1 Papan Nama Kegiatan 2.00 Bh 2.00 Bh 1,181,736.15 Rp. 2,363,472.29 Rp. 2,363,472.29 100.00 0.08 100.00 0.08
2 Pembersihan Lokasi 3,575.00 M2 3,575.00 M2 11,334.94 Rp. 40,522,410.50 Rp. 40,522,410.50 100.00 1.36 100.00 1.36
3 Pengukuran dan Pasang Patok 1.00 Pkt 1.00 Pkt 7,021,720.38 Rp. 7,021,720.38 Rp. 7,021,720.38 100.00 0.23 100.00 0.23
4 Mobilisasi Alat 1.00 Pkt 1.00 Pkt 15,000,000.00 Rp. 15,000,000.00 Rp. 15,000,000.00 100.00 0.50 100.00 0.50
5 Demobilisasi Alat 1.00 Pkt - Pkt 15,000,000.00 Rp. 15,000,000.00 Rp. - 100.00 0.50 - -
6 Langsiran
6.a Langsiran Pasir 1.00 Pkt 0.95 Pkt 13,000,000.00 Rp. 13,000,000.00 Rp. 12,350,000.00 100.00 0.44 95.00 0.41
6.b Langsiran Batu 1.00 Pkt 0.95 Pkt 13,000,000.00 Rp. 13,000,000.00 Rp. 12,350,000.00 100.00 0.44 95.00 0.41
6.c Langsiran Semen 1.00 Pkt 0.95 Pkt 10,000,000.00 Rp. 10,000,000.00 Rp. 9,500,000.00 100.00 0.33 95.00 0.32
6.d Langsiran Kerikil 1.00 Pkt 0.95 Pkt 10,000,000.00 Rp. 10,000,000.00 Rp. 9,500,000.00 100.00 0.33 95.00 0.32
JUMLAH II Rp. 125,907,603.17 Rp. 108,607,603.17
III PEKERJAAN SALURAN
1 Pekerjaan Galian Saluran Primer Kiri (1800 Meter) 4,829.00 M3 3,621.75 M3 26,121.64 Rp. 126,141,399.56 Rp. 94,606,049.67 100.00 4.22 75.00 3.17
2 Pekerjaan Galian Saluran Primer Kanan (1400 Meter) 9,516.95 M3 7,137.71 M3 26,121.64 Rp. 248,598,341.80 Rp. 186,448,756.35 100.00 8.32 75.00 6.24
3 Pekerjaan Galian Saluran Pembuang (375 Meter) 1,546.88 M3 1,160.16 M3 26,121.64 Rp. 40,407,042.48 Rp. 30,305,281.86 100.00 1.35 75.00 1.01
B PEKERJAAN REHABILITASI SALURAN LAMA
1 Pembentukan Ulang Saluran Primer Kiri (1900 Meter) 3,145.76 M3 2,516.61 M3 26,121.64 Rp. 82,172,410.25 Rp. 65,737,928.20 100.00 2.75 80.00 2.20
2 Pembentukan Ulang Saluran Primer Kanan (2300 Meter) 8,249.82 M3 6,599.86 M3 26,121.64 Rp. 215,498,828.10 Rp. 172,399,062.48 100.00 7.21 80.00 5.77
JUMLAH III Rp. 712,818,022.19 Rp. 549,497,078.56
TOTAL HARGA TOTAL HARGA
VOLUME
NO URAIAN PEKERJAAN VOLUME KONTRAK HARGA SATUAN KONTRAK REALISASI BOBOT (%) TERHADAP BOBOT (%) TERHADAP
TERLAKSANA
(Rp) (Rp) (Rp) BAGIAN SELURUH BAGIAN SELURUH
IV PEKERJAAN BANGUNAN AIR
1 Pembersihan Lokasi 287.04 M2 287.04 M2 11,334.98 Rp. 3,253,592.66 Rp. 3,253,592.66 100.00 0.11 100.00 0.11
2 Pengukuran dan Bouwplank 168.00 M' 168.00 M' 80,448.02 Rp. 13,515,267.36 Rp. 13,515,267.36 100.00 0.45 100.00 0.45
3 Pekerjaan Timbunan Tanah 70.00 M3 70.00 M3 241,141.89 Rp. 16,879,932.30 Rp. 16,879,932.30 100.00 0.56 100.00 0.56
4 Pekerjaan Beton 62.71 M3 53.30 M3 1,680,741.28 Rp. 105,399,285.67 Rp. 89,589,392.82 100.00 3.53 85.00 3.00
5 Pekerjaan Pembesian 2,471.57 Kg 2,100.83 Kg 21,312.67 Rp. 52,675,755.79 Rp. 44,774,392.42 100.00 1.76 85.00 1.50
6 Pekerjaan Bekisting 436.32 M2 436.32 M2 109,653.13 Rp. 47,843,853.68 Rp. 47,843,853.68 100.00 1.60 100.00 1.60
7 Pekerjaan Pasangan Batu Saluran Sadap (Tersier) 52.20 M3 39.15 M3 1,657,764.93 Rp. 86,535,329.35 Rp. 64,901,497.01 100.00 2.90 75.00 2.17
8 Pekerjaan Plesteran Saluran Sadap (Tersier) 100.00 M2 50.00 M2 88,169.06 Rp. 8,816,906.00 Rp. 4,408,453.00 100.00 0.30 50.00 0.15
9 Pekerjaan Cor Lantai Saluran Sadap (Tersier) 3.60 M3 2.70 M3 1,598,767.56 Rp. 5,755,563.22 Rp. 4,316,672.41 100.00 0.19 75.00 0.14
10 Pekerjaan Pasangan Batu Perkuatan Linning Saluran (Primer) 192.00 M3 153.60 M3 1,657,764.93 Rp. 318,290,866.56 Rp. 254,632,693.25 100.00 10.65 80.00 8.52
11 Pekerjaan Plesteran Perkuatan Linning Saluran (Primer) 736.00 M2 368.00 M2 88,169.06 Rp. 64,892,428.16 Rp. 32,446,214.08 100.00 2.17 50.00 1.09
12 Pekerjaan Pasangan Batu Kosong Lantai Saluran (Primer) 212.00 M3 169.60 M3 1,025,087.00 Rp. 217,318,444.00 Rp. 173,854,755.20 100.00 7.27 80.00 5.82
13 Pekerjaan Cor Lantai Saluran (Primer) 22.40 M3 15.68 M3 1,598,767.56 Rp. 35,812,393.34 Rp. 25,068,675.34 100.00 1.20 70.00 0.84
B PEKERJAAN BANGUNAN SADAP TIPE 2 (6 UNIT)
1 Pembersihan Lokasi 317.46 M2 317.46 M2 11,334.98 Rp. 3,598,402.75 Rp. 3,598,402.75 100.00 0.12 100.00 0.12
2 Pengukuran dan Bouwplank 162.00 M' 162.00 M' 80,448.02 Rp. 13,032,579.24 Rp. 13,032,579.24 100.00 0.44 100.00 0.44
3 Pekerjaan Beton 0.38 M3 0.23 M3 1,680,741.28 Rp. 638,681.69 Rp. 383,209.01 100.00 0.02 60.00 0.01
4 Pekerjaan Pembesian 20.83 Kg 12.50 Kg 21,312.67 Rp. 443,942.92 Rp. 266,365.75 100.00 0.01 60.00 0.01
5 Pekerjaan Bekisting 2.52 M2 1.51 M2 109,653.13 Rp. 276,325.89 Rp. 165,795.53 100.00 0.01 60.00 0.01
6 Pekerjaan Pasangan Batu 97.79 M3 58.67 M3 1,657,764.93 Rp. 162,112,832.50 Rp. 97,267,699.50 100.00 5.43 60.00 3.26
7 Pekerjaan Plesteran 150.00 M2 45.00 M2 88,169.06 Rp. 13,225,359.00 Rp. 3,967,607.70 100.00 0.44 30.00 0.13
8 Pekerjaan Cor Lantai 7.56 M3 4.54 M3 1,598,767.56 Rp. 12,086,682.75 Rp. 7,252,009.65 100.00 0.40 60.00 0.24
C PEKERJAAN PINTU AIR BANGUNAN
1 Pintu Air Tipe 1 8.00 Bh 8.00 Bh 10,000,000.00 Rp. 80,000,000.00 Rp. 80,000,000.00 100.00 2.68 100.00 2.68
2 Pintu Air Tipe 2 10.00 Bh 10.00 Bh 7,500,000.00 Rp. 75,000,000.00 Rp. 75,000,000.00 100.00 2.51 100.00 2.51
D PEKERJAAN DEWATERING
1 Kistdam 224.00 Bh 134.40 Bh 11,335.32 Rp. 2,539,111.68 Rp. 1,523,467.01 100.00 0.08 60.00 0.05
2 Pekerjaan Pengoperasian pompa air diesel daya 10 kW 630.00 Jam 378.00 Jam 23,758.71 Rp. 14,967,987.30 Rp. 8,980,792.38 100.00 0.50 60.00 0.30
JUMLAH IV Rp. 1,354,911,523.81 Rp. 1,066,923,320.06
TOTAL HARGA TOTAL HARGA
VOLUME
NO URAIAN PEKERJAAN VOLUME KONTRAK HARGA SATUAN KONTRAK REALISASI BOBOT (%) TERHADAP BOBOT (%) TERHADAP
TERLAKSANA
(Rp) (Rp) (Rp) BAGIAN SELURUH BAGIAN SELURUH
V PEKERJAAN TANGGUL
1 Pekerjaan Penambahan Tanah Tanggul Kiri (900 Meter) 1,800.00 M3 720.00 M3 243,916.46 Rp. 439,049,628.00 Rp. 175,619,851.20 100.00 14.69 40.00 5.88
2 Pekerjaan Penambahan Tanah Tanggul Kanan (468 Meter) 936.00 M3 374.40 M3 243,916.46 Rp. 228,305,806.56 Rp. 91,322,322.62 100.00 7.64 40.00 3.06
B FINISHING BADAN TANGGUL
1 Pekerjaan Finishing Tanggul Kiri (900 Meter) 2,250.00 M2 900.00 M2 33,437.00 Rp. 75,233,250.00 Rp. 30,093,300.00 100.00 2.52 40.00 1.01
2 Pekerjaan Finishing Tanggul Kanan (468 Meter) 1,170.00 M2 468.00 M2 33,437.00 Rp. 39,121,290.00 Rp. 15,648,516.00 100.00 1.31 40.00 0.52
JUMLAH V Rp. 781,709,974.56 Rp. 312,683,989.82
TOTAL JUMLAH I-V Rp. 2,988,202,623.73 Rp. 2,047,996,391.62
PAJAK PERTAMBAHAN NILAI (PPN 11%) Rp. 328,702,288.61 Rp. 225,279,603.08 68.54
TOTAL FISIK PEKERJAAN + PAJAK Rp. 3,316,904,912.34 Rp. 2,273,275,994.70
PEMBULATAN (KONTRAK) Rp. Rp.
REALISASI PEKERJAAN S.D BULAN KE I TELAH MENCAPAI 68,54 % (ENAM PULUH DELAPAN KOMA LIMA PULUH EMPAT PERSEN)