RUMAH POMPA PEKERJAAN PERSIAPAN Pengukuran dan Pemasangan Bouwpl ank Printing Banner 100 x 80 Cm

Start: Mon 19/06/23


ID: 1 Start: Mo n 19/06/23
ID: 2 Start: Mon 19/06/23ID: 14 Start: Mon 19/06/23ID: 7
Finish: W ed 27/12/23
Dur: 165 days? Finish: Thu 14/12/23
Dur: 154 days? Finish: Mon 26/06/23
Dur: 7 days Finish: Mon 26/06/23
Dur: 7 days
Comp: 0% Comp: 0% Res: Res:

Direksi Keet/Kantor Ukur an 3 x 5 M Bedeng Pekerja Uk uran 4 x 5 M


Start: Mon 19/06/23ID: 8 Start: Mon 19/06/23ID: 9
Finish: Tue 04/07/23Dur: 14 days Finish: Tue 04/07/23Dur: 14 days
Res: Res:

Membersihk an Lapangan dan Peralatan


Start: Tue 27/06/23ID: 10
Finish: Tue 04/07/23Dur: 7 days
Res:

Penyediaan Listrik Ker ja


Start: Tue 27/06/23ID: 11
Finish: Tue 04/07/23Dur: 7 days
Res:

Penyediaan Air Kerja


Start: Tue 27/06/23ID: 12
Finish: Tue 04/07/23Dur: 7 days
Res:

Pagar Sementara Seng Gelombang Tebal 0.20 Mm, Tinggi 1.80 Mm


Start: Tue 27/06/23ID: 13
Finish: Tue 04/07/23Dur: 7 days
Res:

Mobilisasi/Demobilisasi Alat Berat


Start: Mon 19/06/23ID: 15
Finish: Thu 14/12/23Dur: 154 days
Res:

Plakat Dinas (dipasang di area umum yang terlihat oleh masy arakat)
Start: Mon 19/06/23ID: 16
Finish: Mon 26/06/23
Dur: 7 days
Res:

Dokumentasi (Foto & Video 0%, 25%, 50%, 75%, 100%)


Start: Mon 19/06/23ID: 17
Finish: Mon 19/06/23
Dur: 1 day?
Res:

Pondasi Cor Beton


Start: Tue 27/06/23ID: 3
Finish: Tue 04/07/23Dur: 7 days
Res:

Pipa Besi dia. 2 inch


Start: Tue 27/06/23ID: 4
Finish: Tue 04/07/23Dur: 7 days
Res:

Pipa Besi dia. 1 inch


Start: Tue 27/06/23ID: 5
Finish: Tue 04/07/23Dur: 7 days
Res:

Plat Besi Galvani s Tebal 0,9mm


Start: Tue 27/06/23ID: 6
Finish: Tue 04/07/23Dur: 7 days
Res:

PEKERJAAN SIPIL Pekerjaan Kisdam Pengadaan CCSP W.400.1000 Kelas A Pemancang an CCS P W.400.1000 Kelas A Dengan Vibro Hammer
Sewa(incl
Genset
. handling
10 kVA
& unloading)
Start: Tue 27/06/23ID: 18 Start: Tue 27/06/23ID: 19 Start: Tue 27/06/23ID: 20 Start: Wed 05/07/23ID: 21 Start: Wed 05/07/23ID: 22
Finish: Fri 22/12/23Dur: 154 days Finish: Mon 14/08/23
Dur: 42 days Finish: Fri 28/07/23 Dur: 28 days Finish: Mon 14/08/23Dur: 35 days Finish: Mon 14/08/23Dur: 35 days
Comp: 0% Comp: 0% Res: Res: Res:

Pekerjaan Dewater ing


Start: Wed 05/07/23ID: 23
Finish: Mon 14/08/23Dur: 35 days
Res:

Pekerjaan Rumah Pompa dan Rumah Genset Galian Tanah Biasa Kedal aman 3 Meter (Area Kolam Pompa)Cerucuk Dolken dia. 10cm Panjang 2 m, Dipasang Zi g Zag per 50 cm
Start: Sat 29/07/23ID: 24 Start: Sat 29/07/23 ID: 25 Start: Tue 15/08/23 ID: 26
Finish: Thu 14/12/23
Dur: 119 days Finish: Mon 14/08/23Dur: 14 days Finish: Tue 22/08/23Dur: 7 days
Comp: 0% Res: Res:

Pengadaan Tiang Pancang Beton Spun Pile d=50 cm, P=18 m Kelas
Pengangk
A1 utan Tiang Pancang ke Titik Pancang Pemancangan Spun Pile dia. 30 cm dengan Di esel Hammer Bekisting Koneksi Spun Pile Expose Mul tiplek Tebal 15 mm (2x
CorPakai)
Beton Koneksi Spun Pile Tinggi 1 m, Readymix K-350 Slump 12, Tanpa Fly Ash
Start: Sat 29/07/23 ID: 27 Start: Mon 07/08/23ID: 28 Start: Mon 07/08/23ID: 29 Start: Thu 31/08/23 ID: 31 Sta rt: Thu 31/08/23ID: 32
Finish: Wed 30/08/23Dur: 28 days Finish: Thu 07/09/23Dur: 28 days Finish: Thu 07/09/23Dur: 28 days Finish: Fri 15/09/23 Dur: 14 days Finish: Fri 15/09/23 Dur: 14 days
Res: Res: Res: Res: Res:

Pembesian Ulir Tulangan Koneksi Spun Pile


Sta rt: Thu 31/08/23ID: 33
Finish: Fri 15/09/23 Dur: 14 days
Res:

Pasir Urug t=10 cm, Plat Lantai Kolam (elv . +0.00)


Start: Fri 08/09/23 ID: 34
Finish: Fri 15/09/23 Dur: 7 days
Res:

Lantai Kerja t=5 cm, Plat Lantai Kolam (elv. +0.00)


Start: Fri 08/09/23 ID: 35
Finish: Fri 15/09/23 Dur: 7 days
Res:

Lantai Kerja t=5 cm, Plat Lantai Kolam (elv. +0.00) Plat Lantai Kolam Tebal 50 cm, Rumah Pompa Cor Beton K350
Pembesian
slump 12,Ulir
tanpaPlatflyLantai
ash, (elv.
Kolam,
+0.00)
(elv. +0.00)
Start: Fri 08/09/23 ID: 36 Sta rt: Sat 16/09/23 ID: 37 Sta rt: Sat 16/09/23 ID: 38
Finish: Fri 15/09/23 Dur: 7 days Finish: Tue 10/10/23Dur: 21 days Finish: Tue 10/10/23Dur: 21 days
Res: Res: Res:

Bekisti ng Dinding Kolam, Expose Triplex tebal 15 mm (s/d elv.Dinding


+5.40) Kolam
(2x Pakai)
Tebal 40 cm, Rumah Pompa Cor Beton K350 slump
Bekisting
12, tanpa
Plat Lantai,
fly ash,
Rumah
(s/d elv.
Pom +5.40)
pa E xpose Triplex tebal 15 Plat
mm (elv.
Lantai+5.40)
Tebal(2x
20Pakai
cm, Rumah
) Pompa Cor Beton K350 slump 12, tanpa fly ash, (el v. +5.40)
Sta rt: Mon 25/09/23ID: 39 Start: Mon 25/09/23ID: 40 Start: Wed 11/10/23ID: 42 Start: Wed 11/10/23ID: 43
Finish: Thu 26/10/23Dur: 28 days Finish: Thu 26/10/23Dur: 28 days Finish: Fri 03/11/23 Dur: 21 days Finish: Fri 03/11/23 Dur: 21 da ys
Res: Res: Res: Res:

Pembesian Ulir Plat Lantai, Rumah Pompa (elv. +5.40)


Start: Wed 11/10/23ID: 44
Finish: Fri 03/11/23 Dur: 21 da ys
Res:

Bekisting Kolom K1, Rumah Genset Expose Triplex tebal 15 mm


Kolom
(elv.K1
+5.40
Uk. 300
s/d x+9.40)
300 mm,
(2x Pakai)
Rumah Genset Cor Beton K300 slump 12, tanpa fl y ash, (elv. +5.40 s/d +9.40)
Start: Fri 27/10/23 ID: 51 Start: Fri 27/10/23 ID: 52
Finish: Sat 11/11/23 Dur: 14 days Finish: Sat 11/11/23 Dur: 14 da ys
Res: Res:

Pembesian Ulir Kolom K1, Rumah Genset (elv. +5.40 s/d +9.40)
Start: Fri 27/10/23 ID: 53
Finish: Sat 11/11/23 Dur: 14 da ys
Res:

Plat Lantai Tebal 12 cm, Lantai Atap Rumah Genset, Cor Beton
Pembesian
K300 slump Ulir12,
Plat
tanpa
Lantai,
fly Lantai
ash, (elv.
Atap+9.40)
Rumah Genset (elv. +9.40)
Bek isting Plat Lantai, Lantai A tap Rumah Pompa, Expose Tr iplex
Plattebal
Lantai15Tebal
mm (elv.
12 cm,
+12.40)
Lantai(2x
Atap
Pakai)
Rumah Pompa, Cor Beton
Pembesi
K300 slump
an Ulir12,
Plat
tanpa
Lantai,
fly Lantai
ash, (elv.
Atap+12.40)
Rumah Pompa (elv. +12.40)
Start: Mon 13/11/23ID: 46 Start: Mon 13/11/23ID: 47 Start: Mon 13/11/23ID: 48 Start: Mon 13/11/23ID: 49 Start: Mon 13/11/23ID: 50
Finish: Tue 28/11/23Dur: 14 da ys Finish: Tue 28/11/23Dur: 14 da ys Finish: Tue 28/11/23Dur: 14 days Finish: Tue 28/11/23Dur: 14 days Finish: Tue 28/11/23Dur: 14 days
Res: Res: Res: Res: Res:

Bekisting Pl at Lantai , Lantai Atap Rumah Genset Expose Tr iplex tebal 12 mm (elv. +9.40) (2x Pakai)
Start: Mon 13/11/23ID: 45
Finish: Tue 28/11/23Dur: 14 da ys
Res:

Bekisting Kolom K2, Rumah Pompa Expose Triplex tebal 15 mm


Kolom
(elv.K2
+5.40
Uk. 400
s/d x+8.90)
4000 (2x
mm,Pakai)
Rumah Pompa Cor Beton K300Pembesian
slump 12, tanpa
Ulir Kolom
fly ash,
K2,(elv.
Rumah+5.40
Pompa
s/d +8.90)
(elv. +5.40 s/d +8.90)
Start: Fri 27/10/23 ID: 54 Start: Fri 27/10/23 ID: 55 Start: Fri 27/10/23 ID: 56
Finish: Sat 11/11/23 Dur: 14 days Finish: Sat 11/11/23 Dur: 14 da ys Finish: Sat 11/11/23 Dur: 14 da ys
Res: Res: Res:

Bekisting Balok B1 Uk. 250 x 350mm, Rumah Pompa Expose Triplex


Balok B1tebal
Uk. 15
250mm
x 350
(elv.
mm,+8.90)
Rumah
(2x Pakai)
Pompa Cor Beton K300 slump 12, tanpa fly ash (elv. +8.90)
Start: Mon 13/11/23ID: 66 Start: Mon 13/11/23ID: 67
Finish: Tue 28/11/23Dur: 14 da ys Finish: Tue 28/11/23Dur: 14 days
Res: Res:

Pembesian Ulir Balok B1 Uk. 250 x 350 mm, Rumah Pompa (elv. +8.90)
Start: Mon 13/11/23ID: 68
Finish: Tue 28/11/23Dur: 14 days
Res:

Bek isting Balok B1 Uk . 250 x 350mm, Atap Rumah Genset Expose Triplex tebal 15 mm (elv. +9.40) (2x Pakai)
Start: Mon 13/11/23ID: 69
Finish: Tue 28/11/23Dur: 14 days
Res:

Balok B1 Uk. 250 x 350 mm, A tap Rumah Genset Cor Beton K300 slump 12, tanpa fl y ash (elv. +9.40)
Start: Mon 13/11/23ID: 70
Finish: Tue 28/11/23Dur: 14 days
Res:

Pembesian Ulir Balok B1 Uk. 250 x 350 mm, A tap Rumah Genset (elv. +9.40)
Start: Mon 13/11/23ID: 71
Finish: Tue 28/11/23Dur: 14 days
Res:

Bek isting Listplank L1 Uk. 10 x 80 mm, Atap Rumah Genset Expose Triplex tebal 15 mm (elv. +9.40) (2x Pakai)
Start: Mon 13/11/23ID: 72
Finish: Tue 28/11/23Dur: 14 days
Res:

Listplank L1 Uk. 10 x 80 mm, A tap Rumah Genset Cor Beton K300 slump 12, tanpa fl y ash (elv. +9.40)
Start: Mon 13/11/23ID: 73
Finish: Tue 28/11/23Dur: 14 days
Res:

Pembesian Polos Listplank L1 Uk. 10 x 80 mm, Atap Rum ah Genset (elv. +9.40)
Start: Mon 13/11/23ID: 74
Finish: Tue 28/11/23Dur: 14 days
Res:

Bekisting Balok B1 Uk. 250 x 350mm, Atap Rumah Pompa Expose


BalokTriplex
B1 Uk.tebal
250 x15
350
mmmm,
(elv.
A tap
+12.40)
Rumah(2xPompa
Pakai) Cor Beton K300 slump 12, tanpa fly ash (elv. +12.40)
Start: Mon 13/11/23ID: 75 Start: Mon 13/11/23ID: 76
Finish: Tue 28/11/23Dur: 14 da ys Finish: Tue 28/11/23Dur: 14 days
Res: Res:

Pembesian Ulir Balok B1 Uk. 250 x 350 mm, A tap Rumah Pompa (elv. +12.40)
Start: Mon 13/11/23ID: 77
Finish: Tue 28/11/23Dur: 14 days
Res:

Bek isting Listplank L1 Uk. 10 x 80 mm, Atap Rumah Pompa E Listplank


xpose Triplex
L1 Uk.
tebal
10 15
x 80mm
mm,
(elv.
A tap
+12.40)
Rumah (2xPompa
Pakai) Cor Beton K300 slump 12, tanpa fly ash (elv. +12.40)
Start: Mon 13/11/23ID: 78 Start: Mon 13/11/23ID: 79
Finish: Tue 28/11/23Dur: 14 days Finish: Tue 28/11/23Dur: 14 days
Res: Res:

Pembesian Polos Listplank L1 Uk. 10 x 80 mm, Atap Rum ah Genset (elv. +9.40)
Start: Mon 13/11/23ID: 80
Finish: Tue 28/11/23Dur: 14 days
Res:

Bek isting Balok B2 Uk . 250 x 350mm, Rum ah Pompa Expose Triplex


Balok B2tebal
Uk. 15
250mm
x 350
(elv.
mm,+8.90)
Rumah
(2x Pakai)
Pompa Cor Beton K300 slump 12, tanpa fly ash (elv. +8.90)
Start: Mon 13/11/23ID: 81 Start: Mon 13/11/23ID: 82
Finish: Wed 06/12/23Dur: 21 days Finish: Wed 06/12/23Dur: 21 days
Res: Res:

Pembesian Ulir Balok B2 Uk. 250 x 350 mm, (el v. +8.90)


Start: Mon 13/11/23ID: 83
Finish: Wed 06/12/23Dur: 21 days
Res:

Bek isting Plat Beton tebal 200 mm, Dudukan Genset Expose Tr
Plat
iplex
Beton
tebal
tebal
15 m200
m (2x
mm,Pakai)
Dudukan Genset Cor Beton K300 slump 12, tanpa fly ash
Start: Thu 07/12/23ID: 84 Start: Thu 07/12/23ID: 85
Finish: Thu 14/12/23Dur: 7 days Finish: Thu 14/12/23Dur: 7 days
Res: Res:

Pembesi an Ulir Plat Beton tebal 200 mm, Dudukan Genset


Start: Thu 07/12/23ID: 86
Finish: Thu 14/12/23Dur: 7 days
Res:

Beki sting Plat Beton tebal 200 mm, Dudukan Trafo Expose Triplex tebal 15 mm (2x Pakai)
Start: Thu 07/12/23ID: 87
Finish: Thu 14/12/23Dur: 7 days
Res:

Plat Beton tebal 200 mm, Dudukan Tr afo Cor Beton K300 slump 12, tanpa fly ash
Start: Thu 07/12/23ID: 88
Finish: Thu 14/12/23Dur: 7 days
Res:

Pembesi an Ulir Plat Beton tebal 200 mm, Dudukan Trafo


Start: Thu 07/12/23ID: 89
Finish: Thu 14/12/23Dur: 7 days
Res:

Bekisting Balok Korbel, Rumah Pompa Expose Tr iplek Tebal 15 mm (2x Pakai)
Start: Fri 27/10/23 ID: 57
Finish: Sat 11/11/23 Dur: 14 days
Res:

Balok Korbel Uk . 400 x 500 mm, Rum ah Pompa Cor Beton K300 slump 12, tanpa fly ash
Start: Fri 27/10/23 ID: 58
Finish: Sat 11/11/23 Dur: 14 days
Res:

Pembesian Uli r Balok Korbel


Start: Fri 27/10/23 ID: 59
Finish: Sat 11/11/23 Dur: 14 days
Res:

Bekisting Balok B1 Uk. 250 x 350 mm, Tr iplex tebal 15 mm (elv.


Bal+5.40)
ok B1 Uk.
(2x 250
Pakai)
x 350 mm, Cor Beton K300 slump 12, tanpa fly ash (elv. +5.40)
Start: Fri 27/10/23 ID: 60 Start: Fri 27/10/23 ID: 61
Finish: Mon 20/11/23D ur: 21 days Finish: Mon 20/11/23 Dur: 21 da ys
Res: Res:

Pembesian Ulir Balok B1 Uk. 250 x 350 mm, (elv. +5.40)


Start: Fri 27/10/23 ID: 62
Finish: Mon 20/11/23
Dur: 21 da ys
Res:

Bekisting Pl at Topian tebal 100 m m, Rumah Pompa Expose Triplex tebal 15 mm (elv. +5.40) (2x Pakai)
Start: Fri 27/10/23 ID: 63
Finish: Mon 20/11/23Dur: 21 da ys
Res:

Plat Topian tebal 100 mm, Rumah Pompa Cor Beton K300 sl ump 12, tanpa fly ash (el v. +5.40)
Start: Fri 27/10/23 ID: 64
Finish: Mon 20/11/23Dur: 21 da ys
Res:

Pembesian Wir emesh M8, Plat Topian tebal 100 mm, (elv. +5.40)
Start: Fri 27/10/23 ID: 65
Finish: Mon 20/11/23Dur: 21 da ys
Res:

Pembesian Uli r Dinding Kolam, (s/d elv. +5.40)


Start: Mon 25/09/23ID: 41
Finish: Thu 26/10/23Dur: 28 days
Res:

Handling Spun Pile dia. 30 cm


Start: Mon 07/08/23ID: 30
Finish: Thu 07/09/23Dur: 28 days
Res:

Pekerjaan Penyangga Pipa Penyangga Pipa Tebal 80 cm, Cor Beton K300 slump 12, tanpaBekisting
fly ash Penyangga Pipa Triplex tebal 15 mm (2x Pakai)
Start: Fri 15/12/23 ID: 90 Start: Fri 15/12/23 ID: 91 Start: Fri 15/12/23 ID: 92
Finish: Fri 22/12/23Dur: 7 days Finish: Fri 22/12/23 Dur: 7 days Finish: Fri 22/12/23 Dur: 7 days
Comp: 0% Res: Res:

Pembesian Ulir Penyangg a Pipa


Start: Fri 15/12/23 ID: 93
Finish: Fri 22/12/23 Dur: 7 days
Res:

Pekerjaan Crossing Box Culvert Precast Uk. 1.50m x 1.50m


Bongkaran Crossing Eksisting Cerucuk Dolken dia. 10cm Panjang 2 m, Dipasang Zig Zag perPasir
30 cmUrug tebal 10 cm
Start: Thu 19/10/23ID: 94 Start: Thu 19/10/23ID: 95 Start: Tue 24/10/23 ID: 96 Start: Fri 27/10/23 ID: 97
Finish: Fri 03/11/23Dur: 14 days Finish: Mon 23/10/23
Dur: 4 days Finish: Thu 26/10/23Dur: 3 days Finish: Fri 27/10/23 Dur: 1 day
Comp: 0% Res: Res: Res:

Lantai kerja tebal 5 cm Box Culvert Precast Uk. 1.50m x 1.50m x 1.00m Mutu Beton K-350
Perbaikan Berem/Bahu Jalan Lapis Aspal Tebal 5 cm
Start: Fri 27/10/23 ID: 98 Start: Sat 28/10/23 ID: 99 Start: Thu 02/11/23ID: 100 Start: Fri 03/11/23 ID: 101
Finish: Fri 27/10/23 Dur: 1 day Finish: Wed 01/11/23Dur: 4 days Finish: Thu 02/11/23Dur: 1 day Finish: Fri 03/11/23 Dur: 1 day
Res: Res: Res: Res:

PEKERJAAN ARSITEKTUR Artisektur Rumah Pompa Pasangan Bata Rumah Pompa, Tebal 1/2 Bata, Campuran Spesi
Pekerjaan
(1 PC 3 PP)
Plesteran
(elv. +5.40
Ruangs/d
Pompa
+12.70) Pekerjaan Acian Ruang Pompa Pekerjaan Pengecatan Tembok Baru (1 Lapis Plamir , 1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
Start: Fri 27/10/23 ID: 102 Start: Fri 27/10/23 ID: 103 Start: Fri 27/10/23 ID: 104 Start: Sat 04/11/23 ID: 105 Start: Sat 04/11/23 ID: 106 Start: Thu 07/12/23ID: 107
Finish: Fri 22/12/23Dur: 49 day s Finish: Fri 22/12/23Dur: 49 days Finish: Tue 28/11/23Dur: 28 days Finish: Wed 06/12/23 Dur: 28 da ys Finish: Wed 06/12/23Dur: 28 da ys Finish: Fri 22/12/23 Dur: 14 days
Comp: 0% Comp: 0% Res: Res: Res: Res:

Pekerjaan Keramik Lantai 40 x 40 cm


Start: Thu 07/12/23ID: 108
Finish: Fri 22/12/23 Dur: 14 days
Res:

Pintu P1 Rangka Real Atas Besi+Roda, Daun Pintu Besi Plat, Engsel Kupu-Kupu, Uk . 305 cm x 260 cm
Start: Thu 07/12/23ID: 109
Finish: Thu 14/12/23Dur: 7 days
Res:

Pintu P3 Rangka Kusen Alumini um Warna Cokl at, Daun Pintu Aluminium warna Coklat +Multiplek, Uk. 205 cm x 90 cm
Start: Thu 07/12/23ID: 110
Finish: Thu 14/12/23Dur: 7 days
Res:

Jendela J1 Rangka Kusen All uminium Warna Putih, Daun Pintu Kaca Polos 5mm, Uk. 125 cm x 140 cm
Start: Thu 07/12/23ID: 111
Finish: Thu 14/12/23Dur: 7 days
Res:

Boven Light BV Rangka Kusen Hollow 5x10, Kaca Jalusi, Uk. 100 cm x 50 cm
Start: Thu 07/12/23ID: 112
Finish: Thu 14/12/23Dur: 7 days
Res:

Arsitektur Rumah Genset dan Rumah Trafo Pasangan Bata Rumah Genset & Rumah Trafo, Tebal 1/2 Bata,
Pekerjaan
Campuran
Plesteran
Spesi (1Rumah
PC 3 PP)
Genset
(elv. +5.40
& Rumah
s/d +9.70)
Trafo Pekerjaan Acian Rumah Genset & Rumah Trafo Pekerjaan Pengecatan Tembok Baru Rumah Genset & Rumah Trafo (1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
Start: Tue 21/11/23ID: 113 Start: T ue 21/11/23ID: 114 Start: Wed 29/11/23ID: 115 Start: Thu 07/12/23ID: 116 Start: Thu 07/12/23ID: 117
Finish: Thu 14/12/23
Dur: 21 days Finish: Tue 28/11/23Dur: 7 days Finish: Wed 06/12/23
Dur: 7 days Finish: Thu 14/12/23Dur: 7 days Finish: Thu 14/12/23Dur: 7 days
Comp: 0% Res: Res: Res: Res:

Pintu P2 Rangka Rel Atas Besi+Roda, Daun Pintu Besi Plat, Engsel Kupu-Kupu, Uk. 260 cm x 260 cm
Start: Thu 07/12/23ID: 118
Finish: Thu 14/12/23Dur: 7 days
Res:

Boven Light BV Rangka Kusen Hollow 5x10, Kaca Jalusi, Uk. 100 cm x 50 cm
Start: Thu 07/12/23ID: 119
Finish: Thu 14/12/23Dur: 7 days
Res:

PEKERJAAN MEKANIKAL DAN ELEKTRIKAL Pekerjaan Penerangan Rumah Pompa Instalansi Penerangan Lampu TL LED (V-Shape) 2 x 18 Watt (termasuk kap TL Waterproof)
Start: Mo n 09/10/23
ID: 120 Start: Thu 07/12/23ID: 121 Start: T hu 07/12/23ID: 126 Start: Fri 15/12/23 ID: 122
Finish: Fri 22/12/23Dur: 65 day s Finish: Fri 22/12/23Dur: 14 days Finish: Thu 14/12/23Dur: 7 days Finish: Fri 22/12/23 Dur: 7 days
Comp: 0% Comp: 0% Res: Res:

Pengadaan dan Pemasangan Saklar Double


Start: Fri 15/12/23 ID: 123
Finish: Fri 22/12/23 Dur: 7 days
Res:

Pengadaan dan Pemasangan Stop kontak 3 Phase


Start: Fri 15/12/23 ID: 124
Finish: Fri 22/12/23 Dur: 7 days
Res:

Lampu LED 13 Watt


Start: Fri 15/12/23 ID: 125
Finish: Fri 22/12/23 Dur: 7 days
Res:

Pekerjaan Penerangan Rumah Genset Instalansi Penerangan Lampu TL LED (V-Shape) 2 x 18 Watt (termasuk kap TL Waterproof)
Start: Thu 07/12/23ID: 127 Start: T hu 07/12/23ID: 132 Start: Fri 15/12/23 ID: 128
Finish: Fri 22/12/23Dur: 14 days Finish: Thu 14/12/23Dur: 7 days Finish: Fri 22/12/23 Dur: 7 days
Comp: 0% Res: Res:

Pengadaan dan Pemasangan Saklar Tunggal


Start: Fri 15/12/23 ID: 129
Finish: Fri 22/12/23 Dur: 7 days
Res:

Pengadaan dan Pemasangan Saklar Double


Start: Fri 15/12/23 ID: 130
Finish: Fri 22/12/23 Dur: 7 days
Res:

Pengadaan dan Pemasangan Stop kontak 3 Phase


Start: Fri 15/12/23 ID: 131
Finish: Fri 22/12/23 Dur: 7 days
Res:

Pekerjaan Panel Biaya Penyambungan PLN, leng kap dengan accessori es dan meter
Pengadaan
ing (Termasuk
dan Pemasangan
Uang Jaminan
Kabel&NYY
Bea4Cx240
Materai)
mm2 (from Genset)
Pengadaan
(Kabelmetal)
dan Pemasangan Kabel NYY 4Cx150 mm2 (from PLN)
Pengadaan
(Kabel metal)
dan Pemasangan Kabel NYY 4Cx95 mm2 (from PLN) (Kabelmetal)
Start: Mon 09/10/23
ID: 133 Start: Mon 09/10/23ID: 139 Start: Thu 02/11/23ID: 136 Start: Thu 02/11/23ID: 137 Start: Thu 02/11/23ID: 138
Finish: Sat 25/11/23Dur: 42 days Finish: Fri 17/11/23 Dur: 35 days Finish: Fri 17/11/23 Dur: 14 days Finish: Fri 17/11/23 Dur: 14 days Finish: Fri 17/11/23 Dur: 14 days
Comp: 0% Res: Res: Res: Res:

Pengadaan dan Pemasangan Panel Hubung dan Kelengkapannya - MCCB 3P/500A - MCCB 3P/200A - MCCB 3P/40A - MCCB 4x1P/10A - Pilot Lamp & Push Button - Fuse Pi ntu - Power Meter
Start: Sat 18/11/23 ID: 134
Finish: Sat 25/11/23 Dur: 7 days
Res:

Pengadaan dan Pemasangan Panel Chang e Over Switch (COS) dan Kelengkapannya - MCCB 3P/500A - COS 4P/500A - Pilot Lamp & Illum. Push Button - Fuse Pintu - Power Meter
Start: Sat 18/11/23 ID: 135
Finish: Sat 25/11/23 Dur: 7 days
Res:

- Kapasitas Daya (Daya tersambung di atas 197 kVA s.d. 1 MVA)


Start: Fri 10/11/23 ID: 140
Finish: Fri 17/11/23 Dur: 7 days
Res:

Batas Atas Bi aya Pemerik saan dan Pengujian Kubikel dan Jaringan
Start: Fri 10/11/23 ID: 141
Finish: Fri 17/11/23 Dur: 7 days
Res:

Pekerjaan Mekanikal dan Elektrikal Saringan Sampah Pengadaan dan Perakitan Saringan Sampah Manual Pengadaan dan Perakitan Stop Log
Start: Fri 27/10/23 ID: 142 Start: Fri 27/10/23 ID: 143 Start: T ue 21/11/23ID: 144
Finish: Wed 06/12/23
Dur: 35 days Finish: Wed 06/12/23D ur: 35 days Finish: Wed 06/12/23Dur: 14 da ys
Comp: 0% Res: Res:

Pekerjaan Electric al Hoist Crane Pengadaan dan Pemasangan Electric Hoist Crane, Ex. DEMAG- Balok runway IWF 300 x 150 x 6,5 9 - Rail track besi as - Balok gir der IWF 350 x 175 x 7 x 11
Start: Mon 13/11/23
ID: 145 Start: Mon 13/11/23ID: 146 Start: Tue 21/11/23 ID: 147 Start: Tue 21/11/23 ID: 148 Start: Tue 21/11/23 ID: 149
Finish: Thu 14/12/23
Dur: 28 days Finish: Thu 14/12/23Dur: 28 days Finish: Wed 06/12/23Dur: 14 days Finish: Wed 06/12/23Dur: 14 days Finish: Wed 06/12/23Dur: 14 days
Comp: 0% Res: Res: Res: Res:

Pekerjaan Penangkal Petir Pengadaan dan Pemasangan Penangkal Petir Radius 25 Meter
Start: Mon 13/11/23
ID: 150 Start: Mon 13/11/23ID: 151
Finish: Mon 20/11/23
Dur: 7 days Finish: Mon 20/11/23Dur: 7 days
Comp: 0% Res:

PEKERJAAN INSTALASI ROOF DRAIN PVC 75 mm


Start: Fri 15/12/23 ID: 152 Start: Fri 15/12/23 ID: 153
Finish: Fri 22/12/23Dur: 7 days Finish: Fri 22/12/23 Dur: 7 days
Comp: 0% Res:

SISTEM MANAJEMEN KESELAMATAN DAN KESEHATAN KERJA (SMK3) Papan Informasi K3 Triplek 1,22 x 2,44 cm @1 Lembar Lapis Ster
Poster
oform
Kegiatan
digantung,
Proyek
Paku Dinding dan Asesori s Lainnya
Start: Mo n 19/06/23
ID: 154 Start: Mon 19/06/23ID: 157 Start: Tue 27/06/23 ID: 156
Finish: Wed 27/12/23
Dur: 165 days? Finish: Mon 26/06/23
Dur: 7 days Finish: Tue 04/07/23Dur: 7 days
Comp: 0% Res: Res:

Spanduk (Banner) Informasi Kegi atan Proyek 4x1 m


Start: Tue 27/06/23 ID: 155
Finish: Tue 04/07/23Dur: 7 days
Res:

Tali Kesel amatan (Safety Belt)


Start: Tue 27/06/23 ID: 158
Finish: Fri 22/12/23 Dur: 154 days
Res:

Pelindung Jatuh, Size M 32-38


Start: Tue 27/06/23 ID: 159
Finish: Fri 22/12/23 Dur: 154 days
Res:

Helm Pelindung + Tali Dagu (Helmet S afety)


Start: Tue 27/06/23 ID: 160
Finish: Fri 22/12/23 Dur: 154 days
Res:

Pelindung Mata (Kaca Mata Anti UV)


Start: Tue 27/06/23 ID: 161
Finish: Fri 22/12/23 Dur: 154 days
Res:

Tameng Muka Kedok Las (Welding Helmet)


Start: Tue 27/06/23 ID: 162
Finish: Fri 22/12/23 Dur: 154 days
Res:

Pelindung Pernafasan dan Mulut (Masker Biasa)


Start: Tue 27/06/23 ID: 163
Finish: Fri 22/12/23 Dur: 154 days
Res:

Sar ung Tangan Pemadam


Start: Tue 27/06/23 ID: 164
Finish: Fri 22/12/23 Dur: 154 days
Res:

Sepatu Tahan Benturan


Start: Tue 27/06/23 ID: 165
Finish: Fri 22/12/23 Dur: 154 days
Res:

Penujang Seluruh Tubuh, Full Body Harness


Start: Tue 27/06/23 ID: 166
Finish: Fri 22/12/23 Dur: 154 days
Res:

Rompi Polyester Double List


Start: Tue 27/06/23 ID: 167
Finish: Fri 22/12/23 Dur: 154 days
Res:

Peralatan P3K Kotak P3, Tandu, Tabung Oksigen, Obat Luka, Perban, dan Lainnya
Start: Tue 27/06/23 ID: 168
Finish: Fri 22/12/23 Dur: 154 days
Res:

Pembuatan Rambu-Rambu Bahan Akrilik dicat, dituli s dengan Peri ngatan Rambu
Start: Tue 27/06/23 ID: 169
Finish: Fri 22/12/23 Dur: 154 days
Res:

Bendera K3 Bahan Dril l


Start: Tue 27/06/23 ID: 170
Finish: Fri 22/12/23 Dur: 154 days
Res:

Safety Str ipe Tape


Start: Tue 27/06/23 ID: 171
Finish: Fri 22/12/23 Dur: 154 days
Res:

SERAH TERIMA PEKERJAA


Start: Sat 23/12/23 ID: 172
Finish: Wed 27/12/23Dur: 4 days
Res:

Page 1