUNAN POWER HOUSE PEKERJAAN PENDAHULUAN PEKERJAAN PONDASI PEKERJAAN STRUKTUR
Start: Mon 23/05/22
ID: 246 Start: 23/05/22 ID: 247 Start: 23/05/22 ID: 248 Start: 25/05/22 ID: 249
Finish: Wed 29/06/22
Dur: 28 days Finish: 23/05/22 Dur: 1 day Finish: 27/05/22 Dur: 5 days Finish: 02/06/22 Dur: 7 days
Comp: 0% Res: Res: Res:

PEKERJAAN DINDING PEKERJAAN LANTAI PEKERJAAN FINISHING


Start: 31/05/22 ID: 250 Start: 15/06/22 ID: 251 Start: 27/06/22 ID: 253
Finish: 02/06/22 Dur: 3 days Finish: 24/06/22 Dur: 8 days Finish: 29/06/22 Dur: 3 days
Res: Res: Res:

PEKERJAAN RABAT KELILING


Start: 27/06/22 ID: 254
Finish: 29/06/22 Dur: 3 days
Res:

PEKERJAAN MEP
Start: 15/06/22 ID: 256
Finish: 28/06/22 Dur: 10 days
Res:

PEKERJAAN PINTU DAN JENDELA


Start: 10/06/22 ID: 252
Finish: 17/06/22 Dur: 6 days
Res:

PEKERJAAN PEMBANGUNAN RUMAH POMPA PEKERJAAN PENDAHULUAN


Start: Mon 23/05/22
ID: 258 Start: 23/05/22 ID: 259
Finish: Wed 29/06/22
Dur: 28 days Finish: 23/05/22 Dur: 1 day
Comp: 0% Res:

PEKERJAAN PONDASI PEKERJAAN STRUKTUR


Start: 23/05/22 ID: 260 Start: 25/05/22 ID: 261
Finish: 27/05/22 Dur: 5 days Finish: 02/06/22 Dur: 7 days
Res: Res:

PEKERJAAN DINDING PEKERJAAN LANTAI PEKERJAAN FINISHING


Start: 31/05/22 ID: 262 Start: 15/06/22 ID: 263 Start: 27/06/22 ID: 265
Finish: 02/06/22 Dur: 3 days Finish: 24/06/22 Dur: 8 days Finish: 29/06/22 Dur: 3 days
Res: Res: Res:

PEKERJAAN RABAT KELILING


Start: 27/06/22 ID: 266
Finish: 29/06/22 Dur: 3 days
Res:

PEKERJAAN PINTU DAN JENDELA


Start: 10/06/22 ID: 264
Finish: 17/06/22 Dur: 6 days
Res:

PEKERJAAN PEMBANGUNAN RUMAH WATERTANK PEKERJAAN PENDAHULUAN PEKERJAAN PONDASI


Start: Mon 23/05/22
ID: 268 Start: 23/05/22 ID: 269 Start: 23/05/22 ID: 270
Finish: Wed 29/06/22
Dur: 28 days Finish: 23/05/22 Dur: 1 day Finish: 27/05/22 Dur: 5 days
Comp: 0% Res: Res:

PEKERJAAN STRUKTUR PEKERJAAN KAP ATAP PEKERJAAN LANTAI PEKERJAAN FINISHING


Start: 25/05/22 ID: 271 Start: 03/06/22 ID: 272 Start: 15/06/22 ID: 273 Start: 27/06/22 ID: 274
Finish: 02/06/22 Dur: 7 days Finish: 07/06/22 Dur: 3 days Finish: 24/06/22 Dur: 8 days Finish: 29/06/22 Dur: 3 days
Res: Res: Res: Res:

PEKERJAAN RABAT KELILING


Start: 27/06/22 ID: 275
Finish: 29/06/22 Dur: 3 days
Res:

Page 2
Project: MP SIJUNJUNG Critical Noncritical Critical Milestone Milestone Critical Summary Summary Critical Inserted Inserted Critical Marked Marked Critical External External Project Summary Highlighted Critical Highlighted Noncritical
Date: Wed 18/05/22

Page 3