Pembuatan steger dan perancah dari bambu Pembuatan kotak adukan uk. 40cm x 50cm x 25cm
Start: 6/1/21 ID: 5 Start: 6/3/21 ID: 6
Finish: 6/2/21 Dur: 2 days Finish: 6/5/21 Dur: 3 days
Res: Res:
Pengurugan dengan pasir urug Pemasangan pondasi batu belah campuran 1PC : 3PP
Start: 6/1/21 ID: 10 Start: 6/4/21 ID: 12
Finish: 6/3/21 Dur: 3 days Finish: 6/10/21 Dur: 7 days
Res: Res:
- PEKERJAAN DINDING DAN PLESTERAN Pas. Dinding bata merah (5x11x22)cm tebal 1/2 batu
Pas.campuran
Dinding bata
1PCmerah
: 3KP (5x11x22)cm
: 10PP tebal 1/2 batu
Pemasangan
campuran 1PC
plesteran
: 3PP 1 PC : 3 PP tebal 15mm
Start: 6/10/21 ID: 13 Start: 6/10/21 ID: 15 Start: 6/17/21 ID: 14 Start: 6/24/21 ID: 16
Finish: 7/4/21 Dur: 25 days Finish: 6/16/21 Dur: 7 days Finish: 6/23/21 Dur: 7 days Finish: 6/27/21 Dur: 4 days
Comp: 0% Res: Res: Res:
- PEKERJAAN BETON kolom praktis 15x15 -pembesian -bekisting (2 x pakai) -cor beton 1 PC: 2PS : 3 Kr
Start: 6/1/21 ID: 18 Start: 6/1/21 ID: 19 Start: 6/1/21 ID: 21 Start: 6/3/21 ID: 22 Start: 6/6/21 ID: 20
Finish: 7/6/21 Dur: 36 days Finish: 6/9/21 Dur: 9 days Finish: 6/4/21 Dur: 4 days Finish: 6/5/21 Dur: 3 days Finish: 6/9/21 Dur: 4 days
Comp: 0% Comp: 0% Res: Res: Res:
Dak Beton
Start: 6/27/21 ID: 31
Finish: 7/6/21 Dur: 10 days
Comp: 0%
- PEKERJAAN KUSEN PINTU DAN JENDELA Pembuatan dan pemasangan kusen pintu dan jendela, kayu kruing
Start: 6/20/21 ID: 35 Start: 6/20/21 ID: 36
Finish: 6/30/21 Dur: 11 days? Finish: 6/25/21 Dur: 6 days
Comp: 0% Res:
Page 1
- PEMASANGAN KERAMIK
Start: 7/29/21 ID: 48
Finish: 8/8/21 Dur: 11 days
Comp: 0%
- PEKERJAAN PENGECATAN Pengecatan bidang kayu baru (sek. Avian) Pengecatan tembok baru (sek. Catylac)
Start: 6/1/21 ID: 59 Start: 6/1/21 ID: 60 Start: 6/6/21 ID: 61
Finish: 7/28/21 Dur: 58 days Finish: 6/5/21 Dur: 5 days Finish: 6/13/21 Dur: 8 days
Comp: 0% Res: Res:
Page 2
Pemasangan acian
Start: 6/28/21 ID: 17
Finish: 7/4/21 Dur: 7 days
Res:
Page 3
- PEKERJAAN ATAP DAN LANGIT-LANGIT Pemasangan atap baja ringan Pemasangan atap genteng Pemasangan bubung genteng Pemasangan listplang kasiplank ukuran 2 x 20 Pemasangan
cm rangka langit-langit 60x80 cm
Start: 7/7/21 ID: 40 Start: 7/7/21 ID: 41 Start: 7/12/21 ID: 43 Start: 7/15/21 ID: 44 Start: 7/17/21 ID: 42 Start: 7/20/21 ID: 45
Finish: 7/28/21 Dur: 22 days Finish: 7/11/21 Dur: 5 days Finish: 7/14/21 Dur: 3 days Finish: 7/16/21 Dur: 2 days Finish: 7/19/21 Dur: 3 days Finish: 7/23/21 Dur: 4 days
Comp: 0% Res: Res: Res: Res: Res:
Page 4
Page 5
Pemasangan langit-langit gypsum Pemasangan list langit-langit
Start: 7/24/21 ID: 46 Start: 7/27/21 ID: 47
Finish: 7/26/21 Dur: 3 days Finish: 7/28/21 Dur: 2 days
Res: Res:
Pemasangan instalasi titik lampu Pemasangan lampu LED 9 watt sek. Philips Pemasangan lampu LED 3 watt sek. Philips
Start: 7/24/21 ID: 64 Start: 7/27/21 ID: 66 Start: 7/29/21 ID: 67
Finish: 7/26/21 Dur: 3 days Finish: 7/28/21 Dur: 2 days Finish: 7/30/21 Dur: 2 days
Res: Res: Res:
Pemasangan saklar tunggal sek. Broco Pemasangan saklar double sek. Broco
Start: 7/24/21 ID: 68 Start: 7/26/21 ID: 69
Finish: 7/25/21 Dur: 2 days Finish: 7/27/21 Dur: 2 days
Res: Res:
Page 6
Critical Critical Milestone Critical Summary Critical Inserted Critical Marked Critical External Project Summary Highlighted Noncritical
Project: MUGI WALUYO (1841010319
Date: Apr 25 '21
Noncritical Milestone Summary Inserted Marked External Highlighted Critical
Page 7