NETWORK PLANNING

146 173
9 146
12 173
M O
G J 13 7
36 14

0 A 7 B 26 C 47 D 61 E 110 160 K 170 O 180


1 0
2 7
3 26
4 47
6 61
8 11 160
13 173
15 180
7 19 21 14 49 110 10 7

I J
H 7 14 N O
14 11 7
40 F 54 L 68 171
5 118
7 132
10 146
14 173
14 14

Keterangan : Jalur 1 (Jalur Kritis) Jalur 6


Kode Uraian Pekerjaan Durasi Kegiatan Mendahului
A-B-C-D-E-G-J-M-O = 180 A-B-C-D-E-I-J-N-O = 149
A Pekerjaan Persiapan 7 - 7+19+21+14+49+36+14+13+7 = 180 7+19+21+14+49+7+14+11+7 = 149
: Jalur Kritis
B Pekerjaan Pondasi 19 A Jalur 2 Jalur 7
C Pekerjaan Beton Sloof & Kolom 21 B A-B-C-D-E-G-J-K-O = 177 A-B-H-F-L-J-M-O = 102
D Pekerjaan Beton Ringbalk 14 C : Jalur Non-Kritis 7+19+21+14+49+36+14+10+7 = 177 7+19+14+14+14+14+13+7 = 102
E Pekerjaan Pas. Dinding 49 D Jalur 3 Jalur 8
F Pekerjaan Plasteran & Acian 14 H A-B-C-D-E-G-J-N-O = 178 A-B-H-F-L-J-K-O = 99
G Pekerjaan Atap 36 E 7+19+14+14+14+14+10+7 = 99
7+19+21+14+49+36+14+11+7 = 178
H Pembuatan Kusen 14 B Jalur 4
Jalur 9
I Pemasangan Kusen 14 E, L A-B-H-F-L-J-N-O = 100
A-B-C-D-E-I-J-M-O = 151
J Pekerjaan Lantai 14 G, I 7+19+14+14+14+14+11+7 = 100
7+19+21+14+49+7+14+13+7 = 151
K Pekerjaan Instalasi Listrik 10 J Jalur 5
L Pekerjaan Air Bersih 14 F A-B-C-D-E-I-J-K-O = 148
M Pekerjaan Air Kotor 13 J 7+19+21+14+49+7+14+10+7 = 148
N Pekerjaan Pengecatan 11 J
O Pembersihan Akhir 7 K, N, M