ENGINEERING - PRODUKSI

PT. PRIMA SARANA GEMILANG - PADA IDI PROJECT


2023

SITE : PT. Pada Idi - Luwe Overburden Coal Mining


DATE : 19_20 Des 2023 PLAN : 435,225 BCM 74,304 TON
TIME (From-Until) : 18.00 - 09.00 MTD : 244,814 BCM 20,130 TON
PIT / BLOCK : B Tengah / PER DAY : 15,868 BCM 4,515 TON
CLASSIFICATION : Loading OB dan CG B1/B2 KURANG : 190,411 BCM 54,174 TON
HALAMAN : 1 / 6 31-Dec ## 12 #######
Day Shift Night Shift

PIT UTARA BLOCK 22 - 28

- Exa 1250 - 04
- Loading ob/Regrade Jalan
- Hauler : 5 Unit
- Distance : 1500 m
- Elevasi : :5_0 m
- Dumpingan : IPD

SERAH TERIMA INSTRUKSI PELAKSANAAN PEKERJAAN SERAH TERIMA LAPORAN PELAKSANAAN PEKERJAAN
Dibuat Oleh, Diketahui Oleh, Diterima Oleh, Dilaporkan Oleh, Diketahui Oleh,

Pit Control Eng. Engineering Dept. Head Product. Dept. Head Product. Sect. Head Pit Control Eng. Engineering Sect. Head
ENGINEERING - PRODUKSI
PT. PRIMA SARANA GEMILANG - PADA IDI PROJECT
2023

SITE : PT. Pada Idi - Luwe Overburden Coal Mining


DATE : 15_16 Des 2023 PLAN : 435,225 BCM 74,304 TON
TIME (From-Until) : 18.00 - 09.00 MTD : 244,814 BCM 20,130 TON
PIT / BLOCK : B Tengah / PER DAY : 15,868 BCM 4,515 TON
CLASSIFICATION : Loading OB dan CG B1/B2 KURANG : 190,411 BCM 54,174 TON
HALAMAN : 2 / 6 31-Dec ## 15 #######
Day Shift Night Shift

PIT UTARA BLOCK 22 - 28

Dumpingan OB dari fleet selatan 1250 - 04 to RL 35

SERAH TERIMA INSTRUKSI PELAKSANAAN PEKERJAAN SERAH TERIMA LAPORAN PELAKSANAAN PEKERJAAN
Dibuat Oleh, Diketahui Oleh, Diterima Oleh, Dilaporkan Oleh, Diketahui Oleh,

Pit Control Eng. Engineering Dept. Head Product. Dept. Head Product. Sect. Head Pit Control Eng. Engineering Sect. Head
ENGINEERING - PRODUKSI
PT. PRIMA SARANA GEMILANG - PADA IDI PROJECT
2023

SITE : PT. Pada Idi - Luwe Overburden Coal Mining


DATE : 14_15 Des 2023 PLAN : 435,225 BCM 74,304 TON
TIME (From-Until) : 18.00 - 09.00 MTD : 244,814 BCM 20,130 TON
PIT / BLOCK : B Tengah / PER DAY : 15,868 BCM 4,515 TON
CLASSIFICATION : Loading OB dan CG B1/B2 KURANG : 190,411 BCM 54,174 TON
HALAMAN : 3 / 6 31-Dec ## 15 #######
Day Shift Night Shift

PIT UTARA BLOCK 22 - 28

- Peralihan EX 950 - 06
- Loading ob/Regrade Jalan
- Hauler : 5 Unit
- Distance : 1500 m
- Elevasi : :10 m
- Dumpingan : OPD 80

SERAH TERIMA INSTRUKSI PELAKSANAAN PEKERJAAN SERAH TERIMA LAPORAN PELAKSANAAN PEKERJAAN
Dibuat Oleh, Diketahui Oleh, Diterima Oleh, Dilaporkan Oleh, Diketahui Oleh,

Pit Control Eng. Engineering Dept. Head Product. Dept. Head Product. Sect. Head Pit Control Eng. Engineering Sect. Head
ENGINEERING - PRODUKSI
PT. PRIMA SARANA GEMILANG - PADA IDI PROJECT
2023

SITE : PT. Pada Idi - Luwe Overburden Coal Mining


DATE : 14_15 Des 2023 PLAN : 435,225 BCM 74,304 TON
TIME (From-Until) : 18.00 - 09.00 MTD : 244,814 BCM 20,130 TON
PIT / BLOCK : B Utara / PER DAY : 15,868 BCM 4,515 TON
CLASSIFICATION : Loading OB dan Coal Getting B2 KURANG : 190,411 BCM 54,174 TON
HALAMAN : 4 / 6 25-Dec ##
Day Shift Night Shift

PIT Utara BLOK 33_36

-Peralihan Ex 950_05 -Peralihan Ex 950_05


- Loading OB /Mud/Expose B1 - Loading OB Expose B1
- Hauler : 7 Unit - Hauler : 7 Unit
- Distance : 2600 - Distance : 2600
- Elevasi 4 - Elevasi 2
- Dumpingan : OPD 80 /MUD - Dumpingan : OPD 80 /MUD

SERAH TERIMA INSTRUKSI PELAKSANAAN PEKERJAAN SERAH TERIMA LAPORAN PELAKSANAAN PEKERJAAN
Dibuat Oleh, Diketahui Oleh, Diterima Oleh, Dilaporkan Oleh, Diketahui Oleh,

Pit Control Eng. Engineering Dept. Head Product. Dept. Head Product. Sect. Head Pit Control Eng. Engineering Sect. Head
ENGINEERING - PRODUKSI
PT. PRIMA SARANA GEMILANG - PADA IDI PROJECT
2023

SITE : PT. Pada Idi - Luwe Overburden Coal Mining


DATE : 14_15 Des 2023 PLAN : 435,225 BCM 74,304 TON
TIME (From-Until) : 18.00 - 09.00 MTD : 244,814 BCM 20,130 TON
PIT / BLOCK : B Utara / PER DAY : 15,868 BCM 4,515 TON
CLASSIFICATION : Dumpingan OPD KURANG : 190,411 BCM 54,174 TON
HALAMAN : 6 / 6 25-Dec ##
Day Shift Night Shift

DISPOSAL

Dumpingan OB dari fleet utara (950 -06 dan 950 -05)


Reminder : to elv 80 sisi utara EX TBU(pita Merah/limit dumping)

OB
ENGINEERING - PRODUKSI
PT. PRIMA SARANA GEMILANG - PADA IDI PROJECT
2023

GENERAL JOB LIST

No JOB LIST START DATE OVERDUE

Elevasi sump :

1 Blok 28 : -2,461

2 Blok 30 : -2,461

3 Blok 36 : 4.7

Aktivitas ketika hujan :

1 Blokade air dari jalan ke pit di arahkan ke blok 37 (PIT UTARA)

2 Blokade air dari jalan ke pit di arahkan ke blok 24 (PIT SELATAN)

General

1 Perapian tanggul pit dan disposal IPD blok 09

2 Reslope area HW blok 37_40 Bench 10

3 Reslope area HW blok 32_33 Bench 0

4 Reslope area HW blok 18_19 Bench 40