Harga Satuan
NO Uraian Satuan
( Rp )
1 Pekerja OH 137,477.27
2 Buruh semi terampil OH 142,975.20
3 Buruh terampil OH 151,225.00
4 Tukang Cat OH 197,250.00
5 Tukang OH 197,250.00
6 Tukang batu OH 197,250.00
7 Tukang batu/pipa OH 197,250.00
8 Tukang besi OH 197,250.00
9 Tukang besi konstruksi OH 197,250.00
10 Tukang kayu OH 197,250.00
11 Kepala tukang OH 242,363.63
12 Tukang las OH 197,250.00
13 Tukang Listrik OH 197,250.00
14 Pembatu sopir OH 157,338.84
15 Sopir / Driver OH 170,950.00
16 Operator Semi Terampil OH 263,000.00
17 Operator Terampil OH 433,950.00
18 Mekanik Semi Terampil OH 263,000.00
19 Mekanik Terampil OH 604,900.00
20 Mandor Lapangan OH 263,000.00
sopir pribadi
pembantu sopir
pekerja
buruh semi terampil
buruh terampil
K
O
L
O
M
DAFTAR HARGA SATUAN BAHAN BANGUNAN KONSTRUKSI
I
TAHUN ANGGARAN 2018 N
I
###
PROPINSI : PAPUA J
A
KABUPATEN/KOTA : KABUPATEN JAYAWIJAYA N
G
ANGKUTAN A
HARGA SATUAN N
NO JENIS BARANG KUALITAS BARANG SAT HARGA SATUAN WAMENA
WAMENA
WAMENA - BBI( Rp ) BBI - LOKASI D
I
A B C D E F G E H
A
1 Pasir Pasir Pasang M³ 1,490,000.00 1,354,545.45 650,000.00 400,000.00 2,404,545.45 P
Pasir Beton M³ 1,490,000.00 1,354,545.45 650,000.00 400,000.00 2,404,545.45 U
Pasir Plester M³ 1,490,000.00 1,354,545.45 650,000.00 400,000.00 2,404,545.45 S
Pasir Urug M³ 1,118,000.00 1,016,363.64 650,000.00 400,000.00 2,066,363.64
Timbunan Biasa M³ 857,000.00 779,090.91 650,000.00 400,000.00 1,829,090.91
Timbunan Pilihan M³ 931,000.00 846,363.64 650,000.00 400,000.00 1,896,363.64
Tanah M³ 67,000.00 60,909.09 650,000.00 400,000.00 1,110,909.09
2 Batu Pondasi Batu Kali M³ 1,184,000.00 1,076,363.64 650,000.00 400,000.00 2,126,363.64
Batu Gunung M³ 1,184,000.00 1,076,363.64 650,000.00 400,000.00 2,126,363.64
Batu Belah M³ 1,315,000.00 1,195,454.55 650,000.00 400,000.00 2,245,454.55
3 batu split Ukuran 5 - 7 cm M³ 1,315,000.00 1,195,454.55 650,000.00 400,000.00 2,245,454.55
Ukuran 3 - 5 cm M³ 1,716,000.00 1,560,000.00 650,000.00 400,000.00 2,610,000.00
Ukuran 2 - 3 cm M³ 1,993,000.00 1,811,818.18 650,000.00 400,000.00 2,861,818.18
Ukuran 1 - 2 cm M³ 2,409,000.00 2,190,000.00 650,000.00 400,000.00 3,240,000.00
Abu Batu M³ 4,997,000.00 4,542,727.27 650,000.00 400,000.00 5,592,727.27
Kerikil Sungai tanpa saring M³ 1,065,000.00 968,181.82 650,000.00 400,000.00 2,018,181.82
Kerikil Sungai Tanpa Pasir M³ 114,000.00 103,636.36 650,000.00 400,000.00 1,153,636.36
ANGKUTAN
HARGA SATUAN BERAT
NO JENIS BARANG KUALITAS BARANG SAT HARGA SATUAN WAMENA
WAMENA (KG/SATUAN) WAMENA - BBI( Rp
BBI - LOKASI
)
A B C D E F G H E
4 Batu Bata Batu Merah biasa Bh 6,000 5,454.55 1.900 1,000.00 700.00 8,684.55
5 Bataco/Paving Bataco biasa Bh 12,000 10,909.09 4.800 1,000.00 700.00 19,069.09
7 Semen PC @50 Kg biasa Tonasa Zak 806,000 732,727.27 50.000 1,000.00 700.00 817,727.27
Tiga Roda Zak 806,000 732,727.27 50.000 1,000.00 700.00 817,727.27
Gresik Zak 806,000 732,727.27 50.000 1,000.00 700.00 817,727.27
Holcim Zak 806,000 732,727.27 50.000 1,000.00 700.00 817,727.27
8 Semen PC @50 Kg warna Tiga Roda Zak 723,000 657,272.73 50.000 1,000.00 700.00 742,272.73
Gresik Zak 723,000 657,272.73 50.000 1,000.00 700.00 742,272.73
Tonasa Zak 723,000 657,272.73 50.000 1,000.00 700.00 742,272.73
Holcim Zak 723,000 657,272.73 50.000 1,000.00 700.00 742,272.73
Semen Instan MU 250 Kg 21,000 19,090.91 1.000 1,000.00 700.00 20,790.91
Semen Gysum Kg 20,000 18,181.82 1.000 1,000.00 700.00 19,881.82
10 Besi Beton Polos full Besi Beton 6mm Btg 118,000 107,272.73 2.441 1,000.00 700.00 111,422.43
Besi Beton 8mm Btg 197,000 179,090.91 4.340 1,000.00 700.00 186,468.91
Besi Beton 10mm Btg 263,000 239,090.91 6.782 1,000.00 700.00 250,620.31
Besi Beton 12mm Btg 309,000 280,909.09 9.765 1,000.00 700.00 297,509.59
Besi Beton 16mm Btg 592,000 538,181.82 17.361 1,000.00 700.00 567,695.52
Baja/Aluminium Baja Siku 50.50.5 Btg 888,000 807,272.73 22.600 1,000.00 700.00 845,692.73
Baja Siku 40.40.5 Btg 526,000 478,181.82 14.500 1,000.00 700.00 502,831.82
Baja Siku 30.30.5 Btg 250,000 227,272.73 8.160 1,000.00 700.00 241,144.73
Baja Strip 20.2 Btg 125,000 113,636.36 1,000.00 700.00 113,636.36
Baja Ringan ( C. 80. 0,75 ) m' 33,333 30,303.03 1.290 1,000.00 700.00 32,496.03
Reng V 16, 0,45 m' 19,167 17,424.24 0.570 1,000.00 700.00 18,393.24
Talang Jurai / valery gutter m' 36,667 33,333.33 1.230 1,000.00 700.00 35,424.33
ACP ( Aluminium Composite Panel ) Lbr 3,303,000 3,002,727.27 10.419 1,000.00 700.00 3,020,439.23
Hollow Zink Aluminium ( 4 x 4 cm ) m' 71,000 64,545.45 1.500 1,000.00 700.00 67,095.45
Hollow ( 3 x 3 ) tebal m' 60,000 54,545.45 1.167 1,000.00 700.00 56,528.79
11 Kawat Kawat Beton Kg 49,000 44,545.45 1.000 1,000.00 700.00 46,245.45
Kawat Harmonika lubang 4 cm M' 118,000 107,272.73 0.250 1,000.00 700.00 107,697.73
Kawat Harmonika lubang 2 cm M' 99,000 90,000.00 0.200 1,000.00 700.00 90,340.00
Kawat Harmonika lubang 1 cm M' 92,000 83,636.36 0.150 1,000.00 700.00 83,891.36
Kawat Harmonika lubang 0,5 cm M' 85,000 77,272.73 0.100 1,000.00 700.00 77,442.73
Kawat Has Nyamuk M' 66,000 60,000.00 0.100 1,000.00 700.00 60,170.00
Kawat Duri Roll 460,000 418,181.82 15.000 1,000.00 700.00 443,681.82
Kawat Las Dos 329,000 299,090.91 1.000 1,000.00 700.00 300,790.91
13 Paku dan Sekrup Paku Jembatan Kg 60,000 54,545.45 1.000 1,000.00 700.00 56,245.45
Paku 15 cm Kg 46,000 41,818.18 1.000 1,000.00 700.00 43,518.18
Paku 10 cm Kg 34,000 30,909.09 1.000 1,000.00 700.00 32,609.09
Paku 7 cm Kg 34,000 30,909.09 1.000 1,000.00 700.00 32,609.09
Paku 5 cm Kg 36,000 32,727.27 1.000 1,000.00 700.00 34,427.27
Paku 3 cm Kg 47,000 42,727.27 1.000 1,000.00 700.00 44,427.27
Paku Seng Kg 48,000 43,636.36 1.000 1,000.00 700.00 45,336.36
Paku Triplek Kg 44,000 40,000.00 1.000 1,000.00 700.00 41,700.00
Paku Sekrup Besar Dos 329,000 299,090.91 1.000 1,000.00 700.00 300,790.91
Paku Sekrup Sedang Dos 289,000 262,727.27 1.000 1,000.00 700.00 264,427.27
Paku Skrup Kecil Dos 460,000 418,181.82 1.000 1,000.00 700.00 419,881.82
Paku Sekrup Gypsum 5/8" Kg 375,000 340,909.09 1.000 1,000.00 700.00 342,609.09
14 Keramik Putih Polos (KW1) standar KIA 60 x 60 cm Dos 888,000 807,272.73 21.000 1,000.00 700.00 842,972.73
40 x 40 cm Dos 539,000 490,000.00 17.000 1,000.00 700.00 518,900.00
30 x 30 cm Dos 356,000 323,636.36 14.000 1,000.00 700.00 347,436.36
20 x 25 cm Dos 333,000 302,727.27 13.000 1,000.00 700.00 324,827.27
134,750 20 x 20 cm Dos 330,000 300,000.00 13.000 1,000.00 700.00 322,100.00
10 x 20 cm Dos 283,000 257,272.73 12.000 1,000.00 700.00 277,672.73
10 x 40 cm Dos 566,000 514,545.45 24.000 1,000.00 700.00 555,345.45
15 Keramik Warna (KW1) standar KIA 60 x 60 cm Dos 910,000 827,272.73 21.000 1,000.00 700.00 862,972.73
40 x 40 cm Dos 427,000 388,181.82 17.000 1,000.00 700.00 417,081.82
30 x 30 cm Dos 397,000 360,909.09 14.000 1,000.00 700.00 384,709.09
20 x 25 cm Dos 352,000 320,000.00 13.000 1,000.00 700.00 342,100.00
20 x 20 cm Dos 334,000 303,636.36 13.000 1,000.00 700.00 325,736.36
10 x 20 cm Dos 283,000 257,272.73 12.000 1,000.00 700.00 277,672.73
16 Kloset standar KIA Kloset Duduk Bh 5,589,000 5,080,909.09 15.000 1,000.00 700.00 5,106,409.09
Kloset Jongkok standar DUTY Bh 572,000 520,000.00 8.000 1,000.00 700.00 533,600.00
17 Wastefel Wastafel Stainless Bh 1,184,000 1,076,363.64 12.000 1,000.00 700.00 1,096,763.64
Wastafel Stainless Keramik Bh 1,973,000 1,793,636.36 13.000 1,000.00 700.00 1,815,736.36
Wastafel Lengkap Cermin Bh 4,957,000 4,506,363.64 17.000 1,000.00 700.00 4,535,263.64
18 Kran Air dan Perlengkapannya Water Drain + Accessories Bh 132,000 120,000.00 0.450 1,000.00 700.00 120,765.00
Kran Air 3/4" Stainless Steel Bh 388,000 352,727.27 0.800 1,000.00 700.00 354,087.27
Kran 3/4" Bh 65,000 59,090.91 0.800 1,000.00 700.00 60,450.91
19 Bak Cuci Piring Stainless 1 Lubang Bh 953,000 866,363.64 2.000 1,000.00 700.00 869,763.64
Stainless 2 Lubang Bh 1,710,000 1,554,545.45 4.000 1,000.00 700.00 1,561,345.45
20 Bak Fiberglass Bak Mandi Fiberglass Biasa Bh 986,000 896,363.64 10.000 1,000.00 700.00 913,363.64
Galon Fiberglass 500 ltr Bh 2,762,000 2,510,909.09 8.000 1,000.00 700.00 2,524,509.09
Galon Fiberglass 1000 ltr Bh 4,098,000 3,725,454.55 10.000 1,000.00 700.00 3,742,454.55
Galon Fiberglass 2000 ltr Bh 8,548,000 7,770,909.09 18.000 1,000.00 700.00 7,801,509.09
Tangki Air Stainless Steel 1000 ltr Unit 13,454,000 12,230,909.09 25.000 1,000.00 700.00 12,273,409.09
22 Pipa Galvanis Medium "B" Pipa GIP Ø 4" Btg 1,973,000 1,793,636.36 8.500 1,000.00 700.00 1,808,086.36
Pipa GIP Ø 3" Btg 1,447,000 1,315,454.55 4.160 1,000.00 700.00 1,322,526.55
Pipa GIP Ø 2" Btg 723,000 657,272.73 3.330 1,000.00 700.00 662,933.73
Pipa GIP Ø 1,5" Btg 592,000 538,181.82 2.660 1,000.00 700.00 542,703.82
Pipa GIP Ø 1" Btg 460,000 418,181.82 2.330 1,000.00 700.00 422,142.82
Pipa GIP Ø 3/4" Btg 329,000 299,090.91 2.000 1,000.00 700.00 302,490.91
Pipa GIP Ø 1/2" Btg 256,000 232,727.27 1.650 1,000.00 700.00 235,532.27
23 Pipa PVC Merk Maspion dan Sejenisnya Pipa PVC 1/2" Btg 72,000 65,454.55 0.450 1,000.00 700.00 66,219.55
Pipa PVC 3/4" Btg 92,000 83,636.36 0.450 1,000.00 700.00 84,401.36
Pipa Union 5/8" M¹ 7,000 6,363.64 0.050 1,000.00 700.00 6,448.64
Pipa PVC 1" Btg 118,000 107,272.73 1.550 1,000.00 700.00 109,907.73
Pipa PVC 1,5" Btg 205,000 186,363.64 2.000 1,000.00 700.00 189,763.64
Pipa PVC 2" Btg 275,000 250,000.00 2.600 1,000.00 700.00 254,420.00
Pipa PVC 2,5" Btg 298,000 270,909.09 3.000 1,000.00 700.00 276,009.09
Pipa PVC 3" Btg 393,000 357,272.73 3.670 1,000.00 700.00 363,511.73
Pipa PVC 4" Btg 592,000 538,181.82 4.680 1,000.00 700.00 546,137.82
25 Seng Sakura Roof Lbr 99,000 90,000.00 2.200 1,000.00 700.00 93,740.00
Nok Nok Sakura bh 99,000 90,000.00 0.350 1,000.00 700.00 90,595.00
Seng Gelombang bjls 20 Lbr 92,000 83,636.36 4.350 1,000.00 700.00 91,031.36
Seng Gelombang bjls 30 Lbr 130,000 118,181.82 5.650 1,000.00 700.00 127,786.82
Seng Plat bjls 20 lebar 90 Lbr/M¹ 108,000 98,181.82 4.200 1,000.00 700.00 105,321.82
Seng Plat bjls 30 lebar 90 Lbr 162,000 147,272.73 5.450 1,000.00 700.00 156,537.73
Seng Plat bjls 20 lebar 45 Lbr/M¹ 57,000 51,818.18 2.100 1,000.00 700.00 55,388.18
Atap Spandek Zincalum 1 x 3 x 0,4 Lbr 300,000 300,000 10.650 1,000.00 700.00 318,105.00
Nok Spandek Lbr 220,000 220,000 3.550 1,000.00 700.00 226,035.00
26 Kaca Polos Tebal 3 mm M² 592,000 538,181.82 8.250 1,000.00 700.00 552,206.82
Polos Tebal 5 mm M² 1,100,000 1,000,000.00 10.120 1,000.00 700.00 1,017,204.00
Riben Tebal 3 mm M² 622,000 565,454.55 8.250 1,000.00 700.00 579,479.55
Riben Tebal 5 mm M² 1,375,000 1,250,000.00 10.120 1,000.00 700.00 1,267,204.00
Kaca Naco Polos tebal 5mm 7 klip Set 516,000 469,090.91 8.500 1,000.00 700.00 483,540.91
Kaca Naco Riben tebal 5mm 7 klip Set 544,000 494,545.45 8.500 1,000.00 700.00 508,995.45
28 Kayu Lapis Triplek Tebal 3 mm Lbr 125,000 113,636.36 2.800 1,000.00 700.00 118,396.36
Triplek Tebal 4 mm Lbr 171,000 155,454.55 6.800 1,000.00 700.00 167,014.55
Triplek Tebal 6 mm Lbr 256,000 232,727.27 8.800 1,000.00 700.00 247,687.27
Triplek Tebal 9 mm Lbr 388,000 352,727.27 10.800 1,000.00 700.00 371,087.27
Triplek Tebal 12 mm Lbr 519,000 471,818.18 1,000.00 700.00 471,818.18
Triplek Tebal 18 mm Lbr 752,000 683,636.36 1,000.00 700.00 683,636.36
Gypsum Lbr 1,042,000 947,272.73 1,000.00 700.00 947,272.73
Eternit Lbr 692,000 629,090.91 1,000.00 700.00 629,090.91
Teakwood Lbr 119,000 108,181.82 2.800 1,000.00 700.00 112,941.82
Kalsiboard Lbr 227,000.00 206,363.64 32.000 1,000.00 700.00 260,763.64
29 Cat Tembok Biasa merk Inatex Inatex 20 Kg Klg 540,000 490,909.09 20.000 1,000.00 700.00 524,909.09
dan sejenisnya 5 kg aries Klg 171,000 155,454.55 5.000 1,000.00 700.00 163,954.55
20 kg aries Klg 562,000 510,909.09 5.000 1,000.00 700.00 519,409.09
Cat Tembok Super merk Danabrite dan 25 Kg Klg 1,134,000 1,030,909.09 25.000 1,000.00 700.00 1,073,409.09
sejenisnya 5 kg Klg 250,000 227,272.73 5.000 235,772.73
1,000.00 700.00
Cat Kayu/Besi merk Avian dan sejenisnya 1 kg Klg 102,000 92,727.27 1.000 1,000.00 700.00 94,427.27
Cat Kayu/Besi merk Jotun dan sejenisnya Lem kayu Kg 112,000 101,818.18 1.000 1,000.00 700.00 103,518.18
Cat meni Kayu Kg 88,000 80,000.00 1.000 1,000.00 700.00 81,700.00
Cat Atap 5 Kg Klg 234,000 212,727.27 1.000 1,000.00 700.00 214,427.27
30 Peralatan Cat lainnya Meni ltr 79,000 71,818.18 1.000 1,000.00 700.00 73,518.18
Teak Oil Klg 105,000 95,454.55 1.000 1,000.00 700.00 97,154.55
Vernis ltr 105,000 95,454.55 1.000 1,000.00 700.00 97,154.55
Politur ltr 99,000 90,000.00 1.000 1,000.00 700.00 91,700.00
Dempul Klg 79,000 71,818.18 1.000 1,000.00 700.00 73,518.18
Residu ltr 33,000 30,000.00 1.000 1,000.00 700.00 31,700.00
Amplas Lbr 7,000 6,363.64 0.050 1,000.00 700.00 6,448.64
Kuas 4" Bh 53,000 48,181.82 0.100 1,000.00 700.00 48,351.82
Plamur ltr 62,000 56,363.64 1.000 1,000.00 700.00 58,063.64
Kuas 3" Bh 39,000 35,454.55 0.080 1,000.00 700.00 35,590.55
Kuas 2" Bh 27,000 24,545.45 0.070 1,000.00 700.00 24,664.45
Kuas 1" Bh 16,000 14,545.45 0.060 1,000.00 700.00 14,647.45
31 Minyak Minyak Cat/tiner Ltr 66,000 60,000.00 1.000 1,000.00 700.00 61,700.00
Minyak Begisting/oli kotor Ltr 17,000 15,454.55 1.000 1,000.00 700.00 17,154.55
Minyak Olie Ltr 99,000 90,000.00 1.000 1,000.00 700.00 91,700.00
32 Kunci Pintu Merk Yale Besar Bh 236,000 214,545.45 0.350 1,000.00 700.00 215,140.45
Merk Yale Kecil Bh 115,000 104,545.45 0.350 1,000.00 700.00 105,140.45
Kunci Tanam Pintu Exclusive 2 Slug Bh 395,000 359,090.91 0.200 1,000.00 700.00 359,430.91
33 Engsel Pintu dan Jendela Engsel Kupu-kupu Besar Psg 81,000 73,636.36 0.250 1,000.00 700.00 74,061.36
Engsel Kupu-kupu Sedang Psg 68,000 61,818.18 0.240 1,000.00 700.00 62,226.18
Engsel Kupu-kupu Kecil Psg 41,000 37,272.73 0.230 1,000.00 700.00 37,663.73
Engsel H Besar Psg 68,000 61,818.18 0.250 1,000.00 700.00 62,243.18
Engsel H Sedang Psg 54,000 49,090.91 0.240 1,000.00 700.00 49,498.91
Engsel H Kecil Psg 47,000 42,727.27 0.230 1,000.00 700.00 43,118.27
34 Grendel Pintu Grendel Antik Bh 203,000 184,545.45 0.150 1,000.00 700.00 184,800.45
Grendel Sedang Bh 47,000 42,727.27 0.150 1,000.00 700.00 42,982.27
Grendel Biasa Bh 47,000 42,727.27 0.150 1,000.00 700.00 42,982.27
35 Grendel Jendela Grendel Antik Bh 77,000 70,000.00 0.150 1,000.00 700.00 70,255.00
Grendel Sedang Bh 37,000 33,636.36 0.150 1,000.00 700.00 33,891.36
Grendel Biasa Bh 20,000 18,181.82 0.150 1,000.00 700.00 18,436.82
36 Kait Angin Antik Bh 59,000 53,636.36 0.100 1,000.00 700.00 53,806.36
Sedang Bh 39,000 35,454.55 0.100 1,000.00 700.00 35,624.55
Biasa Bh 33,000 30,000.00 0.100 1,000.00 700.00 30,170.00
37 Handle/Pegangan Handle Pintu (no.1) Bh 526,000 478,181.82 1.100 1,000.00 700.00 480,051.82
38 Instalatur Listrik Lampu XL 18 Watt Bh 137,000 124,545.45 0.150 1,000.00 700.00 124,800.45
Lampu SL 25 Watt Bh 184,000 167,272.73 0.150 1,000.00 700.00 167,527.73
Lampu SL 45 Watt Bh 336,000 305,454.55 0.150 1,000.00 700.00 305,709.55
Lampu TL Philips 2x40 Watt+Fiting RM+Kisi-kisi Set 1,509,000 1,371,818.18 1.500 1,000.00 700.00 1,374,368.18
Lampu TL 1x20 watt + bak Bh 299,000 271,818.18 0.250 1,000.00 700.00 272,243.18
Lampu TL 1x40 watt + bak Bh 427,000 388,181.82 0.250 1,000.00 700.00 388,606.82
Bolam Pijar 40 Watt Bh 43,000 39,090.91 0.250 1,000.00 700.00 39,515.91
Sakelar Tunggal Bh 34,000 30,909.09 0.025 1,000.00 700.00 30,951.59
Sakelar Ganda Bh 51,000 46,363.64 0.030 1,000.00 700.00 46,414.64
Stop Kontak Bh 27,000 24,545.45 0.025 1,000.00 700.00 24,587.95
Sekring Box 1 Group Bh 72,000 65,454.55 1.000 1,000.00 700.00 67,154.55
Sekring Box 2 Group merek Philips Bh 359,000 326,363.64 1.200 1,000.00 700.00 328,403.64
Kabel NYM 2.5 x 2 Roll 1,105,000 1,004,545.45 15.000 1,000.00 700.00 1,030,045.45
Kabel NYM 3 x 4 mm Roll 498,000 452,727.27 18.000 1,000.00 700.00 483,327.27
Kabel NYM 4 x 4 mm Roll 1,148,000 1,043,636.36 18.000 1,000.00 700.00 1,074,236.36
Fitting (Broco) Bh 68,000 61,818.18 0.025 1,000.00 700.00 61,860.68
ANGKUTAN
HARGA SATUAN
NO JENIS BARANG KUALITAS BARANG SAT HARGA SATUAN WAMENA
WAMENA WAMENA - BBI( Rp ) BBI - LOKASI
A B C D E F G E
39 Kayu Lokal Panjang 4 M mutu Kelas I balok kayu sage 10/10cm M³ 9,055,000 8,231,818.18 650,000.00 400,000.00 9,281,818.18
balok kayu sage 5/10cm M³ 6,325,000 5,750,000.00 650,000.00 400,000.00 6,800,000.00
balok kayu sage 5/5cm M³ 6,325,000 5,750,000.00 650,000.00 400,000.00 6,800,000.00
Papan kayu sage 2/20cm M³ 6,325,000 5,750,000.00 650,000.00 400,000.00 6,800,000.00
Papan kayu sage 3.5/20cm M³ 6,325,000 5,750,000.00 650,000.00 400,000.00 6,800,000.00
Papan kayu sage 5/20cm M³ 6,325,000 5,750,000.00 650,000.00 400,000.00 6,800,000.00
40 Kayu Lokal Panjang 4 M mutu Kelas II balok kayu non sage 10/10cm M³ 5,096,000 4,632,727.27 650,000.00 400,000.00 5,682,727.27
balok kayu non sage 5/10cm M³ 5,096,000 4,632,727.27 650,000.00 400,000.00 5,682,727.27
balok kayu sage 5/5cm M³ 5,096,000 4,632,727.27 650,000.00 400,000.00 5,682,727.27
Papan kayu non sage 2/20cm M³ 5,096,000 4,632,727.27 650,000.00 400,000.00 5,682,727.27
Papan kayu non sage 3.5/20cm M³ 5,096,000 4,632,727.27 650,000.00 400,000.00 5,682,727.27
Papan kayu non sage 5/20cm M³ 5,096,000 4,632,727.27 650,000.00 400,000.00 5,682,727.27
Dolken Kayu Galam Kayu Galam Dia (8-10) cm Panjang 4m' Btg 70,000 63,636.36 10,000.00 5,000.00 78,636.36
Kayu Profil Kayu profil 2/5 cm pjg 4m Btg 126,000 114,545.45 10,000.00 5,000.00 129,545.45
?
###
Cor Kolom 20 / 20
BESI POKOK = 12 mm
BEGEL = 8 mm
SELIMUT BETON = 0.02 m
TINGGI BETON = 20 cm
LEBAR BETON = 20 cm
PERHITUNGAN BEKISTING
LUAS BEKISTING/M3 = 20.000 m2
JADI 1 M3 BETON MEMBUTUHKAN:
BESI POKOK = 88.776 Kg
BEGEL = 46.295 Kg 135.071
BEKISTING = 20.000 m2
Cor Kolom 20 / 50
BESI POKOK = 12 mm
BEGEL = 8 mm
SELIMUT BETON = 0.02 m
TINGGI BETON = 50 cm
LEBAR BETON = 20 cm
PERHITUNGAN BEKISTING
LUAS BEKISTING/M3 = 14.000 m2
JADI 1 M3 BETON MEMBUTUHKAN:
BESI POKOK = 53.266 Kg
BEGEL = 34.300 Kg 87.56602
BEKISTING = 14.000 m2
Cor Kolom 30 / 30
BESI POKOK = 16 mm
BESI POKOK = 12 mm
BEGEL = 8 mm
SELIMUT BETON = 0.02 m
TINGGI BETON = 30 cm
LEBAR BETON = 30 cm
Cor Kolom 15 / 15
BESI POKOK = 12 mm
BESI POKOK = 0 mm
BEGEL = 8 mm
SELIMUT BETON = 0.02 m
TINGGI BETON = 15 cm
LEBAR BETON = 15 cm
Cor Kolom 15 / 20
BESI POKOK = 0 mm
BESI POKOK = 10 mm
BEGEL = 6 mm
SELIMUT BETON = 0.02 m
TINGGI BETON = 20 cm
LEBAR BETON = 15 cm
PERHITUNGAN BEKISTING
LUAS BEKISTING/M3 = 25.000 m2
JADI 1 M3 BETON MEMBUTUHKAN:
BESI POKOK = 369.900 Kg
BEGEL = 83.296 Kg 453.196
BEKISTING = 25.000 m2
Cor Balok 15 / 25
BESI POKOK = 12 mm
BEGEL = 6 mm
SELIMUT BETON = 0.02 m
TINGGI BETON = 25 cm
LEBAR BETON = 15 cm
PERHITUNGAN BEKISTING
LUAS BEKISTING/M3 = 17.333 m2
JADI 1 M3 BETON MEMBUTUHKAN:
BESI POKOK = 0.000 Kg
BEGEL = 48.259 Kg 48.25907
BEKISTING = 17.333 m2
140.29
-
140.29
PAKE
1
PAKE
1.578
PAKE
TANDA TANYA
Cor Balok 25 / 40
BESI POKOK = 16 mm
BESI POKOK = 0 mm
BEGEL = 8 mm
SELIMUT BETON = 0.02 m
TINGGI BETON = 40 cm
LEBAR BETON = 25 cm
Cor Balok 20 / 30
BESI POKOK = 12 mm
BEGEL = 8 mm
SELIMUT BETON = 0.02 m
TINGGI BETON = 30 cm
LEBAR BETON = 20 cm
PERHITUNGAN BEKISTING
LUAS BEKISTING/M3 = 13.333 m2
JADI 1 M3 BETON MEMBUTUHKAN:
BESI POKOK = 147.960 Kg
BEGEL = 39.631 Kg 187.591
BEKISTING = 13.333 m2
Cor Balok 20 / 30
BESI POKOK = 16 mm
BESI POKOK = 0 mm
BEGEL = 8 mm
SELIMUT BETON = 0.02 m
TINGGI BETON = 30 cm
LEBAR BETON = 20 cm
Cor rb Balok 10 / 20
BESI POKOK = 12 mm
BESI POKOK = 0 mm
BEGEL = 8 mm
SELIMUT BETON = 0.02 m
TINGGI BETON = 20 cm
LEBAR BETON = 10 cm
PERHITUNGAN BEKISTING
LUAS BEKISTING/M3 = 17.333 m2
JADI 1 M3 BETON MEMBUTUHKAN:
BESI POKOK = 142.042 Kg
BEGEL = 49.381 Kg 191.423
BEKISTING = 17.333 m2
Cor rb Balok 20 / 30
BESI POKOK = 16 mm
BEGEL = 8 mm
SELIMUT BETON = 0.02 m
TINGGI BETON = 30 cm
LEBAR BETON = 20 cm
PERHITUNGAN BEKISTING
LUAS BEKISTING/M3 = 13.333 m2
JADI 1 M3 BETON MEMBUTUHKAN:
BESI POKOK = 210.432 Kg
BEGEL = 39.631 Kg 250.063
BEKISTING = 13.333 m2
Cor rb Balok 15 / 20
BESI POKOK = 12 mm
BEGEL = 8 mm
SELIMUT BETON = 0.02 m
TINGGI BETON = 20 cm
LEBAR BETON = 15 cm
PERHITUNGAN BEKISTING
LUAS BEKISTING/M3 = 18.333 m2
JADI 1 M3 BETON MEMBUTUHKAN:
BESI POKOK = 118.368 Kg
BEGEL = 52.959 Kg 171.327
BEKISTING = 18.333 m2
Cor rb Balok 15 / 64
BESI POKOK = 12 mm
BEGEL = 8 mm
SELIMUT BETON = 0.02 m
TINGGI BETON = 64 cm
LEBAR BETON = 15 cm
PERHITUNGAN BEKISTING
LUAS BEKISTING/M3 = 13.333 m2
JADI 1 M3 BETON MEMBUTUHKAN:
BESI POKOK = 184.950 Kg
BEGEL = 0.000 Kg 184.950
BEKISTING = 13.333 m2
198.283
Cor Kolom 25 / 40
BESI POKOK = 12 mm
BEGEL = 8 mm
SELIMUT BETON = 0.02 m
TINGGI BETON = 40 cm
LEBAR BETON = 25 cm
PERHITUNGAN BEKISTING
LUAS BEKISTING/M3 = 13.000 m2
JADI 1 M3 BETON MEMBUTUHKAN:
BESI POKOK = 53.266 Kg
BEGEL = 31.670 Kg 84.93562
BEKISTING = 13.000 m2
Cor Beton Sloof 20 / 20
BESI POKOK = 12 mm
BESI POKOK = 0 mm
BEGEL = 8 mm
SELIMUT BETON = 0.02 m
TINGGI BETON = 20 cm
LEBAR BETON = 20 cm
PERHITUNGAN BEKISTING
LUAS BEKISTING/M3 = 10.000 m2
PERHITUNGAN BEKISTING
LUAS BEKISTING/M3 = 8.000 m2
PERHITUNGAN BEKISTING
LUAS BEKISTING/M3 = 13.333 m2
PERHITUNGAN BEKISTING
LUAS BEKISTING/M3 = 10.000 m2
PERHITUNGAN BEKISTING
LUAS BEKISTING/M3 = 10.000 m2
100
157.824
177.552
335.376
0.006165
PAKE
PAKE
ANALISA HARGA SATUAN
1 M3 Membuat sloof beton bertulang 15/20
SNI Kebutuhan Satuan Indeks Harga Satuan Jumlah Harga
Pasang Bekisting m² 13.333 x Rp 403,133.55 = Rp 5,375,113.94
Beton mutu K.200 m³ 1.000 x Rp 9,561,343.81 = Rp 9,561,343.81
Bahan
Pasang Besi Polos 8 mm kg 52.959 x Rp 48,423.41 = Rp 2,564,441.81
Pasang Besi Polos 12 mm kg 118.368 x Rp 35,300.73 = Rp 4,178,476.40
JUMLAH = Rp 21,679,375.95
JUMLAH DIBULATKAN = Rp 21,679,375.95
A. A.4.1.1.4 Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87
SNI Kebutuhan Kode Satuan Indeks Harga Satuan Jumlah Harga
A. Bahan Portland Cement kg 230.000 x Rp 16,354.55 = Rp 3,761,545.45
Pasir beton kg 893.000 x Rp 1,717.53 = Rp 1,533,756.49
koral beton kg 1,027.000 x Rp 2,119.87 = Rp 2,177,101.68
Air Liter 200.000 x Rp 250.00 = Rp 50,000.00
A.A. 4.1.1.5 Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), slump (12 ± 2) cm, w/c = 0,66
SNI Kebutuhan Kode Satuan Indeks Harga Satuan Jumlah Harga
A. Bahan Portland Cement kg 326.000 x Rp 16,354.55 = Rp 5,331,581.82
Pasir Beton kg 760.000 x Rp 1,717.53 = Rp 1,305,324.68
Koral Beton kg 1,029.000 x Rp 2,119.87 = Rp 2,181,341.41
Air Liter 215.000 x Rp 250.00 = Rp 53,750.00
A.A. 4.1.1.6 Membuat 1 m3 beton mutu f’c = 16,9 MPa (K 200), slump (12 ± 2) cm, w/c = 0,61
SNI Kebutuhan Kode Satuan Indeks Harga Satuan Jumlah Harga
A. Bahan Portland Cement kg 352.000 x Rp 16,354.55 = Rp 5,756,800.00
Pasir Beton kg 731.000 x Rp 1,717.53 = Rp 1,255,516.23
Koral Beton kg 1,031.000 x Rp 2,119.87 = Rp 2,185,581.14
Air Liter 215.000 x Rp 250.00 = Rp 53,750.00
A. 4.1.1.8. Membuat 1 m3 beton mutu f’c = 21,7 MPa (K 250), slump (12 ± 2) cm, w/c = 0,56
SNI Kebutuhan Kode Satuan Indeks Harga Satuan Jumlah Harga
A. Bahan Portland Cement kg 384.000 x Rp 16,354.55 = Rp 6,280,145.45
Pasir Beton kg 692.000 x Rp 1,717.53 = Rp 1,188,532.47
Koral Beton kg 1,039.000 x Rp 2,119.87 = Rp 2,202,540.07
Air Liter 215.000 x Rp 250.00 = Rp 53,750.00
A. 4.1.1.9. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275), slump (12 ± 2) cm, w/c = 0,53
SNI Kebutuhan Kode Satuan Indeks Harga Satuan Jumlah Harga
A. Bahan Portland Cement kg 406.000 x Rp 16,354.55 = Rp 6,639,945.45
Pasir Beton kg 684.000 x Rp 1,717.53 = Rp 1,174,792.21
Koral Beton kg 1,026.000 x Rp 2,119.87 = Rp 2,174,981.82
Air Liter 215.000 x Rp 250.00 = Rp 53,750.00
A. 4.1.1.10. Membuat 1 m3 beton mutu f’c = 26,4 MPa (K 300), slump (12 ± 2) cm, w/c = 0,52
SNI Kebutuhan Kode Satuan Indeks Harga Satuan Jumlah Harga
A. Bahan Portland Cement kg 413.000 x Rp 16,354.55 = Rp 6,754,427.27
Pasir Beton kg 681.000 x Rp 1,717.53 = Rp 1,169,639.61
Koral Beton kg 1,021.000 x Rp 2,119.87 = Rp 2,164,382.49
Air Liter 215.000 x Rp 250.00 = Rp 53,750.00
A. 4.1.1.11. Membuat 1 m3 beton mutu f’c = 28,8 MPa (K 325), slump (12 ± 2) cm, w/c = 0,49
SNI Kebutuhan Kode Satuan Indeks Harga Satuan Jumlah Harga
A. Bahan Portland Cement kg 439.000 x Rp 16,354.55 = Rp 7,179,645.45
Pasir Beton kg 670.000 x Rp 1,717.53 = Rp 1,150,746.75
Koral Beton kg 1,006.000 x Rp 2,119.87 = Rp 2,132,584.51
Air Liter 215.000 x Rp 250.00 = Rp 53,750.00
A.4.1.1.17. Pembesian 10 kg dengan besi polos atau besi ulir ( Besi Polos Ø 6 mm )
SNI Kebutuhan Kode Satuan Indeks Harga Satuan Jumlah Harga
A. Bahan Besi beton (polos/ulir) kg 10.500 x Rp 45,639.86 = Rp 479,218.58
Kawat beton kg 0.150 x Rp 46,245.45 = Rp 6,936.82
A.4.1.1.17. Pembesian 10 kg dengan besi polos atau besi ulir ( Besi Polos Ø 8 mm )
SNI Kebutuhan Kode Satuan Indeks Harga Satuan Jumlah Harga
A. Bahan Besi beton (polos/ulir) kg 10.500 x Rp 42,963.60 = Rp 451,117.83
Kawat beton kg 0.150 x Rp 46,245.45 = Rp 6,936.82
A.4.1.1.17. Pembesian 10 kg dengan besi polos atau besi ulir ( Besi Polos Ø 10 mm )
SNI Kebutuhan Kode Satuan Indeks Harga Satuan Jumlah Harga
A. Bahan Besi beton (polos/ulir) kg 10.500 x Rp 36,956.47 = Rp 388,042.95
Kawat beton kg 0.150 x Rp 46,245.45 = Rp 6,936.82
A.4.1.1.17. Pembesian 10 kg dengan besi polos atau besi ulir ( Besi Polos Ø 12 mm )
SNI Kebutuhan Kode Satuan Indeks Harga Satuan Jumlah Harga
A. Bahan Besi beton (polos/ulir) kg 10.500 x Rp 30,465.81 = Rp 319,890.99
Kawat beton kg 0.150 x Rp 46,245.45 = Rp 6,936.82
Memasang 1 m2 dinding bata tela ukuran (8 x 14 x 28) cm tebal 1/2 bata, campuran spesi 1 PC : 4 PP
SNI Kebutuhan Kode Satuan Indeks Harga Satuan Jumlah Harga
Bahan Bata Tela Buah 22.000 x Rp 19,069.09 = Rp 419,520.00
6897-2008 Portland Cement kg 8.030 x Rp 16,354.55 = Rp 131,327.00
Pasir Pasang m3 0.026 x Rp 2,404,545.45 = Rp 62,518.18
A. 4.4.1.9. Pemasangan 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC : 4 PP
SNI Kebutuhan Kode Satuan Indeks Harga Satuan Jumlah Harga
A. Bahan Bata merah Buah 70.000 x Rp 8,684.55 = Rp 607,918.18
Portland Cement kg 11.500 x Rp 16,354.55 = Rp 188,077.27
Pasir Pasang m3 0.043 x Rp 2,404,545.45 = Rp 103,395.45
Memasang 1 m2 acian
SNI Kebutuhan Kode Satuan Indeks Harga Satuan Jumlah Harga
A. Bahan Portland Cement kg 3.250 x Rp 16,354.55 = Rp 53,152.27
A.4.6.1.1 Pembuatan dan Pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas I
SNI Kebutuhan Kode Satuan Indeks Harga Satuan Jumlah Harga
A. Bahan Balok Kayu Kelas I m 3
1.100 x Rp 6,800,000.00 = Rp 7,480,000.00
Paku 10 cm kg 1.250 x Rp 32,609.09 = Rp 40,761.36
Lem Kayu kg 1.000 x Rp 103,518.18 = Rp 103,518.18
A.4.6.1.2 Pembuatan dan Pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas II atau III
SNI Kebutuhan Kode Satuan Indeks Harga Satuan Jumlah Harga
A. Bahan Balok kayu kelas II m3 1.200 Rp 5,682,727.27 Rp 6,819,272.73
Paku 10 cm kg 1.250 Rp 32,609.09 Rp 40,761.36
Lem kayu kg 1.000 Rp 103,518.18 Rp 103,518.18
A.4.6.1.5. Pembuatan dan Pemasangan 1 m2 daun pintu panel, kayu kelas I atau II
SNI Kebutuhan Kode Satuan Indeks Harga Satuan Jumlah Harga
A. Bahan Papan Kayu kelas I m 3
0.040 x Rp 6,800,000.00 = Rp 272,000.00
Lem kayu kg 0.500 x Rp 103,518.18 = Rp 51,759.09
A.4.6.1.6. Pembuatan dan Pemasangan 1 m2 pintu dan jendela jalusi kayu kelas I atau II
SNI Kebutuhan Kode Satuan Indeks Harga Satuan Jumlah Harga
A. Bahan Papan Kayu I m3 0.064 Rp 6,800,000.00 Rp 435,200.00
Lem kayu kg 0.500 Rp 103,518.18 Rp 51,759.09
A.4.6.1.21. Pemasangan 1 m1 lisplank ukuran (3 x 20) cm, kayu kelas I atau kelas II
SNI Kebutuhan Kode Satuan Indeks Harga Satuan Jumlah Harga
A. Bahan Papan Kayu Kelas I m3 0.0108 x Rp 6,800,000.00 = Rp 73,440.00
Paku 5 cm dan 7 cm kg 0.100 x Rp 32,609.09 = Rp 3,260.91
A.4.6.1.22. Pemasangan 1 m1 lisplank ukuran (3 x 30) cm, kayu kelas I atau Kelas II
SNI Kebutuhan Kado Satuan Indeks Harga Satuan Jumlah Harga
A. Bahan Papan Kayu Kelas I m3 0.011 x Rp 6,800,000.00 = Rp 74,800.00
Paku 5 cm dan 7 cm kg 0.050 x Rp 32,609.09 = Rp 1,630.45
A.4.6.1.24. Pemasangan 1 m2 dinding pemisah tripleks 12mm/ Teakwood rangkap, rangka kayu kelas II
SNI Kebutuhan Kode Satuan Indeks Harga Satuan Jumlah Harga
A. Bahan Balok Kayu, ukuran (5 x 10) cm m3 0.028 x Rp 5,682,727.27 = Rp 159,116.36
Paku 5 cm dan 10 cm kg 0.150 x Rp 32,609.09 = Rp 4,891.36
Tripleks tebal 12 mm, Ukuran 120 Lbr 0.860 x Rp 471,818.18 = Rp 405,763.64
cm
Lemx 240
kayucm kg 0.560 x Rp 103,518.18 = Rp 57,970.18
1 m' Saluran Got Keliling (Air Hujan), ukuran tinggi 20 cm; Lebar 30 cm
SNI Kebutuhan Satuan Indeks Harga Satuan Jumlah Harga
A.4.7.1.4. 1 m2 Pengecatan Bidang Kayu Baru ( 1 Lapis Plamir ), 1 Lapis Cat Dasar, 2 Lapis Cat Penutup
SNI Kebutuhan Kode Satuan Indeks Harga Satuan Jumlah Harga
A. Bahan Cat Meni Kg 0.200 x Rp 73,518.18 = Rp 14,703.64
Plamir Kg 0.150 x Rp 58,063.64 = Rp 8,709.55
Cat Dasar Kg 0.170 x Rp 94,427.27 = Rp 16,052.64
( Cat Penutup 2 X ) Kg 0.260 x Rp 94,427.27 = Rp 24,551.09
Kuas bh 0.010 x Rp 48,351.82 = Rp 483.52
Pengencer ( thiner ) kg 0.030 x Rp 61,818.18 = Rp 1,854.55
Ampelas lbr 0.200 x Rp 6,448.64 = Rp 1,289.73
A.4.7.1.10. Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup )
SNI Kebutuhan Kode Satuan Indeks Harga Satuan Jumlah Harga
A. Bahan Plamir Kg 0.100 x Rp 58,063.64 = Rp 5,806.36
Cat Dasar Kg 0.100 x Rp 42,936.36 = Rp 4,293.64
Cat Penutup Kg 0.260 x Rp 42,936.36 = Rp 11,163.45
I PEKERJAAN PERSIAPAN
1 Pagar Sementara dari Kayu tinggi 2 m #NAME?
2 Pagar Sementara dari Seng Gelombang tinggi 2 m #NAME?
3 Pagar Sementara dari Kawat Duri tinggi 1.8 m #NAME?
4 Pek. Pengukuran & Pemasangan Bowplank #NAME?
5 Pek. Kantor Direksi Keet , dengan lantai plesteran #NAME?
6 Pembuatan Gudang Semen dan Alat - alat #NAME?
7 Pembuatan Rumah Jaga / Konstruksi Kayu #NAME?
8 Membersihkan Lapangan dan Perataan #NAME?
9 Pembuatan Bedeng Buruh #NAME?
10 Pembuatan Bak Adukan ( 40 x 50 x 20 ) cm #NAME?
11 Pembuatan Stegger dari Bambu, ( 40 x 50 x 20 ) cm #NAME?
12 Pembuatan Jalan Sementara #NAME?
13 Bongkaran Beton Bertulang #NAME?
14 Bongkaran Dinding Tembok Bata Merah #NAME?
II PEKERJAAN TANAH
1 Menggali tanah biasa sedalam 1 meter A. 2.3.1.1 Penggalian 1 m3 tanah biasa sedalam 1 m
2 Menggali tanah biasa sedalam 2 meter A. 2.3.1.2 Pengglian 1 m3 tanah sedalam 2 m
3 Menggali tanah biasa sedalam 3 meter A. 2.3.1.3 Menggali 1 m3 tanah biasa sedalam 3 m
4 Menggali tanah keras sedalam 1 meter A. 2.3.1.4 Menggali 1 m3 tanah Keras sedalam 1 m
5 Menggali tanah cadas sedalam 1 meter Menggali 1 m3 tanah cadas sedalam 1 meter
6 Menggali tanah lumpur sedalam 1 meter A.2.3.1.6 Menggali 1 m3 tanah lumpur sedalam 1 m
7 Mengerjakan stripping tebing setinggi 1 meter Mengerjakan 1 m2 stripping tebing setinggi 1 meter
8 Membuang tanah sejauh 30 meter A.2.3.1.8 Pembuangan 1 m3 tanah sejauh 30 meter
RENCANA ANGGARAN BIAYA
PEKERJAAN : ------------------------
PROYEK : ------------------------
10 Memasang pondasi siklop, 60% beton campuran 1 PC : 2 PB : 3 KR dan 40% batu belah Memasang 1 m3 pondasi siklop, 60% beton campuran 1 PC : 2 PB : 3 KR dan 40% batu belah
11 Memasang pondasi sumuran, diameter 100 cm Memasang 1 m3 pondasi sumuran, diameter 100 cm
IV PEKERJAAN BETON
1 Pekerjaan beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87 A. 4.1.1.1 Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87
2 Pekerjaan beton mutu f’c = 9,8 MPa (K 125), slump (12 ± 2) cm, w/c = 0,78 A. 4.1.1.2 Membuat 1 m3 beton mutu f’c = 9,8 MPa (K 125), slump (12 ± 2) cm, w/c = 0,78
3 Pekerjaan beton mutu f’c = 12,2 MPa (K 150), slump (12 ± 2) cm, w/c = 0,72 A. 4.1.1.3 Membuat 1 m3 beton mutu f’c = 12,2 MPa (K 150), slump (12 ± 2) cm, w/c = 0,72
4 Pekerjaan lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 A. A.4.1.1.4 Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c =
5 Pekerjaan beton mutu f’c = 14,5 MPa (K 175), slump (12 ± 2) cm, w/c = 0,66 A.A. 4.1.1.5 Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), slump (12 ± 2) cm, w/c = 0,66
6 Pekerjaan beton mutu f’c = 16,9 MPa (K 200), slump (12 ± 2) cm, w/c = 0,61 A.A. 4.1.1.6 Membuat 1 m3 beton mutu f’c = 16,9 MPa (K 200), slump (12 ± 2) cm, w/c = 0,61
RENCANA ANGGARAN BIAYA
PEKERJAAN : ------------------------
PROYEK : ------------------------
7 Pekerjaan beton mutu f’c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58 A. 4.1.1.7. Membuat 1 m3 beton mutu f’c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58
8 Pekerjaan beton mutu f’c = 21,7 MPa (K 250), slump (12 ± 2) cm, w/c = 0,56 A. 4.1.1.8. Membuat 1 m3 beton mutu f’c = 21,7 MPa (K 250), slump (12 ± 2) cm, w/c = 0,56
9 Pekerjaan beton mutu f’c = 24,0 MPa (K 275), slump (12 ± 2) cm, w/c = 0,53 A. 4.1.1.9. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275), slump (12 ± 2) cm, w/c = 0,53
10 Pekerjaan beton mutu f’c = 26,4 MPa (K 300), slump (12 ± 2) cm, w/c = 0,52 A. 4.1.1.10. Membuat 1 m3 beton mutu f’c = 26,4 MPa (K 300), slump (12 ± 2) cm, w/c = 0,52
11 Pekerjaan beton mutu f’c = 28,8 MPa (K 325), slump (12 ± 2) cm, w/c = 0,49 A. 4.1.1.11. Membuat 1 m3 beton mutu f’c = 28,8 MPa (K 325), slump (12 ± 2) cm, w/c = 0,49
12 Pekerjaan beton mutu f’c = 31,2 MPa (K 350), slump (12 ± 2) cm, w/c = 0,48 A. 4.1.1.12. Membuat 1 m3 beton mutu f’c = 31,2 MPa (K 350), slump (12 ± 2) cm, w/c = 0,48
13 Pekerjaan beton kedap air dengan strorox – 100 A.4.1.1.13. Membuat 1 m3 beton kedap air dengan strorox – 100
14 Pemasangan PVC Waterstop lebar 150 mm Memasang 1 m’ PVC Waterstop lebar 150 mm
15 Pemasangan PVC Waterstop lebar 200 mm Memasang 1 m’ PVC Waterstop lebar 200 mm
16 Pemasangan PVC Waterstop lebar 230 mm – 320 mm Membuat 1 m’ PVC Waterstop lebar 230 mm – 320 mm
17 Pembesian besi polos atau besi ulir A.4.1.1.17. Pembesian 10 kg dengan besi polos atau besi ulir ( Besi Polos Ø 16 mm )
18 Pekerjaan kabel presstressed polos/strands Memasang 1 kg kabel presstressed polos/strands
19 Pekerjaan jaring kawat baja/wire mesh Memasang 1 kg jaring kawat baja/wire mesh
20 Pekerjaan bekisting untuk pondasi A.4.1.1.20. Memasang 1 m2 bekisting untuk pondasi
21 Pekerjaan bekisting untuk sloof A.4.1.1.21. Memasang 1 m2 bekisting untuk sloof
22 Pekerjaan bekisting untuk kolom A.4.1.1.22. Memasang 1 m2 bekisting untuk kolom
23 Pekerjaan bekisting untuk balok A.4.1.1.23. Memasang 1 m2 bekisting untuk balok
24 Pekerjaan bekisting untuk lantai A.4.1.1.24. Memasang 1 m2 bekisting untuk lantai
25 Pekerjaan bekisting untuk dinding A.4.1.1.25. Memasang 1 m2 bekisting untuk dinding
26 Pekerjaan bekisting untuk tangga A.4.1.1.26. Memasang 1 m2 bekisting untuk tangga
27 Pekerjaan jembatan untuk pengecoran beton A.4.1.1.27. Memasang 1 m2 jembatan untuk pengecoran beton
28 Pekerjaan pondasi beton bertulang (150 kg besi + bekisting) A.4.1.1.28. Membuat 1 m3 pondasi beton bertulang (150 kg besi + bekisting)
29 Pekerjaan sloof beton bertulang (200 kg besi + bekisting) A.4.1.1.29. Membuat 1 m3 sloof beton bertulang (200 kg besi + bekisting)
30 Pekerjaan kolom beton bertulang (300 kg besi + bekisting) A.4.1.1.30. Membuat 1 m3 kolom beton bertulang (300 kg besi + bekisting)
31 Pekerjaan balok beton bertulang (200 kg besi + bekisting) A.4.1.1.31. Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting)
32 Pekerjaan kolom beton bertulang (150 kg besi + bekisting) A.4.1.1.32. Membuat 1 m3 Kolom beton bertulang (150 kg besi + bekisting)
33 Pekerjaan dinding beton bertulang (150 kg besi + bekisting) A.4.1.1.33 Membuat 1 m3 dinding beton bertulang (150 kg besi + bekisting)
34 Pekerjaan dinding beton bertulang (200 kg besi + bekisting) A.4.1.1.34. Membuat 1 m3 dinding beton bertulang (200 kg besi + bekisting)
RENCANA ANGGARAN BIAYA
PEKERJAAN : ------------------------
PROYEK : ------------------------
35 Pekerjaan kolom praktis beton bertulang (11 x 11) cm Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm
36 Pekerjaan ring balok beton bertulang (10 x 15) cm Membuat 1 m’ ring balok beton bertulang (10 x 15) cm
Pekerjaan dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 KP : 1 SM Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata,
14 : 1 PP campuran spesi 1 KP : 1 SM : 1 PP
Pekerjaan dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 KP : 1 SM Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata,
15 : 2 PP campuran spesi 1 KP : 1 SM : 2 PP
16 Pekerjaan dinding Hollow block 20 , campuran spesi 1 PC : 3 PP Memasang 1 m2 dinding HB 20 , campuran spesi 1 PC : 3 PP
17 Pekerjaan dinding Hollow block 20, cam puran spesi 1 PC : 4 PP Memasang 1 m2 dinding HB 20, cam puran spesi 1 PC : 4 PP
18 Pekerjaan dinding Hollow block 15, campuran spesi 1 PC : 3 PP Memasang 1 m2 dinding HB 15, campuran spesi 1 PC : 3 PP
19 Pekerjaan dinding Hollow block 15, campuran spesi 1 PC : 4 PP Memasang 1 m2 dinding HB 15, campuran spesi 1 PC : 4 PP
20 Pekerjaan dinding Hollow block 10, campuran spesi 1 PC : 3 PP Memasang 1 m2 dinding HB 10, campuran spesi 1 PC : 3 PP
21 Pekerjaan dinding Hollow block 10, campuran spesi 1 PC : 4 PP Memasang 1 m2 dinding HB 10, campuran spesi 1 PC : 4 PP
22 Pekerjaan dinding terawang (roster) ukuran (12 x 11 x 24) cm, campuran spesi 1 PC : 3 PP Memasang 1 m2 dinding terawang (roster) ukuran (12 x 11 x 24) cm, campuran spesi 1 PC : 3 P
23 Pekerjaan dinding terawang (roster) ukuran (12 x 11 x 24) cm, campuran spesi 1 PC : 4 PP Memasang 1 m2 dinding terawang (roster) ukuran (12 x 11 x 24) cm, campuran spesi 1 PC : 4 P
24 Pekerjaan dinding bata berongga ekspose ukuran (5 x 11 x 24) cm, campuran spesi 1 PC : 3 PP Memasang 1 m2 dinding bata berongga ekspose ukuran (5 x 11 x 24) cm, campuran spesi 1 PC
VI PEKERJAAN KAYU
1 kusen pintu dan kusen jendela, kayu kelas I A.4.6.1.1 Pembuatan dan Pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas I
2 kusen pintu dan kusen jendela, kayu kelas II atau III A.4.6.1.2 Pembuatan dan Pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas II atau II
3 pintu klamp standar, kayu kelas II Membuat dan memasang 1 m2 pintu klamp standar, kayu kelas II
4 pintu klamp sederhana, kayu kelas III Membuat dan memasang 1 m2 pintu klamp sederhana, kayu kelas III
5 daun pintu panel, kayu kelas I atau II A.4.6.1.5. Pembuatan dan Pemasangan 1 m2 daun pintu panel, kayu kelas I atau II
6 pintu dan jendela kaca, kayu kelas I atau II A.4.6.1.6. Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu kelas I atau II
7 pintu dan jendela jalusi kayu kelas I atau II A.4.6.1.6. Pembuatan dan Pemasangan 1 m2 pintu dan jendela jalusi kayu kelas I atau II
8 daun pintu kayu lapis (plywood) rangkap, rangka tertutup kayu kelas II (lebar sampai 90 cm) #NAME?
9 pintu plywood rangkap, rangka expose kayu kelas I atau II A.4.6.1.9. Pembuatan 1 m2 pintu plywood rangkap, rangka expose kayu kelas I atau II
10 jalusi kusen, kayu kelas I atau II A.4.6.1.10. Memasang 1 m2 jalusi kusen, kayu kelas I atau II
11 teakwood rangkap, rangka expose kayu kelas I A.4.6.1.10. Pemasangan 1 m2 teakwood rangkap, rangka expose kayu kelas I
12 teakwood rangkap lapis formika, rangka expose kayu kelas II Memasang 1 m2 teakwood rangkap lapis formika, rangka expose kayu kelas II
RENCANA ANGGARAN BIAYA
PEKERJAAN : ------------------------
PROYEK : ------------------------
13 konstruksi kuda-kuda konvensional, kayu kelas I, II dan III bentang 6 meter A.4.6.1.13. Pemasangan 1 m3 konstruksi kuda-kuda konvensional, kayu kelas I, II dan III
14 konstruksi kuda-kuda expose, kayu kelas I A.4.6.1.14. Pemasangan 1 m3 konstruksi kuda-kuda expose, kayu kelas I
15 konstruksi gordeng, kayu kelas II A.4.6.1.15. Pemasangan 1 m3 konstruksi gording, kayu kelas I
16 rangka atap genteng keramik, kayu kelas II Memasang 1 m2 rangka atap genteng keramik, kayu kelas I
17 rangka atap genteng beton, kayu kelas II Memasang 1 m2 rangka atap genteng beton, kayu kelas II
18 rangka atap sirap, kayu kelas II Memasang 1 m2 rangka atap sirap, kayu kelas II
19 rangka langit-langit (50 x 100) cm, kayu kelas II atau III Memasang 1 m2 rangka langit-langit (50 x 100) cm, kayu kelas II atau III
20 rangka langit-langit (60 x 60) cm, kayu kelas II atau III A.4.6.1.20 Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III
21 lisplank ukuran (3 x 20) cm, kayu kelas I atau kelas II A.4.6.1.21. Pemasangan 1 m1 lisplank ukuran (3 x 20) cm, kayu kelas I atau kelas II
22 lisplank ukuran (3 x 30) cm, kayu kelas I atau kelas II Memasang 1 m1 lisplank ukuran 2 X (2,5 x 25) cm, kayu kelas I
23 rangka dinding pemisah (60 x 120) cm kayu kelas II atau III A.4.6.1.23. Pemasangan 1 m2 rangka dinding pemisah (60 x 120) cm kayu kelas II atau kelas II
24 dinding pemisah teakwood rangkap, rangka kayu kelas II A.4.6.1.24. Pemasangan 1 m2 dinding pemisah tripleks 12mm/ Teakwood rangkap, rangka kayu
25 dinding pemisah plywood rangkap, rangka kayu kelas II A.4.6.1.25. Memasang 1 m2 dinding pemisah plywood rangkap, rangka kayu kelas II
26 dinding lambriziring dari papan kayu kelas I A.4.6.1.26 Pemasangan 1 m2 dinding Lambrisering dari papan kayu kelas I
27 dinding lambriziring dari plywood ukuran (120 x 240) cm Memasang 1 m2 dinding tripleks t : 12mm ukuran (120 x 240) cm
28 dinding bilik, rangka kayu kelas III atau IV Memasang 1 m2 dinding bilik, rangka kayu kelas III atau IV
1 Pekerjaan lantai ubin PC abu-abu ukuran (40 x 40) cm A.4.4.3.1. Pemasangan 1 m2 lantai ubin PC abu-abu ukuran (40 x 40) cm
2 Pekerjaan lantai ubin PC abu-abu ukuran (30 x 30) cm Memasang 1 m2 lantai ubin PC abu-abu ukuran (30 x 30) cm
3 Pekerjaan lantai ubin PC abu-abu ukuran (20 x 20) cm Memasang 1 m2 lantai ubin PC abu-abu ukuran (20 x 20) cm
4 Pekerjaan lantai ubin warna ukuran (40 x 40) cm A.4.4.3.4 Pemasangan 1 m2 lantai ubin warna ukuran (40 x 40) cm
5 Pekerjaan lantai ubin warna ukuran (30 x 30) cm A.4.4.3.5 Memasang 1 m2 lantai ubin warna ukuran (30 x 30) cm
6 Pekerjaan lantai ubin warna ukuran (20 x 20) cm A.4.4.3.6 Memasang 1 m2 lantai ubin warna ukuran (20 x 20) cm
7 Pekerjaan lantai ubin teraso ukuran (40 x 40) cm A.4.4.3.7 Pemasangan 1 m2 lantai ubin teraso ukuran (40 x 40) cm
8 Pekerjaan lantai ubin teraso ukuran (30 x 30) cm Memasang 1 m2 lantai ubin teraso ukuran (30 x 30) cm
9 Pekerjaan lantai ubin granit ukuran (40 x 40) cm Memasang 1 m2 lantai ubin granit ukuran (40 x 40) cm
10 Pekerjaan lantai ubin granit ukuran (30 x 30) cm Memasang 1 m2 lantai ubin granit ukuran (30 x 30) cm
11 Pekerjaan lantai ubin teralux ukuran (40 x 40) cm A.4.4.3.11. Pemasangan 1 m2 lantai ubin teralux ukuran (40 x 40) cm
RENCANA ANGGARAN BIAYA
PEKERJAAN : ------------------------
PROYEK : ------------------------
12 Pekerjaan lantai ubin teralux ukuran (30 x 30) cm A.4.4.3.12. Pemasangan 1 m2 lantai ubin teralux ukuran (30 x 30) cm
13 Pekerjaan lantai ubin teralux marmer ukuran (60 x 60) cm A.4.4.3.14. Pemasangan 1 m2 Lantai ubin teralux marmer ukuran (60 x 60) cm
14 Pekerjaan lantai ubin teralux marmer ukuran (40 x 40) cm A.4.4.3.11. Memasang 1 m2 lantai ubin teralux marmer ukuran (40 x 40) cm
15 Pekerjaan lantai ubin teralux marmer ukuran (30 x 30) cm Memasang 1 m2 lantai ubin teralux marmer ukuran (30 x 30) cm
16 Pekerjaan plint ubin PC abu-abu ukuran (15 x 20) cm Memasang 1 m plint ubin PC abu-abu ukuran (15 x 20) cm
17 Pekerjaan plint ubin PC abu-abu ukuran (10 x 30) cm Memasang 1 m plint ubin PC abu-abu ukuran (10 x 30) cm
18 Pekerjaan plint ubin PC abu-abu ukuran (10 x 40) cm A.4.4.3.18 Pemasangan 1 m plint ubin PC abu-abu ukuran (10 x 40) cm
19 Pekerjaan plint ubin PC warna ukuran (10 x 20) cm Memasang 1 m plint ubin PC warna ukuran (10 x 20) cm
20 Pekerjaan plint ubin PC warna ukuran (10 x 30) cm Memasang 1 m plint ubin PC warna ukuran (10 x 30) cm
21 Pekerjaan plint ubin PC warna ukuran (10 x 40) cm Memasang 1 m plint ubin PC warna ukuran (10 x 40) cm
22 Pekerjaan plint ubin teraso ukuran (10 x 30) cm Memasang 1 m plint ubin teraso ukuran (10 x 30) cm
23 Pekerjaan plint ubin teraso ukuran (10 x 40) cm Memasang 1 m plint ubin teraso ukuran (10 x 40) cm
24 Pekerjaan plint ubin granit ukuran (10 x 40) cm A.4.4.3.21. Pemasangan 1 m plint Ubin warna ukuran (10 x 40) cm
25 Pekerjaan plint ubin granit ukuran (10 x 30) cm Memasang 1 m plint ubin granit ukuran (10 x 30) cm
26 Pekerjaan plint ubin teralux kerang ukuran (10 x 40) cm Memasang 1 m plint ubin teralux kerang ukuran (10 x 40) cm
27 Pekerjaan plint ubin teralux kerang ukuran (10 x 30) cm Memasang 1 m plint ubin teralux kerang ukuran (10 x 30) cm
28 Pekerjaan plint ubin teralux marmer ukuran (10 x 60) cm A.4.4.3.28 Pemasangan 1 m plint ubin teralux marmer ukuran (10 x 60) cm
29 Pekerjaan plint ubin teralux marmer ukuran (10 x 40) cm A.4.4.3.29 Pemasangan 1 m plint ubin teralux marmer ukuran (10 x 40) cm
30 Pekerjaan plint ubin teralux marmer ukuran (10 x 30) cm Memasang 1 m plint ubin teralux marmer ukuran (10 x 30) cm
31 Pekerjaan lantai teraso cor ditempat, tebal 3 cm Memasang 1 m2 lantai teraso cor ditempat, tebal 3 cm
32 Pekerjaan lantai keramik artistik ukuran (10 x 20) cm Memasang 1 m2 lantai keramik artistik ukuran (10 x 20) cm
33 Pekerjaan lantai keramik artistik ukuran (10 x 10) cm atau (5 x 20) cm Memasang 1 m2 lantai keramik artistik ukuran (10 x 10) cm atau (5 x 20) cm
34 Pekerjaan lantai keramik ukuran (33 x 33) cm A.4.4.3.34. Pemasangan 1 m2 lantai keramik ukuran (33 x 33) cm
35 Pekerjaan lantai keramik ukuran (30 x 30) cm #NAME?
36 Pekerjaan lantai keramik ukuran (20 x 20) cm A.4.4.3.36 Pemasangan 1 m2 lantai keramik ukuran (20 x 20) cm
37 Pekerjaan lantai keramik ukuran (10 x 33) cm, variasi/border Memasang 1 m2 lantai keramik ukuran (10 x 33) cm, variasi/border
38 Pekerjaan lantai mosaik ukuran (30 x 30) cm, campuran spesi 1 PC : 3 PP Memasang 1 m2 lantai mosaik ukuran (30 x 30) cm, campuran spesi 1 PC : 3 PP
39 Pekerjaan plint keramik ukuran (10 x 20) cm A.4.4.3.39. Pemasangan 1 m’ plint keramik ukuran (10 x 20) cm
40 Pekerjaan plint keramik ukuran (10 x 10) cm Memasang 1 m’ plint keramik ukuran (10 x 10) cm
41 Pekerjaan plint keramik ukuran (5 x 20) cm Memasang 1 m’ plint keramik ukuran (5 x 20) cm
RENCANA ANGGARAN BIAYA
PEKERJAAN : ------------------------
PROYEK : ------------------------
42 Pekerjaan plint internal cove artistik ukuran (5 x 5 x 20) cm Memasang 1 m’ plint internal cove artistik ukuran (5 x 5 x 20) cm
43 Pekerjaan lantai marmer ukuran (100 x 100) cm Memasang 1 m2 lantai marmer ukuran (100 x 100) cm
44 Pekerjaan lantai karpet Memasang 1 m2 lantai karpet
45 Pekerjaan underlayer Memasang 1 m2 underlayer
46 Pekerjaan lantai parquet Memasang 1 m2 lantai parquet
47 Pekerjaan lantai kayu (gym floor) Memasang 1 m2 lantai kayu (gym floor)
48 Pekerjaan dinding porselen ukuran (11 x 11) cm Memasang 1 m2 dinding porselen ukuran (11 x 11) cm
49 Pekerjaan dinding porselin ukuran (10 x 20) cm Memasang 1 m2 dinding porselin ukuran (10 x 20) cm
50 Pekerjaan dinding porselin ukuran (20 x 20) cm Memasang 1 m2 dinding porselin ukuran (20 x 20) cm
51 Pekerjaan dinding keramik artistik ukuran (10 x 20) cm Memasang 1 m2 dinding keramik artistik ukuran (10 x 20) cm
52 Pekerjaan dinding keramik artistik ukuran (5 x 20) cm Memasang 1 m2 dinding keramik artistik ukuran (5 x 20) cm
53 Pekerjaan dinding keramik ukuran (10 x 20) cm Memasang 1 m2 dinding keramik ukuran (10 x 20) cm
54 Pekerjaan dinding keramik ukuran (20 x 20) cm A.4.4.3.54 Pemasangan 1 m2 dinding keramik ukuran (20 x 20) cm
55 Pekerjaan dinding marmer ukuran (100 x 100) cm Memasang 1 m2 dinding marmer ukuran (100 x 100) cm
56 Pekerjaan dinding bata pelapis ukuran (3 x 7 x 24) cm Memasang 1 m2 dinding bata pelapis ukuran (3 x 7 x 24) cm
57 Pekerjaan dinding batu paras Memasang 1 m2 dinding batu paras
58 Pekerjaan dinding batu tempel hitam A.4.4.3.58. Pemasangan 1 m2 dinding batu tempel hitam
59 Pekerjaan lantai vinyl ukuran (30 x 30) cm KL I Memasang 1 m2 lantai vinyl ukuran (30 x 30) cm KL I
60 Pekerjaan wall paper, lebar 50 cm Memasang 1 m2 wall paper, lebar 50 cm
61 Pekerjaan floor hardener Memasang 1 m2 floor hardener
62 Pekerjaan plint vinyil karet ukuran (30 x 30) cm dengan perekat Memasang 1 m plint vinyil karet ukuran (30 x 30) cm dengan perekat
63 Pekerjaan plint kayu kelas II ukuran (2 x 10) cm Memasang 1 m plint kayu kelas II ukuran (2 x 10) cm
1 Pekerjaan langit-langit asbes semen, tebal 4 mm, 5 mm, dan 6 mm Memasang 1 m2 langit-langit asbes semen, tebal 4 mm, 5 mm, dan 6 mm
2 Pekerjaan langit-langit akustik ukuran (30 x 30) cm Memasang 1 m2 langit-langit akustik ukuran (30 x 30) cm
3 Pekerjaan langit-langit akustik ukuran (30 x 60) cm Memasang 1 m2 langit-langit akustik ukuran (30 x 60) cm
4 Pekerjaan langit-langit akustik ukuran (60 x 120) cm Memasang 1 m2 langit-langit akustik ukuran (60 x 120) cm
RENCANA ANGGARAN BIAYA
PEKERJAAN : ------------------------
PROYEK : ------------------------
5 Pekerjaan langit-langit tripleks ukuran (120 x 240) cm, tebal 3 mm, 4 mm dan 6 mm A.4.5.1.5 Pemasangan 1 m2 langit-langit tripleks ukuran (120 x 240) cm, tebal 4 mm
6 Pekerjaan langit-langit lambriziring kayu, tebal 9 mm Memasang 1 m2 langit-langit lambriziring kayu, tebal 9 mm
7 Pekerjaan langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm Memasang 1 m2 langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm
8 Pekerjaan list langit-langit gypsum profil Memasang 1 m’ list langit-langit gysum profil
9 Pekerjaan langit-langit akustik ukuran (60 x 120) cm + rangka alluminium Memasang 1 m2 langit-langit akustik ukuran (60 x 120) cm + rangka alluminium
10 Pekerjaan list langit-langit kayu profil A.4.5.1.9. Pemasangan 1 m’ list langit-langit kayu profil
2 Pekerjaan Atap Genteng Kodok / Glazzur 1m² Pasang Atap Genteng Kodok / Glazzur
3 Pekerjaan Atap Genteng Palentong Super / Besar 1m² Pasang Atap Genteng Palentong Super / Besar
4 Pekerjaan Genteng Bubung Palentong 1m' Pasang Genteng Bubung Palentong
5 Pekerjaan Genteng Bubung Kodok Glazzur 1 m' Pasang Genteng Bubung Kodok Glazzur
6 Pekerjaan Genteng Bubung Palentong Besar 1m' Pasang Genteng Bubung Palentong Besar
7 Pekerjaan Rooflight Fiberglass ( 180 x 90 ) cm 1m' Pasang Rooflight Fiberglass ( 180 x 90 ) cm
8 Pekerjaan Asbes Gelombang ( 2.50 x 0.92 m ) X 5mm A.4.5.2.8. Pemasangan 1 m2 Atap Asbes Gelombang ( 2.50 x 0.92 m ) X 5mm
9 Pekerjaan Asbes Gelombang ( 2.25 x 0.92 m ) X 5mm A.4.5.2.9. Pemasangan 1 m2 Atap Asbes Gelombang ( 2.25 x 0.92 m ) X 5mm
10 Pekerjaan Asbes Gelombang ( 2.00 x 0.92 m ) X 5mm A.4.5.2.10. Pemasangan 1 m2 Atap Asbes Gelombang ( 2.00 x 0.92 m ) X 5mm
11 Pekerjaan Asbes Gelombang ( 1.80 x 0.92 m ) X 5mm A.4.5.2.11.Pemasangan 1 m2 Atap Asbes Gelombang ( 1.80 x 0.92 m ) X 5mm
12 Pekerjaan Asbes Gelombang ( 300 x 1.05 m ) X 4mm A.4.5.2.12. Pemasangan 1 m2 Atap Asbes Gelombang ( 300 x 1.05 m ) X 4mm
13 Pekerjaan Asbes Gelombang ( 270 x 1.05 m ) X 4mm A.4.5.2.13. Pemasangan 1 m2 Atap Asbes Gelombang ( 270 x 1.05 m ) X 4mm
14 Pekerjaan Asbes Gelombang ( 240 x 1.05 m ) X 4mm 1m² Pasang Atap Asbes Gelombang ( 3 x 1.05 m ) X 3mm
15 Pekerjaan Asbes Gelombang ( 210 x 1.05 m ) X 4mm 1m² Pasang Atap Asbes Gelombang ( 210 x 1.05 m ) X 4mm
16 Pekerjaan Asbes Gelombang ( 1.5 x 1.05 m ) X 4mm 1m² Pasang Atap Asbes Gelombang ( 1.5 x 1.05 m ) X 4mm
17 Pekerjaan Asbes Gelombang ( 3.00 x 1.08 m ) X 6mm A.4.5.2.17. 1 Pemasangan 1 m2 Atap Asbes Gelombang ( 3.00 x 1.08 m ) X 6mm
18 Pekerjaan Asbes Gelombang ( 2.7 x 1.08 m ) X 6mm 1m² Pasang Atap Asbes Gelombang ( 2.7 x 1.08 m ) X 6mm
19 Pekerjaan Asbes Gelombang ( 2.4 x 1.08 m ) X 6mm 1m² Pasang Atap Asbes Gelombang ( 2.4 x 1.08 m ) X 6mm
20 Pekerjaan Asbes Gelombang ( 2.1 x 1.08 m ) X 6mm 1m² Pasang Atap Asbes Gelombang ( 2.1 x 1.08 m ) X 6mm
21 Pekerjaan Asbes Gelombang ( 1.80 x 1.08 m ) X 6mm 1m² Pasang Atap Asbes Gelombang ( 1.80 x 1.08 m ) X 6mm
22 Pekerjaan Bubung Stel Gelombang 0.92m A.4.5.2.22. Pemasangan 1m' Bubung Stel Gelombang 0.92m
23 Pekerjaan Nok Stel Gelombang 0.92m A.4.5.2.23 .Pemasangan 1m' Nok Stel Gelombang 1,05m
24 Pekerjaan Nok Stel Gelombang 1.05m 1m' Pasang Bubungan Asbes Gelombang 3mm
25 Pekerjaan Nok Stel Gelombang 1.08m A.4.5.2.24. Pemasangan 1 m' Bubung Stel Gelombang 1.08m
26 Pekerjaan Nok Paten 0.92m 1m' Pasang Nok Paten 0.92m
27 Pekerjaan Nok Paten 1.05m 1m' Pasang Nok Paten 1.05m
28 Pekerjaan Nok Paten 1.08m 1m' Pasang Nok Paten 1.08m
29 Pekerjaan Nok Stel rata 0.92m 1m' Pasang Nok Stel rata 0.92m
30 Pekerjaan Nok Stel rata 1.05m 1m' Pasang Nok Stel rata 1.05m
31 Pekerjaan Atap Genteng Beton 1m² Pasang Atap Genteng Beton
RENCANA ANGGARAN BIAYA
PEKERJAAN : ------------------------
PROYEK : ------------------------
XI PEKERJAAN SANITASI
1 Pekerjaan Kloset Duduk / Monoblok A.5.1.1.1. Pemasangan 1 Buah Kloset Duduk / Monoblok
2 Pekerjaan Kloset Jongkok Porselen A.5.1.1.2. Pemasangan 1 buah Kloset Jongkok Porselen
3 Pekerjaan Kloset Jongkok Teraso Memasang 1 buah Kloset Jongkok Teraso
4 Pekerjaan Urinoir A.5.1.1.4.Pemasangan 1 buah Urinoir
5 Pekerjaan buah Wastafel A.5.1.1.5. Pemasangan 1 buah Wastafel
6 Pekerjaan Bak Mandi Teraso, volume 0.30 m³ Memasang 1 buah Bak Mandi Teraso, volume 0.30 m³
7 Pekerjaan Bak Mandi Fiberglass, volume 0.30 m³ A.5.1.1.7. Pemasangan Bak Fiberglass, volume 1 m³
8 Pekerjaan Bak Mandi Batu bata, volume 0.30 m³ Memasang 1 buah Bak Mandi Batu bata, volume 0.30 m³
9 Pekerjaan Badkip Porselen Memasang 1 buah Badkip Porselen
10 Pekerjaan Bak Fiberglass volume 1 m³ air A.5.1.1.10. Pemasangan 1 buah Bak air Fiberglass volume 1 m³ air
11 Pekerjaan Penyalur Air limbah jenis Pipa Tanah Ø15 cm Memasang 1 m' Pipa Penyalur Air limbah jenis Pipa Tanah Ø 20 cm
12 Pekerjaan Penyalur Air limbah jenis Pipa Tanah Ø 20 cm Memasang 1 m' Pipa Penyalur Air limbah jenis Pipa Tanah Ø 15 cm
13 Pekerjaan Pipa Beton Ø 5 cm - 20 cm Memasang 1 m' Pipa Beton Ø 15 cm - 20 cm
14 Pekerjaan Pipa Beton Ø 30 cm - 100 cm Memasang 1 m' Pipa Beton Ø 30 cm - 100 cm
15 Pekerjaan Bak Kontrol pasangan Batu Bata ukuran (30 x 30 )cm, t = 35cm Memasang 1 m' buah Bak Kontrol pasangan Batu Bata ukuran (30 x 30 )cm, t = 50cm
RENCANA ANGGARAN BIAYA
PEKERJAAN : ------------------------
PROYEK : ------------------------
16 Pekerjaan Bak Kontrol pasangan Batu Bata ukuran (45 x 45 )cm, t = 50cm Memasang 1 m' buah Bak Kontrol pasangan Batu Bata ukuran (45 x 45 )cm, t = 50cm
17 Pekerjaan Bak Kontrol pasangan Batu Bata ukuran (60 x 60 )cm, t = 65cm Memasang 1 m' buah Bak Kontrol pasangan Batu Bata ukuran (60 x 60 )cm, t = 65cm
18 Pekerjaan Pipa Galvanis Ø ½" A.5.1.1.25. Pemasangan 1 m' Pipa PVC tipe AW diameter ½"
19 Pekerjaan Pipa Galvanis Ø ¾" A.5.1.1.20. Pemasangan 1 m' Pipa Galvanis Ø ¾"
20 Pekerjaan Pipa Galvanis Ø 1" A.5.1.1.21. Pemasangan 1 m' Pipa Galvanis Ø 1"
21 Pekerjaan Pipa Galvanis Ø 1½" A.5.1.1.22. Memasang 1 m' Pipa Galvanis Ø 1½"
22 Pekerjaan Pipa Galvanis Ø 3" #NAME?
23 Pekerjaan Pipa Galvanis Ø 4" Memasang 1 m' Pipa Galvanis Ø 4"
24 Pekerjaan Pipa PVC tipe AW Ø ½" A.5.1.1.25. Pemasangan 1 m' Pipa PVC tipe AW Ø ½"
25 Pekerjaan Pipa PVC tipe AW Ø ¾" A.5.1.1.26. Pemasangan 1 m' Pipa PVC tipe AW Ø ¾"
26 Pekerjaan Pipa PVC tipe AW Ø 1" A.5.1.1.27. Pemasangan 1 m' Pipa PVC tipe AW Ø 1"
27 Pekerjaan Pipa PVC tipe AW Ø 1½" Memasang 1 m' Pipa PVC tipe AW Ø 1½"
28 Pekerjaan Pipa PVC tipe AW Ø 2" A.5.1.1.29. Pemasangan 1 m' Pipa PVC tipe AW Ø 2"
29 Pekerjaan Pipa PVC tipe AW Ø 2½" Memasang 1 m' Pipa PVC tipe AW Ø 2½"
30 Pekerjaan Pipa PVC tipe AW Ø 3" A.5.1.1.31. Pemasangan 1 m' Pipa PVC tipe AW Ø 3"
31 Pekerjaan Pipa PVC tipe AW Ø 4" A.5.1.1.32. Pemasangan 1 m' Pipa PVC tipe AW Ø 4"
32 Pekerjaan Bak Cuci Piring Stainles Steel A.5.1.1.12. Pemasangan 1 bh Bak Cuci Piring Stainles Steel
33 Pekerjaan Bak Cuci Piring Teraso Memasang 1 bh Bak Cuci Piring Teraso
34 Pekerjaan Kran Ø ¾" atau ½" A.5.1.1.19. Pemasangan 1 bh Kran Ø ¾" atau ½" ( Wastafel )
35 Pekerjaan Floor Drain A.5.1.1.14. Pemasangan 1 bh Floor Drain
1 Pekerjaan kunci Tanam Antik A.4.6.2.1. Pemasangan 1 Buah kunci Tanam Antik
2 Pekerjaan kunci Tanam Biasa A.4.6.2.2. Pemasangan 1 Buah kunci Tanam Biasa
3 Pekerjaan kunci Tanam Kamar Mandi 1 Buah Pasang kunci Silinder
4 Pekerjaan kunci Silinder A.4.6.2.3. Pemasangan 1 buah kunci Tanam Kamar Mandi
5 Pekerjaan Engsel Pintu A.4.6.2.5. Pemasangan 1 Buah Engsel Pintu
6 Pekerjaan Engsel Jendela Kupu - kupu A.4.6.2.6. Pemasangan 1 buah Engsel Jendela Kupu - kupu
7 Pekerjaan Engsel Angin 1 Buah Pasang Engsel Angin
RENCANA ANGGARAN BIAYA
PEKERJAAN : ------------------------
PROYEK : ------------------------
m2 Rp - Rp - Rp - Rp -
m2 Rp - Rp - Rp - Rp -
m2 Rp - Rp - Rp - Rp -
WAKTU PELAKSANAAN
MASA
NO UARAIAN PEKERJAAN BOBOT % BULAN I BULAN II BULAN III BULAN IV BULAN V BULAN VI PEMELIHA KET
AAN
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
JUMLAH % #REF!
RENCANA PROGRES #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
RENCANA PROGRES KOMULATIF #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF!
KONSULTAN PERENCANA
CV.TRIO MERLY BERSAUDARA
YOHANIS TUKU,ST
Pimpinan Cabang
PEKERJAAN : PEMBANGUNAN POS JAGA INLET
LOKASI : BBI MUSATFAK
TOTAL HARGA
NO URAIAN PEKERJAAN SAT VOLUME HARGA SATUAN ( Rp. )
(Rp.)
a b c d e f
I. PEKERJAAN PENDAHULUAN
1 Pengukuran dan Pemasangan Bowplank m' 19.00 145,871.73 2,771,562.82
SUB TOTAL : 2,771,562.82
II. PEK. TANAH
1 Pek.Galian Tanah Pondasi m³ 7.200 109,682.95 789,717.27
2 Pek. Urugan Kembali Bekas Galian m³ 2.400 81,888.64 196,532.73
3 Pek. Urungan Pasir Bawah pondasi m³ 0.800 2,523,509.55 2,018,807.64
SUB TOTAL : 3,005,057.64
III PEK.PONDASI
1 Pas. Pondasi Batu Kosong Batu Kali/Aanstamping m³ 3.200 3,648,174.41 11,674,158.11
2 Pas. Pondasi Batu Kali 1 PC : 4 PS m³ 5.400 6,859,846.59 37,043,171.59
SUB TOTAL : 48,717,329.70
IV PEK. BETON
1 Pek. Beton Sloof ( 20 /25 ) beton mutu K.200 m³ 1.00 18,774,693.40 18,774,693.40
2 Pek. Kolom Praktis ( 8 / 12 ) beton mutu K.200 m³ 0.181 42,437,798.67 7,681,241.56
3 Pek. Kolom ( 15/15) beton mutu K.175 m³ 0.061 34,443,739.09 2,101,068.08
4 Pek. Beton Ring Balok ( 15 / 20 ) beton mutu K.175 m³ 0.600 26,529,005.04 15,917,403.02
SUB TOTAL : 44,474,406.06
V. PEK. DINDING
1 Pas. Dinding Batako 1 Pc : 4 Ps m² 36.409 680,701.00 24,783,642.71
2 Pek. Plesteran Dinding 1 Pc : 4 Ps m² 72.817 238,172.59 17,343,013.54
3 Pek. Plesteran Dinding Kolom 1 Pc : 3 Ps m² 6.156 260,888.63 1,606,030.39
4 Pek. Plesteran Dinding Sloof 1 Pc : 3 Ps m² 3.750 260,888.63 978,332.35
5 Pek. Acian Dinding m² 72.817 105,426.36 7,676,831.51
6 Pek. Acian Dinding Kolom m² 6.156 105,426.36 649,004.69
7 Pek. Acian Dinding Sloof m² 3.750 105,426.36 395,348.86
SUB TOTAL : 53,432,204.06
VI. PEK. PINTU
1 Kusen Pintu Kayu Sage 5/10 m³ 0.128 13,329,884.07 1,706,225.16
2 Pas.Pintu Panel m² 3.600 1,138,845.45 4,099,843.63
3 Pas.jendela Panel m² 0.800 819,510.00 655,608.00
4 Pas. Kaca t : 5mm m² 1.430 1,161,238.10 1,660,570.48
SUB TOTAL : 8,122,247.26
VII. PEK.KUDA-KUDA DAN ATAP
1 Pek. Kuda-Kuda 5/10 Kayu kls I m³ 0.308 10,922,956.35 3,364,270.56
2 Pek. Gording 5/10 Kayu kls II m³ 0.338 13,038,905.89 4,407,150.19
3 Pek.Atap Seng Gelombang Bjls 30 m² 39.117 121,721.95 4,761,397.69
4 Pek. Nok Seng Plat Bjls 30 m' 13.300 66,390.19 882,989.59
5 Pek Papan Lisplank 2 x ( 2,5 /20 ) m' 21.720 136,060.91 2,955,242.94
SUB TOTAL : 16,371,050.97
VIII. PEK. PLAFON
1 Pek. Rangka Plafond Kayu 5/7 m² 26.483 197,352.09 5,226,475.42
2 Pek. Penutup Plafond Tripleks 4 mm m² 26.483 101,092.82 2,677,241.10
3 Pek.List Plafond ( Kayu Di Profil ) m' 62.800 53,087.14 3,333,872.16
SUB TOTAL : 11,237,588.68
IX. PEK. LANTAI
1 Pek. Urungan Timbunan Bawah Lantai ( Pasir ) m³ 0.629 2,523,509.55 1,587,287.50
2 Pek. Timbunan Pilihan bawa lantai m³ 3.771 2,316,580.68 8,735,825.75
3 Pek. Cor Beton tumbuk Lantai T : 10 Cm m³ 1.257 7,747,453.63 9,738,549.21
4 Pek.Acian lantai m² 12.570 105,426.36 1,325,209.39
SUB TOTAL : 21,386,871.86
X. PEK. PENGECETAN
1 Pek.Cat Dinding m² 82.723 38,755.64 3,205,982.88
2 Pek. Cat Plafond m² 26.483 38,755.64 1,026,365.64
3 Cat Kilap Kusen Pintu,Jendela m² 4.662 81,286.54 378,957.85
4 Pek. Cat Kilap Daun Pintu m² 7.200 81,286.54 585,263.09
5 Pek.Kilap Daun Jendela m² 0.794 81,286.54 64,541.51
6 Pek.Cat Lisplank m² 4.344 81,286.54 353,108.73
SUB TOTAL : 5,614,219.71
XI. PEK. INSTALASI LISTRIK
1 Pas. Instalasi Titik Saklar tunggal 2x1,5NYM ttk 1.00 269,467.73 269,467.73
2 Pas. Instalasi Titik Saklar double 2x1,5NYM ttk 1.00 284,930.77 284,930.77
3 Pas. Instalasi Titik Stop Kontak 3x2.5NYM ttk 1.00 263,104.09 263,104.09
4 Pas. Instalasi Lampu XL 18 Wtt bh 3.00 360,777.73 1,082,333.18
SUB TOTAL : 1,899,835.77
XII. PEK.PENGGANTUNG/ PENGUNCI
1 Pas. Engsel Pintu Psg 2.00 109,556.88 219,113.75
2 Pas. Engsel Jendela Psg 2.00 85,881.09 171,762.18
3 Pas. Kait/ Hak Angin Bh 4.00 73,013.66 292,054.64
4 Pas.Kunci Tanam Biasa ( Royal Besar ) Psg 2.00 328,573.41 657,146.82
SUB TOTAL : 1,340,077.39
TOTAL : 218,372,451.92
PEKERJAAN : REHABILITASI SALURAN PEMASUKKAN INLET PADA PINTU AIR MASUK
LOKASI : BBI MUSATFAK
a b c d e f
I. PEKERJAAN PENDAHULUAN
1 Pek.Pembersihan Lokasi / Pembongkaran pagar lama Ls 1.000 2,500,000 2,500,000.00
2 Sewa direksikeet / Barak Kerja Ls 1.000 8,000,000.00 8,000,000.00
3 Pek. Papan Nama Proyek Ls 1.000 500,000.00 500,000.00
4 Pek. Pengukuran dan Pemasangan Bowplank m' 32.000 145,871.73 4,667,895.27
SUB TOTAL : 15,667,895.27
TOTAL : 526,032,344.56
PEKERJAAN : PEMBANGUNAN JALAN AKSES INLET
LOKASI : BBI MUSATFAK
a b c d e f
I. PEKERJAAN PENDAHULUAN
1 Pembersihan dan pemadatan tanah halaman Ls 1.00 5,000,000.00 5,000,000.00
2 Pengukuran dan Pemasangan Bowplank m' 19.00 145,871.73 2,771,562.82
SUB TOTAL : 7,771,562.82
II. PEK. TANAH
1 Pek.Galian Tanah Pondasi m³ 3.965 109,682.95 434,892.91
2 Pek. Urugan Kembali Bekas Galian m³ 1.322 81,888.64 108,256.78
3 Pek. Urungan Pasir Bawah pondasi m³ 0.486 2,523,509.55 1,226,425.64
SUB TOTAL : 1,769,575.33
III PEK.PONDASI
1 Pas. Pondasi Batu Kali 1 PC : 4 PS m³ 4.536 6,859,846.59 31,116,264.13
3 Pek Cor Kaki Tiang beton mutu K.175 m³ 0.032 9,181,694.34 293,814.22
SUB TOTAL : 31,410,078.35
IV. PEK.KOLOM DAN ATAP
1 Kolom Kayu 2x5/10 m³ 0.126 10,744,584.63 1,353,817.66
2 Pek.Kuda - Kuda balok 5/10 m³ 0.137 10,922,956.35 1,496,445.02
3 Pek.Gording balok 5/10 m³ 0.471 13,038,905.89 6,141,324.67
4 Pek.Atap Seng Bjls 30 m² 37.814 121,721.95 4,602,793.99
5 Pek.Lisplank kayu m' 29.850 159,590.45 4,763,775.06
SUB TOTAL : 18,358,156.41
V. PEK. LANTAI
1 Pek.Urugan Timbunan Pilihan m³ 3.900 2,316,580.68 9,034,664.66
2 Pek. Timbunan Pasir Urug Bawah Lantai m³ 1.300 2,523,509.55 3,280,562.41
3 Pek. Cor Beton tumbuk Lantai T : 10 Cm beton mutu K.100 m³ 3.390 7,747,453.63 26,263,867.81
SUB TOTAL : 38,579,094.88
Terbilang :
Dua Milyar Sembilan Puluh Lima Juta Lima Ratus Ribu Rupiah
DINAS PERIKANAN
KABUPATEN JAYAWIJAYA
LAMBERT HASEGEM,S.IP
NIP 19640102 198603 1 026