Kurva S Progress Lap Mingguan Dan Bulanan Sampai Minggu Ke 10 Addendum Nonmaterial Terpasang1
Kurva S Progress Lap Mingguan Dan Bulanan Sampai Minggu Ke 10 Addendum Nonmaterial Terpasang1
Kegiatan : PEMBANGUNAN PINTU AIR DAN NORMALISASI DI HANDIL BARU DAN MUARA SEMBILANG KECAMATAN SAMBOJA
Pelaksana : CV. PAGI PETANG
No. Kontrak : P.342/DPU/SDA/600.1.4.1/7/2023
Tanggal Kontrak : 24 Juli 2023
Nilai Kontrak : 1,221,543,853.00 bulan1 bulan 2 bulan 3 bulan 4
Waktu Pelaksanaan : 90 ( Sembilan Puluh ) Hari Kalender
PROGRESS
Lokasi : KEC. SAMBOJA prestasi
25-Jul 1-Aug 8-Aug 15-Aug 22-Aug 29-Aug 5-Sep 12-Sep 19-Sep 26-Sep 3-Oct 10-Oct 17-Oct
31-Jul 7-Aug 14-Aug 21-Aug 28-Aug 4-Sep 11-Sep 18-Sep 25-Sep 2-Oct 9-Oct 16-Oct 23-Oct
No. Uraian Pekerjaan Kode Analisa Volume bobot
1 2 3 4 5 6 7 8 9 10 11 12 13
I. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi LA.1 1.00 7.15% 1.37% 1.30% 0.90% 0.90% 0.90% 0.90% 87%
-demob 6.27%
-pemasangan papan kegiatan 0.06%
-sewa barak 0.82%
2 Sistem Manajemen dan Keselamatan Konstruksi (SMKK) - 1.00 1.20% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 46%
100%
RENCANA MINGGUAN ADD-01 (%) 0.64% 0.73% 2.70% 4.68% 6.64% 10.23% 12.47% 13.76% 13.49% 13.37% 10.44% 8.20% 2.64%
RENCANA KOMULATIF ADD-01 (%) 0.64% 1.37% 4.07% 8.75% 15.39% 25.63% 38.10% 51.86% 65.35% 78.72% 89.16% 97.36% 100.00%
REALISASI MINGGUAN ADD-01 (%) 1.46% 0.00% 0.00% 0.00% 0.00% 13.62% 19.91% 9.95% 3.59% 4.24%
REALISASI KOMULATIF ADD-01 (%) 1.46% 1.46% 1.46% 1.46% 1.46% 15.08% 34.98% 44.94% 48.53% 52.77%
DEVIASI (%) 0.82% 0.09% -2.61% -7.29% -13.93% -10.55% -3.11% -6.92% -16.82% -25.95%
44.78%
KONTRAK REALISASI MINGGU LALU REALISASI MINGGU INI REALISASI S/D MINGGU INI
NO URAIAN BOBOT BOBOT BOBOT BOBOT
% (%) (%) (%)
I. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi 1 Ls 78,700,000.00 78,700,000.00 7.15% 0.19 1.37% 0.19 1.37%
-demob 69,000,000.00 6.27%
-pemasangan papan kegiatan 700,000.00 0.06%
-sewa barak 9,000,000.00 0.82%
2 Sistem Manajemen dan Keselamatan Konstruksi (SMKK) 1 Ls 13,152,307.77 13,152,307.77 1.20% 0.08 0.09% 0.08 0.09%
-
II. PEKERJAAN NORMALISASI -
I. Pekerjaan Normalisasi -
1 Galian Tanah Berlumpur di Sungai 526.47 m3 52,680.00 27,734,439.60 2.52% 0.00% - 0.00%
- tenaga 34453.50 19,952,607.56 1.81%
- peralatan sewa long-arm 13437.41 7,781,832.57 0.71%
KONTRAK REALISASI BULAN LALU REALISASI BULAN INI REALISASI S/D BULAN INI
NO URAIAN BOBOT BOBOT BOBOT BOBOT
% (%) (%) (%)
I. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi 1 Ls
-demob
-pemasangan papan kegiatan
-sewa barak
2 Sistem Manajemen dan Keselamatan Konstruksi (SMKK) 1 Ls
JUMLAH TOTAL PEKERJAAN PERSIAPAN
II. PEKERJAAN NORMALISASI
I. Pekerjaan Normalisasi
1 Galian Tanah Berlumpur di Sungai 903.75 m3
- tenaga 34453.50
- peralatan sewa long-arm 13437.41
JUMLAH TOTAL PEKERJAAN NORMALISASI
III. PEKERJAAN PINTU AIR
I. Pekerjaan Tanah
1 Pasang 1 m' Profil Melintang Galian Tanah 49 m
tenaga 20870
bahan 26150
peralatan 400
2 1 m3 Galian Tanah Biasa sedalam > 1 m s.d 2 m 633.65 m3
3 1 m3 Urugan Kembali Tanah Biasa 316.83 m3
JUMLAH TOTAL Pekerjaan Tanah
II. Pekerjaan Pintu Air
1 Mengangkut 1 m3 material atau hasil galian dengan jarak angkut 600 m s/d 700 m. 85.07 m3
2 1 m3 Pasangan Batu Kosong yang teratur dan padat - sedikit rongga beda tinggi >0 sd 1 m 75.89 m3
tenaga 263750
material batu 552000
3 1 m3 beton mutu fc' = 7,4 Mpa (K100) 13.49 m3
tenaga 259835
bahan 1116865
4 1 m3 beton mutu fc' = 21,7 Mpa (K250) 85.07 m3
tenaga 259835
bahan 1315893.5
5 1 m3 Pemadatan beton pada saat mengecor (Concrete Vibrator) 85.07 m3
tenaga 42375
peralatan concrete 43987.72
6 Untuk pembesian polos 2,290.37 Kg
tenaga 2,506.00
bahan 15,075.00
7 Untuk pembesian Deformasi 4,131.11 Kg
tenaga 6,198.50
bahan 15,225.00
8 1 m2 Bekesting dinding beton biasa dengan multiplek 12 mm. 79.15 m2
tenaga 63300
bahan 127660
9 1 m2 bongkar bekesting cara biasa (membersihkan dan membereskan puing-puing). 79.15 m2
10 Per-m' penetrasi Cerucuk Kayu 10 x 10 cm 932 m
tenaga 17060
bahan 78750
peralatan 30500
11 1 buah kistdam pasir/tanah dibungkus karung plastik bagor 43 cm x 65 cm 310 Bh
tenaga 6780
bahan 15160
12 Pintu Klep Fiber (1,2 x 1,4 m) 6 Bh
JUMLAH TOTAL Pekerjaan Pintu Air
III. Pekerjaan Turap
1 Mengangkut 1 m3 material atau hasil galian dengan jarak angkut 600 m s/d 700 m. 22 m3
2 1 m3 beton mutu fc' = 21,7 Mpa (K250) 22 m3
tenaga 259835
bahan 1315893.5
3 1 m3 Pemadatan beton pada saat mengecor (Concrete Vibrator) 22 m3
tenaga 42375
peralatan concrete 43987.72
4 Untuk pembesian polos 421.93 Kg
tenaga 2,506.00
bahan 15,075.00
5 Untuk pembesian Deformasi 1,044.41 Kg
tenaga 6,198.50
bahan 15,225.00
6 1 m2 Bekesting dinding beton biasa dengan multiplek 12 mm. 56 m2
tenaga 63300
bahan 127660
7 1 m2 bongkar bekesting cara biasa (membersihkan dan membereskan puing-puing). 56 m2
8 Per-m' penetrasi Cerucuk Kayu 10 x 10 cm 20 m
tenaga 17060
bahan 78750
peralatan 30500
9 1 m' Pipa Drainase PVC 2" 10 m
10 1 m3 beton mutu fc' = 7,4 Mpa (K100) 2 m
tenaga 259835
bahan 1116865
JUMLAH TOTAL Pekerjaan Turap
IV. PEKERJAAN PEMBONGKARAN
1 Mengangkut Hasil Pembongkaran Pintu Air Eksisting 1 Ls
2 Pembongkaran Pintu Air Lama 1 Ls
JUMLAH TOTAL PEKERJAAN PEMBONGKARAN
Diperiksa Oleh :
Konsultan Supervisi
CV. ISAM STUDIO KONSULTAN
Purwaningsih, ST
Site Engineer
REALISASI PEKERJAAN BULANAN
ENGELOLAAN SUMBER DAYA AIR (SDA)
EMBANGUNAN PINTU AIR DAN NORMALISASI SUNGAI DI HANDIL BARU DAN MUARA SEMBILANG KECAMATAN SAMBOJA
ECAMATAN SAMBOJA KABUPATEN KUTAI KARTANAGARA
.342/DPU/SDA/600.1.4.1/7/2023
4 JULI 2023
0 HARI KALENDER
PBD KAB. KUTAI KARTANEGARA
CV. PAGI PETANG
CV. ISAM STUDIO KONSULTAN
Dibuat Oleh :
Kontraktor Pelaksana
CV. PAGI PETANG
Zulkipli Fahrijal
Direktur
ATAN SAMBOJA
BULAN PERTAMA
PERIODE 25 Juli - 31 juli
Bulan JULI
0.19 0.01
0.077 0.09%
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
1.46%
ktor Pelaksana
AGI PETANG
REKAPITULASI - MINGGUAN
PROGRAM : PENGELOLAAN SUMBER DAYA AIR (SDA)
PEKERJAAN : PEMBANGUNAN PINTU AIR DAN NORMALISASI SUNGAI DI HANDIL BARU DAN MUARA SEMBILANG KECAMATAN SAMBOJA
LOKASI : KECAMATAN SAMBOJA KABUPATEN KUTAI KARTANAGARA
NOMOR KONTRAK : P.342/DPU/SDA/600.1.4.1/7/2023
TANGGAL KONTRAK : 24 JULI 2023
WAKTU PELAKSANAAN : 90 HARI KALENDER
SUMBER DANA : APBD KAB. KUTAI KARTANEGARA MINGGU KEDUA
KONTRAKTOR PELAKSANA : CV. PAGI PETANG Tanggal 1 - 7 Agustus 2023
KONSULTAN PENGAWAS : CV. ISAM STUDIO KONSULTAN Bulan AGUSTUS
KONTRAK REALISASI MINGGU LALU REALISASI MINGGU INI REALISASI S/D MINGGU INI
NO URAIAN BOBOT BOBOT BOBOT BOBOT
% (%) (%) (%)
I. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi 1 Ls 78,700,000.00 78,700,000.00 7.15% 0.19 1.37% - 0.00% 0.19 1.37%
-demob 69,000,000.00 6.27%
-pemasangan papan kegiatan 700,000.00 0.06%
-sewa barak 9,000,000.00 0.82%
2 Sistem Manajemen dan Keselamatan Konstruksi (SMKK) 1 Ls 13,152,307.77 13,152,307.77 1.20% 0.08 0.09% - 0.00% 0.08 0.09%
-
II. PEKERJAAN NORMALISASI -
I. Pekerjaan Normalisasi -
1 Galian Tanah Berlumpur di Sungai 526.47 m3 52,680.00 27,734,439.60 2.52% - 0.00% 0.00% - 0.00%
- tenaga 34453.50 19,952,607.56 1.81%
- peralatan sewa long-arm 13437.41 7,781,832.57 0.71%
KONTRAK REALISASI MINGGU LALU REALISASI MINGGU INI REALISASI S/D MINGGU INI
NO URAIAN BOBOT BOBOT BOBOT BOBOT
% (%) (%) (%)
I. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi 1 Ls 78,700,000.00 78,700,000.00 7.15% 0.19 1.37% 0.00% 0.19 1.37%
-demob 69,000,000.00 6.27%
-pemasangan papan kegiatan 700,000.00 0.06%
-sewa barak 9,000,000.00 0.82%
2 Sistem Manajemen dan Keselamatan Konstruksi (SMKK) 1 Ls 13,152,307.77 13,152,307.77 1.20% 0.08 0.09% 0.00% 0.08 0.09%
-
II. PEKERJAAN NORMALISASI -
I. Pekerjaan Normalisasi -
1 Galian Tanah Berlumpur di Sungai 526.47 m3 52,680.00 27,734,439.60 2.52% - 0.00% 0.00% - 0.00%
- tenaga 34453.50 19,952,607.56 1.81%
- peralatan sewa long-arm 13437.41 7,781,832.57 0.71%
KONTRAK REALISASI MINGGU LALU REALISASI MINGGU INI REALISASI S/D MINGGU INI
NO URAIAN BOBOT BOBOT BOBOT BOBOT
% (%) (%) (%)
I. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi 1 Ls 78,700,000.00 78,700,000.00 7.15% 0.19 1.37% - 0.00% 0.19 1.37%
-demob 69,000,000.00 6.27%
-pemasangan papan kegiatan 700,000.00 0.06%
-sewa barak 9,000,000.00 0.82%
2 Sistem Manajemen dan Keselamatan Konstruksi (SMKK) 1 Ls 13,152,307.77 13,152,307.77 1.20% 0.08 0.09% - 0.00% 0.08 0.09%
-
II. PEKERJAAN NORMALISASI -
I. Pekerjaan Normalisasi -
1 Galian Tanah Berlumpur di Sungai 526.47 m3 52,680.00 27,734,439.60 2.52% - 0.00% - 0.00% - 0.00%
- tenaga 34453.50 19,952,607.56 1.81%
- peralatan sewa long-arm 13437.41 7,781,832.57 0.71%
KONTRAK REALISASI MINGGU LALU REALISASI MINGGU INI REALISASI S/D MINGGU INI
NO URAIAN BOBOT BOBOT BOBOT BOBOT
% (%) (%) (%)
I. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi 1 Ls 78,700,000.00 78,700,000.00 7.15% 0.19 1.37% - 0.00% 0.19 1.37%
-demob 69,000,000.00 6.27%
-pemasangan papan kegiatan 700,000.00 0.06%
-sewa barak 9,000,000.00 0.82%
2 Sistem Manajemen dan Keselamatan Konstruksi (SMKK) 1 Ls 13,152,307.77 13,152,307.77 1.20% 0.08 0.09% - 0.00% 0.08 0.09%
-
II. PEKERJAAN NORMALISASI -
I. Pekerjaan Normalisasi -
1 Galian Tanah Berlumpur di Sungai 526.47 m3 52,680.00 27,734,439.60 2.52% - 0.00% - 0.00% - 0.00%
- tenaga 34453.50 19,952,607.56 1.81%
- peralatan sewa long-arm 13437.41 7,781,832.57 0.71%
KONTRAK REALISASI BULAN LALU REALISASI BULAN INI REALISASI S/D BULAN INI
NO URAIAN BOBOT BOBOT BOBOT BOBOT
% (%) (%) (%)
I. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi 1 Ls
-demob
-pemasangan papan kegiatan
-sewa barak
2 Sistem Manajemen dan Keselamatan Konstruksi (SMKK) 1 Ls
JUMLAH TOTAL PEKERJAAN PERSIAPAN
II. PEKERJAAN NORMALISASI
I. Pekerjaan Normalisasi
1 Galian Tanah Berlumpur di Sungai 903.75 m3
- tenaga 34453.50
- peralatan sewa long-arm 13437.41
JUMLAH TOTAL PEKERJAAN NORMALISASI
III. PEKERJAAN PINTU AIR
I. Pekerjaan Tanah
1 Pasang 1 m' Profil Melintang Galian Tanah 49 m
tenaga 20870
bahan 26150
peralatan 400
2 1 m3 Galian Tanah Biasa sedalam > 1 m s.d 2 m 633.65 m3
3 1 m3 Urugan Kembali Tanah Biasa 316.83 m3
JUMLAH TOTAL Pekerjaan Tanah
II. Pekerjaan Pintu Air
1 Mengangkut 1 m3 material atau hasil galian dengan jarak angkut 600 m s/d 700 m. 85.07 m3
2 1 m3 Pasangan Batu Kosong yang teratur dan padat - sedikit rongga beda tinggi >0 sd 1 m 75.89 m3
tenaga 263750
material batu 552000
3 1 m3 beton mutu fc' = 7,4 Mpa (K100) 13.49 m3
tenaga 259835
bahan 1116865
4 1 m3 beton mutu fc' = 21,7 Mpa (K250) 85.07 m3
tenaga 259835
bahan 1315893.5
5 1 m3 Pemadatan beton pada saat mengecor (Concrete Vibrator) 85.07 m3
tenaga 42375
peralatan concrete 43987.72
6 Untuk pembesian polos 2,290.37 Kg
tenaga 2,506.00
bahan 15,075.00
7 Untuk pembesian Deformasi 4,131.11 Kg
tenaga 6,198.50
bahan 15,225.00
8 1 m2 Bekesting dinding beton biasa dengan multiplek 12 mm. 79.15 m2
tenaga 63300
bahan 127660
9 1 m2 bongkar bekesting cara biasa (membersihkan dan membereskan puing-puing). 79.15 m2
10 Per-m' penetrasi Cerucuk Kayu 10 x 10 cm 932 m
tenaga 17060
bahan 78750
peralatan 30500
11 1 buah kistdam pasir/tanah dibungkus karung plastik bagor 43 cm x 65 cm 310 Bh
tenaga 6780
bahan 15160
12 Pintu Klep Fiber (1,2 x 1,4 m) 6 Bh
JUMLAH TOTAL Pekerjaan Pintu Air
III. Pekerjaan Turap
1 Mengangkut 1 m3 material atau hasil galian dengan jarak angkut 600 m s/d 700 m. 22 m3
2 1 m3 beton mutu fc' = 21,7 Mpa (K250) 22 m3
tenaga 259835
bahan 1315893.5
3 1 m3 Pemadatan beton pada saat mengecor (Concrete Vibrator) 22 m3
tenaga 42375
peralatan concrete 43987.72
4 Untuk pembesian polos 421.93 Kg
tenaga 2,506.00
bahan 15,075.00
5 Untuk pembesian Deformasi 1,044.41 Kg
tenaga 6,198.50
bahan 15,225.00
6 1 m2 Bekesting dinding beton biasa dengan multiplek 12 mm. 56 m2
tenaga 63300
bahan 127660
7 1 m2 bongkar bekesting cara biasa (membersihkan dan membereskan puing-puing). 56 m2
8 Per-m' penetrasi Cerucuk Kayu 10 x 10 cm 20 m
tenaga 17060
bahan 78750
peralatan 30500
9 1 m' Pipa Drainase PVC 2" 10 m
10 1 m3 beton mutu fc' = 7,4 Mpa (K100) 2 m
tenaga 259835
bahan 1116865
JUMLAH TOTAL Pekerjaan Turap
IV. PEKERJAAN PEMBONGKARAN
1 Mengangkut Hasil Pembongkaran Pintu Air Eksisting 1 Ls
2 Pembongkaran Pintu Air Lama 1 Ls
JUMLAH TOTAL PEKERJAAN PEMBONGKARAN
Diperiksa Oleh :
Konsultan Supervisi
CV. ISAM STUDIO KONSULTAN
Purwaningsih, ST
Site Engineer
REALISASI PEKERJAAN BULANAN
ENGELOLAAN SUMBER DAYA AIR (SDA)
EMBANGUNAN PINTU AIR DAN NORMALISASI SUNGAI DI HANDIL BARU DAN MUARA SEMBILANG KECAMATAN SAMBOJA
ECAMATAN SAMBOJA KABUPATEN KUTAI KARTANAGARA
.342/DPU/SDA/600.1.4.1/7/2023
4 JULI 2023
0 HARI KALENDER
PBD KAB. KUTAI KARTANEGARA
CV. PAGI PETANG
CV. ISAM STUDIO KONSULTAN
Dibuat Oleh :
Kontraktor Pelaksana
CV. PAGI PETANG
Zulkipli Fahrijal
Direktur
ATAN SAMBOJA
BULAN KEDUA
PERIODE 1 - 28 Agustus 2023
Bulan AGUSTUS
0.19 1.37%
0.077 0.09%
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
1.46%
ktor Pelaksana
AGI PETANG
REKAPITULASI - MINGGUAN
PROGRAM : PENGELOLAAN SUMBER DAYA AIR (SDA)
PEKERJAAN : PEMBANGUNAN PINTU AIR DAN NORMALISASI SUNGAI DI HANDIL BARU DAN MUARA SEMBILANG KECAMATAN SAMBOJA
LOKASI : KECAMATAN SAMBOJA KABUPATEN KUTAI KARTANAGARA
NOMOR KONTRAK : P.342/DPU/SDA/600.1.4.1/7/2023
TANGGAL KONTRAK : 24 JULI 2023
WAKTU PELAKSANAAN : 90 HARI KALENDER
SUMBER DANA : APBD KAB. KUTAI KARTANEGARA MINGGU KE ENAM
KONTRAKTOR PELAKSANA : CV. PAGI PETANG Tanggal 29-4 Sept 2023
KONSULTAN PENGAWAS : CV. ISAM STUDIO KONSULTAN Bulan SEPTEMBER
KONTRAK REALISASI MINGGU LALU REALISASI MINGGU INI REALISASI S/D MINGGU INI
NO URAIAN BOBOT BOBOT BOBOT BOBOT
% (%) (%) (%)
I. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi 1 Ls 78,700,000.00 78,700,000.00 7.15% 0.19 1.37% 0.18 1.30% 0.37 2.67%
-demob 69,000,000.00 6.27%
-pemasangan papan kegiatan 700,000.00 0.06%
-sewa barak 9,000,000.00 0.82%
2 Sistem Manajemen dan Keselamatan Konstruksi (SMKK) 1 Ls 13,152,307.77 13,152,307.77 1.20% 0.08 0.09% 0.08 0.09% 0.15 0.18%
-
II. PEKERJAAN NORMALISASI -
I. Pekerjaan Normalisasi -
1 Galian Tanah Berlumpur di Sungai 526.47 m3 52,680.00 27,734,439.60 2.52% - 0.00% - 0.00% - 0.00%
- tenaga 34453.50 19,952,607.56 1.81%
- peralatan sewa long-arm 13437.41 7,781,832.57 0.71%
KONTRAK REALISASI MINGGU LALU REALISASI MINGGU INI REALISASI S/D MINGGU INI
NO URAIAN BOBOT BOBOT BOBOT BOBOT
% (%) (%) (%)
I. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi 1 Ls 78,700,000.00 78,700,000.00 7.15% 0.37 2.67% 0.13 0.90% 0.50 3.57%
-demob 69,000,000.00 6.27%
-pemasangan papan kegiatan 700,000.00 0.06%
-sewa barak 9,000,000.00 0.82%
2 Sistem Manajemen dan Keselamatan Konstruksi (SMKK) 1 Ls 13,152,307.77 13,152,307.77 1.20% 0.15 0.18% 0.08 0.09% 0.23 0.28%
-
II. PEKERJAAN NORMALISASI -
I. Pekerjaan Normalisasi -
1 Galian Tanah Berlumpur di Sungai 526.47 m3 52,680.00 27,734,439.60 2.52% - 0.00% - 0.00% - 0.00%
- tenaga 34453.50 19,952,607.56 1.81%
- peralatan sewa long-arm 13437.41 7,781,832.57 0.71%
KONTRAK REALISASI MINGGU LALU REALISASI MINGGU INI REALISASI S/D MINGGU INI
NO URAIAN BOBOT BOBOT BOBOT BOBOT
% (%) (%) (%)
I. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi 1 Ls 78,700,000.00 78,700,000.00 7.15% 0.50 3.57% 0.13 0.90% 0.62 4.46%
-demob 69,000,000.00 6.27%
-pemasangan papan kegiatan 700,000.00 0.06%
-sewa barak 9,000,000.00 0.82%
2 Sistem Manajemen dan Keselamatan Konstruksi (SMKK) 1 Ls 13,152,307.77 13,152,307.77 1.20% 0.23 0.28% 0.08 0.09% 0.31 0.37%
-
II. PEKERJAAN NORMALISASI -
I. Pekerjaan Normalisasi -
1 Galian Tanah Berlumpur di Sungai 526.47 m3 52,680.00 27,734,439.60 2.52% - 0.00% - 0.00% - 0.00%
- tenaga 34453.50 19,952,607.56 1.81%
- peralatan sewa long-arm 13437.41 7,781,832.57 0.71%
KONTRAK REALISASI MINGGU LALU REALISASI MINGGU INI REALISASI S/D MINGGU INI
NO URAIAN BOBOT BOBOT BOBOT BOBOT
% (%) (%) (%)
I. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi 1 Ls 78,700,000.00 78,700,000.00 7.15% 0.62 4.46% 0.13 0.90% 0.75 5.36%
-demob 69,000,000.00 6.27%
-pemasangan papan kegiatan 700,000.00 0.06%
-sewa barak 9,000,000.00 0.82%
2 Sistem Manajemen dan Keselamatan Konstruksi (SMKK) 1 Ls 13,152,307.77 13,152,307.77 1.20% 0.31 0.37% 0.08 0.09% 0.38 0.46%
-
II. PEKERJAAN NORMALISASI -
I. Pekerjaan Normalisasi -
1 Galian Tanah Berlumpur di Sungai 526.47 m3 52,680.00 27,734,439.60 2.52% - 0.00% - 0.00% - 0.00%
- tenaga 34453.50 19,952,607.56 1.81%
- peralatan sewa long-arm 13437.41 7,781,832.57 0.71%
I. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi 1 Ls
2 Sistem Manajemen dan Keselamatan Konstruksi (SMKK) 1 Ls
JUMLAH TOTAL PEKERJAAN PERSIAPAN
II. PEKERJAAN NORMALISASI
I. Pekerjaan Normalisasi
1 Galian Tanah Berlumpur di Sungai 903.75 m3
JUMLAH TOTAL PEKERJAAN NORMALISASI
III. PEKERJAAN PINTU AIR
I. Pekerjaan Tanah
1 Pasang 1 m' Profil Melintang Galian Tanah 49 m
2 1 m3 Galian Tanah Biasa sedalam > 1 m s.d 2 m 633.65 m3
3 1 m3 Urugan Kembali Tanah Biasa 316.83 m3
JUMLAH TOTAL Pekerjaan Tanah
II. Pekerjaan Pintu Air
1 Mengangkut 1 m3 material atau hasil galian dengan jarak angkut 600 m s/d 700 m. 85.07 m3
2 1 m3 Pasangan Batu Kosong yang teratur dan padat - sedikit rongga beda tinggi >0 sd 1 m 75.89 m3
3 1 m3 beton mutu fc' = 7,4 Mpa (K100) 13.49 m3
4 1 m3 beton mutu fc' = 21,7 Mpa (K250) 85.07 m3
5 1 m3 Pemadatan beton pada saat mengecor (Concrete Vibrator) 85.07 m3
6 Untuk pembesian polos 2,290.37 Kg
7 Untuk pembesian Deformasi 4,131.11 Kg
8 1 m2 Bekesting dinding beton biasa dengan multiplek 12 mm. 79.15 m2
9 1 m2 bongkar bekesting cara biasa (membersihkan dan membereskan puing-puing). 79.15 m2
10 Per-m' penetrasi Cerucuk Kayu 10 x 10 cm 932 m
11 1 buah kistdam pasir/tanah dibungkus karung plastik bagor 43 cm x 65 cm 310 Bh
12 Pintu Klep Fiber (1,2 x 1,4 m) 6 Bh
JUMLAH TOTAL Pekerjaan Pintu Air
III. Pekerjaan Turap
1 Mengangkut 1 m3 material atau hasil galian dengan jarak angkut 600 m s/d 700 m. 22 m3
2 1 m3 beton mutu fc' = 21,7 Mpa (K250) 22 m3
3 1 m3 Pemadatan beton pada saat mengecor (Concrete Vibrator) 22 m3
4 Untuk pembesian polos 421.93 Kg
5 Untuk pembesian Deformasi 1,044.41 Kg
6 1 m2 Bekesting dinding beton biasa dengan multiplek 12 mm. 56 m2
7 1 m2 bongkar bekesting cara biasa (membersihkan dan membereskan puing-puing). 56 m2
8 Per-m' penetrasi Cerucuk Kayu 10 x 10 cm 20 m
9 1 m' Pipa Drainase PVC 2" 10 m
10 1 m3 beton mutu fc' = 7,4 Mpa (K100) 2 m
JUMLAH TOTAL Pekerjaan Turap
IV. PEKERJAAN PEMBONGKARAN
1 Mengangkut Hasil Pembongkaran Pintu Air Eksisting 1 Ls
2 Pembongkaran Pintu Air Lama 1 Ls
JUMLAH TOTAL PEKERJAAN PEMBONGKARAN
A JUMLAH TOTAL
B PPN = 11% X A
C TOTAL HARGA (termasuk ppn11%) = A + B
D MATERIAL ON SITE
E JUMLAH SERTIFIKASI BULANAN SAMPAI DENGAN SAAT INI = C
F JUMLAH SERTIFIKASI BULANAN SAMPAI DENGAN BULAN LALU
G JUMLAH KOTOR SERTIFIKASI BULANAN SAAT INI = E - F
H POTONGAN POTONGAN
1. JAMINAN PEMELIHARAAN (5% x G)
2. PENGEMBALIAN UANG MUKA
3. LAIN-LAIN
I JUMLAH POTONGAN - POTONGAN = ( 1 + 2 + 3)
J JUMLAH BERSIH SERTIFIKASI BULANAN BULAN LALU
K JUMLAH BERSIH SERTIFIKASI BULANANAN SAAT INI = G - I
L JUMLAH BESIH SERTIFIKASI SAMPAI DENGAN BULAN INI = J + K
Diperiksa Oleh :
Konsultan Supervisi
CV. ISAM STUDIO KONSULTAN
Purwaningsih, ST
Site Engineer
ERJAAN BULANAN
ENGELOLAAN SUMBER DAYA AIR (SDA)
EMBANGUNAN PINTU AIR DAN NORMALISASI SUNGAI DI HANDIL BARU DAN MUARA SEMBILANG KECAMATAN SAMBOJA
ECAMATAN SAMBOJA KABUPATEN KUTAI KARTANAGARA
.342/DPU/SDA/600.1.4.1/7/2023
4 JULI 2023
0 HARI KALENDER
PBD KAB. KUTAI KARTANEGARA BULAN
CV. PAGI PETANG PERIODE
CV. ISAM STUDIO KONSULTAN Bulan
C 592,810,961.79
U -
592,810,961.79
29,640,548.09
162,184,222.50
191,824,770.59
400,986,191.20
K 400,986,191.20
ANG KECAMATAN SAMBOJA
KETIGA
29 agust-25 Sept 2023
SEPTEMBER
Prestasi Pekerjaan
bobot
5.36%
0.46%
0.00%
0.23%
7.25%
0.00%
1.80%
5.85%
1.86%
2.68%
0.00%
0.86%
2.10%
0.00%
0.00%
11.77%
0.68%
7.63%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
48.53%
REKAPITULASI
PROGRAM : PENGELOLAAN SUMBER DAYA AIR (SDA)
PEKERJAAN : PEMBANGUNAN PINTU AIR DAN NORMALISASI SUNGAI DI HANDIL BARU DAN MUARA SEMBILANG KECAMATAN SAMBOJA
LOKASI : KECAMATAN SAMBOJA KABUPATEN KUTAI KARTANAGARA
NOMOR KONTRAK : P.342/DPU/SDA/600.1.4.1/7/2023
TANGGAL KONTRAK : 24 JULI 2023
WAKTU PELAKSANAAN : 90 HARI KALENDER
SUMBER DANA : APBD KAB. KUTAI KARTANEGARA BULAN KETIGA
KONTRAKTOR PELAKSANA : CV. PAGI PETANG Tanggal 29 agust-25 Sept 2023
KONSULTAN PENGAWAS : CV. ISAM STUDIO KONSULTAN Bulan SEPTEMBER
KONTRAK REALISASI BULAN LALU REALISASI BULAN INI REALISASI S/D BULAN INI
NO URAIAN BOBOT BOBOT BOBOT BOBOT
% (%) (%) (%)
I. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi 1 Ls
-demob
-pemasangan papan kegiatan
-sewa barak
2 Sistem Manajemen dan Keselamatan Konstruksi (SMKK) 1 Ls
JUMLAH TOTAL PEKERJAAN PERSIAPAN
II. PEKERJAAN NORMALISASI
I. Pekerjaan Normalisasi
1 Galian Tanah Berlumpur di Sungai 903.75 m3
- tenaga 34453.50
- peralatan sewa long-arm 13437.41
JUMLAH TOTAL PEKERJAAN NORMALISASI
III. PEKERJAAN PINTU AIR
I. Pekerjaan Tanah
1 Pasang 1 m' Profil Melintang Galian Tanah 49 m
tenaga 20870
bahan 26150
peralatan 400
2 1 m3 Galian Tanah Biasa sedalam > 1 m s.d 2 m 633.65 m3
3 1 m3 Urugan Kembali Tanah Biasa 316.83 m3
JUMLAH TOTAL Pekerjaan Tanah
II. Pekerjaan Pintu Air
1 Mengangkut 1 m3 material atau hasil galian dengan jarak angkut 600 m s/d 700 m. 85.07 m3
2 1 m3 Pasangan Batu Kosong yang teratur dan padat - sedikit rongga beda tinggi >0 sd 1 m 75.89 m3
tenaga 263750
material batu 552000
3 1 m3 beton mutu fc' = 7,4 Mpa (K100) 13.49 m3
tenaga 259835
bahan 1116865
4 1 m3 beton mutu fc' = 21,7 Mpa (K250) 85.07 m3
tenaga 259835
bahan 1315893.5
5 1 m3 Pemadatan beton pada saat mengecor (Concrete Vibrator) 85.07 m3
tenaga 42375
peralatan concrete 43987.72
6 Untuk pembesian polos 2,290.37 Kg
tenaga 2,506.00
bahan 15,075.00
7 Untuk pembesian Deformasi 4,131.11 Kg
tenaga 6,198.50
bahan 15,225.00
8 1 m2 Bekesting dinding beton biasa dengan multiplek 12 mm. 79.15 m2
tenaga 63300
bahan 127660
9 1 m2 bongkar bekesting cara biasa (membersihkan dan membereskan puing-puing). 79.15 m2
10 Per-m' penetrasi Cerucuk Kayu 10 x 10 cm 932 m
tenaga 17060
bahan 78750
peralatan 30500
11 1 buah kistdam pasir/tanah dibungkus karung plastik bagor 43 cm x 65 cm 310 Bh
tenaga 6780
bahan 15160
12 Pintu Klep Fiber (1,2 x 1,4 m) 6 Bh
JUMLAH TOTAL Pekerjaan Pintu Air
III. Pekerjaan Turap
1 Mengangkut 1 m3 material atau hasil galian dengan jarak angkut 600 m s/d 700 m. 22 m3
2 1 m3 beton mutu fc' = 21,7 Mpa (K250) 22 m3
tenaga 259835
bahan 1315893.5
3 1 m3 Pemadatan beton pada saat mengecor (Concrete Vibrator) 22 m3
tenaga 42375
peralatan concrete 43987.72
4 Untuk pembesian polos 421.93 Kg
tenaga 2,506.00
bahan 15,075.00
5 Untuk pembesian Deformasi 1,044.41 Kg
tenaga 6,198.50
bahan 15,225.00
6 1 m2 Bekesting dinding beton biasa dengan multiplek 12 mm. 56 m2
tenaga 63300
bahan 127660
7 1 m2 bongkar bekesting cara biasa (membersihkan dan membereskan puing-puing). 56 m2
8 Per-m' penetrasi Cerucuk Kayu 10 x 10 cm 20 m
tenaga 17060
bahan 78750
peralatan 30500
9 1 m' Pipa Drainase PVC 2" 10 m
10 1 m3 beton mutu fc' = 7,4 Mpa (K100) 2 m
tenaga 259835
bahan 1116865
JUMLAH TOTAL Pekerjaan Turap
IV. PEKERJAAN PEMBONGKARAN
1 Mengangkut Hasil Pembongkaran Pintu Air Eksisting 1 Ls
2 Pembongkaran Pintu Air Lama 1 Ls
JUMLAH TOTAL PEKERJAAN PEMBONGKARAN
Diperiksa Oleh :
Konsultan Supervisi
CV. ISAM STUDIO KONSULTAN
Purwaningsih, ST
Site Engineer
REALISASI PEKERJAAN BULANAN
ENGELOLAAN SUMBER DAYA AIR (SDA)
EMBANGUNAN PINTU AIR DAN NORMALISASI SUNGAI DI HANDIL BARU DAN MUARA SEMBILANG KECAMATAN SAMBOJA
ECAMATAN SAMBOJA KABUPATEN KUTAI KARTANAGARA
.342/DPU/SDA/600.1.4.1/7/2023
4 JULI 2023
0 HARI KALENDER
PBD KAB. KUTAI KARTANEGARA
CV. PAGI PETANG
CV. ISAM STUDIO KONSULTAN
Dibuat Oleh :
Kontraktor Pelaksana
CV. PAGI PETANG
Zulkipli Fahrijal
Direktur
ATAN SAMBOJA
BULAN KETIGA
PERIODE 29 agust-25 Sept 2023
Bulan SEPTEMBER
0.75 5.36%
0.38 0.46%
- 0.00%
32.67 0.23%
633.65 7.25%
- 0.00%
42.54 1.80%
71.80 5.85%
13.49 1.86%
17.01 2.68%
- 0.00%
490.98 0.86%
978.62 2.10%
- 0.00%
- 0.00%
932.00 11.77%
310.00 0.68%
3.00 7.63%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
48.53%
ktor Pelaksana
AGI PETANG
REKAPITULASI - MINGGUAN
PROGRAM : PENGELOLAAN SUMBER DAYA AIR (SDA)
PEKERJAAN : PEMBANGUNAN PINTU AIR DAN NORMALISASI SUNGAI DI HANDIL BARU DAN MUARA SEMBILANG KECAMATAN SAMBOJA
LOKASI : KECAMATAN SAMBOJA KABUPATEN KUTAI KARTANAGARA
NOMOR KONTRAK : P.342/DPU/SDA/600.1.4.1/7/2023
TANGGAL KONTRAK : 24 JULI 2023
WAKTU PELAKSANAAN : 90 HARI KALENDER
SUMBER DANA : APBD KAB. KUTAI KARTANEGARA MINGGU KE SEPULUH
KONTRAKTOR PELAKSANA : CV. PAGI PETANG Tanggal 26-2 Oktober 2023
KONSULTAN PENGAWAS : CV. ISAM STUDIO KONSULTAN Bulan OKTOBER
KONTRAK REALISASI MINGGU LALU REALISASI MINGGU INI REALISASI S/D MINGGU INI
NO URAIAN BOBOT BOBOT BOBOT BOBOT
% (%) (%) (%)
I. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi 1 Ls 78,700,000.00 78,700,000.00 7.15% 0.75 5.36% 0.13 0.90% 0.87 6.26%
-demob 69,000,000.00 6.27%
-pemasangan papan kegiatan 700,000.00 0.06%
-sewa barak 9,000,000.00 0.82%
2 Sistem Manajemen dan Keselamatan Konstruksi (SMKK) 1 Ls 13,152,307.77 13,152,307.77 1.20% 0.38 0.46% 0.08 0.09% 0.46 0.55%
-
II. PEKERJAAN NORMALISASI -
I. Pekerjaan Normalisasi -
1 Galian Tanah Berlumpur di Sungai 526.47 m3 52,680.00 27,734,439.60 2.52% - 0.00% - 0.00% - 0.00%
- tenaga 34453.50 19,952,607.56 1.81%
- peralatan sewa long-arm 13437.41 7,781,832.57 0.71%