Pembangunan Gedung IGD Puskesmas Blangpidie PEKERJAAN PERSIAPAN Papan Nama Proyek Uk.

90 x120 Administrasi/Dokumentasi dan Pelaporan


Start: 02/01/23 I D: 0 Start: 02/01/23 I D: 1 Start: Mon 02/ 01/23ID : 2 Start: Mon 02/ 01/23ID : 3
Finish: 18/07/23 Dur: 142 days Finish: 09/01/23 Dur: 6 days Finish: Mon 02/01/23Dur: 1 day Finish: Mon 02/01/23Dur: 1 day
Comp: 0% Comp: 0% Res: Res:

Direksi Keet/sewa
Start: Mon 02/ 01/23ID : 4
Finish: Mon 09/01/23Dur: 6 days
Res:

Perlengkapan P3k
Start: Mon 02/ 01/23ID : 5
Finish: Mon 02/01/23Dur: 1 day
Res:

Pengukuran dan Pemasangan Bouwpla nk


Start: Mon 02/ 01/23ID : 6
Finish: Tue 03/01/23 Dur: 2 days
Res:

Pekerjaan Kesehatan dan Keselamatan Kerja


Start: Mon 02/ 01/23ID : 7
Finish: Mon 02/01/23Dur: 1 day
Res:

Pagar pelindung proyek


Start: Mon 02/ 01/23ID : 8
Finish: Tue 03/01/23 Dur: 2 days
Res:

PEKERJAAN TANAH PEKERJAAN GALIAN Galian Tanah Pondasi Tapak Galian Tanah Pondasi Menerus
Start: 04/01/23 I D: 9 Start: 04/01/23 I D: 10 Start: Wed 04/01/23ID: 11 Start: Tue 10/01/23 ID: 12
Finish: 22/02/23 Dur: 36 days Finish: 13/01/23 Dur: 8 days Finish: Mon 09/01/23Dur: 4 days Finish: Fri 13/01 /23 Dur: 4 days
Comp: 0% Comp: 0% Res: Res:

PEKERJAAN TIMBUNAN Urugan Kembali Beka s Galian Timbunan Tanah Dibawah Lantai Pasir Urugan dibaw ah Lantai
Start: 16/01/23 I D: 13 Start: Wed 01/02/23ID: 14 Start: Tue 07/02/23 ID: 17 Start: Mon 20/02/23ID: 16
Finish: 22/02/23 Dur: 28 days Finish: Mon 06/02/23Dur: 4 days Finish: Fri 17/02 /23 Dur: 9 days Finish: We d 22/02/23Dur: 3 days
Comp: 0% Res: Res: Res:

Pasir Urugan Bawah Pondasi Menerus


Start: Mon 16/01/23ID: 15
Finish: Fri 20/01 /23 Dur: 5 days
Res:

PEKERJAAN STRUKTUR LANTAI 1


Start: 02/01/23 I D: 18 Start: Mon 02/ 01/23ID : 19
Finish: 03/05/23 Dur: 88 days Finish: Mon 02/01/23Dur: 1 day
Comp: 0% Res:

PEKERJAAN PONDASI TAPAK BETON BERTULANG Lantai Kerja Pondasi Tapak Setempa t ( K. 175)
Start: 10/01/23 I D: 20 Start: Tue 10/01/23 ID: 21
Finish: 21/03/23 Dur: 51 days Finish: Tue 10/01/23 Dur: 1 day
Comp: 0% Res:

Pekerjaan Beton Bertulang Pondasi Tap ak Pembesian Bekisting Cor Beton K 250
Start: 11/01/23 I D: 22 Start: Wed 11/01/23ID: 24 Start: Wed 18/01/23ID: 25 Start: Fri 20/01/23 ID: 23
Finish: 23/01/23 Dur: 9 days Finish: Tue 17/01/23 Dur: 5 days Finish: Thu 19/0 1/23 Dur: 2 days Finish: Mon 23/01/23Dur: 2 days
Comp: 0% Res: Res: Res:

Pekerjaan Pondasi Menerus Anstamping / Pasanga n Batu Kosong Tebal 10 Cm Pasangan Pondasi Batu Gunung 1 PC : 4 PS
Start: 24/01/23 I D: 26 Start: Tue 24/01/23 ID: 27 Start: Thu 26/01/23 ID: 28
Finish: 30/01/23 Dur: 5 days Finish: We d 25/01/23Dur: 2 days Finish: Mon 30/01/23Dur: 3 days
Comp: 0% Res: Res:

Sloof (30/40) Pembesian Bekisting Cor Beton K 250


Start: 31/01/23 I D: 29 Start: Tue 31/01/23 ID: 30 Start: Thu 02/02/23 ID: 31 Start: Tue 07/02/23 ID: 32
Finish: 08/02/23 Dur: 7 days Finish: We d 01/02/23Dur: 2 days Finish: Mon 06/02/23Dur: 3 days Finish: We d 08/02/23Dur: 2 days
Comp: 0% Res: Res: Res:

Sloof (15/20) Pembesian Bekisting Cor Beton K 175


Start: 31/01/23 I D: 33 Start: Tue 31/01/23 ID: 34 Start: Wed 01/02/23ID: 35 Start: Thu 02/02/23 ID: 36
Finish: 02/02/23 Dur: 3 days Finish: Tue 31/01/23 Dur: 1 day Finish: We d 01/02/23Dur: 1 day Finish: Thu 02/0 2/23 Dur: 1 day
Comp: 0% Res: Res: Res:

Kolom Uk. 30/40 Pembesian Bekisting Cor Beton K 250


Start: 09/02/23 I D: 37 Start: Thu 09/02/23 ID: 38 Start: Mon 13/02/23ID: 39 Start: Wed 15/02/23ID: 40
Finish: 16/02/23 Dur: 6 days Finish: Fri 10/02 /23 Dur: 2 days Finish: Tue 14/02/23 Dur: 2 days Finish: Thu 16/0 2/23 Dur: 2 days
Comp: 0% Res: Res: Res:

Kolom Uk. 15/15 Pembesian Bekisting Cor Beton K 175


Start: 17/02/23 I D: 41 Start: Fri 17/02/23 ID: 42 Start: Mon 20/02/23ID: 43 Start: Tue 21/02/23 ID: 44
Finish: 21/02/23 Dur: 3 days Finish: Fri 17/02 /23 Dur: 1 day Finish: Mon 20/02/23Dur: 1 day Finish: Tue 21/02/23 Dur: 1 day
Comp: 0% Res: Res: Res:

Balok Latai ( 13/13) Elevasi ± 2.23 m Bekisting Pembesian


Start: 28/02/23 I D: 45 Start: Tue 28/02/23 ID: 47 Start: Thu 02/03/23 ID: 46
Finish: 02/03/23 Dur: 3 days Finish: We d 01/03/23Dur: 2 days Finish: Thu 02/0 3/23 Dur: 1 day
Comp: 0% Res: Res:

Cor Beton K 175


Start: Thu 02/03/23 ID: 48
Finish: Thu 02/0 3/23 Dur: 1 day
Res:

Balok Uk. 25/40 Elevasi ± 3.45 m Pembesian


Start: 28/02/23 I D: 49 Start: Tue 28/02/23 ID: 50
Finish: 06/03/23 Dur: 5 days Finish: We d 01/03/23Dur: 2 days
Comp: 0% Res:

Bekisting Cor Beton K 250


Start: Wed 01/03/23ID: 51 Start: Fri 03/03/23 ID: 52
Finish: Thu 02/0 3/23 Dur: 2 days Finish: Mon 06/03/23Dur: 2 days
Res: Res:

Ring Balok Uk. 15/20 Elevasi ± 3.45 m Pembesian Bekisting Cor Beton K 175
Start: 28/02/23 I D: 53 Start: Tue 28/02/23 ID: 54 Start: Wed 01/03/23ID: 55 Start: Thu 02/03/23 ID: 56
Finish: 02/03/23 Dur: 3 days Finish: Tue 28/02/23 Dur: 1 day Finish: We d 01/03/23Dur: 1 day Finish: Thu 02/0 3/23 Dur: 1 day
Comp: 0% Res: Res: Res:

Plat Tangga dan Plat Bordes Tebal 10cm Pembesian Bekisting Cor Beton K 250
Start: 17/03/23 I D: 57 Start: Fri 17/03/23 ID: 58 Start: Mon 20/03/23ID: 59 Start: Tue 21/03/23 ID: 60
Finish: 21/03/23 Dur: 3 days Finish: Fri 17/03 /23 Dur: 1 day Finish: Mon 20/03/23Dur: 1 day Finish: Tue 21/03/23 Dur: 1 day
Comp: 0% Res: Res: Res:

LANTAI 2 Kolom Uk. 30/30 Pembesian Bekisting Cor Beton K 250


Start: 07/03/23 I D: 61 Start: 22/03/23 I D: 62 Start: Wed 22/03/23ID: 63 Start: Fri 24/03/23 ID: 64 Start: Tue 28/03/23 ID: 65
Finish: 03/05/23 Dur: 42 days Finish: 29/03/23 Dur: 6 days Finish: Thu 23/0 3/23 Dur: 2 days Finish: Mon 27/03/23Dur: 2 days Finish: We d 29/03/23Dur: 2 days
Comp: 0% Comp: 0% Res: Res: Res:

Kolom Uk. 15/15 Pembesian Bekisting Cor Beton K 175


Start: 30/03/23 I D: 66 Start: Thu 30/03/23 ID: 67 Start: Fri 31/03/23 ID: 68 Start: Tue 04/04/23 ID: 69
Finish: 04/04/23 Dur: 4 days Finish: Thu 30/0 3/23 Dur: 1 day Finish: Mon 03/04/23Dur: 2 days Finish: Tue 04/04/23 Dur: 1 day
Comp: 0% Res: Res: Res:

Balok Latai ( 13/13) Elevasi ± 6.23 m Pembesian


Start: 11/04/23 I D: 70 Start: Tue 11/04/23 ID: 71
Finish: 12/04/23 Dur: 2 days Finish: Tue 11/04/23 Dur: 1 day
Comp: 0% Res:

Bekisting Cor Beton K 175


Start: Tue 11/04/23 ID: 72 Start: Wed 12/04/23ID: 73
Finish: Tue 11/04/23 Dur: 1 day Finish: We d 12/04/23Dur: 1 day
Res: Res:

Ring Balok Uk. 25/40 Elevasi ± 7.50 m Pembesian Bekisting Cor Beton K 250
Start: 11/04/23 I D: 74 Start: Tue 11/04/23 ID: 75 Start: Thu 13/04/23 ID: 76 Start: Mon 17/04/23ID: 77
Finish: 18/04/23 Dur: 6 days Finish: We d 12/04/23Dur: 2 days Finish: Fri 14/04 /23 Dur: 2 days Finish: Tue 18/04/23 Dur: 2 days
Comp: 0% Res: Res: Res:

Ring Balok Uk. 15/20 Elevasi ±7.5 m Pembesian Bekisting Cor Beton K 175
Start: 11/04/23 I D: 78 Start: Tue 11/04/23 ID: 79 Start: Wed 12/04/23ID: 80 Start: Thu 13/04/23 ID: 81
Finish: 13/04/23 Dur: 3 days Finish: Tue 11/04/23 Dur: 1 day Finish: We d 12/04/23Dur: 1 day Finish: Thu 13/0 4/23 Dur: 1 day
Comp: 0% Res: Res: Res:

Plat Lantai Tebal 12cm Bekisting Pembesian Cor Beton K 250


Start: 07/03/23 I D: 82 Start: Tue 07/03/23 ID: 84 Start: Thu 09/03/23 ID: 83 Start: Wed 15/03/23ID: 85
Finish: 16/03/23 Dur: 8 days Finish: We d 08/03/23Dur: 2 days Finish: Tue 14/03/23 Dur: 4 days Finish: Thu 16/0 3/23 Dur: 2 days
Comp: 0% Res: Res: Res:

Plat dak dan Talang Beton Pembesian Bekisting Cor Beton K 250
Start: 19/04/23 I D: 86 Start: Wed 19/04/23ID: 87 Start: Thu 20/04/23 ID: 88 Start: Fri 21/04/23 ID: 89
Finish: 21/04/23 Dur: 3 days Finish: We d 19/04/23Dur: 1 day Finish: Thu 20/0 4/23 Dur: 1 day Finish: Fri 21/04 /23 Dur: 1 day
Comp: 0% Res: Res: Res:

PEKERJAAN ATAP Rangka kuda -kuda dan gording baja ringan Multytruss
Start: 24/04/23 I D: 90 Start: Mon 24/04/23ID: 91
Finish: 03/05/23 Dur: 8 days Finish: We d 03/05/23Dur: 8 days
Comp: 0% Res:

PEKERJAAN ARSITEKTUR LANTAI 1 Pekerjaan Dinding Pasangan Trasram Bata 1 PC : 2 PP Pasangan Dinding Bata 1 PC : 4 PP
Start: 17/02/23 I D: 92 Start: 17/02/23 I D: 93 Start: 17/02/23 I D: 94 Start: Fri 17/02/23 ID: 95 Start: Mon 20/02/23ID: 96
Finish: 20/06/23 Dur: 88 days Finish: 17/04/23 Dur: 42 days Finish: 14/03/23 Dur: 18 days Finish: Fri 17/02 /23 Dur: 1 day Finish: Mon 27/02/23Dur: 6 days
Comp: 0% Comp: 0% Comp: 0% Res: Res:

Plesteran Trasram Bata 1 PC : 2 PP Plesteran Dinding Bata 1PC : 4 PP Pesangan Batu Alam Tempel Susun Sirih + cat Vernis Batu Alam
Start: Mon 27/02/23ID: 97 Start: Tue 28/02/23 ID: 98 Start: Mon 13/03/23ID: 100
Finish: Mon 27/02/23Dur: 1 day Finish: Fri 10/03 /23 Dur: 9 days Finish: Tue 14/03/23 Dur: 2 days
Res: Res: Res:

Plasteran Beton 1 PC : 3 PP
Start: Tue 28/02/23 ID: 99
Finish: We d 08/03/23Dur: 7 days
Res:

Pekerjaan Lantai Pekerjaan Beton T umbuk Tebal 7 cm (K 125)


Start: 23/02/23 I D: 101 Start: Thu 23/02/23 ID: 102
Finish: 31/03/23 Dur: 27 days Finish: Thu 23/0 2/23 Dur: 1 day
Comp: 0% Res:

Pekerjaan Lantai Granite 60 x 60 Cm (Halus) Pekerjaan Lantai Granite 60 x 60 Cm (Kasar) Pekerjaan Lantai Kera mik untuk Ruangan Wc/Km 20 X 20 CmPasangan Dinding Keramik KM/WC 20 x 25 cm
Start: Fri 17/03/23 ID: 103 Start: Fri 24/03/23 ID: 104 Start: Wed 29/03/23ID: 105 Start: Thu 30/03/23 ID: 106
Finish: Thu 23/0 3/23 Dur: 5 days Finish: Tue 28/03/23 Dur: 3 days Finish: We d 29/03/23Dur: 1 day Finish: Fri 31/03 /23 Dur: 2 days
Res: Res: Res: Res:

Pekerjaan Pintu, Jendela, Ventilasi Pintu Pane l Kaca Tempere d Glass 12mm + Aksesoris Lengka p Terpasang (Type P1)
Start: 23/02/23 I D: 107 Start: Fri 14/04/23 ID: 108
Finish: 17/04/23 Dur: 38 days Finish: Fri 14/04 /23 Dur: 1 day
Comp: 0% Res:

Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Le ngkap T erpasang Sesuai Gambar ( Type P2)
Start: Fri 14/04/23 ID: 109
Finish: Mon 17/04/23Dur: 2 days
Res:

Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Le ngkap T erpasang Sesuai Gambar ( Type P5)
Start: Thu 23/02/23 ID: 110
Finish: Thu 23/0 2/23 Dur: 1 day
Res:

Kusen UPVC + Daun Pintu UPVC+ Aksesoris Lengkap Terpasang Sesuai Gambar (Type P4)
Start: Fri 14/04/23 ID: 111
Finish: Fri 14/04 /23 Dur: 1 day
Res:

Kusen UPVC + Daun Pintu UPVC+ Aksesoris Lengkap Terpasang Sesuai Gambar (Type P3)
Start: Fri 14/04/23 ID: 112
Finish: Fri 14/04 /23 Dur: 1 day
Res:

Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm + Akse soris Lengkap Terpasang Sesuai Gambar (Type JV1)
Start: Fri 14/04/23 ID: 113
Finish: Mon 17/04/23Dur: 2 days
Res:

Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm + Akse soris Lengkap Terpasang Sesuai Gambar (Type J2)
Start: Thu 23/02/23 ID: 114
Finish: Thu 23/0 2/23 Dur: 1 day
Res:

Kusen UPVC + Daun ventilasi Kaca 5mm + Aksesoris Lengkap Terpasang Sesuai Gambar (Type V2)
Start: Fri 14/04/23 ID: 115
Finish: Fri 14/04 /23 Dur: 1 day
Res:

Pekerjaan Plafond Pasang Plafon PVC/Fiber + Rangka + Aksesoris Lengkap T erpasang Sesuai Gambar
Start: 13/03/23 I D: 116 Start: Mon 13/03/23ID: 117
Finish: 16/03/23 Dur: 4 days Finish: Thu 16/0 3/23 Dur: 4 days
Comp: 0% Res:

Pekerjaan Peng ecatan Pengecatan T embok dan Sealer 3x(L/D) Setara Vinilex
Start: 03/04/23 I D: 118 Start: Mon 03/04/23ID: 119
Finish: 06/04/23 Dur: 4 days Finish: Thu 06/0 4/23 Dur: 4 days
Comp: 0% Res:

LANTAI 2 Pekerjaan Dinding Pasangan Trasram Bata 1 PC : 2 PP Pasangan Dinding Bata 1 PC : 4 PP


Start: 30/03/23 I D: 120 Start: 30/03/23 I D: 121 Start: Thu 30/03/23 ID: 122 Start: Mon 03/04/23ID: 123
Finish: 20/06/23 Dur: 59 days Finish: 29/05/23 Dur: 43 days Finish: Fri 31/03 /23 Dur: 2 days Finish: Mon 10/04/23Dur: 6 days
Comp: 0% Comp: 0% Res: Res:

Plesteran Trasram Bata 1 PC : 2 PP Plesteran Dinding Bata 1PC : 4 PP Plasteran Beton 1 PC : 3 PP


Start: Thu 04/05/23 ID: 124 Start: Fri 05/05/23 ID: 125 Start: Thu 25/05/23 ID: 126
Finish: Thu 04/0 5/23 Dur: 1 day Finish: We d 24/05/23Dur: 14 days Finish: Mon 29/05/23Dur: 3 days
Res: Res: Res:

Pesangan Batu Alam Tempel Susun Sirih + cat Vernis Batu Alam
Start: Thu 25/05/23 ID: 127
Finish: Fri 26/05 /23 Dur: 2 days
Res:

Pekerjaan Lantai Pekerjaan Beton T umbuk Tebal 7 cm (K 125)


Start: 25/05/23 I D: 128 Start: Thu 25/05/23 ID: 129
Finish: 07/06/23 Dur: 10 days Finish: Fri 26/05 /23 Dur: 2 days
Comp: 0% Res:

Pekerjaan Lantai Granite 60 x 60 Cm (Halus) Pekerjaan Lantai Kera mik untuk Ruangan Wc/Km 20 X 20 CmPasangan Dinding Keramik KM/WC 20 x 25 cm
Start: Tue 30/05/23 ID: 130 Start: Tue 06/06/23 ID: 131 Start: Wed 07/06/23ID: 132
Finish: Mon 05/06/23Dur: 5 days Finish: Tue 06/06/23 Dur: 1 day Finish: We d 07/06/23Dur: 1 day
Res: Res: Res:

Pekerjaan Pintu, Jendela, Ventilasi


Start: 20/06/23 I D: 133
Finish: 20/06/23 Dur: 1 day
Comp: 0%

PEKERJAAN ATAP Penutup Atap genteng Onduline Rabung genteng Onduline Lisplank Kayu 2/20 cm
Start: 04/05/23 I D: 140 Start: Thu 04/05/23 ID: 141 Start: Thu 11/05/23 ID: 142 Start: Mon 15/05/23ID: 143
Finish: 17/05/23 Dur: 10 days Finish: We d 10/05/23Dur: 5 days Finish: Fri 12/05 /23 Dur: 2 days Finish: We d 17/05/23Dur: 3 days
Comp: 0% Res: Res: Res:

Pekerjaan Plafond Pasang Plafon PVC/Fiber + Rangka + Aksesoris Lengkap T erpasang Sesuai Gambar
Start: 25/05/23 I D: 144 Start: Thu 25/05/23 ID: 145
Finish: 29/05/23 Dur: 3 days Finish: Mon 29/05/23Dur: 3 days
Comp: 0% Res:

Pekerjaan Peng ecatan


Start: 08/06/23 I D: 146
Finish: 13/06/23 Dur: 4 days
Comp: 0%

PEKERJAAN ELEKTRIKAL Instlasi titik penerangan, instala si termasuk ka bel NYA 2,5 mm dalam pipa PVC fitting la mpu dan kelengkapan instalasi terpasang
Start: 07/04/23 I D: 148 Start: Fri 07/04/23 ID: 149
Finish: 19/06/23 Dur: 52 days Finish: Fri 07/04 /23 Dur: 1 day
Comp: 0% Res:

Instalasi titik Stop kontak, instalasi termasuk kabel NYA 2,5 mm dalam pipa PVC fitting lampu dan kelengkapan instalasi terpasang
Start: Fri 07/04/23 ID: 150
Finish: Fri 07/04 /23 Dur: 1 day
Res:

Pemasangan Box Sekring


Start: Fri 07/04/23 ID: 151
Finish: Fri 07/04 /23 Dur: 1 day
Res:

Pemasukan Arus Listrik 12 Ampere


Start: Fri 07/04/23 ID: 152
Finish: Fri 07/04 /23 Dur: 1 day
Res:

LANTAI 1 Armatur Lampu Downlight 23 watt + Accesori Lengka p Terpasang Lampu RM T L 2X36 watt + Accesori Lengkap Terpasang
Start: 10/04/23 I D: 153 Start: 10/04/23 I D: 154 Start: Mon 10/04/23ID: 155 Start: Tue 11/04/23 ID: 156
Finish: 13/04/23 Dur: 4 days Finish: 11/04/23 Dur: 2 days Finish: Mon 10/04/23Dur: 1 day Finish: Tue 11/04/23 Dur: 1 day
Comp: 0% Comp: 0% Res: Res:

Saklar lampu Merk Setara Broco 2 seri Sakalar 1 Se ri setara Broco


Start: 12/04/23 I D: 157 Start: Wed 12/04/23ID: 158
Finish: 13/04/23 Dur: 2 days Finish: We d 12/04/23Dur: 1 day
Comp: 0% Res:

Sakalar 2 Se ri setara Broco Stop Kontak


Start: Wed 12/04/23ID: 159 Start: Thu 13/04/23 ID: 160
Finish: We d 12/04/23Dur: 1 day Finish: Thu 13/0 4/23 Dur: 1 day
Res: Res:

LANTAI 2 Armatur
Start: 14/06/23 I D: 161 Start: 14/06/23 I D: 162
Finish: 19/06/23 Dur: 4 days Finish: 15/06/23 Dur: 2 days
Comp: 0% Comp: 0%

Saklar lampu Merk Setara Broco 2 seri


Start: 16/06/23 I D: 165
Finish: 19/06/23 Dur: 2 days
Comp: 0%

PEKERJAAN MEKANIKAL PEKERJAAN SALURAN DRAINASE


Start: 02/01/23 I D: 169 Start: 21/06/23 I D: 170
Finish: 04/07/23 Dur: 132 days Finish: 04/07/23 Dur: 10 days
Comp: 0% Comp: 0%

LANTAI 1 Pekerjaan Sanitasi


Start: 02/01/23 I D: 176 Start: Mon 02/ 01/23ID : 177
Finish: 15/05/23 Dur: 96 days Finish: Mon 02/01/23Dur: 1 day
Comp: 0% Res:

INSTALASI AIR KOTOR Pasang Floordrain


Start: 30/03/23 I D: 178 Start: Thu 30/03/23 ID: 179
Finish: 03/04/23 Dur: 3 days Finish: Thu 30/0 3/23 Dur: 1 day
Comp: 0% Res:

Pipa SNI 3 Inch AW


Start: Mon 03/04/23ID: 180
Finish: Mon 03/04/23Dur: 1 day
Res:

INSTALASI AIR BERSIH Memasang Wastafel + Keran Air + Pe mbungan Air Type Sifon angsa Aksesoris Lengkap Terpasang Setara Toto
Start: 24/02/23 I D: 181 Start: Mon 03/04/23ID: 182
Finish: 03/04/23 Dur: 27 days Finish: Mon 03/04/23Dur: 1 day
Comp: 0% Res:

Pipa SNI 1/2 Inch AW


Start: Fri 24/02/23 ID: 183
Finish: Fri 24/02 /23 Dur: 1 day
Res:

Pasang Pipa Air Sampai Ketitik Air


Start: Fri 24/02/23 ID: 184
Finish: Fri 24/02 /23 Dur: 1 day
Res:

INSTALASI AIR HUJAN Pipa SNI 2 1/2 Inch AW


Start: 15/05/23 I D: 185 Start: Mon 15/05/23ID: 186
Finish: 15/05/23 Dur: 1 day Finish: Mon 15/05/23Dur: 1 day
Comp: 0% Res:

INSTALASI KOTORAN Pipa SNI 3 Inch AW Septick Tank + Resapan Lengkap Terpa sang
Start: 31/01/23 I D: 187 Start: Tue 31/01/23 ID: 188 Start: Wed 01/02/23ID: 189
Finish: 30/03/23 Dur: 43 days Finish: Tue 31/01/23 Dur: 1 day Finish: We d 01/02/23Dur: 1 day
Comp: 0% Res: Res:

Pasang Kloset Duduk Setara Toto


Start: Thu 30/03/23 ID: 190
Finish: Thu 30/0 3/23 Dur: 1 day
Res:

LANTAI 2 Pekerjaan Sanitasi


Start: 02/01/23 I D: 191 Start: Mon 02/ 01/23ID : 192
Finish: 08/06/23 Dur: 114 days Finish: Mon 02/01/23Dur: 1 day
Comp: 0% Res:

INSTALASI AIR BERSIH


Start: 13/03/23 I D: 193
Finish: 08/06/23 Dur: 64 days
Comp: 0%

Pasang Kran Air 1/2"


Start: Mon 13/03/23ID: 195
Finish: Mon 13/03/23Dur: 1 day
Res:

Pipa SNI 1 Inch AW


Start: Mon 13/03/23ID: 196
Finish: Mon 13/03/23Dur: 1 day
Res:

Pipa SNI 1/2 Inch AW


Start: Mon 13/03/23ID: 197
Finish: Mon 13/03/23Dur: 1 day
Res:

Pasang Pipa Air Sampai Ketitik Air


Start: Mon 13/03/23ID: 198
Finish: Mon 13/03/23Dur: 1 day
Res:

INSTALASI AIR KOTOR Pipa SNI 3 Inch AW


Start: 13/03/23 I D: 199 Start: Mon 13/03/23ID: 200
Finish: 08/06/23 Dur: 64 days Finish: Mon 13/03/23Dur: 1 day
Comp: 0% Res:

INSTALASI KOTORAN Pipa SNI 3 Inch AW


Start: 15/05/23 I D: 202 Start: Mon 15/05/23ID: 203
Finish: 08/06/23 Dur: 19 days Finish: Mon 15/05/23Dur: 1 day
Comp: 0% Res:

INSTALASI AIR HUJAN Pipa SNI 2 1/2 Inch AW


Start: 15/05/23 I D: 205 Start: Mon 15/05/23ID: 206
Finish: 15/05/23 Dur: 1 day Finish: Mon 15/05/23Dur: 1 day
Comp: 0% Res:

Page 1
PEKERJAAN FINISHING PEKERJAAN BESI, ALUMUNIUM, ORNAMEN DAN DIND ING COMPOSITE
Start: 05/07/23 I D: 207 Start: 05/07/23 I D: 208
Finish: 18/07/23 Dur: 10 days Finish: 11/07/23 Dur: 5 days
Comp: 0% Comp: 0%

Pekerjan Po t Bunga
Start: 12/07/23 I D: 215
Finish: 17/07/23 Dur: 4 days
Comp: 0%

Page 2
Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Le ngkap T erpasang Sesuai Gambar ( Type P2)
Start: Tue 20/06/23 ID: 134
Finish: Tue 20/06/23 Dur: 1 day
Res:

Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Le ngkap T erpasang Sesuai Gambar ( Type P5)
Start: Tue 20/06/23 ID: 135
Finish: Tue 20/06/23 Dur: 1 day
Res:

Kusen UPVC + Daun Pintu UPVC+ Aksesoris Lengkap Terpasang Sesuai Gambar (Type P4)
Start: Tue 20/06/23 ID: 136
Finish: Tue 20/06/23 Dur: 1 day
Res:

Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm + Akse soris Lengkap Terpasang Sesuai Gambar (Type JV1)
Start: Tue 20/06/23 ID: 137
Finish: Tue 20/06/23 Dur: 1 day
Res:

Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm + Akse soris Lengkap Terpasang Sesuai Gambar (Type J2)
Start: Tue 20/06/23 ID: 138
Finish: Tue 20/06/23 Dur: 1 day
Res:

Kusen UPVC + Daun ventilasi Kaca 5mm + Aksesoris Lengkap Terpasang Sesuai Gambar (Type V2)
Start: Tue 20/06/23 ID: 139
Finish: Tue 20/06/23 Dur: 1 day
Res:

Pengecatan T embok dan Sealer 3x(L/D) Setara Vinilex


Start: Thu 08/06/23 ID: 147
Finish: Tue 13/06/23 Dur: 4 days
Res:

Lampu Downlight 23 watt + Accesori Lengka p Terpasang Lampu RM T L 2X36 watt + Accesori Lengkap Terpasang
Start: Wed 14/06/23ID: 163 Start: Thu 15/06/23 ID: 164
Finish: We d 14/06/23Dur: 1 day Finish: Thu 15/0 6/23 Dur: 1 day
Res: Res:

Sakalar 1 Se ri setara Broco


Start: Fri 16/06/23 ID: 166
Finish: Fri 16/06 /23 Dur: 1 day
Res:

Sakalar 2 Se ri setara Broco Stop Kontak


Start: Fri 16/06/23 ID: 167 Start: Mon 19/06/23ID: 168
Finish: Fri 16/06 /23 Dur: 1 day Finish: Mon 19/06/23Dur: 1 day
Res: Res:

Pasangan Bata Dinding Saluran 1 PC : 2 PP Pasangan Pla steran Bata Dinding Saluran 1 PC : 2 PP Cor Lantai Saluran Buis Beton Dia. 20 cm Pemasangan Grill Saluran Bentuk Sesuai Gambar + Cat Meni Hitam
Start: Wed 21/06/23ID: 171 Start: Fri 23/06/23 ID: 172 Start: Tue 27/06/23 ID: 173 Start: Thu 29/06/23 ID: 174 Start: Mon 03/07/23ID: 175
Finish: Thu 22/0 6/23 Dur: 2 days Finish: Mon 26/06/23Dur: 2 days Finish: We d 28/06/23Dur: 2 days Finish: Fri 30/06 /23 Dur: 2 days Finish: Tue 04/07/23 Dur: 2 days
Res: Res: Res: Res: Res:

Bak Mandi Pyber Gla ss (60 x 60)


Start: Thu 08/06/23 ID: 194
Finish: Thu 08/0 6/23 Dur: 1 day
Res:

Pasang Flordrain
Start: Thu 08/06/23 ID: 201
Finish: Thu 08/0 6/23 Dur: 1 day
Res:

Pasang Kloset Jongkok Setara American Standar


Start: Thu 08/06/23 ID: 204
Finish: Thu 08/0 6/23 Dur: 1 day
Res:

Page 3
Pekerjaan Almunium Composite Panel Setara Seven Type PVD
Huruf
F + Rangka
Timbul +Gedung
Aksesoris
IGDLengkap
+ Akse soris
TerpaLengkap
sang Sesuai
Terpasa
Ga mbar
ng Sesuai Gamba r (Bahan Stainless)
Start: Wed 05/07/23ID: 209 Start: Mon 10/07/23ID: 210
Finish: Fri 07/07 /23 Dur: 3 days Finish: Tue 11/07/23 Dur: 2 days
Res: Res:

Huruf Timbul Gedung Utama + Aksesoris Lengkap Terpasang Sesuai Gambar (Bahan Stainless)
Start: Mon 10/07/23ID: 211
Finish: Tue 11/07/23 Dur: 2 days
Res:

Logo Puskesmas + Aksesoris Lengkap T erpasang Sesuai Gambar (Bahan Stainle ss)
Start: Mon 10/07/23ID: 212
Finish: Tue 11/07/23 Dur: 2 days
Res:

Reling T angga Stainless + Aksesoris Lengkap Terpasang Sesuai Gambar


Start: Mon 10/07/23ID: 213
Finish: Tue 11/07/23 Dur: 2 days
Res:

Ha ndrail (Pegangan Tangan) Stainless + Aksesoris Lengkap Terpasang Sesuai Gambar


Start: Mon 10/07/23ID: 214
Finish: Tue 11/07/23 Dur: 2 days
Res:

Pasangan Dinding Bata 1PC : 4 PP Plasteran Dinding Bata 1PC : 4 PP


Start: Wed 12/07/23ID: 216 Start: Fri 14/07/23 ID: 217
Finish: Thu 13/0 7/23 Dur: 2 days Finish: Fri 14/07 /23 Dur: 1 day
Res: Res:

Pesangan Batu Alam Tempel Susun Sirih + Cat Vernis Ba tu Alam


Start: Fri 14/07/23 ID: 218
Finish: Fri 14/07 /23 Dur: 1 day
Res:

Relif Pot Bunga Sesuai Gambar


Start: Fri 14/07/23 ID: 219
Finish: Mon 17/07/23Dur: 2 days
Res:

Pembersihan Akhir
Start: Tue 18/07/23 ID: 220
Finish: Tue 18/07/23 Dur: 1 day
Res:

Page 4
Project: Pembanguna n Gedung Critical Noncritical Critical Milest one Milest one Critical Summary Summar y Critical Inserted Inserted Critical Marked Marked Critical Ext ernal Ext er nal Project Summary Highlighted C rit ical Highlighted Noncr itical