NETWORK PLANING

PEMBANGUNAN BALAI KENDARAAN BERMOTOR


PEMBANGUNAN BALAI KEN PEKERJAAN PERSIAPAN
Start: 23/05/18 ID: 1 Start: 23/05/18 ID: 2
Finish: 30/11/18 Dur: 138 days Finish: 31/05/18 Dur: 7 days
Comp: 0% Res:

PEKERJAAN PEMBANGUNA PEKERJAAN TANAH


Start: 24/05/18 ID: 3 Start: 24/05/18 ID: 4
Finish: 26/06/18 Dur: 24 days Finish: 01/06/18 Dur: 7 days
Comp: 0% Res:

PEKERJAAN PONDASI PEKERJAAN ATAP


Start: 28/05/18 ID: 5 Start: 01/06/18 ID: 7
Finish: 31/05/18 Dur: 4 days Finish: 20/06/18 Dur: 14 days
Res: Res:

PEKERJAAN PLAFOND DAN PEKERJAAN PENUTUP LANT


Start: 01/06/18 ID: 9 Start: 01/06/18 ID: 10
Finish: 08/06/18 Dur: 6 days Finish: 19/06/18 Dur: 13 days
Res: Res:

PEKERJAAN PENGECATAN PEKERJAAN LAIN-LAIN


Start: 01/06/18 ID: 11 Start: 21/06/18 ID: 14
Finish: 20/06/18 Dur: 14 days Finish: 26/06/18 Dur: 4 days
Res: Res:

PEKERJAAN SANITERI DAN


Start: 01/06/18 ID: 12
Finish: 05/06/18 Dur: 3 days
Res:

PEKERJAAN ELEKTRIKAL
Start: 01/06/18 ID: 13
Finish: 08/06/18 Dur: 6 days
Res:

PEKERJAAN PASANGAN DIN PEKERJAAN KUSEN, PINTU,


Start: 29/05/18 ID: 6 Start: 31/05/18 ID: 8
Finish: 01/06/18 Dur: 4 days Finish: 06/06/18 Dur: 5 days
Res: Res:

PEKERJAAN PEMBANGUNA PEKERJAAN TANAH PEKERJAAN PONDASI PEKERJAAN BETON BERTU PEKERJAAN PASANGAN DA PEKERJAAN KUSEN, PINTU,
Start: 24/05/18 ID: 15 Start: 24/05/18 ID: 16 Start: 31/05/18 ID: 17 Start: 19/06/18 ID: 19 Start: 24/07/18 ID: 18 Start: 28/08/18 ID: 21
Finish: 30/11/18 Dur: 137 days Finish: 12/06/18 Dur: 14 days Finish: 18/06/18 Dur: 13 days Finish: 04/09/18 Dur: 56 days Finish: 24/09/18 Dur: 45 days Finish: 27/09/18 Dur: 23 days
Comp: 0% Res: Res: Res: Res: Res:

PEKERJAAN PENGECATAN PEKERJAAN LAIN-LAIN


Start: 25/09/18 ID: 24 Start: 13/11/18 ID: 27
Finish: 12/11/18 Dur: 35 days Finish: 20/11/18 Dur: 6 days
Res: Res:

PEKERJAAN ATAP PEKERJAAN PLAFOND DAN PEKERJAAN PENUTUP LANT PEKERJAAN SANITERI DAN
Start: 05/09/18 ID: 20 Start: 15/10/18 ID: 22 Start: 18/10/18 ID: 23 Start: 18/10/18 ID: 25
Finish: 12/10/18 Dur: 28 days Finish: 09/11/18 Dur: 20 days Finish: 15/11/18 Dur: 21 days Finish: 02/11/18 Dur: 12 days
Res: Res: Res: Res:

PEKERJAAN MEKANIKAL EL
Start: 15/10/18 ID: 26
Finish: 30/11/18 Dur: 35 days
Res:

PEKERJAAN PERBAIKAN BA PEKERJAAN PASANGAN DA PEKERJAAN PERBAIKAN PI PEKERJAAN PEMBUATAN R PEKERJAAN PENGECATAN PEKERJAAAN LAIN-LAIN
Start: 02/08/18 ID: 28 Start: 02/08/18 ID: 29 Start: 08/08/18 ID: 30 Start: 04/09/18 ID: 31 Start: 09/10/18 ID: 32 Start: 24/10/18 ID: 33
Finish: 30/10/18 Dur: 64 days Finish: 04/09/18 Dur: 24 days Finish: 03/09/18 Dur: 19 days Finish: 22/10/18 Dur: 35 days Finish: 23/10/18 Dur: 11 days Finish: 30/10/18 Dur: 5 days
Comp: 0% Res: Res: Res: Res: Res:

PT. KARYA BUMI INDAH


NETWORK PLANING
PEMBANGUNAN BALAI KENDARAAN BERMOTOR

Project: Project1 Critical Noncritical Critical Milestone Milestone Critical Summary Summary Critical Inserted Inserted Critical Marked Marked Critical External External Project Summary Highlighted Critical Highlighted Noncritical
Date: Fri 04/05/18

PT. KARYA BUMI INDAH