No URAIAN PEKERJAAN KETERANGAN SAT VOL HARGA SATUAN

A PEKERJAAN PERSIAPAN & GALIAN TANAH


1 Mob Demob Proteksi area kerja Ls 1.00 Rp
2 Pengukuran & bouplank Kaso, benang, paku m² 19.76 Rp
3 Galian kolam renang Alat & tenaga m³ 27.66 Rp
4 Galian Sloof / Pondasi Alat & tenaga m³ 1.76 Rp
TOTA
B PEKERJAAN KOLAM RENANG
1 Pasang bata hebel Dinding Luar Kolam renang m² 25.20 Rp
2 Urugan pasir t=5 cm Pasir urug m³ 0.99 Rp
3 Lantai kerja t=5 cm Semen,pasir m³ 0.99 Rp
4 Balok lantai Tulangan besi beton 12Ø uk 20/20 m³ 1.76 Rp
5 Pekerjaan instalasi pipa kolam renang Pipa rucika AW Lot 1.00 Rp
6 Bekesting kayu Kaso, multipleks m² 25.20 Rp
7 Beton lantai t=15 cm K300, besi beton 10mm jarak 20x20, 2 lapis m² 14.00 Rp
8 Beton dinding t=12 cm K300, besi beton 10mm jarak 20x20, 2 lapis m² 25.20 Rp
9 Bongkar bekisting kayu Kaso, multipleks m² 25.20 Rp
10 Waterprofing 2 Lapis Sika top m² 40.20 Rp
11 Plester Pasir, semen t=2cm m² 40.20 Rp
12 Pemasangan Keramik Finishing Keramik Motif Mozaik m² 40.20 Rp
13 Toping bibir batu alam Andesit Andesit=2cm,pinggul,coating m¹ 19.00 Rp
14 Ruang Mesin Galian, Beton K-175, Besi beton 8Ø, Lot 1.00 Rp
Finishing Plester, Tutup Plat Bordess
15 Pencucian keramik HCL + air m² 40.20 Rp
16 Pengisian Air Kolam Renang Air Tangki 8000 liter Tangki 2.00 Rp
17 Maintenance / Treatmen Awal Obat + tenaga Ls 1.00 Rp
TOTA
C EQUIPMENT PUMP & FILTER
1 Pompa sirkulasi Emaux 0,5 Hp Unit 1.00 Rp
2 Sand Filter Emaux 0,5 Hp Unit 1.00 Rp
3 Pasir Pasir Silikas Sak 1.00 Rp
- Pipa Rucika aw 1,5"
4 Pemasangan & Instalasi Mesin & Filter - Ball Valve 1,5" Ls 1.00 Rp
- Lem Pipa

5 Skimmer Box Diamond Unit 1.00 Rp


6 Cover Maindrain Diamond 1,5" Unit 1.00 Rp
7 inled fitting Diamond 1,5" bh 3.00 Rp
TOTA
D AKSESORIS KOLAM RENANG
1 Alat Perawatan Kolam Renang Telescopic Stick, Vacum Hose, vacum Head, Set 1.00 Rp
Leaf Skimmer, Pool Brush
2 tangga stainles Aquastics 3 Strap bh 1.00 Rp
3 Underwater Light LED & Trafo Waterway 12 Volt bh 2.00 Rp
4 Cable Nyyhy 2x1,5 Supreme 50m rol 1.00 Rp
TOTA
HARGA SATUAN JUMLAH HARGA

1,000,000 Rp 1,000,000
25,000 Rp 494,000
285,000 Rp 7,884,240
285,000 Rp 501,600
TOTAL Rp 9,879,840

185,000 Rp 4,662,000
750,000 Rp 741,000
1,800,000 Rp 1,778,400
2,100,000 Rp 3,696,000
400,000 Rp 400,000
180,000 Rp 4,536,000
675,000 Rp 9,450,000
650,000 Rp 16,380,000
15,000 Rp 378,000
105,000 Rp 4,221,000
105,000 Rp 4,221,000
350,000 Rp 14,070,000
300,000 Rp 5,700,000
7,000,000 Rp 7,000,000

10,000 Rp 402,000
650,000 Rp 1,300,000
1,500,000 Rp 1,500,000
TOTAL Rp 80,435,400

5,100,000 Rp 5,100,000
4,100,000 Rp 4,100,000
250,000 Rp 250,000

3,000,000 Rp 3,000,000

1,500,000 Rp 1,500,000
1,100,000 Rp 1,100,000
225,000 Rp 675,000
TOTAL Rp 15,725,000

2,950,000 Rp 2,950,000

1,750,000 Rp 1,750,000
2,250,000 Rp 4,500,000
650,000 Rp 650,000
TOTAL Rp 9,850,000
TOTAL KESELURUHAN PEKERJAAN SUB TOTAL

A PEKERJAAN PERSIAPAN & GALIAN TANAH Rp


B PEKERJAAN KOLAM RENANG Rp
C EQUIPMENT PUMP & FILTER Rp
D AKSESORIS KOLAM RENANG Rp

TOTAL Rp
DISKON 5% Rp
TOTAL KESELURUHAN Rp
SUB TOTAL

9,879,840
80,435,400
15,725,000
9,850,000

115,890,240
5,794,512
110,095,728
Nb:
- Garansi kebocoran kolam renang selama 5 (lima) tahun diluar bencana alam
- Gransi mesin mati 6 (enam) bulan di luar spare part
- Maksimal Pengerjaan 60 Hari Kalender
- Harga sudah termasuk biaya material dan jasa
- Penawaran ini berlaku 1 bulan setelah berkas diterima
PROSEDUR PENAGIHAN DAN PEMBAYARAN
1. Termin I (Satu) 30 % Dari nilai total Pekerjaan dibayarkan setelah SPK ini di tanda tangani dan tukang (pekerja) mulai pekerjaan.
2. Termin II (Dua) 40 % Dari nilai total Pekerjaan dibayarkan akan dilakukan pengecoran.
3. Termin III (Tiga) 25 % Dari nilai total Pekerjaan dibayarka setelah selesai waterprofing,plester selesai sebelum dilakukan pemasangan keramik & equipment
4. Termin IV (Empat) 5 % Dari nilai total Pekerjaan dibayarkan setelah pekerjaan di nyatakan selesai Pekerjaan
- Serah Terima Pekerjaan
- Retensi Satu (1) Minggu
Demikian kami buat prosedur penagihan dan pembayaran pekerjaan pembuatan kolam renang. NB : pembayaran dilakukan via transfer melalui            :3610199169 a/n DARM
Jakarta, 14
KARYA UTAMA
POOL

DARMI
N