Direksi Keet/sewa
Start: Mon 02/ 01/23ID : 4
Finish: Mon 09/01/23Dur: 6 days
Res:
Perlengkapan P3k
Start: Mon 02/ 01/23ID : 5
Finish: Mon 02/01/23Dur: 1 day
Res:
PEKERJAAN TANAH PEKERJAAN GALIAN Galian Tanah Pondasi Tapak Galian Tanah Pondasi Menerus
Start: 04/01/23 I D: 9 Start: 04/01/23 I D: 10 Start: Wed 04/01/23ID: 11 Start: Tue 10/01/23 ID: 12
Finish: 22/02/23 Dur: 36 days Finish: 13/01/23 Dur: 8 days Finish: Mon 09/01/23Dur: 4 days Finish: Fri 13/01 /23 Dur: 4 days
Comp: 0% Comp: 0% Res: Res:
PEKERJAAN TIMBUNAN Urugan Kembali Beka s Galian Timbunan Tanah Dibawah Lantai Pasir Urugan dibaw ah Lantai
Start: 16/01/23 I D: 13 Start: Wed 01/02/23ID: 14 Start: Tue 07/02/23 ID: 17 Start: Mon 20/02/23ID: 16
Finish: 22/02/23 Dur: 28 days Finish: Mon 06/02/23Dur: 4 days Finish: Fri 17/02 /23 Dur: 9 days Finish: We d 22/02/23Dur: 3 days
Comp: 0% Res: Res: Res:
PEKERJAAN PONDASI TAPAK BETON BERTULANG Lantai Kerja Pondasi Tapak Setempa t ( K. 175)
Start: 10/01/23 I D: 20 Start: Tue 10/01/23 ID: 21
Finish: 21/03/23 Dur: 51 days Finish: Tue 10/01/23 Dur: 1 day
Comp: 0% Res:
Pekerjaan Beton Bertulang Pondasi Tap ak Pembesian Bekisting Cor Beton K 250
Start: 11/01/23 I D: 22 Start: Wed 11/01/23ID: 24 Start: Wed 18/01/23ID: 25 Start: Fri 20/01/23 ID: 23
Finish: 23/01/23 Dur: 9 days Finish: Tue 17/01/23 Dur: 5 days Finish: Thu 19/0 1/23 Dur: 2 days Finish: Mon 23/01/23Dur: 2 days
Comp: 0% Res: Res: Res:
Pekerjaan Pondasi Menerus Anstamping / Pasanga n Batu Kosong Tebal 10 Cm Pasangan Pondasi Batu Gunung 1 PC : 4 PS
Start: 24/01/23 I D: 26 Start: Tue 24/01/23 ID: 27 Start: Thu 26/01/23 ID: 28
Finish: 30/01/23 Dur: 5 days Finish: We d 25/01/23Dur: 2 days Finish: Mon 30/01/23Dur: 3 days
Comp: 0% Res: Res:
Ring Balok Uk. 15/20 Elevasi ± 3.45 m Pembesian Bekisting Cor Beton K 175
Start: 28/02/23 I D: 53 Start: Tue 28/02/23 ID: 54 Start: Wed 01/03/23ID: 55 Start: Thu 02/03/23 ID: 56
Finish: 02/03/23 Dur: 3 days Finish: Tue 28/02/23 Dur: 1 day Finish: We d 01/03/23Dur: 1 day Finish: Thu 02/0 3/23 Dur: 1 day
Comp: 0% Res: Res: Res:
Plat Tangga dan Plat Bordes Tebal 10cm Pembesian Bekisting Cor Beton K 250
Start: 17/03/23 I D: 57 Start: Fri 17/03/23 ID: 58 Start: Mon 20/03/23ID: 59 Start: Tue 21/03/23 ID: 60
Finish: 21/03/23 Dur: 3 days Finish: Fri 17/03 /23 Dur: 1 day Finish: Mon 20/03/23Dur: 1 day Finish: Tue 21/03/23 Dur: 1 day
Comp: 0% Res: Res: Res:
Ring Balok Uk. 25/40 Elevasi ± 7.50 m Pembesian Bekisting Cor Beton K 250
Start: 11/04/23 I D: 74 Start: Tue 11/04/23 ID: 75 Start: Thu 13/04/23 ID: 76 Start: Mon 17/04/23ID: 77
Finish: 18/04/23 Dur: 6 days Finish: We d 12/04/23Dur: 2 days Finish: Fri 14/04 /23 Dur: 2 days Finish: Tue 18/04/23 Dur: 2 days
Comp: 0% Res: Res: Res:
Ring Balok Uk. 15/20 Elevasi ±7.5 m Pembesian Bekisting Cor Beton K 175
Start: 11/04/23 I D: 78 Start: Tue 11/04/23 ID: 79 Start: Wed 12/04/23ID: 80 Start: Thu 13/04/23 ID: 81
Finish: 13/04/23 Dur: 3 days Finish: Tue 11/04/23 Dur: 1 day Finish: We d 12/04/23Dur: 1 day Finish: Thu 13/0 4/23 Dur: 1 day
Comp: 0% Res: Res: Res:
Plat dak dan Talang Beton Pembesian Bekisting Cor Beton K 250
Start: 19/04/23 I D: 86 Start: Wed 19/04/23ID: 87 Start: Thu 20/04/23 ID: 88 Start: Fri 21/04/23 ID: 89
Finish: 21/04/23 Dur: 3 days Finish: We d 19/04/23Dur: 1 day Finish: Thu 20/0 4/23 Dur: 1 day Finish: Fri 21/04 /23 Dur: 1 day
Comp: 0% Res: Res: Res:
PEKERJAAN ATAP Rangka kuda -kuda dan gording baja ringan Multytruss
Start: 24/04/23 I D: 90 Start: Mon 24/04/23ID: 91
Finish: 03/05/23 Dur: 8 days Finish: We d 03/05/23Dur: 8 days
Comp: 0% Res:
PEKERJAAN ARSITEKTUR LANTAI 1 Pekerjaan Dinding Pasangan Trasram Bata 1 PC : 2 PP Pasangan Dinding Bata 1 PC : 4 PP
Start: 17/02/23 I D: 92 Start: 17/02/23 I D: 93 Start: 17/02/23 I D: 94 Start: Fri 17/02/23 ID: 95 Start: Mon 20/02/23ID: 96
Finish: 20/06/23 Dur: 88 days Finish: 17/04/23 Dur: 42 days Finish: 14/03/23 Dur: 18 days Finish: Fri 17/02 /23 Dur: 1 day Finish: Mon 27/02/23Dur: 6 days
Comp: 0% Comp: 0% Comp: 0% Res: Res:
Plesteran Trasram Bata 1 PC : 2 PP Plesteran Dinding Bata 1PC : 4 PP Pesangan Batu Alam Tempel Susun Sirih + cat Vernis Batu Alam
Start: Mon 27/02/23ID: 97 Start: Tue 28/02/23 ID: 98 Start: Mon 13/03/23ID: 100
Finish: Mon 27/02/23Dur: 1 day Finish: Fri 10/03 /23 Dur: 9 days Finish: Tue 14/03/23 Dur: 2 days
Res: Res: Res:
Plasteran Beton 1 PC : 3 PP
Start: Tue 28/02/23 ID: 99
Finish: We d 08/03/23Dur: 7 days
Res:
Pekerjaan Lantai Granite 60 x 60 Cm (Halus) Pekerjaan Lantai Granite 60 x 60 Cm (Kasar) Pekerjaan Lantai Kera mik untuk Ruangan Wc/Km 20 X 20 CmPasangan Dinding Keramik KM/WC 20 x 25 cm
Start: Fri 17/03/23 ID: 103 Start: Fri 24/03/23 ID: 104 Start: Wed 29/03/23ID: 105 Start: Thu 30/03/23 ID: 106
Finish: Thu 23/0 3/23 Dur: 5 days Finish: Tue 28/03/23 Dur: 3 days Finish: We d 29/03/23Dur: 1 day Finish: Fri 31/03 /23 Dur: 2 days
Res: Res: Res: Res:
Pekerjaan Pintu, Jendela, Ventilasi Pintu Pane l Kaca Tempere d Glass 12mm + Aksesoris Lengka p Terpasang (Type P1)
Start: 23/02/23 I D: 107 Start: Fri 14/04/23 ID: 108
Finish: 17/04/23 Dur: 38 days Finish: Fri 14/04 /23 Dur: 1 day
Comp: 0% Res:
Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Le ngkap T erpasang Sesuai Gambar ( Type P2)
Start: Fri 14/04/23 ID: 109
Finish: Mon 17/04/23Dur: 2 days
Res:
Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Le ngkap T erpasang Sesuai Gambar ( Type P5)
Start: Thu 23/02/23 ID: 110
Finish: Thu 23/0 2/23 Dur: 1 day
Res:
Kusen UPVC + Daun Pintu UPVC+ Aksesoris Lengkap Terpasang Sesuai Gambar (Type P4)
Start: Fri 14/04/23 ID: 111
Finish: Fri 14/04 /23 Dur: 1 day
Res:
Kusen UPVC + Daun Pintu UPVC+ Aksesoris Lengkap Terpasang Sesuai Gambar (Type P3)
Start: Fri 14/04/23 ID: 112
Finish: Fri 14/04 /23 Dur: 1 day
Res:
Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm + Akse soris Lengkap Terpasang Sesuai Gambar (Type JV1)
Start: Fri 14/04/23 ID: 113
Finish: Mon 17/04/23Dur: 2 days
Res:
Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm + Akse soris Lengkap Terpasang Sesuai Gambar (Type J2)
Start: Thu 23/02/23 ID: 114
Finish: Thu 23/0 2/23 Dur: 1 day
Res:
Kusen UPVC + Daun ventilasi Kaca 5mm + Aksesoris Lengkap Terpasang Sesuai Gambar (Type V2)
Start: Fri 14/04/23 ID: 115
Finish: Fri 14/04 /23 Dur: 1 day
Res:
Pekerjaan Plafond Pasang Plafon PVC/Fiber + Rangka + Aksesoris Lengkap T erpasang Sesuai Gambar
Start: 13/03/23 I D: 116 Start: Mon 13/03/23ID: 117
Finish: 16/03/23 Dur: 4 days Finish: Thu 16/0 3/23 Dur: 4 days
Comp: 0% Res:
Pekerjaan Peng ecatan Pengecatan T embok dan Sealer 3x(L/D) Setara Vinilex
Start: 03/04/23 I D: 118 Start: Mon 03/04/23ID: 119
Finish: 06/04/23 Dur: 4 days Finish: Thu 06/0 4/23 Dur: 4 days
Comp: 0% Res:
Pesangan Batu Alam Tempel Susun Sirih + cat Vernis Batu Alam
Start: Thu 25/05/23 ID: 127
Finish: Fri 26/05 /23 Dur: 2 days
Res:
Pekerjaan Lantai Granite 60 x 60 Cm (Halus) Pekerjaan Lantai Kera mik untuk Ruangan Wc/Km 20 X 20 CmPasangan Dinding Keramik KM/WC 20 x 25 cm
Start: Tue 30/05/23 ID: 130 Start: Tue 06/06/23 ID: 131 Start: Wed 07/06/23ID: 132
Finish: Mon 05/06/23Dur: 5 days Finish: Tue 06/06/23 Dur: 1 day Finish: We d 07/06/23Dur: 1 day
Res: Res: Res:
PEKERJAAN ATAP Penutup Atap genteng Onduline Rabung genteng Onduline Lisplank Kayu 2/20 cm
Start: 04/05/23 I D: 140 Start: Thu 04/05/23 ID: 141 Start: Thu 11/05/23 ID: 142 Start: Mon 15/05/23ID: 143
Finish: 17/05/23 Dur: 10 days Finish: We d 10/05/23Dur: 5 days Finish: Fri 12/05 /23 Dur: 2 days Finish: We d 17/05/23Dur: 3 days
Comp: 0% Res: Res: Res:
Pekerjaan Plafond Pasang Plafon PVC/Fiber + Rangka + Aksesoris Lengkap T erpasang Sesuai Gambar
Start: 25/05/23 I D: 144 Start: Thu 25/05/23 ID: 145
Finish: 29/05/23 Dur: 3 days Finish: Mon 29/05/23Dur: 3 days
Comp: 0% Res:
PEKERJAAN ELEKTRIKAL Instlasi titik penerangan, instala si termasuk ka bel NYA 2,5 mm dalam pipa PVC fitting la mpu dan kelengkapan instalasi terpasang
Start: 07/04/23 I D: 148 Start: Fri 07/04/23 ID: 149
Finish: 19/06/23 Dur: 52 days Finish: Fri 07/04 /23 Dur: 1 day
Comp: 0% Res:
Instalasi titik Stop kontak, instalasi termasuk kabel NYA 2,5 mm dalam pipa PVC fitting lampu dan kelengkapan instalasi terpasang
Start: Fri 07/04/23 ID: 150
Finish: Fri 07/04 /23 Dur: 1 day
Res:
LANTAI 1 Armatur Lampu Downlight 23 watt + Accesori Lengka p Terpasang Lampu RM T L 2X36 watt + Accesori Lengkap Terpasang
Start: 10/04/23 I D: 153 Start: 10/04/23 I D: 154 Start: Mon 10/04/23ID: 155 Start: Tue 11/04/23 ID: 156
Finish: 13/04/23 Dur: 4 days Finish: 11/04/23 Dur: 2 days Finish: Mon 10/04/23Dur: 1 day Finish: Tue 11/04/23 Dur: 1 day
Comp: 0% Comp: 0% Res: Res:
LANTAI 2 Armatur
Start: 14/06/23 I D: 161 Start: 14/06/23 I D: 162
Finish: 19/06/23 Dur: 4 days Finish: 15/06/23 Dur: 2 days
Comp: 0% Comp: 0%
INSTALASI AIR BERSIH Memasang Wastafel + Keran Air + Pe mbungan Air Type Sifon angsa Aksesoris Lengkap Terpasang Setara Toto
Start: 24/02/23 I D: 181 Start: Mon 03/04/23ID: 182
Finish: 03/04/23 Dur: 27 days Finish: Mon 03/04/23Dur: 1 day
Comp: 0% Res:
INSTALASI KOTORAN Pipa SNI 3 Inch AW Septick Tank + Resapan Lengkap Terpa sang
Start: 31/01/23 I D: 187 Start: Tue 31/01/23 ID: 188 Start: Wed 01/02/23ID: 189
Finish: 30/03/23 Dur: 43 days Finish: Tue 31/01/23 Dur: 1 day Finish: We d 01/02/23Dur: 1 day
Comp: 0% Res: Res:
Page 1
PEKERJAAN FINISHING PEKERJAAN BESI, ALUMUNIUM, ORNAMEN DAN DIND ING COMPOSITE
Start: 05/07/23 I D: 207 Start: 05/07/23 I D: 208
Finish: 18/07/23 Dur: 10 days Finish: 11/07/23 Dur: 5 days
Comp: 0% Comp: 0%
Pekerjan Po t Bunga
Start: 12/07/23 I D: 215
Finish: 17/07/23 Dur: 4 days
Comp: 0%
Page 2
Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Le ngkap T erpasang Sesuai Gambar ( Type P2)
Start: Tue 20/06/23 ID: 134
Finish: Tue 20/06/23 Dur: 1 day
Res:
Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Le ngkap T erpasang Sesuai Gambar ( Type P5)
Start: Tue 20/06/23 ID: 135
Finish: Tue 20/06/23 Dur: 1 day
Res:
Kusen UPVC + Daun Pintu UPVC+ Aksesoris Lengkap Terpasang Sesuai Gambar (Type P4)
Start: Tue 20/06/23 ID: 136
Finish: Tue 20/06/23 Dur: 1 day
Res:
Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm + Akse soris Lengkap Terpasang Sesuai Gambar (Type JV1)
Start: Tue 20/06/23 ID: 137
Finish: Tue 20/06/23 Dur: 1 day
Res:
Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm + Akse soris Lengkap Terpasang Sesuai Gambar (Type J2)
Start: Tue 20/06/23 ID: 138
Finish: Tue 20/06/23 Dur: 1 day
Res:
Kusen UPVC + Daun ventilasi Kaca 5mm + Aksesoris Lengkap Terpasang Sesuai Gambar (Type V2)
Start: Tue 20/06/23 ID: 139
Finish: Tue 20/06/23 Dur: 1 day
Res:
Lampu Downlight 23 watt + Accesori Lengka p Terpasang Lampu RM T L 2X36 watt + Accesori Lengkap Terpasang
Start: Wed 14/06/23ID: 163 Start: Thu 15/06/23 ID: 164
Finish: We d 14/06/23Dur: 1 day Finish: Thu 15/0 6/23 Dur: 1 day
Res: Res:
Pasangan Bata Dinding Saluran 1 PC : 2 PP Pasangan Pla steran Bata Dinding Saluran 1 PC : 2 PP Cor Lantai Saluran Buis Beton Dia. 20 cm Pemasangan Grill Saluran Bentuk Sesuai Gambar + Cat Meni Hitam
Start: Wed 21/06/23ID: 171 Start: Fri 23/06/23 ID: 172 Start: Tue 27/06/23 ID: 173 Start: Thu 29/06/23 ID: 174 Start: Mon 03/07/23ID: 175
Finish: Thu 22/0 6/23 Dur: 2 days Finish: Mon 26/06/23Dur: 2 days Finish: We d 28/06/23Dur: 2 days Finish: Fri 30/06 /23 Dur: 2 days Finish: Tue 04/07/23 Dur: 2 days
Res: Res: Res: Res: Res:
Pasang Flordrain
Start: Thu 08/06/23 ID: 201
Finish: Thu 08/0 6/23 Dur: 1 day
Res:
Page 3
Pekerjaan Almunium Composite Panel Setara Seven Type PVD
Huruf
F + Rangka
Timbul +Gedung
Aksesoris
IGDLengkap
+ Akse soris
TerpaLengkap
sang Sesuai
Terpasa
Ga mbar
ng Sesuai Gamba r (Bahan Stainless)
Start: Wed 05/07/23ID: 209 Start: Mon 10/07/23ID: 210
Finish: Fri 07/07 /23 Dur: 3 days Finish: Tue 11/07/23 Dur: 2 days
Res: Res:
Huruf Timbul Gedung Utama + Aksesoris Lengkap Terpasang Sesuai Gambar (Bahan Stainless)
Start: Mon 10/07/23ID: 211
Finish: Tue 11/07/23 Dur: 2 days
Res:
Logo Puskesmas + Aksesoris Lengkap T erpasang Sesuai Gambar (Bahan Stainle ss)
Start: Mon 10/07/23ID: 212
Finish: Tue 11/07/23 Dur: 2 days
Res:
Pembersihan Akhir
Start: Tue 18/07/23 ID: 220
Finish: Tue 18/07/23 Dur: 1 day
Res:
Page 4
Project: Pembanguna n Gedung Critical Noncritical Critical Milest one Milest one Critical Summary Summar y Critical Inserted Inserted Critical Marked Marked Critical Ext ernal Ext er nal Project Summary Highlighted C rit ical Highlighted Noncr itical
Date: Mon 15/ 05/23
Page 5