NETWORK PLANNING PEMBANGUNAN GEDUNG HALL BELADIRI UNIV.

NASIONAL YOGYAKARTA
PROYEK PEMBANGUNAN GEDUNG HALL OLAHRAGA PEKERJAAN PERSIAPAN Pembersihan lahan awal dan akhir Air dan listrik kerja Papan nama proyek
Start: Thu 04/05/23ID: 1 Start: Thu 04/05/23ID: 2 Start: 04/05/23 ID: 3 Start: 05/05/23 ID: 4 Start: 06/05/23 ID: 8
Finish: Sat 30/09/23Dur: 150 days Finish: Sat 20/05/23Dur: 17 days Finish: 30/09/23 Dur: 42 days Finish: 07/05/23 Dur: 3 days Finish: 06/05/23 Dur: 1 day
Comp: 0% Comp: 0% Res: Res: Res:

Pengukuran dan pemasangan bouwplank Pagar proyek sementara (Sewa) Gudang bahan ( Sewa )
Start: 08/05/23 ID: 5 Start: 08/05/23 ID: 9 Start: 09/05/23 ID: 7
Finish: 11/05/23 Dur: 4 days Finish: 11/05/23 Dur: 4 days Finish: 11/05/23 Dur: 3 days
Res: Res: Res:

Kantor sementara/ Direksi keet ( Sewa )


Start: 09/05/23 ID: 6
Finish: 10/05/23 Dur: 2 days
Res:

Sistem Manajemen Keselamatan dan Kesehatan Kerja


Start: 04/05/23 ID: 10
Finish: 20/05/23 Dur: 17 days
Res:

PEKERJAAN SALURAN KELILING Saluran keliling dengan menggunakan U-Ditch :


Start: Thu 11/05/23ID: 11 Start: 11/05/23 ID: 12
Finish: Thu 18/05/23Dur: 8 days Finish: 18/05/23 Dur: 8 days
Comp: 0% Res:

PEKERJAAN STRUKTUR Galian pondasi Footplat F1 + Cyclope CY+Pair urug Urugan Cyclop+Pondasi Cyclop Urugan Kembali + Pemadatan bekas galian Pembuatan Foot plate Urugan tanah peninggian peil bangunan+Pemadatan
Start: Fri 12/05/23 ID: 13 Start: 12/05/23 ID: 14 Start: 15/05/23 ID: 15 Start: 29/05/23 ID: 16 Start: 22/05/23 ID: 17 Start: 29/05/23 ID: 18
Finish: Sat 30/09/23Dur: 142 days Finish: 19/05/23 Dur: 8 days Finish: 01/06/23 Dur: 18 days Finish: 29/05/23 Dur: 1 day Finish: 01/06/23 Dur: 11 days Finish: 02/07/23 Dur: 35 days
Comp: 0% Res: Res: Res: Res: Res:

Pek. Galian tanah Lantai 1 + Pondasi Pas. Batu Pek. Sloof Lt. 1
Start: 12/05/23 ID: 19 Start: 29/05/23 ID: 20
Finish: 28/05/23 Dur: 17 days Finish: 12/06/23 Dur: 15 days
Res: Res:

Pek. Kolom Lt. 1 Pek. Plat Beton elev. -0.05 Pek. Tangga Lt. 1
Start: 06/06/23 ID: 21 Start: 02/07/23 ID: 22 Start: 10/07/23 ID: 23
Finish: 05/07/23 Dur: 30 days Finish: 05/07/23 Dur: 4 days Finish: 13/07/23 Dur: 4 days
Res: Res: Res:

Pek. BALOK ELV. +1.900 DAN +3.35


Start: 28/06/23 ID: 24
Finish: 06/07/23 Dur: 9 days
Res:

Pek. Dinding Beton Lt. 1


Start: 27/06/23 ID: 25
Finish: 05/07/23 Dur: 9 days
Res:

Pek. Kolom Lt. 2


Start: 31/07/23 ID: 26
Finish: 20/08/23 Dur: 21 days
Res:

Pek. Plat Beton lt. 2


Start: 31/07/23 ID: 27
Finish: 15/08/23 Dur: 16 days
Res:

Pek. Balok Lt. 2


Start: 04/08/23 ID: 28
Finish: 02/09/23 Dur: 30 days
Res:

Pek. Tribun
Start: 31/07/23 ID: 29
Finish: 18/08/23 Dur: 19 days
Res:

Pek. Atap + Penutup Atap


Start: 12/09/23 ID: 30
Finish: 30/09/23 Dur: 19 days
Res:

PEKERJAAN ARSITEKTUR LANTAI 01 - Pek. Beton Kolom dan balok Praktis Lt. 2
Start: Tue 13/06/23ID: 31 Start: Tue 13/06/23ID: 32 Start: 22/08/23 ID: 34
Finish: Sat 30/09/23Dur: 110 days Finish: Sat 30/09/23Dur: 110 days Finish: 02/09/23 Dur: 12 days
Comp: 0% Comp: 0% Res:

- Pek. Beton Kolom dan balok Praktis Lt. atap


Start: 11/09/23 ID: 35
Finish: 16/09/23 Dur: 6 days
Res:

- Pek. Pas. Dinding Bata Ringan Lt. 1 - Pek. Beton Kolom dan balok Praktis Lt. 1
Start: 13/06/23 ID: 36 Start: 03/07/23 ID: 33
Finish: 06/07/23 Dur: 24 days Finish: 25/07/23 Dur: 23 days
Res: Res:

- Pek. Plesteran + Acian Dinding Lt. 1 Pintu + Jendela+Kusen+Louvre, tipe PU (51 unit)
Start: 03/07/23 ID: 37 Start: 24/07/23 ID: 40
Finish: 06/08/23 Dur: 35 days Finish: 20/08/23 Dur: 28 days
Res: Res:

Homogeneous tile, uk. 600 x 600 mm (polished) - Lantai 1 Railing Tangga Tipe A, B dan Ramp Difable
Start: 24/07/23 ID: 41 Start: 15/08/23 ID: 44
Finish: 12/08/23 Dur: 20 days Finish: 30/09/23 Dur: 47 days
Res: Res:

Plafond Lantai 1
Start: 08/08/23 ID: 42
Finish: 13/08/23 Dur: 6 days
Res:

Pek. Pengecatan
Start: 19/09/23 ID: 43
Finish: 28/09/23 Dur: 10 days
Res:

- Pek. Plesteran + Acian Beton struktur Lt. 1


Start: 08/08/23 ID: 38
Finish: 12/08/23 Dur: 5 days
Res:

- Pek. Cement filler plat beton ekspose Lt. 1


Start: 08/08/23 ID: 39
Finish: 09/08/23 Dur: 2 days
Res:

LANTAI 02 Pasangan dinding bata ringan Plesteran dinding bata ringan Acian dinding bata ringan Louvre, Kusen Alumunium dan Jalusi Alumnium (28 unit)
Start: Fri 21/07/23 ID: 45 Start: 21/07/23 ID: 46 Start: 09/08/23 ID: 47 Start: 27/08/23 ID: 48 Start: 05/09/23 ID: 50
Finish: Thu 28/09/23Dur: 70 days Finish: 12/08/23 Dur: 23 days Finish: 28/08/23 Dur: 20 days Finish: 10/09/23 Dur: 15 days Finish: 25/09/23 Dur: 21 days
Comp: 0% Res: Res: Res: Res:

Homogeneous tile, uk. 600 x 600 mm (polished) - Lantai 2


Start: 12/09/23 ID: 51
Finish: 26/09/23 Dur: 15 days
Res:

Plafond Lantai 2
Start: 19/09/23 ID: 52
Finish: 20/09/23 Dur: 2 days
Res:

Pekerjaan Pengecatan
Start: 19/09/23 ID: 53
Finish: 28/09/23 Dur: 10 days
Res:

Plesteran + acian beton struktur


Start: 05/09/23 ID: 49
Finish: 10/09/23 Dur: 6 days
Res:

LANTAI 03 Pasangan dinding bata ringan Plesteran dinding bata ringan Acian dinding bata ringan Louvre (46 unit)
Start: Mon 11/09/23
ID: 54 Start: 11/09/23 ID: 55 Start: 14/09/23 ID: 56 Start: 17/09/23 ID: 57 Start: 19/09/23 ID: 60
Finish: Sat 30/09/23Dur: 20 days Finish: 13/09/23 Dur: 3 days Finish: 16/09/23 Dur: 3 days Finish: 18/09/23 Dur: 2 days Finish: 30/09/23 Dur: 12 days
Comp: 0% Res: Res: Res: Res:

Plafond Lantai Atap


Start: 18/09/23 ID: 61
Finish: 18/09/23 Dur: 1 day
Res:

Pekerjaan Pengecatan
Start: 26/09/23 ID: 62
Finish: 30/09/23 Dur: 5 days
Res:

Plesteran + acian beton struktur Screeding


Start: 12/09/23 ID: 58 Start: 19/09/23 ID: 59
Finish: 19/09/23 Dur: 8 days Finish: 24/09/23 Dur: 6 days
Res: Res:

Perkuatan Plafond
Start: 12/09/23 ID: 63
Finish: 16/09/23 Dur: 5 days
Res:

PEKERJAAN FASADE
Start: Tue 29/08/23ID: 64
Finish: Sat 30/09/23Dur: 33 days
Comp: 0%

PEKERJAAN CERMIN
Start: Tue 19/09/23ID: 170
Finish: Sat 30/09/23Dur: 12 days
Comp: 0%

PEKERJAAN ELEKTRIKAL
Start: Sat 24/06/23 ID: 177
Finish: Fri 18/08/23 Dur: 56 days
Comp: 0%

PEKERJAAN MEKANIKAL
Start: Mon 15/05/23
ID: 356
Finish: Mon 11/09/23
Dur: 120 days
Comp: 0%

PEKERJAAN LANDSCAPE
Start: Mon 28/08/23
ID: 571
Finish: Sat 30/09/23Dur: 34 days

Page 1
NETWORK PLANNING PEMBANGUNAN GEDUNG HALL BELADIRI UNIV. NASIONAL YOGYAKARTA
Comp: 0%

Page 2
NETWORK PLANNING PEMBANGUNAN GEDUNG HALL BELADIRI UNIV. NASIONAL YOGYAKARTA

Project: msproj11 Critical Noncritical Critical Milestone Milestone Critical Summary Summary Critical Inserted Inserted Critical Marked Marked Critical External External Project Summary Highlighted Critical Highlighted Noncritical
Date: Mon 01/05/23

Page 3