KESEHATAN DAN KESELAMATAN KERJA (K3) KESEHATAN DAN KESELAMATAN KERJA (K3)

Start: Mon 24/05/21ID: 1 Start: 24/05/21 ID: 2


Finish: Thu 30/09/21Dur: 94 days Finish: 30/09/21 Dur: 94 days
Comp: 0% Res: Rp 43.887.270,00

PEKERJAAN STRUKTUR LANTAI 1 PEKERJAAN PERSIAPAN DAN PEMBONGKARAN PEKERJAAN TANAH


Start: Mon 31/05/21ID: 4 Start: Mon 24/05/21ID: 5 Start: 24/05/21 ID: 6 Start: 08/06/21 ID: 7
Finish: Sun 05/09/21Dur: 71 days Finish: Mon 19/07/21Dur: 41 days Finish: 07/06/21 Dur: 11 days Finish: 29/06/21 Dur: 16 days
Comp: 0% Comp: 0% Res: Rp 86.532.915,29 Res: Rp 268.970.930,51

PEKERJAAN PONDASI PEKERJAAN BETON


Start: 08/06/21 ID: 8 Start: 28/06/21 ID: 9
Finish: 06/07/21 Dur: 21 days Finish: 19/07/21 Dur: 16 days
Res: Rp 922.641.080,18 Res: Rp 1.078.535.892,98

LANTAI 2 (ELV. +3,45 m) PEKERJAAN BETON


Start: Fri 09/07/21 ID: 10 Start: 09/07/21 ID: 11
Finish: Fri 30/07/21 Dur: 16 days Finish: 30/07/21 Dur: 16 days
Comp: 0% Res: Rp 908.135.820,71

LANTAI 3(ELV. 6,96 m) PEKERJAAN BETON


Start: Thu 22/07/21 ID: 12 Start: 22/07/21 ID: 13
Finish: Thu 12/08/21Dur: 16 days Finish: 12/08/21 Dur: 16 days
Comp: 0% Res: Rp 847.439.293,18

TOP ROOF (ELV. +10.00 m) PEKERJAAN BETON PEKERJAAN RANGKA ATAP PEKERJAAN PENUTUP ATAP
Start: Wed 04/08/21ID: 14 Start: 04/08/21 ID: 15 Start: 26/08/21 ID: 16 Start: 08/09/21 ID: 17
Finish: Wed 22/09/21Dur: 36 days Finish: 25/08/21 Dur: 16 days Finish: 16/09/21 Dur: 16 days Finish: 22/09/21 Dur: 11 days
Comp: 0% Res: Rp 369.165.669,70 Res: Rp 496.087.041,08 Res: Rp 159.293.516,90

PEKERJAAN ARSITEKTUR LANTAI 1 LANTAI 2 LANTAI 3 TOP ROOF PEKERJAAN FASADE


Start: Mon 26/07/21ID: 19 Start: 26/07/21 ID: 20 Start: 02/08/21 ID: 21 Start: 09/08/21 ID: 22 Start: 09/08/21 ID: 23 Start: 23/08/21 ID: 24
Finish: Thu 30/09/21Dur: 49 days Finish: 12/09/21 Dur: 36 days Finish: 19/09/21 Dur: 36 days Finish: 26/09/21 Dur: 36 days Finish: 26/09/21 Dur: 36 days Finish: 30/09/21 Dur: 29 days
Comp: 0% Res: Rp 913.360.292,08 Res: Rp 737.856.634,35 Res: Rp 770.824.379,19 Res: Rp 103.639.212,37 Res: Rp 1.260.687.008,00

PEKERJAAN MEKANIKAL ATAU ELEKTRIKAL PEKERJAAN ELEKTRIKAL PEKERJAAN PANEL DATA PEKERJAAN KABEL FEEDER
Start: Mon 30/08/21ID: 26 Start: Mon 30/08/21ID: 27 Start: 30/08/21 ID: 28 Start: 09/08/21 ID: 29
Finish: Thu 30/09/21Dur: 24 days Finish: Thu 30/09/21Dur: 24 days Finish: 26/09/21 Dur: 21 days Finish: 12/09/21 Dur: 26 days
Comp: 0% Comp: 0% Res: Rp 192.062.759,00 Res: Rp 89.436.243,44

PEKERJAAN KABEL TRAY & KABEL LADDER LANTAI 1 LANTAI 2 LANTAI 3


Start: Mon 09/08/21ID: 30 Start: 09/08/21 ID: 31 Start: 23/08/21 ID: 32 Start: 30/08/21 ID: 33
Finish: Sun 19/09/21Dur: 30 days Finish: 29/08/21 Dur: 16 days Finish: 12/09/21 Dur: 16 days Finish: 19/09/21 Dur: 16 days
Comp: 0% Res: Rp 24.904.762,08 Res: Rp 24.904.762,08 Res: Rp 24.904.762,08

PEKERJAAN LAMPU PENERANGAN, INSTALASI, SAKLAR, DAN STOP KONTAK LANTAI 1 (PANEL DP-1) LANTAI 2 (PANEL DP-2) LANTAI 3 (PANEL DP-3) LANTAI ATAP (PANEL DP-ATAP)
Start: Mon 09/08/21ID: 34 Start: 09/08/21 ID: 35 Start: 23/08/21 ID: 36 Start: 30/08/21 ID: 37 Start: 06/09/21 ID: 38
Finish: Sun 26/09/21Dur: 35 days Finish: 05/09/21 Dur: 21 days Finish: 19/09/21 Dur: 21 days Finish: 26/09/21 Dur: 21 days Finish: 26/09/21 Dur: 16 days
Comp: 0% Res: Rp 141.109.166,18 Res: Rp 121.674.220,54 Res: Rp 118.403.987,05 Res: Rp 10.251.682,79

PEKERJAAN INSTALASI PENANGKAL PETIR


Start: 13/09/21 ID: 39
Finish: 30/09/21 Dur: 14 days
Res: Rp 19.366.150,83

PEKERJAAN ELEKTRONIK PEKERJAAN FIRE ALARM PEKERJAAN PERALATAN UMUM PEKERJAAN TAFA PEKERJAAN KABEL FEEDER
Start: Fri 13/08/21 ID: 40 Start: Fri 13/08/21 ID: 41 Start: 16/09/21 ID: 42 Start: 22/09/21 ID: 43 Start: 15/09/21 ID: 44
Finish: Wed 06/10/21Dur: 39 days Finish: Wed 06/10/21Dur: 39 days Finish: 30/09/21 Dur: 11 days Finish: 06/10/21 Dur: 11 days Finish: 06/10/21 Dur: 16 days
Comp: 0% Comp: 0% Res: Rp 22.701.548,10 Res: Rp 5.224.464,63 Res: Rp 14.994.796,07

PEKERJAAN INSTALASI FIRE ALARM LANTAI 1 LANTAI 2


Start: Fri 13/08/21 ID: 45 Start: 19/08/21 ID: 46 Start: 13/08/21 ID: 47
Finish: Sun 19/09/21Dur: 26 days Finish: 16/09/21 Dur: 21 days Finish: 03/09/21 Dur: 16 days
Comp: 0% Res: Rp 35.061.743,24 Res: Rp 25.432.125,54

PEKERJAAN SOUND SYSTEM


Start: Mon 23/08/21ID: 50
Finish: Wed 06/10/21Dur: 33 days
Comp: 0%

INSTALASI SOUND SYSTEM


Start: Mon 23/08/21ID: 54
Finish: Wed 06/10/21Dur: 33 days
Comp: 0%

PEKERJAAN MA TV
Start: Mon 30/08/21ID: 58
Finish: Wed 06/10/21Dur: 28 days
Comp: 0%

INSTALASI MA TV
Start: Mon 30/08/21ID: 60
Finish: Tue 21/09/21Dur: 17 days
Comp: 0%

PEKERJAAN DATA KOMPUTER


Start: Mon 16/08/21ID: 64
Finish: Tue 21/09/21Dur: 27 days
Comp: 0%

INSTALASI DATA KOMPUTER


Start: Mon 16/08/21ID: 66
Finish: Fri 17/09/21 Dur: 25 days
Comp: 0%

PEKERJAAN CCTV
Start: Tue 17/08/21 ID: 70
Finish: Sun 26/09/21Dur: 29 days
Comp: 0%

INSTALASI CCTV
Start: Tue 17/08/21 ID: 72
Finish: Sun 26/09/21Dur: 29 days
Comp: 0%

PEKERJAAN MEKANIKAL PEKERJAAN PEMADAM KEBAKARAN


Start: Wed 21/07/21ID: 77 Start: Thu 02/09/21ID: 78
Finish: Thu 07/10/21Dur: 57 days Finish: Wed 06/10/21Dur: 25 days
Comp: 0% Comp: 0%

INSTALASI FIRE EXTINGUISER


Start: Mon 06/09/21ID: 80
Finish: Wed 06/10/21Dur: 23 days
Comp: 0%

PERKERJAAN AIR BERSIH


Start: Fri 13/08/21 ID: 84
Finish: Thu 07/10/21Dur: 40 days
Comp: 0%

INSTALASI PIPA AIR BERSIH


Start: Fri 13/08/21 ID: 87
Finish: Thu 07/10/21Dur: 40 days
Comp: 0%

PEKERJAAN AIR KOTOR, AIR BEKAS, DAN VENT


Start: Wed 21/07/21ID: 92
Finish: Wed 22/09/21Dur: 46 days
Comp: 0%

INSTALASI PIPA AIR KOTOR, AIR BEKAS, DAN VENT


Start: Wed 21/07/21ID: 95
Finish: Wed 22/09/21Dur: 46 days
Comp: 0%

PEKERJAAN AIR HUJAN INSTALASI AIR HUJAN


Start: Thu 05/08/21ID: 99 Start: ID: 100
Finish: Sun 26/09/21Dur: 37 days Finish: Dur:
Comp: 0% Res:

PEKERJAAN AIR CONDITIONING (AC)


Start: ID: 105
Finish: Dur:
Res:

PEKERJAAN UNIT AC
Start: Fri 27/08/21 ID: 106
Finish: Fri 01/10/21 Dur: 26 days
Comp: 0%

PEKERJAAN LIFT
Start: Wed 11/08/21ID: 111
Finish: Mon 27/09/21Dur: 34 days
Comp: 0%

DROP OFF BELAKANG


Start: Mon 02/08/21ID: 113
Finish: Fri 10/09/21 Dur: 30 days
Comp: 0%

Start: ID: 117


Finish: Dur:
Res:

Start: ID: 119


Finish: Dur:
Res:

Start: ID: 121


Finish: Dur:
Res:
LANTAI 3 LANTAI ATAP (PANEL DP-ATAP)
Start: 23/08/21 ID: 48 Start: 06/09/21 ID: 49
Finish: 13/09/21 Dur: 16 days Finish: 19/09/21 Dur: 11 days
Res: Rp 26.123.986,24 Res: Rp 3.102.974,94

PERALATAN UTAMA TERMINAL BOX SOUND SYSTEM KABEL FEEDER


Start: 26/08/21 ID: 51 Start: 03/09/21 ID: 52 Start: 13/09/21 ID: 53
Finish: 09/09/21 Dur: 11 days Finish: 17/09/21 Dur: 11 days Finish: 27/09/21 Dur: 11 days
Res: Rp 24.973.651,50 Res: Rp 1.696.256,10 Res: Rp 2.106.883,35

LANTAI 1 LANTAI 2 LANTAI 3


Start: 23/08/21 ID: 55 Start: 02/09/21 ID: 56 Start: 22/09/21 ID: 57
Finish: 06/09/21 Dur: 11 days Finish: 23/09/21 Dur: 16 days Finish: 06/10/21 Dur: 11 days
Res: Rp 3.835.499,85 Res: Rp 5.332.097,10 Res: Rp 2.537.258,70

PERALATAN UTAMA (HEADED SYSTEM)


Start: 10/09/21 ID: 59
Finish: 06/10/21 Dur: 19 days
Res: Rp 10.327.629,90

LANTAI 1 LANTAI 2 LANTAI 3


Start: 30/08/21 ID: 61 Start: 30/08/21 ID: 62 Start: 31/08/21 ID: 63
Finish: 20/09/21 Dur: 16 days Finish: 19/09/21 Dur: 16 days Finish: 21/09/21 Dur: 16 days
Res: Rp 5.595.594,20 Res: Rp 6.447.255,75 Res: Rp 5.328.796,90

PERALATAN UTAMA
Start: 26/08/21 ID: 65
Finish: 21/09/21 Dur: 19 days
Res: Rp 10.510.500,00

LANTAI 1 LANTAI 2 LANTAI 3


Start: 16/08/21 ID: 67 Start: 27/08/21 ID: 68 Start: 30/08/21 ID: 69
Finish: 05/09/21 Dur: 16 days Finish: 17/09/21 Dur: 16 days Finish: 13/09/21 Dur: 11 days
Res: Rp 18.912.278,75 Res: Rp 21.616.162,75 Res: Rp 17.560.336,75

PERALATAN UTAMA
Start: 27/08/21 ID: 71
Finish: 22/09/21 Dur: 19 days
Res: Rp 23.803.485,30

LANTAI 1 LANTAI 2 LANTAI 3 LANTAI ATAP


Start: 17/08/21 ID: 73 Start: 17/08/21 ID: 74 Start: 24/08/21 ID: 75 Start: 06/09/21 ID: 76
Finish: 07/09/21 Dur: 16 days Finish: 07/09/21 Dur: 16 days Finish: 14/09/21 Dur: 16 days Finish: 26/09/21 Dur: 16 days
Res: Rp 21.802.338,30 Res: Rp 11.170.416,15 Res: Rp 11.170.416,15 Res: Rp 5.555.325,25

PIPA OUTDOOR
Start: 02/09/21 ID: 79
Finish: 23/09/21 Dur: 16 days
Res: Rp 45.662.417,90

LANTAI 1 LANTAI 2 LANTAI 3


Start: 06/09/21 ID: 81 Start: 14/09/21 ID: 82 Start: 24/09/21 ID: 83
Finish: 19/09/21 Dur: 11 days Finish: 28/09/21 Dur: 11 days Finish: 06/10/21 Dur: 9 days
Res: Rp 2.034.310,00 Res: Rp 2.034.310,00 Res: Rp 2.034.310,00

PIPA SITE PLAN PIPA RISER


Start: 01/09/21 ID: 85 Start: 23/08/21 ID: 86
Finish: 22/09/21 Dur: 16 days Finish: 12/09/21 Dur: 16 days
Res: Rp 22.728.417,52 Res: Rp 18.056.489,58

LANTAI 1 LANTAI 2 LANTAI 3


Start: 13/08/21 ID: 88 Start: 20/08/21 ID: 89 Start: 31/08/21 ID: 90
Finish: 10/09/21 Dur: 21 days Finish: 17/09/21 Dur: 21 days Finish: 28/09/21 Dur: 21 days
Res: Rp 30.615.020,62 Res: Rp 57.547.768,52 Res: Rp 44.843.253,58
LANTAI ATAP (PANEL DP-ATAP)
Start: 13/09/21 ID: 91
Finish: 07/10/21 Dur: 19 days
Res: Rp 76.759.089,66

PERALATAN UTAMA PEKERJAAN RISER


Start: 03/08/21 ID: 93 Start: 17/08/21 ID: 94
Finish: 07/09/21 Dur: 26 days Finish: 07/09/21 Dur: 16 days
Res: Rp 219.840.061,00 Res: Rp 8.097.847,35

LANTAI 1 & SITE PLAN LANTAI 2 LANTAI 3


Start: 21/07/21 ID: 96 Start: 16/08/21 ID: 97 Start: 25/08/21 ID: 98
Finish: 25/08/21 Dur: 26 days Finish: 13/09/21 Dur: 21 days Finish: 22/09/21 Dur: 21 days
Res: Rp 15.803.040,33 Res: Rp 13.669.780,52 Res: Rp 20.258.785,53

LANTAI 1 LANTAI 2 LANTAI 3 LANTAI ATAP


Start: 05/08/21 ID: 101 Start: 10/08/21 ID: 102 Start: 17/08/21 ID: 103 Start: 30/08/21 ID: 104
Finish: 02/09/21 Dur: 21 days Finish: 07/09/21 Dur: 21 days Finish: 14/09/21 Dur: 21 days Finish: 26/09/21 Dur: 21 days
Res: Rp 61.591.199,50 Res: Rp 16.503.403,69 Res: Rp 18.861.032,79 Res: Rp 7.078.317,52

LANTAI 1 LANTAI 2 LANTAI 3


Start: 27/08/21 ID: 107 Start: 06/09/21 ID: 108 Start: 14/09/21 ID: 109
Finish: 24/09/21 Dur: 21 days Finish: 27/09/21 Dur: 16 days Finish: 01/10/21 Dur: 14 days
Res: Rp 209.925.366,19 Res: Rp 224.173.107,35 Res: Rp 200.339.109,60

INSTALASI PIPA REFERIGERANT, DRAIN, DAN KABEL POWER


Start: 02/08/21 ID: 110
Finish: 27/09/21 Dur: 41 days
Res: Rp 341.514.502,75

PEMASANGAN ELEVATOR
Start: 11/08/21 ID: 112
Finish: 27/09/21 Dur: 34 days
Res: Rp 503.730.713,00

PEKERJAAN TANAH PEKERJAAN BETON PEKERJAAN RANGKA DAN ATAP DROP OFF SELASAR PENGHUBUNG LANDCAPE
Start: 02/08/21 ID: 114 Start: 03/08/21 ID: 115 Start: 13/08/21 ID: 116 Start: 02/08/21 ID: 118 Start: 02/08/21 ID: 120
Finish: 09/08/21 Dur: 6 days Finish: 17/08/21 Dur: 11 days Finish: 10/09/21 Dur: 21 days Finish: 30/09/21 Dur: 44 days Finish: 30/09/21 Dur: 44 days
Res: Rp 1.560.575,15 Res: Rp 30.072.630,45 Res: Rp 185.828.755,66 Res: Rp 75.456.503,16 Res: Rp 192.630.903,43