ID Task Name Duration Start Finish Resource Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr

Resource Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 20
Names Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
1 Pembangunan Pabrik Jamu 335 days 04 Dec '17 18 Mar '19
2 Administrasi 40 days 04 Dec '17 29 Jan '18 A
3 Dokumen Lahan 10 days 04 Dec '17 15 Dec '17
4 Izin Usaha 10 days 04 Dec '17 15 Dec '17 A01 04/12 15/12
5 Pajak 10 days 04 Dec '17 15 Dec '17 A02 04/12 15/12
6 AMDAL 30 days 18 Dec '17 29 Jan '18
7 Desain Konstruksi AMDAL 15 days 18 Dec '17 08 Jan '18 A03 18/12 08/01
8 Pengelolaan Limbah 15 days 09 Jan '18 29 Jan '18 A04 09/01 29/01
9 Detail Engineering Design 65 days 18 Dec '17 19 Mar '18 B
10 Proses dan Layout Pabrik 65 days 18 Dec '17 19 Mar '18
11 Civil Drawing 25 days 18 Dec '17 22 Jan '18 B01 18/12 22/01
12 Architectural Drawing 20 days 30 Jan '18 26 Feb '18 B02 30/01 26/02
13 Structural Drawing 25 days 18 Dec '17 22 Jan '18 B03 18/12 22/01
14 Mechanical Drawing 20 days 23 Jan '18 19 Feb '18 B04 23/01 19/02
15 HVAC Drawing 20 days 23 Jan '18 19 Feb '18 B05 23/01 19/02
16 Plumbing Drawing 15 days 20 Feb '18 12 Mar '18 B06 20/02 12/03
17 Instrumentation Drawing 15 days 27 Feb '18 19 Mar '18 B07 27/02 19/03
18 Electrical Drawing 15 days 27 Feb '18 19 Mar '18 B08 27/02 19/03
19 HSE Plan 30 days 30 Jan '18 12 Mar '18 B09 30/01 12/03
20 Persiapan Lahan 35 days 20 Feb '18 09 Apr '18 C
21 Pembelian Lahan 15 days 20 Feb '18 12 Mar '18 C01 20/02 12/03
22 Kontrak dengan Kontraktor 20 days 13 Mar '18 09 Apr '18 C02 13/03 09/04
23 Konstruksi 195 days 10 Apr '18 07 Jan '19 D
24 Pondasi 30 days 10 Apr '18 21 May '18 D01 10/04 21/05
25 Dinding 30 days 22 May '18 02 Jul '18 D02 22/05 02/07
26 Eksterior 35 days 03 Jul '18 20 Aug '18 D03 03/07 20/08
27 Utilitas 35 days 21 Aug '18 08 Oct '18 D04 21/08 08/10
28 Struktur 20 days 09 Oct '18 05 Nov '18 D05 09/10 05/11
29 Atap 20 days 06 Nov '18 03 Dec '18 D06 06/11 03/12
30 Interior 20 days 06 Nov '18 03 Dec '18 D07 06/11 03/12
31 Finishing 65 days 09 Oct '18 07 Jan '19
32 Plester dan Pengacian 30 days 09 Oct '18 19 Nov '18 D08 09/10 19/11
33 Pengecatan 20 days 20 Nov '18 17 Dec '18 D09 20/11 17/12
34 Pemasangan Asesoris 15 days 18 Dec '18 07 Jan '19 D10 18/12 07/01

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: project 2
Progress Rolled Up Milestone Group By Summary
Date: 06 Dec '17
Milestone Rolled Up Progress Deadline
Summary Split

Page 1
ID Task Name Duration Start Finish Resource Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 20
Names Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
35 Instalasi Peralatan 40 days 08 Jan '19 04 Mar '19
36 Belt Conveyor 10 days 08 Jan '19 21 Jan '19 E01 08/01 21/01
37 Scaling Machine 10 days 08 Jan '19 21 Jan '19 E02 08/01 21/01
38 Washing and Peeling Machine 10 days 22 Jan '19 04 Feb '19 E03 22/01 04/02
39 Crusher 10 days 22 Jan '19 04 Feb '19 E04 22/01 04/02
40 Extractor& Mixing Machine 10 days 22 Jan '19 04 Feb '19 E05 22/01 04/02
41 Gravity Filtration 10 days 05 Feb '19 18 Feb '19 E06 05/02 18/02
42 Evaporation Tank 10 days 05 Feb '19 18 Feb '19 E07 05/02 18/02
43 Filling Machine 10 days 19 Feb '19 04 Mar '19 E08 19/02 04/03
44 Water pump 10 days 19 Feb '19 04 Mar '19 309 19/02 04/03
45 Chemical pump 10 days 19 Feb '19 04 Mar '19 E10 19/02 04/03
46 Comissioning dan Testing 5 days 05 Mar '19 11 Mar '19 F 05/03 11/03
47 Start-up Production 5 days 12 Mar '19 18 Mar '19 G 12/03 18/03

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: project 2
Progress Rolled Up Milestone Group By Summary
Date: 06 Dec '17
Milestone Rolled Up Progress Deadline
Summary Split

Page 2