Commisioning unit light vehicle 2x HILUX (LV702 & LV707) Closed (06 Januari 2022)
Commisioning unit light vehicle 3x HILUX (LV703,LV704 &LV705) due date week-2 (12 Januari 2022)
Test praktek dan teori SIMPER (5 orang an. YP,CP,ZH,AA,A) Closed (3-4 Januari 2022)
Test praktek dan teori SIMPER (2orang an. AR,HR) due date week-2
1 SHE Pendaftaran test online IKABAR (3 karyawanan. WS,SN,OS) SIOK release : 06 Januari 2022
Pembuatan bracket APAR (LV703,LV704 & LV 705) Closed (07 Januari 2022)
Pengajuan Commisioning Excvator (EXD301) due date week-2 (12 Januari 2022)
Pengajuan Commisioning Dozer (DZD201) due date week-2 (12 Januari 2022)
Progress Excavator EX Z470 (EXD301) due date week-2 (10 Januari 2022)
2 PLANT
Progress Komatsu PC200 due date week-2 (11 Januari 2022)
Mobilisasi Kontainer 20ft (5x) due date week-3 (20 Januari 2022)
ENGINEERING &
3 Kapasitas produksi based on kedatangan unit Closed (06 Januari 2022)
PRODUCTION
Man power
double due date week-2 (14 Januari 2022)
due date week-2 (14 Januari 2022)
Penambahan team HCGA (IT officer) due date week-2 (12 Januari 2022)
Pergantian slot HR menjadi External Relation (CSR) due date week-2 (16 Januari 2022)
4 HCGA Pembuatan PLANG NAMA PERUSAHAAN due date week-3 (23 Januari 2022)
Pengadaan TANDOON AIR (5.500 liter 3xpcs) + instalasi due date week-2 (16 Januari 2022)
Kedatangan TRAINEER (an. Pak Saripin) due date week-2 (12 Januari 2022)
Pelunasan Biaya pemasangan GPS & Dash Camera due date week-2 (11 Januari 2022)
Pembayaran invoice vaksin Hepatitis B untuk 12 karyawan due date week-3 (18 Januari 2022)
5 FA
Pembelian kebutuhan Dept Plant Closed (07 Januari 2022)
Pembayaran klaim kedatangan karyawan akhir desember due date week-2 (11 Januari 2022)
Pembayaran hotel untuk tamu (an OV & YD) due date week-2 (12 Januari 2022)